> ") XIAO'S) . 3 o::)^:) 3 533:^^ UNIVERSITY OF ILLINOIS LIBRARY CHEMISTRY DEPABTMfWT => ; o 5 ;>i»s)>D )3 )a>"D :)32> -:>,'> ^^.>^^>>4>-^i?>2 ?-^ :xysyWx^ K)j.ym> ,cc C crc cfcc cccr cGrcc<^CC ccccc < cc c €c .ccc cc:'c ■ce:cccc 8I5 157140 iv CONTENTS. Railroad Location — continued. page Field Work, 823 Problems in Location, -..-.. 832 Specifications for Grading and Bridging, - - 800 Railroad Construction. The Engineer Corps, ..... - - 869 Cross-Sectioning, ...... 870 Culverts, - - - 878 Retaining Walls, - 899 Excavation, - - 912 Tunnel Work, 935 Protection Work, 966 Routine Work, 970 Bridge Work, -....-. 978 Pile Work, 1002 Estimates, 1017 Track Work. Track Laying, 1029 Track Joints, 1036 Rails, 1038 Expansion and Contraction, .... 1043 Spiking Rails, 1045 Surfacing Track, 1048 Drainage, 1052 Care and Maintenance of Track, . . . 1058 Curved Track, 1087 Frogs and Switches, 1102 Yards and Terminals, 1145 General Instructions, . .... 1148 Railroad Structures. Wooden Trestles, 1103 Framed Bents, 1177 Floor System, 1186 Bracing, ' 1195 Iron Details, - - 1198 CONTENTS. V Railroad Structures — cotitinued. Connection of Trestle with Embankment — Pro- page tection Against Accidents, - - - . 1207 Field Engineering and Erecting, - - - 1211 vSpecifications for Wooden Trestles, ... 1213 Bills of Materials, Records, and Maintenance, - 1334 Standard Trestle Plans, 1230 Simple Wooden Truss Bridges, - - - - 1246 Water Stations, - - - - - - - 1374 Coaling Stations, 1381 Turntables, 1385 Questions and Examples. Surveying, - - - Questions 014-705 1397 Land Surveying, - - Questions 706-755 1309 Railroad Location, - - Questions 756-813 1315 Railroad Construction, - Questions 813-873 1331 Railroad Construction, - Questions 873-946 1337 Track Work, - - - Questions 947-1016 1333 Railroad Structures, - Questions 1017-1083 1339 SURVEYING. GEOMETRY. 1 180. If two triangles have two sides and the included angle of the one equal to two sides and the included angle of the other, the triangles are equal in all their parts. Thus, in the two triangles ABC and D E F, Fig. 236, if the side A B is equal to the side D E ; the side B C to the side ^ \ ^ ^ p E F, and the angle B to the fig. 236. angle E, the triangles are equal in every respect. 1181. If a straight line, A B, Fig. 237, intersects two parallel straight lines, C D and E F, it is called a secant with respect to them, and the eight angles formed about the points of in- tersection have different names applied to them with respect to each other, as follows : First — Interior angles on the same side are those which lie on the Fig. 237, same side of the secant and within the other two lines. Thus, in Fig. 237, H G D 2Lnd G H F 2ive interior angles on the same side. Second — Exterior angles on the same side are those which lie on the same side of the secant but ivithout the other two lines. Thus, A G D a^nd F H B 2Lxe exterior angles on the same side. Third — Alternate interior angles are those which lie on opposite sides of the secant and within the other two lines. Thus, C G H and G H Fare alternate interior angles. 602 SURVEYING. Fourth — Alternate exterior uncles are those which lie on opposite sides of the secant and without the other two lines. Thus, A G C and F H B2^x% alternate exterior angles. Fifth — Opposite exterior and interior antcles are those which lie on the same side of the secant, the one within and the other without the other two lines. Thus, A G D and G H F are opposite exterior and interior angles. 1182. If a straight line intersects two parallel lines, the sum of the interior angles on the same side is equal to two right angles, and the sum of the exterior angles on the same side is also equal to two right angles. Thus, in Fig. 237, the interior angles D G H and F H G are together equal to two right angles, and the exterior angles D G A and F H B are together equal to two right angles. 1183. If a line intersects two parallel straight lines, the alternate interior angles are equal to each other, and the alternate exterior angles are also equal to each other. Thus, in Fig. 237, the angle C G H \s equal to F H G, and angle C G A \?, equal to F H B. 1184. The complement of an angle is the difference E B FlO. 238. between that angle and a right angle. Thus, in Fig. 238, A B E is the comple- ment oi D B E. -D 1185. The supplement of an angle is the difference between that angle and two right angles. Thus, C B E is the supplement oiDB E. 1 186. In any triangle, a line drawn parallel to one of the sides divides the other sides proportionally. Thus, in the triangle ABC, Fig. 239, the line D E drawn parallel to B C divides the sides A B and A C proportionally ; that is, A B \ A D\\ A C \ A E; A D '. D B\: A E : E C, and A B : D B :: A C : E C. KiG.a:>i.. SURVEYING. 603 « 1 1 87. Polygons are similar when they are mutually equiangular and have their homologous sides proportional. In similar polygons, any points, lines, or angles similarly situated in each are called homologous. The ratio of a side of one polygon to its homologous side in another is called the ratio of similitude of the polygons. 1188. Triangles which are mutually equiangular are similar, and their areas are to each other as the squares of their homologous sides. Thus, in the triangles A B C ?ind.D E F, Fig. 240, if the angle A is equal to the angle D\ the angle B to the angle E, and the angle C to B^ ^CE^ ^F the angle F, the triangles are Fig. 24o. similar, and their areas are to each other as the squares of their homologous sides. For example, if B C = ^0 feet, EF=oO feet, and the area of the triangle A B C = 1,G00 sq. ft., then 80* : 50' :: 1,600 : area oi D E F, or 6,400 : 2,500 :: 1,600 : 625 sq. ft. Hence, area oi D E Fis 625 sq. ft. 1 1 89. The areas of similar polygons are to each other as the squares of their homologous sides. Thus, if the area of a regular hexagon with a side of 10 inches is 259.809 sq. in., the area of a similar hexagon whose side is 15 inches may be found as follows: 10" : 15'' :: 259.809 : area required, or 100 : 225 :: 259.809 : 584.57 sq. in. 1190. The circumferences of circles are to each other as their diameters, and their areas are to each other as the squares of their diameters. Thus, if the circumference of a circle 12 inches in diam- eter is 37.7 inches, the circumference of a circle of 18 inches diameter may be found by proportion. Thus, 12 : 18 :: 37.7 : 56.55 in., the circumference required. G04 SURVEYING. Again, if the area of a circle of 12 inches diameter is 113.098 sq. in., the area of a circle of 18 inches diameter may be found as follows: 12' : 18' :: 113.098 : area required, or 144 : 324 :: 113.098 :, 254.47 sq. in. 1191. An angle formed by a tangent and a chord meeting at the point of contact is measured by half the included arc. Thus, in Fig. 241, the angle A C D formed by the meeting of the tangent A B and the chord C D '\s measured by half the arc C E D. Similarly, the angle B C D \s measured by half the arc C D. 1192. Two tangents to a circle drawn from any point are equal, and if a chord be drawn joining these tangent points, the angles between the chord and the tangents are equal. Thus, in Fig. 242, the two tangents A B and A C drawn to the circle from the point A are equal, and the angles ABC and A C B, formed by the chord and tangents, are equal to each other. 1 1 93. In similar circles equal chords subtend equal angles at the center and also at the circumference. fig. 242. Thus, in Fig. 243, the angles A O B, B O C, 2.nA C O D subtended by the equal chords A B, B C, and C D are equal to each other. Again, the angles B A C and CAD are also equal to each other. 1194. In Fig be any triangle, sides, as A C, is Fig. 243. 244, let A B C If one of the prolonged, the angle BCD- included between the SURVEYING. 605 side thus prolonged and the other side B C of the triangle, which meets A C a.t C, is called an exterior angle. The two remain- ing angles A and B of the triangle, which are opposite to the angle 6', are called opposite interior angles. In any triangle, an ex- terior angle is equal to the sum of the two opposite interior angles ; that ^"^- "^^• is, in the above figure, the exterior angle B C D is equal to the sum of the two opposite interior angles, A and B. 1 195. Problem. — Having given one of the angles of a triangle, one of the including sides, and the difference of ^ the other two sides, to construct it. Let C, Fig. 245, be the given angle, A the given side, and B the difference of the other sides. Draw D E equal to the given side A\ 2X D make the angle E D F equal to the given angle (7; Fig. 245. on D F lay oK D G equal to the given difference B. Join E G. At the middle point // of E G erect a perpendicular cutting D Fin K. Draw K E. D E K is the required triangle. COMPASS SURVEYING. 1196. The Compass. — The surveyor's compass consists of the magnetic needle, the case in which it is en- closed, and the support on which it is placed when ready for use. 1197. The Magnetic Needle.— The magnetic needle is a slender bar of steel, five or six inches in length, strongly magnetized, and mounted upon a finely pointed pivot on which it freely turns, always pointing in the same 006 SURVEYING. direction, viz. : the north and south line, or, as it is called, the magnetic meridian. 1198. North and South Ends of Needle.— Owing to the earth's attraction, the north end of the needle dips, that is, it is drawn downward from a horizontal position, while the south end is correspondingly raised. To prevent this dipping, several coils of platinum wire are wound _,, ^. „,. around the south end rPlattnum Wire. . , ,, , _. — ■ "^ of the needle (see Pig. 246), keeping it per- fectly balanced upon its pivot and permit- These coils of wire at the north end and \Pivot. Fig. 246. ting entire freedom of movement once indicate to the observer which is which is the south end of the needle. 1199., The Sights. — At either end of a line passing through the needle pivot is a sight, which consists of an upright bar of brass A and B. (See Fig. 247.) Narrow Fig. 247. vertical slits, with holes at their top and bottom, divide this bar, as shown at C and D. These arrangements enable the observer to train the line of sight upon any desired object. SURVEYING. 607 1 200. The Divided Circle. — The compass box con- tains a graduated circle divided to half degrees, at the center of which is the pivot supporting the needle. The degrees are numbered from 0° to 90° both ways from the points where a line drawn through the slits would cut the circle. 1201. Lettering. — The lettering of the surveyor's compass is at first confusing to those learning its use. A person standing with his back to the south and facing the north will have the east on his right hand and the west on his left. These latter directions, viz., the east and. the west, are reversed in the lettering of the compass. The reasons for this apparent error are explained in the following figures: Fig. 248. Fig. 249. Suppose the needle and compass are pointing due north and south in the direction of the line A B, as shown in Fig. 248, and the line of survey changes its direction 45° to the right, or east. The magnetic needle will remain motion- less, while the sights and the circle to which they are fast- ened will move until the sights point in the direction C D, Fig. 240, and, as the north end of the compass is ahead, the needle will read N 45° E, which is the true direction being run. If, however, the east and west points of the compass were the actual magnetic directions, i. e. , the right hand east and the left hand west, the direction of the line C D 608 SURVEYING. would have read N 45° W, which would be the reverse of the actual direction. 1202. Levels. — On the compass plate are two small spirit levels F and G. (See Fig. 247.) They consist of glass tubes, curved slightly upwards and nearly filled with alcohol, leaving a small bubble of air in them. One of these tubes, /% is in the line of sight, the other, C, is at right angles to it. Their object is to enable the observer to place the compass in a perfectly horizontal position. This is done by so moving the compass as to bring the air bubbles to the centers of the tubes. To prove these bubbles to be in adjustment, proceed as fol- lows: Having brought the bubbles to the centers of the tubes, revolve the compass through 180° or one-half of an entire revolution. If the bubbles remain in the cen- ters of the tubes, they are in adjustment. If they do not so remain, bring them half way back to the middle of the tubes by means of small screws attached to the tubes, and the remainder of the way by moving the plate in the ordinary way, repeating the operation until the bubbles remain in the center of the tubes in every position of the compass. 1 203. The Tripod. — The compass is usually supported by a single standard, shod with steel, and called a Jacob's Staff. A more perfect support, called a tripod, consists of three legs shod with steel and connected at the top so as to move freely. Both Jacob's Staff and tripod are connected with the compass by means of a ball and socket joint, which permits free movement in all directions. 1204. Defects of the Compass. — The compass is not intended for work requiring great accuracy. The direc- tion to which the needle points can not be read with pre- cision, and the perfect freedom of movement of the needle may be prevented by local attraction or by particles of dust adhering to the pivot. An inaccuracy of one-quarter of a degree in reading an angle, i. e., the amount of change in SURVEYING. 609 the direction of two lines, will cause them to separate from each other If feet in a distance of 400 feet. Suppose the line A B, Fig. 250, is due east and west, and the line B C, which is an actual boundary, has a true direc- tion of N 85° E, and suppose the surveyor reads the directions ^ 6^ as N 84° 45' E. Let i? C = 400 feet, then, the point C, when mapped, will take the position C\ which is If feet to the left of C where it should be. Another defect of the compass lies in the fact that the magnetic needle does C A B -—===405*^""^ l^fJ^ Fig. 25e. not always point in the same direction. This direction some- times changes between sunrise and noon to the amount of one-quarter of a degree. Frequently its direction is changed by local influence. A piece of iron on the surface of the ground or a mass of iron ore beneath are frequent disturbing influences. 1 205. Taking Bearings. — The bearing of a line is the angle which it makes with the direction of the magnetic needle. By the course of a line we mean its length and its bearing taken together. To take the bearing of a line, set the compass directly over a point of it, at one extremity, if possible. This may be done by means of a plumb bob sus- pended from the compass, or, if the compass be mounted on a. Jacob's Staff, by firmly planting the staff directly on the line. Then, by means of the air bubbles, bring the compass to a perfectly level position. Let a flagman hold a rod care- fully plumbed at another point of the line, preferably the other extremity of it, if he can be distinctly seen. Direct the sights upon this rod and as near the bottom of it as pos- sible. Always keep the same end of the compass ahead; the north end is preferable, as it is readily distinguished by some conspicuous mark, usually a '■'■ fleur de lis," and always read the same end of the needle, that is, the north end of the needle if the nor th point of the compass is ahead, OlO SURVEYING. and vice versa. Before reading the angle, see that the eye is in the direct line of the needle so as to avoid error which would otherwise result from parallax, or apparent change of the position of the needle, due to looking at it obliquely. The angle is read and recorded by noting, first, whether the N OT S point of the compass is nearest the end of the J. needle being read; second, the y number of degrees to which it points, and third, the letter E or W nearest the end of the needle being read. Let A B, in Fig. 251, be the direction of the magnetic needle, B being at the north end. Let the sights of the compass be directed along the line C D. The north point of the compass will be seen to be nearest the north end of the needle which is to be read. The needle which has remained stationary while the sights were being turned to C Z>, now points to 45° between the N and E points, and the angle is read north forty-five degrees east (N45° E). 1 206. Backsights. — A sure test of the accuracy of a bearing is to set up the compass at the other end of the line, i. e., the end first sighted to, and sight to a rod set up at the starting point. This process is called backslKtitliiK. If the second bearing is the same as the first, the reading is correct. If it is not the same, it shows that there is some disturbing influence at either one or the other end of the line. To determine which of these two bearings is the true one, the compass must be set up at one or more intermediate points, when two or more similar bearings will prove the true one. When a line can not be prolonged by magnetic bearings, on account of local attraction, the true direction is maintained by backsighting. SURVEYING, (311 1 207. Declination of tlie Needle. — The magnetic meridian is the direction of the magnetic needle. The true meridian is a true north and south line, which, if produced, would pass through the poles of the earth. The declination of the needle is the angle which the magnetic meridian and the true meridian make with each other. In Fig. 252, let N S he the true meridian for any given place, and iV 5* the magnetic meridian. The angle NA iV* is the declination of the needle for that place. 1 208. The Polar Star. — There is a star in the northern hemisphere known as the North Star or Polaris. It is the extreme star in the row or line of stars forming what is commonly called the ^ handle of the "Little Dipper." This star very ^ nearly coincides with the true north point or ^"^- '^^• pole, being removed only 1^° from it. It revolves about the true pole, and twice in each revolution it is exactly in the true ^--^^---^ meridian ; that is, in a vertical plane passing through the true pole P. See Fig. 253. One may know when the North Star is in the true meridian from the position of another star. This other star is in the handle of the " Big Fig. 253. Dipper, "or Ursa Major, the one nearest the bowl of the dipper, and is called Alioth. When the North Star is in the true meridian, Alioth will be found directly below it. TO DETERMINE A TRUE MERIDIAN. 1 209. By Observations of the North Star.— The time at which the North Star passes the meridian above the pole for every tenth day of the year is given in published tables, but those occurring in the day time are, of course, of no- value with ordinary instruments. The following dates are available in almost every latitude of the United States: J' O 012 SURVEYING. TIME OF NORTH STAR PASSING THE MERIDIAN. Months. 1st Day. 11th Day. 21st Day. January August September October November December 6:30 P. M. 4:33 A. M. 2:31 A. M. 12:34 A. M. 10:28 P. M. 8:30 P. M. 5:51 P. M. 3:53 A. M. 1 :52 A. M. 11:50 P. M. 9:48 P. M. 7 :50 P. M. 5:11 P. M. 3:14 A. M. 1:12 A. M. 11:11 P. M. 9:09 P. M. 7:11 P. M. Note from the table the time of passing the meridian, and, also, that it is the upper transit, i. e., above the pole. Select a suitable spot for permanently establishing the meridian line, and set up the transit and sight to Polaris, following it by moving the cross-hairs with the tangent screw. When it is exactly in line with Alioth, the line of sight will be in the true meridian. Points should be fixed immediately, a lamp being used to illuminate the cross- hairs. 1210. Changes in Magnetic Declination. — The magnetic declination is not fixed for any place, but con- stantly varies, its variations, however, being confined within fixed limits. 1211. To Correct Magnetic Bearings. — The dec- lination at any place being known, the magnetic bearings may readily be reduced to true bearings. In the Northeastern States, the declination is west; in the Western and Southern States, it is east ; hence, the true bearing of a line in a Northeastern State, whose magnetic bearing is N W or S E, will be the sum of the magnetic bearing and the declination. If the magnetic bearing is N E or S W, the true bearing will be the difference of the magnetic bearing and the declination. SURVEYING. 613 EXAMPLES FOR PRACTICE. 1 212. Supposing the declination to be 7° west, what'' will be the true bearings of the following lines Magnetic Bearing. (1) N 12° 10' W ? (2) N 50° 15' W ? (3) S ir 15' E ? (4) S 38° 10' E ? (5) N 50° 20' E ? (6) S 20° 25' W ? (7) N 87° 30' W ? (8) N 5° 10' E ? (9) S 89° 20' E ? (10) S 3° 10' W ? Ans. True Bearings. (1) N 19° 10' W. (2) N 57° 15' W. (3) S 18° 15' E." (4) S 45° 10' E. (5) N 43° 20' E. (6) S 13° 25' W. (7) S 85° 30' W. (8) N 1° 50' W. (9) N 83° 40' E. L (10) S 3° 50' E. 1213. By Equal Shadows of the Sun. — On the south side of any level surface set up a flag-pole and plumb it with a plumb bob. Its horizontal projection will be a point as S in Fig. 254. Two or three hours before noon mark the point yi, which is the extremity of the shadow cast by the flag-pole. Then, describe an arc A B with a radius equal to S A, the distance from S to the extremity of the shadow. After noon, note the moment when the shadow of the flag-pole touches another point of the arc, as B. Bisect the arc A B at N. The line 5 iV is a true meridian. FIELD WORK. 1214. The Engineer's Chain. — The engineer's chain is one hundred feet in length, and is composed of one hun- dred links of steel wire, each one foot in length. Both ends of the chain are fitted with brass handles with swivel move- ments, and fitted with nuts for taking up any excess in length resulting from continual stretching. At each interval of ten feet is a brass tag with tally points to indi- cate its distance from the nearest end of the chain. Each tally point counts ten feet. At the middle point of the 614 SURVEYING chain, the tag is of oval form to prevent confusion in reading the chain. 1215. l>anger of Error. — There is much greater danger of error in reading the chain than in reading bear- ings. The danger arises from the fact that the compassman is usually one of experience, who knows the liability of error, and hence the necessity for care, while chainmen are often inexperienced, and, unfortunately, often careless. 1216. Keeping Chainmen in Line. — When the direction of a line has been given by setting up a flag, it be- comes the business of the hind chainman or follower to keep the measurement on a straight line. The head chainman carries a flag which he moves to right or left, at the di- rection of the hind chainman, until it is in range with the flag towards which the compass is sighted, and this process is repeated at each chain measurement. In railroad surveying, the line is divided into stations, which are one hundred feet or one chain apart. At each station a stake is driven and marked with a number corre- sponding to the number of chains which the station is distant from the starting point, which is numbered 0. When the end of a course falls between regular stations, it is called a sub-station, and the stake is marked by the number of the immediately preceding station plus the number of feet from it to the end of the course. The line A B, in Fig. 255, is 650 feet in length. The starting point A is numbered 0\ each chain or one hundred 1 2 3 4 5 6 6 +50 ^ Pig. 255. -^ feet is marked by a stake with numbers in regular notation. The point B, which is fifty feet from station 6, is marked 6 + 50. 1217. — The Compass in Railroad Surveys. — The compass is of great value in running preliminary railroad lines, where local attraction is absent or very slight. The numerous delays encountered when running by backsights, SURVEYING. 615 as in transit work, where all obstacles to the line of sight must be cleared, are largely avoided in the use of the com- pass. The directions of all lines are referred to the mag- netic needle, and, in case of an obstruction, such as a tree or a mass of rock, the compass can be quickly moved to the op- posite side of the obstacle and the line continued without delay. In case the line produced is a foot or two off the true one, // is a parallel to it, and the error is not to be re- garded as affecting the accuracy oi preliminary information. In the case of transit work, an error in the reading of an angle is a cunmlative one, and practically destroys the value of the work. In the early days of railroad building, some lines were surveyed and built with the aid of the compass alone, but in America all location and construction depend for their precision upon the transit. 1218. Organization of Party. — A well-organized compass party consists of a chief of party, compassman, two chainmen, one flagman, two or more axmen, if the country be thickly wooded, and one stakeman. If possible, provide stakes of light, well-seasoned wood. For preliminary lines where stakes do no permanent service, pine is best. A convenient size is two feet six inches in length by two inches in width and half an inch in thickness. A strong, active stakeman will carry one hundred of these stakes, besides the ax with which to drive them. Provide both chainmen with marking crayons. The best crayon is of red chalk or German kiel. They are bought in a crude state, but a little work will shape them. They make a deep red mark, which will stand exposure for years. Require chainmen to be always provided with crayons. Instances of their forgetful- ness too often occur. Require axmen to keep axes sharp. A dull ax is little better than no ax. Check length of chain with standard steel tape, lengthening or shortening by means explained in Art. 1214. See that the compass is in perfect adjustment. If the line to be surveyed is of consid- erable length, a team of horses and driver with a strong spring wagon should be a part of the outfit. 616 SURVEYING. 1219. Actual Work. — The party is now prepared to move. The compassman sets up the compass at the starting point, which is marked 0. The chief of party goes ahead with the flagman, who carries a rod called a flag. This rod is from eight to twelve feet in length, and is divided into alternate red and white bands, each one foot in length. The flagman sets this flag up at the direction of the chief of party, the compassman sights the instrument to it, and the chainmen commence meas- uring the distance. The head chainman marks the stakes, and should always keep at least ten stakes marked ahead so as to avoid delay while measuring, and to insure con- secutive numbering. Of these he need carry but five, leaving the remaining five with the stakeman. He must also carry a flag eight feet in length, and painted like the one carried by the flagman; this flag is used for "rang- ing in." As soon as the line is indicated by the head flag, the axmen should fall to work clearing whatever obstacles lie in the way of rapid chaining. By a little attention on their own part and occasional direction from the chainmen, they can keep well on line. At each station, and the moment the hind chainman has put the head chainman in line, the former should ^^ gQ.t ^ carefully note the number of the station jh;;;^- g^t >, at whlch hc stands and call the number to the head chainman who must answer by repeat- mg the number next in notation. Thus, if the hind chainman stands at Station 25 he must call " Station 25," and the head chainman must reply "Station 26." The chainmen must be required to hold the chain " taut " while measuring, and in as nearly horizontal a position as possible. When the line of meas- urement rises or falls abruptly, the chainmen must "break the chain," as it is called. The best method of breaking the chain is shown in Fig. 256. SURVEYING. 617 Let A B be a. sloping surface lying in tHe line of measure- ment. The point A is at Station 17. Stretchout the chain to its full length and in proper line. The hind chainman will be at Station 17. The head chainman here takes the chain at the 50-foot tag and raises it until it is practically level. The flag he carries for ranging in will serve for a plumb line to mark the 50-foot point on the ground. The hind chainman then calls the number of his station, 17, the head chainman replying 17 + 50. The former then advances to 17 + 50 and holds the middle tag at the point marked by the rod. The head chainman then advances to the other end of the chain and repeats the operation, reaching Station 18. When the slope is steep, the chain must be broken into smaller sections. It is good practice for the flagman to carry, besides his flag, a number of light stakes at least eight feet in length and some strips of red flannel for targets. If the view for the compass is open, as soon as the compass is sighted and the flagman has a signal to that effect, he should replace the flag by one of the stakes with a piece of flannel attached and join the chief of party, who, unless the line is to be produced, has gone ahead to select another point for the flag. As soon as the compassman has recorded the bearing of the line, he should take the compass and walk rapidly to the next station, marked either by the flag or target, and, if in full view of the chainmen, remove the station mark and set up the compass and be prepared to take the next bearing the moment it is indicated by the chief of party. As soon as the chainmen reach the com- pass and have "taken the plus" from the last full station, the hind chainman calls out the full station and plus, which the head chainman marks on a fresh stake and which the compassman records as the length of the course run. If the same line is to be continued or "produced," the compass is set at the same bearing as the course just run and the chainmen are lined in by the compassman. 1220. Example of the Use of the Compass in Railroad Work. — Suppose C A D in Fig. 257 to be a 618 SURVEYING. Bp4H75 railroad in operation, and that it has been decided to run a compass line from the point A along the valley of the stream X Y to the point B. The bearing of the tangent A I) can not be determined by set- ting up the compass at/i,on account of the attraction of the rails. The direction of this tangent, however, can be obtained by setting up the cortipass at A and sighting to the flag held at D. The point A^ which is the starting point of the line to be run, is marked 0. Producing the line A D 440 feet, the point E is reached, which has been pre- viovisly indicated by the chief of party as a proper place for changing the direction of the line. The compass being set up at E^ the bearing of the line A E, which is the line A D produced, is found by sighting to A^ or, what is preferable, to the point Z>, if that point can be seen. The number of Station E^ viz., 4 + 40, and the bearing SURVEYING. 619 of A E are then recorded by the compassman. By this time the chief of party has located the point F^ and the flag is in place for sighting. The axmen, if there is work for them to do, are put in line by the head chainman, clearing only so much as would interfere with rapid chaining. The bearing of the line E F being recorded, the compass is moved quickly to /%. replacing the target left by the flagman, leveled up, and directed toward the point 6", which is either already, or soon will be, located. The chainmen reaching /% its number 11 -|- 20 is recorded by the compassman, and the instrument sighted to G and the work continued as before. 1221. Form for Keeping Notes. — A plain and con- venient form for compass notes is the following, which is a record of the survey platted in Fig, 257: The first column contains the station numbers, the notation running from the bottom to the top of the page. By such an arrangement, the lengths of the courses are found by subtracting the num- ber of the station of one compass point from the number of the station of the next succeeding compass point. Before commencing the plat, the subtractions are made and the lengths of the courses written in red ink between the station numbers. The second column contains the bearings of the lines. The bearing recorded opposite to a station is the bearing of the course between the given station and the one next above. Thus, the bearing recorded opposite Sta. is N 75° 00' W, and is the bearing of the line extending from Sta. to Sta. 4-|-40 next above. The length of the course is the differ- ence between and 4 + 40 equal to 440 ft. The bearing recorded opposite to 4 + 40 is N 25° 00' W. It is the bear- ing of the line extending from Sta. 4 + 40 to Sta. 11 -|- 20 next above. Its length is found by subtracting 4 + 40 from 11 + 20 equal to 680 ft., and so on. In the third column, under the head of remarks, are recorded notes of reference, topography, and any informa- tion which may aid in platting or subsequent location. 620 SURVEYING. Station. Bearing. Remarks. 47+75 End of line 35 + 75 N 25° 40' E 27 + 50 N 14° 10' E 20+35 N 2° 30' W Woodland 11 + 20 N 15° lo: W 4 + 40 N 25° 00' W N 75° 00' W Sta. is at P. C. of 14° curve to left at Bellford Sta. O. &P. R. R. 1 222. Platting. — After a survey has been finished, a drawing is made showing the courses. This drawing is called a plat, and the operation of making the plat from the field notes is called platting. Since the direction of every line of a compass survey is referred to the same parallel, viz., the magnetic meridian, the readiest mode of platting such a survey is by the use of the T square and protractor. The lines drawn to a T square are parallel, and in platting take the direction of the mag- netic needle, or meridian. The line A B, described in Art. 1 220 and shown in Fig. 257, is platted as follows: The arrow shown in the figure gives the direction of the magnetic meridian. A line A L, parallel to this meridian, is drawn through the starting point A, and from A as a. center the line A £, whose direc- tion N 75° 00' W is taken from the field notes kept by the compassman, is laid off with a protractor. The directions west are laid off to the left of the meridian, and those east to the right of the meridian. The course A E, being a northwest course, is laid off to the left of the meridian A L, as shown in the figure. The length of the line A E is then SURVEYING. 621 measured on this line to any convenient scale, usually 300 feet to the inch, and a parallel to the magnetic meridian drawn through E^ from which the bearing of the line E F^ viz., N 25° 00' W, is laid off and platted. The remaining courses are platted in the same manner. TRANSIT SURVEYING. THE INSTRUMENT. 1223. The engineer's transit, see Fig. 258, is an instrument in which the telescope stakes the place of the plain sights of the compass, and in which the angles are read to single minutes by the vernier. A level C is attached to the underside of the telescope and a ver- tical arc D is attached to the outside of the left hand standard. A vernier E for reading vertical angles is attached to the telescope axis and adjusted by the tangent screw F. The standards G and G, which support the telescope, are fastened to the upper or vernier plate, as is one of the levels 7/, the other being carried by one of the standards at H' . The com- pass circle A", which is divided like that of the ordinary compass, is also a fig. 258. part of the upper plate. The vernier plate covers the lower or divided limb, of which only two small arcs can be seen through the openings where the verniers are placed. A 622 SURVEYING. screw which clamps the vernier plate to the divided limb is shown at /'. Slow motion is given to the upper plate by -Hi the tangent screw J/, and to the divided limb by the screw L. The transit is fastened to the plate N by a ball and socket joint, and is leveled by means of the screws P, Q, R, and S. It is fastened to the tripod 7^ in a variety of ways, usually screwed to the tripod, the edge of the plate N being milled to aid the operator. The transit is brought to center over a point by means of a plumb bob which is suspended fastened to the lower part of the CQ !^^ o-H t^ N$ by a loop transit. 1224. The Telescope. — The telescope is a combination of lenses placed in a tube and so arranged according to the laws of optics that the image of any object toward which the telescope is directed shall be formed within the tube by the rays of light coming from the object and ^ bent in passing through the object glass. This o image is magnified by the eye-piece," which is composed of several lenses. Telescopes are of various kinds, some representing the object erect, i. e., in its natural position, others representing the object inverted. The telescope shown in Fig. 259 represents the object in an erect position. Rays of light from the object A fall upon the object glass B where they are bent, and, crossing each other, form the image at C in an inverted position. Passing on through the lens D, they are refracted or bent, crossing each other again before reaching the lens at E. Passing through the lens F they form an erect image at G, which is in turn magnified by the eye-piece H. 1225. The Cross-Hairs.— In order that the line of sight may be precisely brought to SURVEYING. 623 bear upon any point of an object within the field of the telescope, two fine lines called cross-hairs, or cross- Swires, are placed with their intersection at the common focus of the object glass and the eye-piece. The inter- section of these cross-hairs can be seen through the eye-piece, and seems to be in the same position as that of the image of the distant object. The line passing through the intersection of the cross- hairs and the optical center of the object glass is called the line of collimation. The cross-hairs are fastened to a thick brass ring placed within the telescope and held in position by capstan headed screws. Fig. 260, let into this ring. They are commonly placed at right angles to each other, the one being vertical and the other horizontal. The ring, together with the cross- hairs, can be moved by the capstan headed screws. The cross-hairs are either of platinum wire, drawn very fine, or spider threads. Platinum wire is best, as it is not affected by changes of temperature. Fig. 260. 1226. Focusing the Telescope. — The movement of the object glass is effected by a milled headed screw U, shown in Fig. 258. This screw moves the object glass out or in, according as the object is nearer or further from the instrument. The eye-piece is focused upon the cross-hairs by a similar screw V. The cross-hairs are not in proper focus until they appear to be a part of the object looked at, showing no movement, however the position of the eye may be changed. The telescope is supported upon an axis and so placed that both ends shall be as nearly balanced as possible. The axis 624 SURVEYING. rests on upright legs called the standards. The standards are fastened to the upper plate. 1 227. The Graduated Circle.— This circle is divided into 360 equal parts or degrees, and each degree is further divided into two or three equal parts. If the degree is divided into two equal parts, each part equals 30', and if into three equal parts, each part equals 20'. The degrees number from to 360°, and in most instruments there is an inner graduated circle, which numbers each way from to 90°, as on the compass circle. Each tenth degree is num- bered; each fifth degree is indicated by a longer line of division, and each degree by a line longer than its subdivisions. 1228. Movements. — When the line of sight is to be brought to bear upon a distant object, the observer turns the telescope in the direction of the object by lightly but firmly grasping the upper plate, one hand on either side of the instrument. The eye is ranged along the top of the telescope, which is turned by the hands until it appears to be in the direct line of the object. The eye is then brought to the eye-piece, and the object glass focused upon the ob- ject. The instrument is then clamped, and, by means of either of the tangent screws, the cross-hairs are brought to bear precisely upon any desired point of the object viewed. 1229. The Levels. — Most of the angles measured by the transit are horizontal angles, but whether horizontal or vertical, before an angle can be measured, the plate carry- ing the graduated circle must be brought to a horizontal position. This is effected by means of two small levels placed on the plate at right angles to each other. Each level consists of a glass tube curved upwards at its middle and nearly filled with alcohol, leaving only space for a bubble of air. They are so placed that when the air bubbles are exactly in the middle of the tubes, the plate upon which they rest will be in a level position. The leveling is SURVEYING. 625 performed by means of four leveling screws. They have milled heads and are arranged in pairs, the line passing through one pair being at right angles to that passing through the other pair. 1 230. To Level the Instrument. — Loosen the lower clamp and bring one of the bubble tubes into a parallel to a plane passing through a pair of opposite screws. By turn- ing these screws, the air bubble can be brought exactly to the center of the tube. As the tubes are at right angles to each other, the putting of one in position for leveling ad- justs the other for leveling also, and having leveled one tube with one pair of screws, the other tube is leveled with the other pair. 1231. The Vernier. — A vernier is a contrivance for measuring smaller portions of space than those into which 9\0 7\0 Fig. 261. a line is actually divided. The divided circle of the transit is graduated to half degrees, or 30'. The graduations on the verniers run in both directions from its zero mark, making two distinct verniers, one for reading angles turned to the right, and the other for reading those turned to the left. Each vernier is divided into 30 equal spaces, which are to- gether equivalent to 29 spaces on the divided circle ; hence, each space on the vernier is equal to 29', and the vernier is described as reading to minutes. In reading the vernier, the observer should first note in which direction the graduations of the divided circle run. In Fig. 301 the graduations in- crease from left to right and extend from 57° to 91°. Next he should note the point where the zero mark of the vernier comes on the divided circle. In Fig. 201, the zero mark comes between 7-4° and 74^°. Now, as the circle graduations 626 SURVEYING. read from left to right, we read the right-hand vernier and find that the 23d graduation on the vernier coincides with a graduation on the divided circle, and the vernier reads 23', which we add to 74°, making a reading of 74° 23', an angle to the left. In Fig. 262 the graduations on the circle increase from right to left, and we accordingly read the left-hand vernier. The zero mark of the vernier comes between 67^ and 68°. Reading the vernier, we find that the uiu 7\0 ^*" Fig. 262. 13th graduation on the vernier coincides with a graduation on the circle, and the vernier reads 13'. Accordingly, we add to 67^°, the vernier reading of 13', making a total read- ing of 67° 43', an angle to the right. ADJUSTING THE TRANSIT. 1232. The constant use of an instrument tends to dis- arrange some of its parts, which detracts from the accuracy of its work, without in any way injuring the instrument itself. The correction of this disarrangement of parts is called making the adjustments. The transit, when leveled up, will, if in adjustment, fulfil the following conditions, viz. : 1. It will maintain a perfectly horizontal position during an entire revolution. 2. The line of sight, when directed in opposite direc- tions, will be in the same straight line ; and 3. The line of sight will revolve in a vertical plane perpendicular to the horizontal plane of revolution. SURVEYING. 627 The adjustments should be made in the order of these three conditions. The best time of the day for making the adjustments, especially in the summer season, is the early morning, before the air has become heated and the sun dazzling. 1233. First Adjustment. — Secure, if possible, an open space where a clear sight may be had for at least 400 feet in both directions from the transit. Plant the feet of the tripod firmly in the ground, and then bring the plate to a horizontal position with the leveling screws. Next turn the vernier plate half way around, i. e., revolve it through an angle of 180°. If the bubbles are in adjustment they will remain stationary in the centers of the tubes. If they do not remain so, but run to either end, bring them half way back to the middle of the tubes by means of the capstan headed screws, attached to the tubes, and the rest of the way back by the leveling screws. Then, revolve them again through 180°. Sometimes this adjustment is made by one trial, but it is usually necessary to repeat the operation. 1 234. Second Adjustment. — To cause the line of col- limation to revolve in a plane : Fig. 263. Measure from A, where the instrument is stationed (see *Fig. 203), 400 feet to the point B, where a pin (or tack, if it can be seen) is fixed. Carefully direct the line of sight to this point, and re- verse the telescope, i. e., ttirn it on its axis until it points in the opposite direction. If the line of collimation is "in adjustment," a pin set 400 feet from A, on the opposite side of the instrument from j5, will be at /^and in the same line 2i% A B\ \i '\X. is not in adjustment, the pin will be on one side of /% as at D. Turn the vernier plate half way around, that is, through 180°, and direct the line of sight again to B. 628 SURVEYING. Reverse the telescope, and the pin will be at C. Carefully measure the distance C D, and at E, one-fourth of the dis- tance from C to D, set the pin. Move the cross-hairs by means of the capstan headed screws until the vertical hair shall exactly cover the pin at E, being careful to move them in the opposite direction from that in which it would appear they should move. This movement having been made and the telescope reversed, the line of sight will not be at the point y>, but at G, a distance from B equal to C E. Again sight to B^ and, reversing, the pin will be at /% in the same line as A B. It may be necessary to repeat the operation to secure an exact adjustment. If so, take a new set of points, a few inches removed from those first used, to avoid confusion. 1235. Third Adjustment. — To cause the line of collimation to revolve in a vertical plane: Suspend a plumb bob at as high an elevation as can be A readily found; direct the line of sight to the upper end of this line and then, revolving the telescope slowly downwards, see if the intersec- tion of the cross-hairs closely follows this line throughout its length. If it does follow it, the line of collimation revolves in a vertical plane. If it does not, the adjustment may be made as follows: Take a point A^ in Fig. 204, on a church spire or some other high object, and sight care- fully to it. Depress the telescope until a pin can be set in the ground at its base, as at B. Loosen the clamp and turn the plate through 180° with- out touching the telescope. Clamp the instru- B^—i^-^C ment and sight again to the high point A. Again Fig. 264. depress the telescope and set another pin, which it will be found is at some distance from B^ as at C. The vertical plane is the line A D, and it will be seen that the error is doubled. The adjustment is made by raising or lowering one end of the telescope axis by means of a small screw placed in the standard for that purpose. SURVEYING. 629 DIRECTIONS FOR USING THE TRANSIT. 1 236. Care of the Transit. — The transit, though it will bear a lifetime of legitimate service, will not stand neglect or banging. The bearings are delicate and easily marred by particles of dust or sudden blows. Moisture clouds the lenses, and, when combined with dust, is doubly injurious. Little advantage is gained from working in the rain, and, unless the stress of work requires it, both instru- ment and men are better off under cover. If the instru- ments should encounter a wetting, carefully wipe the object glass, eye-piece, and verniers with a piece of chamois skin, as moisture soon clouds them so as to prevent further work. As soon as the party returns to office or camp, complete the drying process by thoroughly rubbing with a piece of chamois skin, which every engineering party should carry. When a party rides to and from work, the instruments should be carried in their cases, and they should always be kept in their cases when in the office. The common cus- tom of leaving an instrument on its tripod and standing on a board floor can not be too severely condemned. 1237. Setting Up the Instrument. — As much of the work of an engineering party is suspended while the instrument is being set up, it is highly important to acquire facility in setting it up. The following suggestions will be of use, although practice alone will make one expert. In setting up a transit, three preliminary conditions should be met as nearly as possible, viz. : 1. The tripod feet should be firmly planted. 2. The plate on which the leveling screws rest should be level; and 3. The plumb bob should be directly over the given point. The third condition must be met to a nicety, and this is rendered comparatively easy by means of a " shifting head " with which most modern transits are provided. When these three conditions are approximately met, the completion of the operation is quickly performed with the leveling screws. 630 SURVEYING. 1 238. How to Prolong a Straight Line.— Let A B, in Fig. 265, be a straight line, and it is required to prolong or produce it 400 feet to C. 400' Fig. 265. The line can be prolonged in two ways — by means of foresiglit and backsight. 1. By foresight, set up the transit at A and sight to B ; let the chainman measure 400 feet from B in the direction in which the line is to be prolonged. Then, by means of signals, move the flag to right or left until the vertical cross-hair shall exactly divide the flag held at C. Then, the line B C will be the prolongation of the line A B. 2. By backsight, set the transit at B and sight to A. Reverse the telescope, and, having measured 400 feet from B in the opposite direction from A, set the flag at C, then the line B C will be the line A B produced. 1 239. Double Centers. — In prolonging lines, a device known as double centering is sometimes used. It is un- necessary when using an instrument that is in proper adjustment, but it is a good check, and a knowledge of the method is valuable. Let A B, in Fig. 2G6, be a given line which it is re- quired to produce 1,000 feet, ^et up the transit at B; ^ g 500\ P SOO* O Fig. 266. backsight to A, and reverse the instrument. Set a point C 600 feet from B. Unclamp the upper plate and revolve the telescope through 180°, backsighting again to A. Reverse the telescope. If the line of sight does not come at C, then the point C is not in line with the points A and B, and the line of sight will be at some point, as/), on the opposite side of the true line. Measure the space C D and mark its mid- dle point E. The point E will be in the prolongation of the SURVEYING. 631 line A B. Move the transit to E, and, backsighting to B^ determine the point H by the same means used in fixing the point E. 1240. Horizontal Angles and Their Measure- ment. — A horizontal angle is one the boundary lines of which lie in the same horizontal plane. Let A, B, and C, in Fig. 267, be three points, and let it be re- .3,°30^- quired to find the hori- A ^ zontal angle formed by / the lines A B and A C » i joining these points. Set up the instruments ^'^- ^'^• precisely over the angular point A, and carefully level it. Set the vernier at zero, and place the flag at B and at C Sight the flag at B and set the lower clamp. Then, by means of the lower tangent screw cause the vertical cross- hair to exactly bisect the flag at B. Loosen the upper clamp. With a hand on either standard, turn the telescope in the same direction as that of the hands of a watch until the flag at C is covered or nearly covered by the vertical cross-hair. Clamp the upper plate and with the upper tan- gent screw bring the line of sight exactly on the flag at C. The arc of the graduated circle traversed by the zero point of the vernier will be the measure of the angle B A C, equal to 143° 30'. The points A, B, and C are not necessarily in the same horizontal plane, but the level plate of the instru- ment projects them into the horizontal plane in which it revolves. 1 24 1 . A Deflected Line. — A deflected line, or " angle line," is a consecutive series of lines and angles. The direc- tion of each line is referred to the line immediately pre- ceding it, which preceding line is, in imagination, produced, and the angle measured between it and the next line actually run. The angles are recorded R' or IJ, according as they are turned to the right or left of the prolongation of the immediately preceding line. An example of a deflected line 632 SURVEYING. «v N ^^^. is shown in Fig. 2G8. Here the start- ing point, A, of the line is a point in the head-block of the switch at Benton Station, O. & P. R. R. The point A is, of course, in the center line of the track. Set up the transit at A with the vernier at zero. Sight to a flag held at F on the center line of the track, O. & P. R. R. Loosen the vernier clamp, and turn the telescope sight to a flag held at B, the next point on the angle line ; clamp the vernier, and, by means of the tangent screw, ac- curately sight to the flag held at B; the angle reads 32° 30', and is record- ed R^ 32° 30', with a sketch showing the connection in which the term head-block is designated by the abbre- viation //^. ^. The bearing of the line A B can not be taken at A on account of the attraction of the rails. The instrument is now moved to B, the vernier set at zero and backsighted to A ; the bearing oi A B,^ 75° 00' E, is taken, and the number of sta- tion -5, 2 + 90, together with the bear- ing of A B, recorded. The telescope is then reversed, pointing in the di- rection B B'. The point C being de- termined, the upper clamp is loosened and the telescope turned to the right and sighted to C. The reading of the angle is found to be 14° 30', and re- corded R* 14° 30'. It measures the angle B' B C. The bearing of the line B C, N 89° 20' E, is then re- corded. The instrument is next set SURVEYING. 633 up at C, the vernier set at zero, backsighted to B, and then reversed ; the deflection to D, R' 10° 00', is then read and recorded, together with the number of the station at C, 6 + 85. This deflection measures the angle C C D, and Station. Defleetio-i Mag. Bearing. Ded. Bearing. Remarks. 13+63 End of Line. 10+31 L'30°00' y. 69°25'E. y. 69°30'E. :^^^ 6+85 B'10°00' 8. 80°30'E. S.80°30'E. ^^n. 2+90 R^14°30' N. 89°20'E. N.89°30'E. H nnf Stuilr.K N.75°00'E. 8taM\ at Benton Sta. gives the direction of the line C D. A good form of notes for such a survey is that given above. 1 242. Checking Angles by the Needle. — In spite of the greatest care, errors in the reading and recording of angles will occur. The best check to such errors is the magnetic needle. And though it is not an exact check, owing to the lack of precision in reading the needle and to local attraction, yet it is the only reliable one, and in universal use. In Fig. 269, we have an example of the use of the needle Fig. 269. G34 SURVEYING. in checking angles. The bearing of the line A B, which corresponds to y^ i^ in Fig. 208, is N 75" 00' E, and is assumed to be correct. The bearing of the line B C, as read from the needle, is N. 80° 20' E. Its deduced or calcu- lated bearing is obtained as follows: To the bearing of the line A B, N 75° 00' E, we add the R' deflection 14° 30'; the sum is 89° 30', which is recorded in the column headed Ded. Bearing. (See Art. 1241.) The deduced bearing, it will be seen, is ten minutes greater than the magnetic bearing as read from the needle and recorded in the column headed Mag. Bearing. Had the deflection angle been re- corded L* instead of R', the deduced bearing would have been the difference between 75° 00' and 14° 30', which is 60° 30', and would be recorded N 60° 30' E. The magnetic bearing being N 89° 20' E would have at once revealed the error. The confusion of the directions R' and L' is the com- monest source of error in recording deflections, though sometimes a mistake of ten degrees is made in reading the vernier. It is a wise precaution to read both angle and bearing after they are recorded and compare them with the recorded readings. 81^18^7 B TRIANGULATION. 1243. Simple Triangrulatlon. — Triangulation is an application of the principles of trigonometry to the measurement of in- accessible lines and angles. A common — -^ occasion for the use ' of trigonometry is illustrated in Fig. 270, where the line of survey crosses a stream too wide and deep for actual measurement. Set two points A and B on line, one on Fig. 270. SURVEYING. 635 each side of the stream. Estimate roughly the distance A B. Suppose the estimate is 425 feet. Set another point C, making the distance A C equal to the estimated dis- tance A B = 425 feet. Set the transit at A and measure the angle B A C = say 79° 00'. Next set up at the point C and measure the angle A C B -= say 5G° 20'. The angle A B C is then determined by subtracting the sum of the angles A and C from 180° ; thus, 79° 00' + 50° 20' = 135° 20'. 180° 00'- 135° 20'= 44° 40'= the angle ABC. We now have a side and three angles of a triangle given, to find the other two sides A B and C B. These sides may be easily found by the methods given for the solution of triangles (see Arts. '759, etc.) by drawing a line from the vertex of one of the angles A or C so as to divide the triangle ABC into two right-angled triangles. A simpler and easier method, however, is the following: In higher works on trigonometry, it has been demonstrated that, in any triangle, the sines of the angles are proportional to the lengths of the sides opposite to them. In other words, sin A : sin B :: B C : A C; or, sin A : sin C::B C : A B, and sin B : sin C::A C : A B. Hence, we have sin 44° 40' : sin 56° 20' :: 425 : side A B. Sin 56° 20' = .83228; . .83228 X 425 = 353.719; sin 44° 40' = .70298; 353.719 -^. 70298 = 503.17 ft. = side A B. Adding this distance to 76 + 15, the station of the point A, we have 81 + 18.17, the station at B. Another and frequent occasion for the use of trigonome- try is the following: Two tangents, A B and C D, Fig. 271, which are to be united by a curve, meet at some inaccessi- ible point E. Tangents (which will be more fully described later on) are the straight portions of a line of railroad. The angle C E F, which the tangents make with each other, and the distances B E and C E are required. Two points A and B of the tangent A B, and two points C and D of the tan- gent C D, being carefully located, set the transit at />', and. 636 SURVEYING. backsighting to A, measure the angle E B C = 21° A5' ; set up at C, and backsighting to D, measure the angle £ C B=21° 25'. Measure the side B C= 304.2 ft. F Angle C'^jp being exterior to the triangle E B C is equal (see Art. 1 1 94) to the sum of E B C and E C B =21° 45'+ 21° 25' = 43° 10'. The angle B £ C= 180° -C E E = 136° 50'. From the principle stated we have sin 136° 50' : sin 21° 45' :: 304.2 ft. : side C E. Sin 21° 45' = .37056; .37056 X 304.2 = 112.724352; sin 136° 50' = .68412; side CE=s, 112.724352 -r- .68412 = 164.77 ft. 4^ /50' ly •60 ~^ J .1^^ y FlO. 272. Again, we find B E by the following proportion: Sin 136° 50' : sin 21° 25' :: 304.2 : side B E\ sin 21° 25' = .36515; .36515 X 304.2 = 111.07863; sin 136° 50' = .68412; side^-£'= 111.07863-^.6841^=162.36 ft. SURVEYING 637 A building //, Fig. 272, lies directly in the path of the line A B which must be produced beyond H. Set a plug at B and then turn an angle D B C = 00°. Set a plug at C in the line B C, at a suitable distance from B, say 150 feet. Set up at C, and turn an angle B C D = 60°, and set a plug at D, 150 ft. from C. The point D will be in the prolong- ation of A B. Then, set up at D and backsighting to C, turn the angle C D D' = 120°. I) D' will be the line re- quired, and the distance B D will be 150 feet, since BCD is an equilateral triangle. A B and C D, Fig. 273, are tangents intersecting at some inaccessible point H. The line A B crosses a dock O P, too 038 SURVEYING. wide for direct measurement, and the wharf L M. /^ is a point on the Hne A B at the wharf crossing. It is required to find the distance B //and the angle F // G. At />, an angle of 103° 30' is turned to the left and the point E set 217' from B = to the estimated distance B F. Setting up at E, the angle B F F is found to be 39° 00'. Whence, we find the angle B F F = 1S0° - (103° 30' + 39°) =37° 30'. From the above principle we have sin 37° 30' : sin 39° 00' :: 217 ft. : side B F. Sin 39° 00' = .02932; .02932 X 217 = 130.50244; sin 37° 30' = .00870; side B F= 130.50244 ^ .00870 = 224.33 ft. Whence, we find the station of Fto be 20 + 17 -f- 224.33 = 22 + 41.33. Setup at F and turn an angle /TT^ 6^ = 71° 00', and set up at a point G where the line C D prolonged inter- sects/^ G. Measure the angle F G H — 57° 50', and the side F G = 180. 3'. The angle F H G =180° - (71° + 57° 50') = 51° 10'. From the same principle as before we have sin 51° 10' : sin 57° 50' :: 180.3' : side F H. Sin 57° 50' = .84050; . 84050 X 180. 3 = 152. 02395 ; sin 51° 10' = .77897; side FH= 152.02395 -^ .77897 = 195.93 ft. ; whence, we find the station of H to be 24+ 37.20. 1244. Vertical Angles. — A vertical angle is an ry p angle formed by two intersecting lines lying in the same vertical plane, one of which is horizontal. If the lines A B and A C, Fig. j M^ '-^L 274, lying in the vertical plane FIG. 274. D FFG, meet at the point A, and the line A B is horizontal, the angle C A B is a vertical angh\ and is measured by the arc B C. 1245. Intersection of Tangents. — Let A B and C D, Fig. 275, be tangents whose point of intersection is to SURVEYING. 639 be determined and the angle which they make with each other to be measured. First set up a flag or stake at B and another at ^, or some other point in the line A B. Set up the tran- sit at C, backsighting to D. Reverse the instrument. Have a flagman hold a rod in the line C D, at the same time putting himself in range with the stakes at A and B. With a little practice he can nearly determine the intersection / of the two lines. Then drive two stakes K and L firmly in the line C D, one on each side of the point /. Their dis- tance from the point / to be determined by the obtuseness '^y^C Angle of Intersection, \. -/ C Fig. 275. of the angle AID. Carefully center these stakes, driving a tack half its length in each center. Stretch a cord between these tacks. Next set up the instrument at B^ backsighting to A. Reversing the telescope, set a flag at /, which will be the intersection of the line A B prolonged with L D. Drive a stake flush with the ground at /and drive a tack in this stake where the prolongation of A B crosses the cord connecting the stakes at A' and L. The point /is the inter- section of the tangents A B and C D. The external angle C I M, formed by the intersecting tangents, is called the angle of intersection. CURVES. 1 246. A line of railroad consists of a series of straight lines and curves. In general, the straight lines, or, more properly, the tangents, are first located and then they are united by curves best fitting the ground lying between the tangents. There are certain limits of curvature prescribed for all roads, which must not be exceeded. These limits 640 SURVEYING. will depend upon conditions to be explained later. Rail- road curves are circular and are divided into simple, covi- pojind, and reverse curves. A simple curve has but one radius, as y^ ^5 in Fig. 276, whose radius is A C. A compound curve, shown in Fig. 277, is a continuous H Fig. 277. curve of two or more arcs of different radii, as C D E F, which is composed of the arcs C D, D E, and E F, whose respective radii are G C, H D, and K E. A reverse curve, Fig. 278, is a continuous curve com- posed of two arcs L M and M N oi the same or of different radii described in the opposite directions, and having a com- ^^ ~ / x mon point J/, called the point of reversal. Reverse curves, though common in the early days of railroad building in the United States, are now con- P'^- *"*• demned for roads of standard gauge, and only admitted for narrow-gauge roads, when cheapness of construction is the first requirement. 1247. Geometry of the Circle. — Before attempting to lay out curves, a knowledge of geometry relating to the circle must be mastered. The following propositions are of special importance: 1. A tangent to a circle is perpendicular to the radius drawn through its tangent point. Thus, A E, Fig. 279, is perpendicular to B O, and C E is perpendicular to C O. SURVEYING. 641 2. Two tangents drawn to a circle from any point are equal, and if a chord be drawn joining these points, the angles between the chord and the tangents are equal. Thus, B E and C E are equal, and the angles E B C and E C B are equal. 3. An acute angle between a tangent and a chord is equal to half the central angle subtended by the same chord; thus, the angle EBC=ECB = one-half B O C, 4. An acute angle subtended by a chord, and having its vertex in the circumference of a circle, is equal to half the central angle subtended by the same chord. Thus, the angle E B 6", whose vertex B is in the circumference and subtended by the chord B G, is equal to half the central angle BOG, subtended by the same chord B G. 5. Equal chords subtend equal angles at the center of a circle and also at the circumference, if the angles are 642 SURVEYING. inscribed in similar segments. Tlius, i( B,G, G H, H K, and /: Care equal, B O G= GO iT'and G B H = H B K. 6. The angle of intersection of two tangents equals the central angle subtended by the chord uniting the tangent points. Thus, the angle C E F= B O C. 1 248. Deflection Angeles. — When two lines meet in the same plane, they are said to form an angle, and the point of meeting is called the angular point. The rate of diver- gence or deflection of the two lines from their common or angular point determines the size of the angle. The unit of angular measurement is the degree, equal to g-^ part of a circle. Two lines forming an angle of one degree with each other will, at a distance of one hundred feet from the angular point, deflect or diverge 1.745 feet. In Fig. 280, the lines A B and A C, meeting at the point A, are supposed to form an angle of 1°, and the angle BAG is measured by the arc B C, described with the radius A B, Fig. 280. which is 100 feet in length. The arc B C and the straight line joining the extremities of that arc, i. e., the chord B C, are assumed to be of equal length. 1249. Degree of Curvature. — The curve from which, as a unit or basis, all other railroad curves are deduced, is called a one-degree curve. It is the circum- ference of a circle whose radius is 5,730 feet, or, more exactly, 6,729.05 feet, in length. Two radii forming an angle of one degree at the center of a one-degree curve will subtend a chord of 100 feet at its circumference. The arc subtended by this chord of 100 feet is assumed to be of the same length as the chord. In Fig. 281, let A B and A C he radii 5,729.05 feet in length, forming an angle of 1° at the center A ; then the arc B C subtended by these radii will be 100 feet in length. The curve B Ci^ called a 1° curve. If, from the point (? as a SURVEYING. 643 center, with a radius O B equal to 2,864.93 feet, we describe an arc B D 100 feet in length, the radii O B and O D will Bz5729,^LSi Fig. 281. form an angle of 2° at the center O, and the curve B D is called a 2° curve. A curve whose radius is nearly one-third A B, or 1,910.08 feet, is a 3° curve, etc. The deji^ree of a curve is determined by the central angle, which is subtended by a chord of 100 feet. Thus, if B O G {Fig. 282) is 10° and B G is 100 feet, B G H K C is a 10° curve. Fig. 288. The deflection an^le of a curve is the angle formed at any point of the curve between a tangent and a chord of 100 feet. The deflection angle is, therefore, balf the degree 044 SURVEYING. of the curve. Thus, if the chord B G is 100 feet, the angle E B G is the deflection angle of the curve B G H K C, and is half the angle B O G. Example.— Given the deflection angle EB G = D (Fig. 283), to find the radius ^ C> = /?. Solution. — Draw O Z perpendicular to B G. In the right-angled triangle B O L, we have sin BOL = ^^; hut BO L = E B G = D, since OL being perpendicular to the chord B G it bisects the arc BLG. But the angle Z> = ij5(?G; hence, angle i5C>Z= A BL=z 50 feet and the radius BO = R. Substituting these values in the 50 given equation, we have sin D — —\ whence, j^ sin /? = 50, and we have the formula ^ = 7iF3- (89-) For curves of from 1° to 10°, the radius may be found by dividing 5,730 ft. (the radius of a 1° curve) by the degree of the curve. The re- sults obtained are sufficiently accurate for all practical purposes. For sharp curves, i.e., for those exceeding 10°, the above formula, viz., 50 R — —. — =; should be used, especially if the radii are to be used, as a sm Z> basis for further calculation. For example, the radius of a 4° curve is found by both methods as follows: By first method, /? = 5,730 ft. -5- 4 = 1,433.5 ft. By second method, we find the deflection angle Z> of a 4° curve is 2°. Applying the formula, R = -^~-^, we have R = -—rr = 1,432.67 ft. sm Z> .0349 In this case the error is only .27 foot, and may be ignored in prac- 5 730 tical work. For a 30° curve we have by first method, R = ' . =191 50 50 ft. By second method, we have R = -: — r^^ = ^..^^^ = 193.18 ft. In ■^ sm 15 .25882 this case the error is 2.18 ft., and the error increases as the degree of curve increases. The radii given in the table of Radii and Deflections are calculated . r . „ 50 by the formula R = —. — j^. ■' sm D 1250. Sub-Chords for Curves of Short Radii.— On curves of short radii, i. e., curves of 20° and upwards, center stakes are driven at intervals of 25 feet. In Art. 1248, we stated that the standard chord and arc are as- sumed to be of the same length. This is practically true SURVEYING. G45 for curves of large radii, but for curves above 20° the excess of length of arc over the chord constantly increases. If, now, in Fig. 282, the chord B C is 100 feet in length, the arc B G H K C must be greater than 100 feet; and if the arcs B G, G H, H K, and K C are equal, i. e. , each equal to one- quarter the arc B H C, then the equal chords B G, G H, H K, and K C subtending these equal arcs must each be greater than one-quarter of B C, which we assumed to be 100 feet. These greater chords must, therefore, be greater than 25 feet. Suppose the curve B H C to be a 20° curve, and the chord B C, 100 feet ; then the central angle B O C is 20°. As the arc B G is one-quarter of the arc B H C, the 20° central angle B O G \s ~ = 5°. The line O L, drawn to the middle point of the chord B G, is perpendicular to B G and bisects the angle BOG. The deflection angle E B G = B O L ^ G O L. Let C designate the chord B (7, 7?, the radius O B and D, the deflection angle, E B G = B O L. In the right-angled triangle B O L, we have sin B O L = L> T -fTj)- Substituting the above given values, we have sin 1 (^ D = ^^jT-, whence \ C ^^ R sin D, and we have C=1 RsmD. (90.) The central angle for the chord B G is 5°. The deflection angle D is, therefore, |° = 2° 30'. Sin 2° 30' =■ .04362. Since the deflection angle E B C = 10° for this case, R =■ 50 ^ sin 10° = 287.94 ft. Hence, chord 6" = 2 X 287.94 X .04302 = 25.12 ft. Accordingly, in measuring the short chords, 25.12 feet should be used instead of 25 feet. 1251. Tangent Distances. — When an intersection of tangents has been made and the intersection angle meas- ured, the next question is the degree of curve which is to unite them, which being decided, the next step in order is the location of the points on the tangents where the curve 640 SURVEYING. * begins and ends. These two points are equally distant from the point of intersection of the tangents, which is called the P. I. The point where the curve begins is called the point of curve, or the P.C. ; the point where the curve terminates is called the point of tangent, or the P. T. The distance of the P. C. and P. T. from the P. I. is called the tangent distance. In Fig. 282, let A B and C Dht, tangents intersecting at the point E and forming an angle C E F=^ 40° 00' with each other. It is decided to unite these tangents by a 10° curve whose radius is 573.7 feet. Call the angle of intersection /, . the radius B O, R, and the tangent distance B E, T. From Art. 1247, proposition 6, we have B O C= C £ F; hence, the angle B O E = ^ C E F. From the right triangle E B O BE we have tan B O E = -75-7^. x> U T Substituting the above equivalents we have tan ^ /= -p, whence T = R tzn ^ F. (91.) In our example R = 573. 7 f t. ; ^ / = 20° ; tan 20° = . 36397. 573.7 X .36397 = 208.81 ft. Measure back from the point E on both tangents the distance 208.81 ft. to the points B and C. Drive plugs flush with the ground at both points and set accurate center points, marked by tacks, in both. Di- rectly opposite each of these plugs drive a stake called a guard stalce, because it guards or rather indicates where the plug is. The stake at B, if the numbering of the stations runs from B towards C, will be marked P, C, and the stake at C marked P. T. 1252. To Lay Out a Curve With a Transit.— Having set the tangent points B and C, Fig. 282, set up the transit at />, the P. C. Set the vernier at zero and sight to E, the intersection point. Suppose B to be an even or "full station," "say 18, and that it has been decided to set stakes at each hundred feet. Let the central angle B O 6\ measured by the 100-feet chord B G, be 10°; then, the deflection angle E B G, whose vertex B is in the circum- SURVEYING. 647 ference and subtended by the same chord B G, will be ^ B O G ox 5°. Turn an angle of 5° from B, which in this case will be to the right; measure a full chain, 100 feet, from B and line in the flag at G ; drive a stake at 6", which will be marked 19. Turn off an additional 5° making 10° from zero, and at the end of another chain, at //, set a stake marked 20. Continue turning deflections of 5° until 20° or one-half of the intersection angle is reached. This last deflection, if the work has been correctly done, will bring the head chainman to the point of tangent C. It is but rarely that the P. C. comes at a full station. When the P. C. comes between full stations it is called a sub- station, and the chord between it and the next full station is called a sub-chord. Had the P. C. of the curve come at the sub-station, say 17 + 32, the deflection for the sub-chord of 100 — 32 or 68 feet, the distance to the next station, is found as follows: The deflection for a full station, i. e., 100 feet, is 5° = 300', and the deflection for 1 foot is 1^ = 3', and for 68 feet the deflection will be 68 X 3 = 204' = 3° 24', which is turned off from zero and a stake set on line, 68 feet from the transit, at Station 18. The length of a curve uniting two given tangents whose intersection angle is determined, is found as follows: Suppose / = 32° 40', and that the tangents are to be united by a 6° curve ; 32° 40' reduced to the decimal form is 32.666° ; as each central angle of 6° will subtend a 100-foot chord, or one chain, there will be as many such chords or chains as 6 is contained times in 32.666, which is 5.444, that is, there will be 5.444 chains in the curve, or 544.4 feet, which is the required length of the curve. The P. C. and P. T. having been set and the station of the P. C. determined by actual measurement, say 58 + 71, the station of the P. T. is found by adding to 58 + 71, the station of the P. C, the calculated length of the curve, 544. 4 feet. 58 + 71 + 544. 4 = 64 + 15. 4, the station of the P. T. Another method of calculation is the following: The sum of all the deflection angles is equal to one-half the intersection 648 SURVEYING. angle. The intersection angle being 32° 40', one-half equals 10° 20', which, reduced to minutes, equals *.»8()'. The deflection for 100 feet is -° = 3° = 180', and the deflection Z 180 for 1 foot ^s—-' = 1.8'; then, 980', the total deflection, di- vided by 1.8', gives 544.4 feet, the required length of the curve. EXAMPLES FOR PRACTICE. In the following examples, let /= angle of intersection, 7" = tan- gent, and L = length of curve. 1. /= 16° 13', degree of curve = 3°, required, 7" and L. Ans.j ^=272.13 ft. ( L = 540.55 ft. 3. /= 59° 20', degree of curve = 8° 30', required, T'and L. Ans \ ^'=384.32 ft. ^"'- \ L = 698.04 ft. 3. /= 21° 35', degree of curve = 4° 15', required, 7" and L. Ans \ 7^=257.03 ft. ^"'- I Z = 507.84 ft. 4. The degree of a curve is 5° 30' ; what is the deflection angle for a chord of 16.2 feet ? Ans. 26.7'. 5. The degree of a curve is 7° 15' ; what is the deflection angle for a chord of 38.4 feet ? Ans. 1° 23^'. 1253. Obstructions in tlie Line of Curve. — Fre- quently it happens that the entire curve can not be run in from the P. C. on account of obstructions. This is especi- ally the case in either hilly or wooded country, and the transit has to "move up" to an intermediate point. For example, in Fig. 282, we will suppose that Station //, 200 feet from B, is the last point which can be set from the P. C. at B. A plug is driven at // flush with the ground and carefully centered, and a tack driven at the point. The deflection angle E B H is 10° to the right. The transit is set up at //, an angle of 10° to the left is laid off from zero, and the vernier clamped. The instrument is then sighted to a flag at />, the spindle clamped, and a close sight to the flag taken, the lower tangent screw being used to adjust the sight. The vernier clamp is then loosened and the vernier SURVEYING. 649 set at zero. The line of sight will then be on a tangent to the curve at H^ and the deflection angles to K and C can be laid off as before and the stations K and C located. 1 254. Tangent and Chord Deflections.— Let A B in Fig. 283 be a tangent, and B C E H 2i curve commencing at B. Produce the tangent A B to the point D. The line C D vs, 2i tangent deflection, and is the perpendicular distance from the tangent to the curve. If the chord B C be produced to the point 6", making CG^=BC=^C E, the distance G E is 2i chord deflection and is double the tangent deflection D C. 1255. Given the radius B O = R, Fig. 283, to find the chord deflection E G and the tangent deflection C D = E E. ^ Fig. 283. The triangles O C E and C E G are similar, since both are isosceles, and the angle G C E = angle C O E. Hence, 050 SURVEYING. we have O C '. C E::C E \ E G. Denoting the chord C E by c and the chord deflection E G by d^ we have, from the above proportion, R \ cv.c \ d. Therefore, ri ^ ^=-^. (92.) To find the tangent deflection, draw C E to the middle point of E G. By Art. 1254, E E = D C = the tangent deflection. Hence, tangent deflection = one-half the chord deflection, from which tangent deflection = --75. (93.) 1256. Practical Method of Determining Tan- gent and Chord Deflections. — Let it be remembered for a basis of calculation that the chord deflection for a one- degree curve, the chord being 100 feet in length, is 1.745 feet; for a 2° curve, double the deflection for a 1° curve, or 3.49 feet, and so on. The tangent deflection being one-half the chord deflection, for a 1° curve it will be .873 foot, for a 2° curve it will be 1.745 feet, etc. Distances measured either on chords or tangents are expressed in decimal parts of a station, which is 100 feet, and Pig. 284. is assumed as 1. Thus, the tangent deflection for 75 feet will be expressed as the tangent deflection for .75 of a station. This expression is, however, confined entirely to SURVEYING. G51 the calculation, and is spoken of as the tangent deflection for 75 feet. Fig. 284 will be used to demonstrate the principle upon which tangent deflections are based. Let A B he a. tangent, and B the P. C. of a 2° curve to the right. We determine the chord deflection for 100 feet chord of a 2° curve to be 3.49 feet. The tangent deflection is one-half the chord deflection, or 1.745 feet. Let B C = 100 feet, a full station (which express as 1), then CL, the tangent deflection at C, will = 1.745 feet, for, since this is a 2° curve, the chord deflection = 1.745 X 2, and the tangent deflection = — — = 1.745 ft. To find the tangent deflection for any intermediate point G, 75 ft. from B, express the distance as a decimal of the full station, or, in this case, .75. Square the decimal thus formed, and multiply by the tangent deflection, in this case, 1.745; the result Avill be the tangent deflection for the point considered. Thus, the tangent deflection for the point is the line G K, and the length of 6^ A^ = . 75" X 1.745 ==.562 X 1.745:= .981 ft. For the point /?, 125 ft. from B, the tangent deflection is D M, and the length of D M is found as above. Thus, to express 125 as a decimal of a full station, divide 125 by 100, obtaining 1.25. Then 1.25" X 1.745 = 1.562 X 1.745 = 2.725 ft. In the above, we have assumed that the chord and the corresponding tangents were of equal length; i. e., that B 1= B F, B K— B G, etc. This is not strictly true, but is near enough for all practical purposes, particularly when the degree of the curve is small. 1257. Laying Out Curves Without a Transit.— During construction, the engineer is often called upon to restore center stakes on a curve when the transit is not at hand. With the aid of a tape and a few stakes for lining in, a line can be run closely approximating the true one, by applying the principle demonstrated in Art. 1256. A practical application of this principle is shown in G52 SURVEYING. Fig. 285, in which A B is a tangent, B the P. C. of a 4° curve RK The chord deflection of a 4° curve for 100 feet chord is G.98 ft. The tangent deflection = \ the chord deflection, is 3.49 ft. Let B = Sta. 8 + 25, a stake at each full station on the curve being required. Restore the stakes at A and B, which will determine the P. C, and give the direction of the tangent A B. The distance from the P. C. to the next full station C is 75 feet or .75 of a full station; .75* X 3.49 = .502 x 3.49 = 1.9G ft., the tangent deflection at C. The engineer being without a transit, the point C is found by measuring 75 feet from B and setting a stake at C in line with a stake at B, the P. C, and a point A B C Pig. 285. on the tangent ^ .5 as A. With a tape, measure the dis- tance 1.9G ft. from C at right angles to B C, and drive a stake at that point /% which will be Station 9. Measure 100 feet from F and set a point at D in the line B F. By previous calculation, we know the chord deflection for 100 feet is G.98 ft. Measure the distance 6.98 ft. at right angles to the line FD and drive a stake at G, which will be Station 10. In like manner set the remaining Station 11, which is previously known to be the P. T. Although the chord deflection Z^ C is not theoretically at right angles to F D, yet D G is so small compared with FD that for curves of ordinary degree the offset is made at right angles. SURVEYING. 653 EXAMPLES FOR PRACTICE. 1. The degree of curve is 5", the chord 67 ft. ; what are the tangent and chord deflections ? . . ^ Tan def. =1.959 ft. "^' "I Chord def. = 3.918 ft. 2. The degree of curve is 7^ 30', the chord 23.5 ft. ; what are the tangent and chord deflections ? . \ Tan def. = .359 ft. "^' 1 Chord def. = .718 ft. 3. The degree of curve is 6" 15', the chord 117 ft. ; what are the tangent and chord deflections ? . ( Tan def. = 7.465 ft. "^' 1 Chord def. = 14.930 ft. 1258. To Determine Degree of Curve by Meas- uring a Middle Ordinate. — In track work, it is often necessary to know the degree of a curve when no transit is available for measuring it. The degree can be found by measuring the middle ordinate of any convenient chord, and multiplying its length by 8, which will give the chord deflec- tion for that curve. Let A B, in Fig. 286, be a 50-foot chord, measured on the track, and let the middle ordinate ^ <^ be .44 ft. .44 X 8 = 3.53 = chord deflection for 6.44' 50', which, expressed in ^. decimal part of a full sta- 50' tion, is.5; .5' = .25. The fig. 286. chord deflection for 100 feet multiplied by .25 = the chord deflection for 50 feet, which we know by calculation to be 3.52 feet. Hence, 3.52-^.25 = 14.08 ft., the chord deflec- tion for 100 feet, which, divided by 1.745, the chord deflec- tion for a 1° curve, gives a quotient of 8.07, nearly. The inference is that the curve is 8°. EXAMPLES FOR PRACTICE. 1. Length of chord is 50 ft., middle ordinate .35 ft. ; required, de- gree of curve. Ans. 6° 25.08'. (The original curve probably 6' 30.) 2. Length of chord 40 ft., middle ordinate .21 ft. ; required, degree of curve. Ans. 6' 1.02'. (The original curve probably 6°.) 3. Length of chord 25 ft., middle ordinate .22 ft. ; required, degree of curve. Ans. 16° 8.28 . (The original curve probably 16".) G54 SURVEYING. 1259. Field Books. — To facilitate the field work of the engineer, field books have been published. They are portable, being carried in the pocket, and contain, in con- densed form, general directions for the conduct of field work, together with all the necessary data in the form of tables, for prosecuting such work with accuracy and dispatch. One of the first published in America is the work of John B. Henck, to whom most American engineers are under obligation. 1 260. Note Books. — Various styles of note books are published, the pages being ruled to suit the particular kind of work being done. They are of three classes, viz., transit, level, and topography books. The latter are ruled in squares, which may be given any desired scale and greatly facilitate the accurate platting of topography in the field. 1261. How to Keep Transit Notes. — A good form for location notes is the following: SutUm, OifltclioH IU.An9U M»f. Bemrinf. De4. Btmring. Bern June 90. 1994 trk*. 9 T «i*S 4°54'e.T tfiX/ if.as'io'g. tr. afia'g. t-no 4''00' ^ * 9°00' ■ ""V ffi^^ 9-Hm 9'00' 4*80 ^^••' « t°OV S*40 $«^»" 4*90 »•«»' S°W 4 *■>»«' I»t.AufU-iS°00' 4'Cun*V *HU> o-w T.-19>i.9t ft. Dtf. Amflt f*r aOfttfOO 9**0 f.C4°M* r.Ci-3*90 D*f.AmfUf»r tft.-l.r 9 L»»0a •/ 0mrmt-9nft 9 r.l>4*05 1 O -. a.9ois'M. 11.90° tS"*. In the first column the station numbers are recorded. In the second column are recorded the deflections with the abbreviations P. C. and P. T., together with the degree of curve and the abbreviation R' or IJ, according as the line curves to the right or left. At each transit point on the SURVEYING. 655 curve, the total or central angle from the P. C. to that point is calculated and recorded in the third column. This total angle is double the deflection angle between the P. C. and the transit point. In the above notes, there is but one intermediate transit point between the P. C. and the P. T. The deflection from the P. C. at Sta. 3 + 20 to the inter- mediate transit point at Sta. 4 + 50 is 2" 36'. The total angle is double this deflection, or 5° 12', which is recorded on the same line in the third column. The record of total angles at once indicates the stations at which transit points are placed. The total angle at the P. T. will be the same as the angle of intersection, if the work is correct. When the curve is finished, the transit is set up at the P. T., and the bearing of the forward tangent taken, which affords an additional check upon the previous calculations. The magnetic bearing is recorded in the fourth column, and the deduced or calculated bearing is recorded in the fifth column. 1 262. Preservation of Notes and Records. — Notes should never be erased. If, on account of error or change of plan, they should cease to be of any value, they are crossed out, i. e., two diagonals are drawn across the page. All notes of permanent location should be copied each day into a separate book for office reference, to prevent confusion, and for record in case the original notes should be lost. LEVELING. 1263. A Level Surface. — A level surface is one parallel to the surface of standing water. A water surface, though not theoretically level, owing to the curvature of the earth's surface, is assumed to be level and perpendicular to a vertical line, or the line of gravity. The height of a point is its distance above a given level surface, measured on a vertical line, and is called its elevation. The process by which the elevation of a point is determined is called leveling. 65G SURVEYING. 1264. Tlie Three Processes of Determining: Elevations. They are : 1st. By direct leveling. 2d. By indirect leveling ; and 3d. By barometric leveling. 1265. Direct Leveling. — In the process of direct leveling, a level line either actual or visual is prolonged so as to pass directly over or under the given point whose eleva- tion is required. The elevation of any other point being determined in the same way, the difference in the elevations of the two points is found by subtracting the elevation of the lower from the elevation of the higher. 1266. Indirect Leveling. — In the process of indirect leveling, elevations are determined by means of lines and angles. 1267. Barometric Leveling. — In barometric level- ing the elevation of a point is determined by the weight of the atmosphere at that point as registered by a barometer. The second and third processes will be explained later. DIRECT LEVELING. 1268. General Principles. — Direct leveling depends upon three principles, two of which have already been stated, viz. : First, that the surface of a liquid in repose is level; second, that a vertical line is perpendicular to that surface, and, third, that a bubble of air confined in a vessel otherwise filled with liquid will rise to the highest point of that liquid. A common application of the third principle is seen in the spirit level used by carpenters and the level board used by masons. 1269. The " Y " Level. — There are a great variety of instruments for determining elevations. The one in most general use is the " Y " level, shown in Fig. 287. This instrument consists of an erecting telescope A B, i. e., one which shows the image of the object to which the telescope is directed in its erect or natural position, resting in Y-shaped supports C and D, from which it takes its name. SURVEYING. 657 The line of sight, or collimation, is identical to that in the transit explained in Art. 1225, and is parallel to the level E F. The tube containing the eyepiece G has an exterior ring //, which is milled to assist the hand in turning the tube. This movement adjusts the eyepiece to the cross- hairs. The object glass at B is moved in or out by the milled headed screw A'; L and J/are parallel plates; the bar O P supports the Y's and revolves on a spindle which is FIG. 287. clamped by the screw N. By means of the tangent screw X, the telescope can be slowly turned horizontally. The tele- scope is leveled by means of the leveling screws F, Q^ R, and S. The level is supported by the tripod T. The cross-hairs are of either platinum wire or spider threads, and are fastened to a ring which is held in place by capstan screws shown at U, and their movements are regulated in the same way as the movements of the cross-hairs of the transit explained in Art. 1225. fi58 SURVEYING. 1270. The Bubble Tube. — The bubble tube is of glass bent upwards and so nearly filled with alcohol that only a bubble of air remains, which is always at the highest point in the tube. This tube is protected by a brass case, which is fastened to the underside of the telescope, and provided with the means for adjustment. The one end may be raised or lowered and the other end moved horizontally. Through a slit in the upper side of the case, the bubble tube is seen. Directly over it is a scale graduated in both directions from zero, which is over the center of the tube. The Y's C and D support the telescope, which is held in place by hinged clasps, or clips, as they are called, fastened by carefully turned pins, by means of which the tele- ' scope can be firmly held in any desired position. The Y's rest upon the bar O P, to which they are fastened by lock- nuts, the one above, the other below, the bar, for raising or lowering. The bar revolves upon a finely turned steel spindle, resting in a socket of bell metal. The parallel plates L and J/ are united by a ball-and-socket joint, and held in place by the leveling screws V, Q, R, and S. 1271. Adjustments. — The first thing todo in prep- aration for actual leveling is to make the adjustments of the instrument. There are three adjustments, as follows: 1. To make the line of collimation parallel to the bottoms of the collars, or rings, on which the telescope rests. 2. To make the plane of the level parallel to the line. of collimation, or to the bottom of the collars. 3. To cause the bubble to remain in the center of the tube while the telescope is being revolved horizontally. 1 272. First Adjustment. — To make the line of colli- mation parallel with the bottoms of the collars. Plant the tripod firmly ; choose some distant and clearly defined point, the more distant the better so long as the sight is distinct. Remove the pins from the clips and clamp the spindle, bringing the intersection of the cross-hairs to SURVEYING. 659 exactly bear on the ^point by means of the tangent screw. Revolve or turn the telescope on its supports through one- half a revolution, i. e., until it is bottom side up. If the intersection of the cross-hairs is still on the point of sight, it proves that the line of collimation is parallel to the bottoms of the collars. If, however, the line of sight is no longer on the point, move the cross-hairs by means of the capstan* headed screws over one-half the space which measures the apparent error, being careful to move them in the opposite direction to that in which it would appear they should be moved. The apparent error is double the real error, and is explained in Fig. 288. Let the instrument stand at A and sight to the point B^ and suppose that when the telescope has been revolved half way around, the point B appears to be at C, then will the _4 n ' I \ Fig. 288. distance B C h(t double the real error, and the true line of sight will be at D, half way between B and C. Sometimes both cross-hairs are out of adjustment and they must be moved alternately until the intersection of the cross-hairs, i. e., the line of collimation, will pass through the same point throughout a complete revolution of the telescope. 1273. Second Adjustment. — The second adjustment is to make the plane of the level parallel to the line of colli- mation, or to the bottoms of the collars, and is made as follows: Remove the pins and open the clips; place the telescope over a pair of leveling screws and clamp the spindle. Bring the bubble to the middle of the tube by means of the level- ing screws, and revolve the telescope through an eighth of a revolution. The bubble tube will stand out at an angle with the Y's. If the bubble runs it shows that a vertical plane passed through the longitudinal axis of the bubble tube is not parallel to a vertical plane passed through the line of 6G0 SURVEYING. collimation. To correct the error, bring the bubble nearly back by means of the check nuts which regulate the lat- eral movement of the tube, and repeat the operation until the bubble ceases to run while the partial revolution is made. To complete the bubble adjustment, level the telescope and take it out of the Y's and turn it "end for end." If the bubble remains in the center of the tube, the second adjust- ment is complete. If it runs to one end, bring it half way back by means of the check nuts provided for raising or lowering one end, and the rest of the way, i. e., to the middle of the tvibe, by means of the leveling screws. Re- peat the operation, as the adjustment can rarely be made with one trial. 1274, Third Adjustment, sometimes called the *' Bar Adjustment." — This is to cause the bubble to re- main in the center of the tube while the telescope is being revolved horizontally. Level the instrument, using both sets of leveling screws. Having centered the bubble carefully with one pair of level- ing screws, turn the telescope until it stands directly over the other pair of leveling screws. If the bubble runs, bring it half way back by means of the locknuts at the end of the level bar and complete the leveling with the leveling screws. Repeat the operation, as two or three trials will probably be necessary to complete the adjustment, so that the bubble will remain in the center of the tube throughout an entire horizontal revolution of the telescope. The adjustments of the level should be tested every day when in constant use, as any defect in them will detract from the value of the work done, and a serious defect will necessitate a repetition of the work. The cross-hairs are placed at right angles to each other, one of which should be vertical and indicate to the leveler whether the leveling rod is being held plumb. If the verti- cal cross-hair is "out of plumb," adjust it by loosening the capstan screws which hold the ring, to which the cross-hairs are fastened. Suspend a plumb-bob at a suitable distance SURVEYING. 661 from the level, and having sighted to it, tap the capstan screws sufficiently hard to cause the cross-hairs to move. In this way the vertical hair can be made to coincide with the plumb line, which is a true vertical. 1275. Sensibility. — The sensibility of the level de- pends directly upon the radius of the curve of the bubble tube. The graduated scale placed directly over the bubble tube measures the movement of the bubble. The sensibility of the level may be determined as follows: Having leveled the instrument, take a reading on the rod held say 200 feet from the instrument. Suppose this reading to be 5.61 feet; with the leveling screws cause the bubble to move over one division of the scale. Suppose the rod then reads 5. 03 feet. Denote the radius of the bubble by x. Fig. 289, the distance 5.61' Fig. 289. of the rod from the instrument by d, the difference of rod readings by /i, and the movement of the bubble by 5. From the approximately similar triangles we have h : S :: d : x. or .03 : .01 :: 200 : x, whence x = of the bubble tube. 2.00 .02 = 100 feet, the radius 1276. Use and Care of the Level. — The level should not be used in rainy weather if it can be avoided. Moisture obscures the lenses and is otherwise injurious to the instrument. When rain is unavoidable, wipe the lenses frequently with a soft linen handkerchief, and when re- turned to the office or camp, thoroughly wipe, finishing with a piece of dry chamois skin and place in a warm, dry place so that every particle of moisture may be removed. Never 662 SURVEYING. carry the level with the spindle clamped. This rule is especially important when working in a wooded country where underbrush is dense. When undamped, the level turns freely upon the spindle and yields readily to any pres- sure. A blow which would inflict no injury upon an uu- clampcd instrument might seriously damage one while clamped and rigid. X'il'l. Poiiver and Definition. — The power of a tele- scope is measured by the apparent nearness to which the image of the object is brought to the eye of the observer. The definition of a telescope is measured by the degree of clearness of the outline of the image. 1278. Target Rods. — Target rods are divided into two classes, viz., those which are self-reading, or speaking rods, and those which are not self-reading. Railroad work is done chiefly with a self -reading rod. That in most general use is called the Philadelphia rod, and is shown in Fig. 290. It is in two sections held together with brass clamps A and B, one section sliding over the other. When closed, the rod measures 7 feet, sliding to 12 feet. It is graduated to feet, tenths, and hundredths. The feet are marked in large red figures, half above and half below the marks of division; tenths of feet are marked in black figures from 1 to 9, the lines of division reaching half way across the face of the rod; hundredths are marked by lines yijy of a foot in width, alternating white and black, and extending about one-third the way across the face of the rod. The target is either circular or elliptical and divided into quarters, alternating red and white. The division lines are so arranged that when the rod is held in a vertical position one of them will be horizontal Fig. 290. and the other vertical. The target C is fast- ened to a collar which slides up and down the rod, and is SURVEYING. 663 fitted with a screw Z>, which clamps it at any desired point. An opening more than one-tenth of a foot in length is cut in the face of the target. A vernier is fastened to the target whose zero point exactly coincides with the line which divides the target horizontally. It lies within the opening, on the face of the rod, and reads to thousandths of a foot. To prevent wear, the foot of the rod is shod with brass. Rod readings under 7 feet are usually taken with the two sections closed, and the target moved up or down until the horizontal line on the target coincides with the horizontal cross-hair of the telescope. When readings of more than 7 feet are taken, the clamp at B is loosened and the sliding section moved upwards until the horizontal line of the target and the hori- zontal cross-hair of the telescope coincide. The rod is then clamped, and is called a long or higli rod, and can be read to thousandths with the vernier attached to the collar at B. In setting the target, the leveler should read the rod as closely as he can with the level, calling the reading to the rodman, who sets the target at the given reading and holds the rod up for a check reading. Four times out of five the leveler's reading will be the correct one, even to thou- sandths. More mistakes are made in reading the number of feet than the number of tenths. The leveler by first calling the reading to the rodman will be certain to prevent such an error, as it would at once be detected in the check reading. An experienced rodman can hold a rod practically plumb, and for all ordinary work his care is considered sufficient. For work requiring the greatest possible accuracy, such. as bridge foundations, a hand level, which fits closely to the angle of the rod and carries two small spirit levels, is used to accurately plumb it. In using a rod which is not self reading, all readings are taken with the target. 1279. Examples in Direct Leveling. — The princi- ples of direct leveling are illustrated in Fig. 291. Let A be the starting point, which has a known elevation of 20 feet. The instrument is set at B^ leveled up, and sighted to a rod held at A . The target being set, the reading, 664 SURVEYING. 8.42 feet, called a backsight, is the distance which the point where the line of collimation cuts the rod is above the point A, and is to be added to the elevation of the point A. 20.00 + 8.42 = 28.42 is called the height of instrument and designated H. I. The instru- ment being turned in the opposite direction, a point C is chosen, which must be below the line of sight. This point is called a turn- ing point, and is designated by the abbreviation T. P. Drive a peg at C or take for a turning point a point of rock or some other perma- nent object upon which the rod is held. The reading at this point is a foresight, and is to be sub- tracted from the height of the instrument at B to find the ele- vation of the point at C. Let the rod reading be 1.20 ft. As this reading is a foresight, it must be subtracted from 28.42, the height of instrument at B; 28.42 - 1.20 = 27.22', the ele- vation of the point C. As the ground rises abruptly, the rodman should slide the rod to its full length, being careful to keep it on the same point C. The leveler car- ries the instrument to D, which should o be of such a height ■^-^ above C that when SURVEYING. 665 leveled up the line of sight will cut the rod near the top. The backsight to fT gives a reading of 11. 5G ft., which, added to 27.22 ft., the elevation of C, gives 38.78 ft., the height of the instrument at D. The rodman then goes to E, a point where a foresight reading is 1.35, which, subtracted from 38.78, the H. I. at D, gives 37.43 feet, the elevation of E. The level is then set up at F, being careful that the line of sight shall clear the hill at L. The backsight 6.15 ft. added to 37.43 ft., the elevation of E, gives 43.58 ft., the H. I. at F. The rod held at G gives a foresight of 10.90 ft., which, subtracted from 43.58, the H. I. at F, gives 32.68, the elevation at G. Again moving the level to H, the backsight to G of 4.39 ft. added to 32.68, the elevation of G, gives 37.07 ft., the H. I. at H. Holding the rod at A' a foresight of 5.94 subtracted from 37.07 gives 31.13, the elevation of the point K. The elevation of the starting point A is 20.00 ft.; the elevation of the point K '\s found by direct leveling to be 31.13 ft., and the difference in the elevations of A and K is 31.13 — 20.00 = 11.13 ft. ; that is, the point A' is 11.13 feet higher than the point A. 1280. A Datum Line. — A datum line is the base line to which the elevation of every point of a series is re- ferred. Thus, in Fig. 291, the datum line or plaice is 20 feet lower than the point A, and the elevations of the points A, B, C,D . . . .K are their elevations above this datum line. Such a series of elevations is called a line of levels. 1281. Turning Points. — Turning points, men- tioned in Art. 1279, are the points where backsights and foresights are taken. The backsights are plus (-f-) readings, and are to be added; the foresights are minus ( — ) readings, and are to be subtracted. The rodman should make a peg of well-seasoned oak, or other hard wood, about 9 inches in length, 1 inch in diameter, sharpened at one end and rounded at the other end, which is the turning point. For driving the peg he should carry in a leather scabbard a light hatchet. A point for a foresight having been deter- mined, the rodman drives the peg firmly in the ground and 666 SURVEYING. holds the rod upon it. After the instrument is moved, set up, and a backsight taken, the peg is pulled up and carried in the pocket until another turning point is called for. Turning points should be taken at about equal distances from the instrument in order to equalize any small errors in adjustment. In smooth country an ordinary level will per- mit of sights of from 300 to 500 feet. A good rodman is as necessary to accurate and rapid leveling as a good leveler. A man who is inattentive to the work in hand, or averse to rapid movement, is not fit for either place. In most locali- ties, a line of levels of any considerable length will have enough rough places in it, i. e., places where considerable changes in elevation occur, to retard progress, however diligent the level party may be. Laziness or carelessness merit immediate discharge, and usually receive it. 1282. Bench Marks. — On railroad surveys, perma- nent points called bench marks should be established at intervals of from 1,000 to 2,000 feet, depending upon the nature of the country. Any permanent object, such as a stone door sill, a tree, or point of large rock, will serve for a bench mark. Where trees are available, they are always used, the point being cut on a pro- jecting root. On preliminary lines they should be as near to the line as possible. A tree with a large exposed root is chosen, the bench mark is cut into the root in the form of a pyramid, a tack is driven into the apex and the rod held upon it. The tree is blazed smooth and the letters B. M., together with the elevation of the mark, written with red chalk. A bench mark of this kind is shown in Fig. 202, the point being at A and the elevation recorded at />. 1 283. Check Levels. — Check levels or test levels are taken for the purpose of checking and proving the accuracy v'W.^ Fig. 292. SURVEYING. 6G7 of a line of levels before their adoption as a basis for con- struction. Usually intermediate points or stations are not taken, but only the turning points necessary to cover the line. Readings are taken at all the bench marks, and the correct elevations marked. The adjustments of the instru- ment should be frequently tested, and the rodman should carry a rod level to insure the plumbing of the rod. 1284. "Water Checks. — When the line of survey fol- lows the shore of a body of water having no current, such as a lake or pond, its surface can be used as a check, since its level for any ordinary space of time will remain un changed. The sea, whose level is constant, is the base for all barometric leveling, and at all seaports for direct leveling. 1285. Rapid Work. — The rate of progress is limited by the transit party. If the country is open and rolling, where long sights are frequent and chaining easy, the level party will not keep up with the transit party. If the country is smooth and open, both parties can make about the same progress. If, however, the country is thickly cov- ered with underbrush or heavy timber, the level party will have much idle time. A good day's work will vary, accord- ing to conditions, from three to eight miles. The target should be set by signals given by the leveler. An upward movement of the hand is the signal for raising the target, and a downward movement the signal for lower- ing it; a circle described by the hand is the signal for clamping the target, and a wave with both hands indicates that the target is properly set. All intermediate readings are read by the leveler, whose signal "All right" is a single outward wave of the hand, the rodman being careful to keep the rod at full length. The rodman should always call out the rod reading, giving first the number of feet, or, if the reading is less than 1 foot, call the figure " naught," never "ought," then pausing a moment, call the decimal part of the reading. If the rod is being read to hundredths only, the number, 8.40, is read: 668 SURVEYING. eight-four, naught; if 8.04, it is read: eight-naught, four. If the rod is to be read to thousandths, the number, 8.401, is read: eight-four, naught, one; if 8.410, it is read: eight- four, one, naught. The distinctness of a call is in no way proportional to the amount of noise in it. A few days' practice will enable a rodman with moderate effort to call a reading so as to be distinctly heard at a distance of 500 feet. Should a high wind be blowing, the sights will be shorter, owing to the vibration of the instrument, and the rodman's work propor- tionally lessened. The rod reading should always be re- corded before moving the instrument. The leveler may check the reading as he passes the rodman. In general, however, the leveler relies entirely upon the accuracy of the rodman's readings. If he can not be trusted, his place should at once be supplied by one who can be trusted. In taking levels on preliminary railroad surveys, frequently the turning points, as well as intermediate stations, are read by the leveler without being checked by the target. The rodman has still plenty of occasion for the use of judg- ment, as the rate of progress depends largely upon the care shown in the selection of turning points. 1286. Sources of Error. — The principal sources of error are defects in adjustment, which are the fault of the leveler, and failure of the rodman to plumb the rod, and wrong target readings, which are the fault of the latter. Poor levelers and poor rodmen usually go in pairs. Haste or hurry are poor helps to progress. One can do rapid and accurate work without haste, but can not hurry and be either rapid or accurate. The sun shining directly upon the object glass confuses the sight. To prevent this, most instruments are provided with a sun shade, which fits the end of the telescope, projecting over the object glass. If the sun shade is lacking, the leveler can hold his hat so as to shade the object glass. Wind is also a source of error, as it causes the instrument SURVEYING. 669 to vibrate, thus preventing the accurate setting of the target. The leveler should wait for a lull in the wind, dur- ing which, if his rodman is alert, he can get a close shot. At a second lull, he can check the target and feel safe in moving ahead. Individual errors, called "personal equation," are defects in vision peculiar to the individual, so that two persons may- set a target for the same rod, each giving a different read- ing; but as this personal equation, or error, is constant for the same person, it does not materially affect the accuracy of work. 1287. Necessary Degree of Accuracy. — In prelim- inary railroad work an error of .10 of a foot per mile is allowable. Time spent in reducing such inaccuracies is wasted. That painful degree of accuracy termed "hair- splitting " is no recommendation, and the gain in accuracy is more than balanced by increased cost and loss of time. It is a well-known fact that small inaccuracies tend to bal- ance each other, and that a line of levels covering 20 miles, taken with a self -reading rod, will closely check a line taken with target readings and rod level. 1 288. How to Keep Level Notes. — Forms for keep- ing level notes are various. One of the best forms, rarely or never seen in print, and yet one which is in general use among engineers, is shown on the following page: • The distinguishing feature of this form of level notes is a single column for all rod readings. The backsights being additive and the foresights subtractive readings, they are distinguished from other rod readings by the characteristic signs -\- and — . The turning points, whose foresight read- ing is — , are further designated by the abbreviation T. P. 1289. How to Cbeck Level Notes. — There is one method of checking level notes which is in universal use. It provides for checking the elevations of turning points and heights of instrument only, which is sufficient, as all other elevations are deduced from them. The method is very simple and depends upon the fact that all backsights 670 SURVEYING. o d •i t— • 1— t .£* *-> u - a B 4) c O o c u _c 'C a. E ♦J 3 1) o c _o ♦J > o o d o I— 1 o C5 o CO CO C5 o C5 C5 C5 CO o C5 o o o CO 00 00 00 C5 o CO o 1— t o CO 1-5 o l-H o 05 CO ■00 c M 2 en o 00 i 1—1 00 ci o l-H i 3i 1—1 + o o CO o 00 o 1 5< + o CO o o 1 »o 1— t + O 00 o 1— 1 CO »o I— 1 1 1. Station. o T-H »« CO a; ■«*< W3 5 + » i>. 00 Thus, 100.00 10.22 5.61 2.52 5.41 11.53 11.57 24.27 122.59 24.27 SURVEYING. 071 are additive or + quantities, and all foresights are subtrac- tive or — quantities. The level notes described in Art. 1288 are checked as follows: The elevation of the bench mark at Station is 100.00 feet, to which all backsights or -j- readings are to be added, and from this sum all foresights or — readings are to be subtracted. The sum of the + readings or backsights together with the elevation of the bench mark at is 122.59. The sum of the — readings or foresights is 24.27, and the difference 98.32 feet is the elevation of the turning point last taken. As soon as a page of level notes is filled, the leveler should check them, placing a check mark -^ at the last height of instrument or elevation checked. When the work of staking out or cross-sectioning is being done, the levels should be checked at each bench mark on the line. At the close of each day's work, the leveler must check on the near- est bench mark. 1290. Profiles. — A profile represents a vertical sec- tion of the line of survey. In it all abrupt changes in elevation are clearly outlined. Vertical and horizontal meas- urements are usually represented by different scales. Irreg- ularities of surface are thus rendered more distinct through exaggeration. For railroad work profiles are commonly made to the following scales, viz., horizontal, 400 feet = 1 inch ; vertical, 20 feet = 1 inch. A section of profile paper is shown in Fig. 293. Every fifth horizontal line and every tenth vertical line is heavy. By the aid of these heavy lines, distances and elevations are quickly and correctly estimated and the work of platting greatly facilitated. The level notes described in Art. 1288 are platted in Fig. 293. The elevation of some horizontal line is assumed. This elevation is, of course, referred to the datum line, and is the base from which the other eleva- tions are estimated. Every tenth station number is written 672 SURVEYING. at the bottom of the sheet under the heavy vertical lines. The profile is first platted in pencil and then inked in black. Fig. 293. 1291. Grade Lines. — The principal use of a profile is to enable the engineer to establish a grade line, i. e., a line showing the relative proportion of excavation and embankment in the proposed work. The rate of a grade line is measured by the vertical rise or fall in each hundred feet of its length, and is designated by the term per cent. Thus, a grade line which rises or falls 1 foot in each hundred feet of its length is called an ascending or descending 1 per cent, grade, and written + 1.0 or — 1.0 per hundred. A rise or fall of one-half foot in each hundred feet is called a five- tenths per cent, grade, and written + -5 or — .5 per hundred. The grade line having been decided upon, it is drawn in red ink. Example. — The elevation of Station 20 is 140.0 feet; between Sta- tions 20 and 100 there is an ascending grade of .75 per cent. ; what is the elevation of the grade at Station 71 ? Solution. — To obtain the elevation of the grade at Station 71, we add to the elevation of the grade at Station 20, 140 feet, the total rise in grade between Stations 20 and 71. Accordingly, 71 —20= 51; .75 foot X 51 = 38.25 feet; 140 + 38.25 = 178.25 feet, the elevation of grade at Station 71. SURVEYING. 673 TOPOGRAPHICAL SURVEYING. 1292. General Deflnition. — Topographical sur- veying is the location and representation of the inequalities of any portion of the earth's surface. The portion surveyed is conceived to be projected upon a horizontal plane, called a plane of reference, upon which all inequalities of sur- face as well as all conspicuous objects are shown in their true relative positions. The simplest and most generally used method of representing the topography of a given surface is by means of contour lines. A map containing an outline of a given surface, together with the contour lines representing its inequalities, is called a contour map of that surface. 70^ Fig. 294. Let A B C, \n Fig. 294, represent the outline of a hill, and suppose this hill to be gradually submerged in water, the water rising in successive heights of 10 feet. The flow, or shore line, at each successive rise is a contour line. The horizontal lines correspond to the surfaces of the successive elevations of the water. The points where these horizontal lines cut the edge of the hill are projected on the horizontal 074 SURVEYING. line L M. The irregular lines connecting the corresponding points of projection are contours. In Fig. 294 they are assumed to be 10 feet apart in vertical measurement. 1293. Conduct of a Topograptilcal Survey. — The manner of conducting a topographical survey will de- pend upon the extent and outline of the surface and the de- gree of accuracy required. If the area be of comparatively regular dimensions, such as town or park sites, the usual practice is to lay out the area in squares. The lines of di- vision are the bases for the location of all points within the area whose elevations are determined by direct leveling. If the area is long and narrow, as in a railroad survey, the line of survey is the base for the location of all points and for determining their elevations. Cross-sections of the sur- face are taken at suitable intervals, and changes in the slope of the surface are measured either by direct leveling or with a clinometer or slope board. 1 294. The Hand Level. — The usual form, called the "Locke level," from the name of the inventor, is shown in Fig. 295. It consists of a brass tube A B, on the top of which is a spirit level C. In the lower part of the tube is a mirror which reflects the point at which the bubble should be when the instrument is level. A small hole D at one end and a cross-hair at the other give the level line. The ob- server holds the level to one eye, bringing it to a level line while he observes the object to which the level is directed with the other. In taking cross-sections with a Locke level, the following rule is recommended: The topographer has two or more assistants, three is the better number, a rod- man and two tapemen. The rodman is provided with a rod at least 12 feet in length, of light weight, and of sufficient width to admit of large, distinct figures being painted upon SURVEYING. 675 it, and divided to tenths of feet. The rod is painted like the Philadelphia rod; the face white, tenths of feet in black, and feet in red. Tapemen should use a tape 100 feet in length, of durable material. Chesterman with wire warp is best. The topographer first measures the distance of his eye above th'e ground, which is a constant quantity, to be subtracted from all the rod readings. He then stands at a station and keeps the rodman at right angles to the line of survey. The rod- man, having reached the end of a slope, i. e. , a point, where the rate of slope changes, he holds his rod at the point and the topographer takes the reading with the hand level. From this reading the topographer subtracts the constant, i. e., the height of his eye above the ground. The remain- der is the difference between the elevation of the surface where the topographer stands and the surface where the rod- man stands. The tapemen having measured the distance between the two points, the rate of slope is determined by dividing the distance measured by the difference in eleva- tion. This method of taking slopes or cross-sections is illustrated in Fig. 296. Let A be Station 156 of a preliminary survey. The topog- rapher stands at A. The rodman goes to the point B^ Fig. 2%. where the slope changes, holding his rod, which measures 16 feet in length, at that point. The topographer sights with his hand level and reads 7.5 feet on the rod. From this reading he mentally subtracts 5.3 ft., the height of his eye 676 SURVEYING. above the ground. The remainder, 2.2 ft. , is the difference in elevation between the points A and B. Meanwhile, the tape- men find that the horizontal distance from y^ to ^ is 31 feet. The rate of the slope yi Z>'is the horizontal distance between the points A and^, 31 ft., divided by 2.2, their difference in elevation. The quotient is 14.1 and the slope is recorded — -^. The topographer then moves to the point B, and the Ox. rodman goes to C, which is so much lower than B that with the rod held on the ground the line of sight will pass over the top of the rod. Here the rodman gives a "long " or "high " rod. Planting himself firmly at C, he raises the rod until the line of sight, from the topographer's eye, cuts the top of the rod, when the topographer calls "all right." He then notes where the bottom of the rod comes, and allows it to slide to the ground. Then adding to the length of the rod 16 ft., the distance from the ground to the point where the bottom of the rod came when the reading was taken, he calls out their sum to the topographer. In this example the rod is 16 feet and the addition 7 feet, making a high rod of 23 feet, which is common enough. The hori- zontal distance 33 feet, as measured by the tapeman, is also called out. The topographer makes the subtraction 5.3 from 23.0, and the difference 17.7 is written as the numer- ator of a fraction whose denominator is the horizontal dis- tance 33. The slope being a descending one, the fraction 17 7 will be — -, a slope of 1 to 1.9. In Fig. 290, the slopes A B and B C are right slopes, i. e. , on the right side of the line of survey. In taking the left slopes, the rodman and topographer change positions, the topographer going ahead and the rod- man following. The topographer standing at D reads a rod of IG feet held at A. Subtracting the constant 5.3, the remainder 10.7 is the difference between the elevations of A and D and is an ascending slope. The horizontal distance 10.7 from ^ to Z> is 30 feet and the slope is recorded -f- 30 SURVEYING. 677 1295. Slope Angles. — Slopes are often measured with an instrument called a clinometer, which measures the angle which the line of slope makes with the horizontal, and is shown in Fig. 297. Tables are compiled giving the Fig. 297. angle of slope and the horizontal distance for one foot of rise, as follows: 1° is 57.3 feet horizontal per 1 foot rise. 2° is 28.6 feet horizontal per 1 foot rise. 3° is 19.1 feet horizontal per 1 foot rise, etc. 1296. Platting Topography in the Field.— While some engineers favor the platting of contour maps in the field, the majority do not. To plat the map in the field, the topographer carries a case, the cover of which serves for a drawing board. The line of survey is divided into sections which are platted on different sheets, each sheet containing some of the immediately preceding section, so that by over- lapping and pinning them together, a complete map of the line is obtained. The topographer carries in his case the sections covering his day's work, with the numbers and elevations of each station marked on the map. He pins a section to the cover of the case with thumb-tacks; his assistants measure the angle of the slope with a clinometer, 678 SURVEYING. together with the horizontal distance ; and from the table of slopes which he carries, the topographer determines the location of the contours and sketches them on the map. A better practice is to measure and record the slopes, keeping as close to the transit party as possible, and provide an extra man to work up the notes in the office under the direction of the topographer. • 1297. Eye Measurements. — Though practice will greatly aid the eye in estimating distances, yet it is not to be relied upon when anything like exactness is required. In taking slopes, the length of the last one only may b'e esti- mated by the eye. More distant objects which lie without the possible range of location may be sketched in with the aid of the eye alone. 1298. Form of Topographer's Notes. — A good form for a topographer's notes is shown in the accompany- ing diagram : Station. Lt. Line. Rt. Line. ^ 45 10.0 + 30 11.4 35 -1? for 100' 1 for 60' 11.5 ^ 40 11.0 53 7 2 for 60' 10.3 ■^ 40 — 6 B u a c — 4) o 11.5 50 -II for 100' 3 Same as 2 Same as 2 4 for 50' 11.8 ^ 40 10.5 55 - ^' for 100' 5 for 50' 12.0 ■^ 35 11.3 54 - '£ for ICKV G for 60' 10.4 ^ 40 10.5 50 - y for 100' 4.1 SURVEYING. 679 PIO. 296. 680 SURVEYING. They are a record of the cross-sections or slopes ot a pre- liminary railroad survey, the line of which extends along the side of a steep hill. The slopes are taken with a Locke level and rod, giving the actual differences in elevation be- tween the points of change of slope. The alignment of the survey is shown in Fig. 298, and the contours are platted from the foregoing notes. The contours are 5 feet apart, i. e., the vertical rise between them is 5 feet. The elevations of the stations the topographer has obtained from the leveler. The stations are marked on the plat, either by a dot, or, what is better, a dot enclosed in a small circle. The number of the station is marked at the right a little space ahead of the circle, the elevation on the left of the line and opposite to the number of the station. The cross-section lines are sometimes drawn on the map, very fine and at right angles to the center line, but usually the lines are omitted, the draftsman giving the true direction with his offset scale when locating the contours. In Fig. 298, the elevation of Station is 104.6 feet. To reach the next contour above, viz., 105, a rise of .4 foot must be made, and to reach the next lower contour a fall of 4.6 feet is necessary. From the notes, we find on the left of the line a rise of 10 feet in a horizontal distance of 30 feet or a rise of 1 foot in 3 feet, and. for a rise of .4 foot we must go to the left of the line .4x3 = 1.2 feet to contour 105. To reach contour 110, which is 5 feet higher, we must go 5x3 — 15 feet farther to the left. This distance added to 1.2, the distance to contour 105, gives 16.2 feet, the second offset. We find by adding 10 feet (the rise in going 30 feet to the left of the line) to 104.6 feet, the elevation of Station 0, we have 114.6 feet, which is the elevation of the end of the first slope. An additional rise of .4 foot must be made in order to reach contour 115. The second slope is a rise of .8.4 feet in a distance of 45 feet, or a rate of 1 foot in 5.3 feet. Multiplying 5.3 feet by .4, we have 2.1 feet, which is to be added to 30 feet, to reach contour 115, and^fives a distance of 32.1 feet. Contour 120 will be 5.3 feet X 5 = 26.5 feet beyond contour 115, or 58.7 feet from the center line. SURVEYING. 681 In the same way the contours to the right of the line are located. Tenths of feet are dropped in the computed dis- tances, as they are too small for platting, and the nearest foot is taken. Having located the contours by offsets for several con- secutive stations, points of equal elevation are joined free- hand, forming the contour lines, care being taken that lines of different elevation are kept distinct from each other and conforming to the curves and undulations of the original surface. 1 299. Working Up Notes. — A good rule is to work up the notes for a considerable section before platting, thus avoiding the delay from continual change of work. The following form of working up notes is a good one, notes for each station being separated from those for other stations by a few. strokes of a pencil. The example given is for Sta. 0, in Fig. 298. Sta. 0. Elev. 104.6. Rt. 14 feet to contour 100. Lt. 1 foot to contour 105. Rt. 29 feet to contour 95. Lt. 16 feet to contour 110. Rt. 53 feet to contour 90. Lt. 32 feet to contour 115. Rt. 81 feet to contour 85. Lt. 59 feet to contour 120. Rt. 110 feet to contour 80. Rt. 137 feet to contour 75. Contour lines are usually drawn first with pencil and afterwards inked in black. Short gaps are left in the lines at suitable intervals, in v/hich their elevations are written. These should be of sufficient frequency to show at a glance the elevation of any contour. Situations are continually recurring where the side slopes give but an inadequate idea of the topography. This is particularly true when the line of survey follows a stream with numerous tributaries and where highway crossings are frequent. In such cases the topographer will supplement the side slopes with free-hand sketches, which are invaluable helps in making topographical maps. 682 SURVEYING. INDIRECT LEVELING. 1300. Indirect leveling is the process of determining elevations by either lines or angles or both. A common example in indirect leveling is given in Fig. 299. Let D B he a. flag-staff whose height is required. Set up a transit at A. Level carefully both the vernier plate and ff the telescope. The vertical arc will, if in adjustment, read at zero. Sight to C\ the point where the hori- -A jw, (44 g^j.j^gg ^^^ flag-staff. 4.2' ^ Measure the distance FIG. 299. yi C = 180 feet, CD = 4.2 feet, and the diameter of the staff at C= 1.5 feet. Measure the vertical angle C A B = 26° 10'. From rule 5, Art. 754, we have tan A = , ,, , . ,. z=. One-half A C -\- -^ dia. staff diameter staff at C= .75 foot. Substituting known values, we have tan 26° 10' = 7-^77^^^, whence C B— 180.75 X tan 180. i 5 26° 10'= 180.75 X.49134= 88.809 feet; 88.809 4-4.2 = 93.009 feet = D /)', the height of the flag-staff. 1301. Stadia Measurements. — The theory of the stadia is familiar to most engineers, yet comparatively few of them make any practical application of it, even when it would be greatly to their advantage. In stadia work an ordinary leveling rod is generally used, and answers every purpose. It should be made of hard wood, such as mahogany, which is least affected by changes of temperature, and should be from 10 to 12 feet long, 2 inches wide, and about 1^ inches thick. It is divided into feet, and each foot subdivided into tenths. The spaces corresponding to these latter divisions are painted alter- nately red and white, the number of tenths each space represents being painted in prominent black figures on the SURVEYING. 683 lines of division. The space directly below each footmark should be inlaid with a mirror to reflect the light and enable the surveyor to read the rod at long distances with greater precision. The rod should also be provided with a sliding target. The best instrument tX) employ in this class of work is a transit reading to 30". Besides the horizontal and vertical cross-wires which appear in the field of view of the ordinary transit telescope, the stadia transit is provided with two additional horizontal wires placed parallel with the horizontal wire in the plain transit, and at an equal distance above and below it, as shown in Fig. 300. These two extra wires are so placed that, if the stadia rod is held at a point 100 feet distant from the telescope, they will enclose 1 foot of the length of the rod. For ^^°- ^^• example, if the lower wire coincides with the 4-ft. division, and the upper wire with the 5-ft. division of the rod, the distance from the center of the instrument to the rod will be 100 ft. + the constant for the particular transit used. The starting point for stadia measurements is often indis- criminately assumed to be either the center of the instru- ment, the center of the cross-wires, or from a plumb line dropped from the object glass; but, owing to the deflection of the sight due to the action of the lenses, the precise starting point for stadia measurements is a point as far in front of the object glass as its focal length ; for example, if the focal length of the object glass is inches, the starting point is 6 inches in advance of a plumb line dropped from the object glass. The distance from this point to the centei of the instrument is " constant " for the sduie instrument, and must be added to the recorded stadia distance at every sight. In making a stadia survey, the transit should first be tested. Having found as level a plane as possible, test and adjust the. level so that the vertical arc will read zero when the telescope is in a perfectly horizontal position; measure off very carefully from the center of the instru- ment, the short distance equal to the constant of the instru- ment, say 1.25 feet; from this point accurately measure a 684 SURVEYING. distance of 400 feet, driving a stake at each 100 feet. It is advisable to measure this test line with two or more st£el tapes, and then take the average. As it will be necessary to test the cross-wires every few days, it is important that the test line should be conveniently located and very accu- rately measured. The line now measures 401.25 feet, as follows: First section, measuring from the center of the instrument, 101.25 feet, then three sections of 100 feet each, as shown in Fig. 301. ^.25 400' Direct the rodman to hold the rod on the point 201.25 feet from the instrument, and adjust the stadia wires so that they will include 2 feet on the rod. First adjust the upper to the center wire so as to include 1 foot, then adjust the lower to the center to include one foot. When this has been done, let the rod be held at the point 301.25 feet distant. The wires should now inclose 3 feet, 1.5 feet being included between the upper and center wires and 1.5 feet between the center and lower wires. Now test the point at the ex- tremity of the line ; the wires should at this distance include 4 feet. Instruct the rodman to hold the rod o'n the first point, 101.25 feet from the instrument, and if the stadia wires now include one foot, the instrument is in adjust- ment; if not, the operations must be repeated until the instrument^ reads correctly at every point. The ratio of the constant does not increase with the distance, but remains the same whether the distance of the sight be 50 or 2,500 feet. At the .beginning of a survey, the target on the rod is set at a height equal to that of the instrument, i. e., the dis- tance from the ground-line to the axis of the telescope. This is done with the view of having the line of sight par- allel with an imaginary line between the foot of the instru- SURVEYING. 685 ment and the foot of the rod, which gives the exact vertical angle or degree of slope between the instrument and rod and a perfectly level plane. The rod is now held on a point where a sight is desired, and the transitman turns the tele- scope until the center wire and the center line of the target coincide; see Fig. 302. He then clamps the telescope, and reads the angle of elevation or depression, as the case may be, on the vertical arc^ which is say 10° 26' ; and, if the rod is held on a point at a greater elevation than that of the telescope, this angle will be one of elevation, and he will record it thus, + 10° 26'; but if the rod is held on a point lower than the instrument, the telescope will be correspond- ingly depressed, and the angle is recorded thus, — 10° 26'. The distance on the rod intercepted by the stadia wires is Fig. 302. read and recorded. Assuming that the lower wire coincides with the 3.5 ft. division line, and the upper one cuts the rod at 7.46 feet, the intercepted distance is 7.46 — 3.5 = 3.96 feet, and is thus recorded. The needle is next read, or, if it be an angular survey, the direction is platted and recorded. Having thus obtained the vertical angle, intercepted dis- tance, and bearing, this sight is finished and the surveyor is ready to move to the next station. Before any platting can be done, the distances must be calculated and reduced to the horizontal. This may be ac- complished by means of the table of Horizontal Distances and Differences of Elevation for Stadia Measurements. In using the tables, proceed as follows: Look for the vertical angle, in this instance 10° 26', and under the head Hor. Dist. find the number 96.72. Then, this number multiplied by 686 SURVEYING. the distance intercepted by the stadia wires, viz., 3.96, equals 96.72 X 3.96 = 383.01; now, at the foot of the page, under 10° and opposite c = 1.25 (the constant of the instru- rnent), find the corrected distance 1.23, which, added to 383.01, gives 384.24: feet, the corrected horizontal distance, which is recorded in the column provided for that purpose in the note book. The difference of level is found thus : Under the head Diff. Elev., find 17.81, the number corresponding to the vertical angle 10° 26'. This number multiplied by the in- tercepted distance equals 17.81 X 3.96 = 70.53; at the foot of the column find .23, which, added to 70.53, gives 70.76 feet as the difference of elevation, and is recorded as such in its proper place. Proceed in the same manner to find the horizontal distances and differences of level of all the other points observed. The relative elevations of the vari- ous points observed, above or below any adopted datum line or plane of reference, can be readily determined by means of the signs + and — prefixed to each vertical angle recorded. Thus, assuming the survey to start from a B. M. 497.32 feet above the adopted plane of reference, and the first angle re- corded to be, as before stated, + 10° 26', corresponding to a difference of level of + 70.76 feet, the point observed will be 497. 32 + 70. 76 = 568. 08 feet above th3 datum plane. Where, however, boundary lines only are being run, it is unneces- sary to compute the levels, but the vertical angles must be recorded in all cases, in order to correct the distances. The calculations may be made, without the use of tables, in the following manner: To obtain the horizontal distance, the following formula is employed : D—c cos n -\-a k cos' «, (94.) in which D = the corrected distance ; c = the constant ; a k = the stadia distance, and ;/ = the vertical angle. Assume, as before, a vertical angle of + 10° 26' and an intercepted distance of 3.96 feet. As each foot of the rod intercepted by the stadia wires corresponds to a distance of SURVEYING. 687 100 feet, an interception of 3.90 feet corresponds to a dis- tance of 396 feet, called herein the stadia distance, i. e., the distance from the rod to the point outside the telescope where the stadia measurement begins. Applying the formula, we have, D = 1.25 cos 10° 20' + 396 cos' 10° 26' = 125 X . 98347 + 390 X . 98347' = 384. 24 ft. To obtain the difference of level E, apply the following formula: . , sin 2 « /rk- \ Applying this formula to the preceding example, we have E - 1.25 X .18109 + 396 X .17810 = 70.75, since 2 « = 10° 26' X 2 = 20° 52' and sin 20° 52' .35619 2 = .17810. SURVEY OF BEAVER CREEK. c c" _o '■3 OJ 5 4-> cn 5 O o Bearing. Vert. Angle. S 1 t I 21 o 1 396 384 N 1° 15 W + 10° 26' + 70.71 1142.21 A 201 Due E + 20° 11' B 404 S 80° 10 W - 11° 14' C 187 S 76° 20 W - 14° 22' D 563 S 68° 32 W + 3° 12' 2 384 N 20° 15 W - 0° 16' The tables of Horizontal Distances and Differences of Elevation for Stadia Measurements are computed for observations taken on a vertical rod held perfectly plumb. Fig. 303 shows the method of keeping sketch and notes in topographical work. 688 SURVEYING. 1302. An efflcient topoy^raphical survey is one which fully serves every purpose for which it is made. Its value depends more upon the accuracy of that which is represented rather than the minuteness or quantity of detail. The topographer should be able to readily and m- telligently decide between what is important and what is not important, and invest his time and labor accord- FlG. 303. ingly, taking nothing for granted and never indulging in guesswork. 1303. The Aneroid Barometer. — Fig. 304 shows an aneroid barometer, a substitute for the mercurial barom- eter, which latter is not readily portable. It consists of a box of thin corrugated copper, exhausted of air. An in- crease in the weight of the atmosphere compresses the box, and a reduction in weight admits of the box being expanded by a spring inside. This spring is connected, by a system of levers, with a dial which indicates the pressure of the atmosphere. The face is graduated to correspond with the heights of the mercurial barometer. A thermometer is also SURVEYING. 689 attached to the face and shows the temperature when the readings are taken. Fio. :J04. 1304. How to Determine Difference in Eleva- tions With tlie Aneroid Barometer. — The formula given is that used by the Engineer Corps of the United States Army. The aneroid barometers used are adjusted to agree with the mercurial barometer at a temperature of 32° Fahrenheit at the sea level in latitude 45°. Observa- tions at the two stations whose difference in elevation is required should be made as nearly simultaneous as possible, as temperature and atmospheric conditions are constantly changing. Let Z — difference of elevation of the two stations in feet; // = the reading in inches of the barometer at the lower station; 690 SURVEYING. //"= the reading in inches of the barometer at the higher station; / and /' = temperature (Fahr.) of the air at the two sta- tions. Then, Z= (log//- log /^) X G0,384.3 X (l +^^^^=^). (96.) Example. — Reading at lower station, /; = 29.52 in., / = 70°; at higher station, H = 27.15 in., /' = 62°. Log of /4, 29.52=1.47012 Logoff/, 27.15 = 1.43377 Difference = .03635 / + /'-64 . ^ 70+62-64 , .„„ ^+ 900 =^^ 900 = 10'55- Hence, Z= .03635 x 60,384.3 x 1.0755 = 2.360.4 feet, the diflference between the elevations of the two stations. Tables are prepared giving values of (log // — log H) X 60,384.3 and t ■\- 1' — 64' of 1 4 jjjr-r , which greatly simplifies the work of determining differences of elevations. HYDROGRAPHIC SURVEYING. 1305. Hydrographic surveying is the process of determining, by means of soundings, the location of the deep and shallow places of harbors, sounds, rivers, etc., and recording them in charts for the use of engineers and navigators. 1306. Sounding. — Sounding is measuring the depth of water. The surface of the water forms the datum line, and the various depths measure the undulations or changes of elevation of the bottom of the body of water being sounded. The extent of knowledge of the bottom gained will depend upon the number and accuracy of the soundings. For depths to 18 feet, a sounding rod graduated to feet and tenths is used ; for greater depths, a lead line, marked to fathoms and half fathoms, is employed. It will be found necessary to keep the lead line well stretched and its length frequently tested. SURVEYING. 691 1307. Conduct of Survey. — The mode of conduct- ing a hydrographic survey is as follows: Stations at con- spicuous points on shore are first carefully located by trigonometrical surveying. They form the base line by which all irregularities of shore line and the location of all soundings are determined. A good station mark is a post set firmly in the ground with about one foot of its length exposed. A hole is bored in the center of the top of the post and a flagpole set in it. The pole can be pulled out and a transit set directly "over the station. Each station should be distinguished by the combination of colors on the flag, and the number of the station should be distinctly marked on the post. A permanent bench mark must be established and the height of water at the time of the soundings recorded. Buoys are made of light wood, and painted in such colors as will make them conspicuous. Fig. 305. The location of buoys and soundings is illustrated in Fig. .'>05. The stations A and B are located and their distance apart known. A transit is set up at each station and back- sighted to a rod at the other; the vernier plate is then un- damped and the leadsman in the boat is carefully followed with the instrument. At a given signal, the leadsman takes a sounding, and both instruments sight to him and read the angles, which give a side and two adjacent angles of a triangle from which to determine the location of the point D. In the same manner C and any number of points can be located. A man in the boat records the time and the sound- ings as they are read by the leadsman. 692 SURVEYING. 1308. Tide Gauges. — By means of a tide gauge the height of water at any time may be known. The datum or zero line is mean low spring tide. A simple form of tide gauge is a board nailed to the upright front of a dock. The face should be painted white and graduated to half-feet or to feet and tenths, and the zero line set at mean low spring tide. The feet marks should be in heavy black figures, so that they may be easily read. The tide gauges used by the government are automatic, and are provided with an indicator which registers on paper the fluctuations of the tide. LAND SURVEYING. 1 309. The United States System of Surveying Public Lands. — The public lands of the United States are divided and laid out into approximately equal squares, the sides of which are true north and south or east and west lines. This is effected by means of meridian lines and parallels of latitude established six miles apart. The squares thus formed are called to^wnships, and contain 36 square miles or sections. Each section contains, as nearly as may be, 640 acres, giving an approximate area of 23,040 acres for each township. 1310. Principal Meridians. — A principal merid- ian running due north and south and a base line running due east and west are established astronomically, and the half-mile, mile, and six-mile corners are permanently marked on them. These two lines form the basis of all subsequent divisions into townships and sections. All other lines, with the exception of these two and the standard parallels, are run with the compass and chain. Fig. 306 represents a section of country thus laid out. The scale is 10 miles to 1 inch = 633600 : 1. The diagram shows the principal meridian running truly north and south, and a base line which is a parallel of latitude running truly east and west. Parallel to these are other lines 6 miles apart, forming townships. All the townships situated north or south of each other form a range, the ranges being named by their number east or west of the principal meridian. The seven ranges east and seven west of the principal merid- ian, shown in Fig. 306, are described as R. 1 E, R. 1 W, etc. The townships in each range are designated by their num- ber north or south of the base line. Thus, in the diagram. G94 LAND SURVEYING. the township marked A is denoted by T. 3 N, R. 4 W; that marked B, by T. 2 S, R. 3 E. These abbreviations should l^Stknd^rd Parallel Noi^th. Base ,!S Line. It 1^^ Standard Parallel ^out h. Fig. 306. be read townsJiip 3 north, range J^ ivest, and toxvnship 2 south, range 3 east. 1311. To-v^'nslilp Divisions. — Each township is divi- ded into 36 sections, each one mile square and containing 640 acres as nearly as TV ^ maybe. The sections in each township are num bered from 1 to 36, as shown in Fig. 307. The numbering of the sec- tions begins at the north- east corner of the town- ship and goes west from 1 to 6, then east from 7 to 12, and so on alter- nately until section 30 in the southeast angle of the township is reached. The sections are sub- divided into quarter-sections, each half a mile square and W 6 5 4 3 2 1 7 8 9 10 11 12 18 n 16 15 14 13 19 20 21 22 23 24 30 29 28 27 26 25 31 32 33 34 35 3e E S Fig. 307. LAND SURVEYING. 695 containing IGO acres, and sometimes into half quarter-sections of 80 acres and quarter quarter-sections of 40 acres. By this system the smallest subdivision of land can be accurately located ; as, for example, the southeast quarter of section 36 in township one south in range two west of Willamette meridian. 1312. Obstacles. — The law requires that the lines of the public surveys shall be governed by the true meridian, and that the townships shall be six miles square, two condi- tions involving a mathematical impossibility, for strictly conforming to the meridian would necessarily throw the township out of square, for the reason that a degree of longi- tude, which, at the equator, is 69^ miles, constantly dimin- ishes as one approaches the poles. As the meridian lines are strictly adhered to, the requirements of the law respecting areas are not fulfilled. The townships assume a trapezoidal form which increases the higher the latitude of the surveys. To meet these conditions the law provides that the sections shall contain G40 acres, as nearly as may be, and further pro- vides that " in all cases where the exterior lines of the town- ship thus to be subdivided into sections and half-sections shall exceed or shall not exceed six miles, the excess or deficiency shall be specially noted and added or deducted from the western or northern ranges of sections or half- sections in such township, according as the error may be in running the lines from east to west or from south to north." In order to throw the excesses or deficiencies, as the case may be, on the«^r///and tcr.?/ sides of a township, according to law, it is necessary to survey the section lines from south to north on a true meridian, leaving the result in the northern line of the township to be governed by the convexity of the earth and the convergency of meridians. Thus, suppose the land to be surveyed lies between 46° and 47° of north latitude. The length of a degree of longitude in latitude 46° north is taken as 48.0705 statute miles, and in latitude 47° north as 47.1944 miles. The dif- ference, or convergency per square degree, = .8761 mile = 696 LAND SURVEYING. 70.08 chains. The convergency per range (8 per degree of longitude) equals one-eighth of this distance or 8. 76 chains, and per township (11^ per degree of latitude) will equal 8.76 chains divided by 11^=. 76 chain. Hence, we know that the width of townships along their northern boundary is 76 links less than on their southern boundary. The town- ships north of the base line, therefore, become narrower and, narrower than the six-mile width with which they start by that amount. 1313. Standard Parallels. — Standard parallels, called correction lines, are established at intervals of 30 miles to provide for the correction of the error arising from the convergency of the meridians. They also serve to limit errors resulting from inacciiracies in measurement. Such correction lines .when lying north of the principal base line form new base lines for the surveys north of them. The convergency or divergency is taken upon these correc- tion lines, from which, as base lines, the townships start again with their proper widths. On these correction lines, therefore, double corners will be found, one set being the closing corners of the surveys ending there, and the other set the standard corners of the surveys starting there. 1314. Running Township Lines. — The principal meridian, the base line, and the standard parallels having been first astronomically run, measured, and marked accord- ing to instructions on true meridians and true parallels of latitude, the process of running, measuring, and marking the exterior lines of townships is as follows: For townships north of the base line and west of the principal meridian, commence at Station No. / (Fig- 308), the southwest corner of T. 1 N, R. I W, as established on the base line, thence run north on a true meridian line 480 chains, establishing the half-mile and mile corners there- upon, according to instructions, to No. 2, which is the north- west corner of the same township. There establish the corner of townships 1 and l N, ranges 1 and 2 W; thence run east on a random or trial line, setting temporary stakes LAND SURVEYING. 697 at the half-mile and mile points and noting the distance where the line intersects the eastern boundary north or south of the true or established corner. Run and measure westward on the true line, establishing permanent half-mile and mile corners, noting all water crossings and the charac- ter of the land, as per instructions, to No. If., which is iden- tical with No. 2. The last half-mile will fall short of Standard Parallel. 28 14 14 28 27 13 13 27 25 26 11 12 12 11 26 25 24 10 10 24 , 22 23 8 9 9 8 23 22 21 7 7 21 19 20 5 6 6 5 20 19 18 4 4 18 16 17 2 3 3 2 17 16 29 15 1 1 15 Base e Li ne - . Pig. 808. 40 chains by about the amount of the calculated conver- gency per township, which, in the above supposed case, equals 76 links. The terms random and true lines are explained in Fig. 309. The boundary from Station 1 to Station ^ is a true meridian and 480 chains in length, with permanent corners set at each half-mile and mile. From A run and measure 698 LAND SURVEYING. towards ^ on a true east and west line, as shown by ide dot- ted line A B, which is called a random line, setting tem- porary half-mile and mile posts. This random or trial line being run on a parallel of latitude, must intersect the prin- cipal meridian near the true corner C, previously established. The return or true line always connects this true corner with the one from which the random starts. Random lines Random Line 479JSS chains" 47925 links. >*^ '>A,^19^^0^40 40 40 40 40 40 40 40 40 39.23 '^^^^^^^^^^^^"io-lo-io-Jo-io-jo^ True Line. Sta.l 40 T.l.N.Rl.W. S Base Line. 5\ •it Fig. 309. are either true east and west or true north and south lines, i. e., they are either parallels of latitude or true meridians. Suppose the random line intersects the principal meridian X Fat i?, 75 links to the north of the true or established corner at C\ the length of A B is 479 chains and 25 links. The triangle A B C is a right-angled triangle, right angled at B', dividing B C=75 links by A ^=47925 links, we have the tangent of the angle BA C= j^Wr = .00156 = LAND SURVEYING. 699 tan 0° 05'. The angle B C A is, therefore, 90° = 0° 05' = 89° 55', and the return course, or true line, C A is N 89° 55' W. Setting the instrument over the true or estab- lished corner C, the compass is set for the true course C A, N 89° 55' W, and measuring 40 chains from C, a permanent half-mile or quarter-section post is set, 40 chains further a mile or section post is set, and so on, setting half-mile and mile posts at regular intervals of 40 chains until the last half-mile post is set; between it and the township corner A, the distance is but 39 chains and 25 links, thus leaving the deficiency in the western tier of sections as prescribed by law. In case the random line materially falls short, or overruns in measurement, or intersects the eastern boundary at a con- siderable distance from the established corner, it will be evi- dent that there has been considerable error either in direction or measurement of the lines, or both, and the lines must be retraced even if it should be found necessary to rerun the meridianal boundaries of the township (especially the west- ern boundary) so as to discover and correct the error. The true corners must be established, and the false ones destroyed and obliterated, and all facts carefully set forth in the notes so as to avoid future confusion. Then proceed north from 4 to 5, establishing corners as before; No. 5 is the N W corner of T. 2 N, R. 1 W; east to No. 6 (the N E corner of the same township), west to No. 7 (the same as No. 5), north to No. 8 (the N W cor- ner of T. 3 N, R. 1 W), east to No. 9 (the N E corner of the same township), west to No. 10 (same as No. 8), north to No. 11 (the N W corner of T. 4 N, R. 1 W), east to No. 12 (the N E corner of the same township), west to No. IS (same as No. ll), and thence north on a true merid- ian to the standard parallel or correction line (which is here five townships, or 30 miles, north of the base line), throwing the difference over or under four hundred and eighty chains on the last half mile, according to law. At the inter- section with the standard parallel establish the closing corner, the distance of which from the standard corner must be 700 LAND SURVEYING. measured and noted as required by the instructions. In case any obstruction should have prevented the extension of the standard parallel along the field of the present survey, the surveyor will establish a corner for the township, subject to correction, should the parallel be extended. The surveyor then returns to the base line, and, from the southwest corner of T. 1 N, R. 2 W, carries up another tier of townships, closing as before. For townships north of the base line and east of the prin- cipal meridian the order of survey is as follows: Beginning at the southeast corner of T. 1 N, R. 1 E, proceed as with townships north and ivest, except that the trial or random line is run and measured west and the true line east, throw- ing the difference over or under 480 chains on the west end of the line. Accordingly, the surveyor, having measured his trial line west, will first determine the length of the last half- section line, and commence the measurement of the true line with such excess or deficiency, and, consequently, the re- maining measurements will all be exact half miles and miles. 1315. Running Section Lines. — The interior or sectional lines of all townships, however situated with refer- ence to base and meridian lines, are laid off and surveyed, as shown in Fig. 310. In this figure the squares and large figures represent sec- tions; the small figures are referred to in the following di- rections. Commence at No. 1 (see small figure in the diagram) which is a township boundary for sections 1, 2, SS, and 36; thence run north on a true meridian; at 40 chains establish a half-mile or quarter-section post, and at 80 chains establish the corner of sections 25, 26, 35, and 36. Thence east on a random line to No. S, setting a temporary quarter- section post at 40 chains, noting the measurement to No. 3 and the distance of the random's intersection north or south of the true or established corner of sections 25, S6^ 30, and 31. Thence correct west on a true line to No. 4, setting the quarter-section post on this line equidistant from the two LAND SURVEYING. 701 corners whose distance apart is now known. In like manner proceed from J(.to 5, 5 to 6, 6 to 7, and so on to No. 16, the corner of sections i, 2, 11, and 12, thence north on a random line to No. 17, setting a temporary quarter-section post at 40 chains and noting the length of the whole line and the distance of the random's intersection east or west of the true corner of sections 1, 2, 33, and 36 established on the town- ship boundary, then southwardly from the latter on a true 31 32 33 34 35 36 97 71 53 35 17 1 5 4 3 2 1 99 98 96 72 70 54 52 36 34 18 16 94 95 68 69 50 51 32 33 14 15 12 7 8 9 10 11 12 92 91 67 49 31 13 93 89 90 65 66 47 48 29 30 11 12 13 18 17 16 15 14 13 87 86 64 46 28 10 88 84 85 62 63 44 45 26 27 8 9 24 19 20 21 22 23 24 82 81 61 43 25 7 83 79 80 59 60 41 42 23 24 5 6 25 30 29 28 27 26 25 7T 76 58 40 22 4 ' 78 74 75 56 57 38 39 20 21 2 3 36 31 32 33 34 35 36 73 55 37 19 1 6 18 19 30 31 6 4 3 Fig. 310. line, noting the course and distance to No. 16, the established corner to sections 1, 2, 11, and 12, care being taken to estab- lish the quarter-section post at 40 chains from said section corner, thus throwing the excess or deficiency on the north- ern half mile, according to law. Proceed in like manner through all the intervening tiers of sections to No. 13, the corner of sections 31, 32, 5, and 6. Thence north on a true meridian 80 chains to 7^ setting a quarter-section post at 702 LAND SURVEYING. 40 chains, and at 80 chains setting corner of sections 29, 30, 31, and 32; then east on a random to 75, setting temporary quarter-section post at 40 chains, noting the entire measure- ment to the eastern boundary and the distance of the ran- dom's intersection north or south of the true corner of sec- tions 28, 29, 32, and 33; thence west on a true line, setting the quarter-section post on the true line and equidistant from either end, to No. 76, which is identical with 74; thence west on a random line to 77, setting temporary quarter-sec- tion post at 40 chains, noting the full measurement of the line and the distance of the random's intersection with the township boundary nortJi or sontli of the established corner of sections 30, 31, 25, and 3Q; thence eastwardly on the true line, giving its course and setting the quarter-section post 40 chains from the corner of sections 29, 30, 31, and 32, thus throwing the excess or deficiency of measurement on the western half mile of the section according to law. Proceed ftorth in like manner from No. 78 to 79, 79 to 80, 80 to 81, and so on to No. 9J^, the southeast corner of section 6, where, having established the corner of sections 5, 6, 7, and 8, run thence successively the random line east to 95, nortli to 97, and west to 99, and by reverse courses back on true lines to the southeast corner of section 6, establishing the quarter- section corners, and noting courses, measurements, and distances as prescribed by law. In townships contiguous to standard parallels the above method is varied as follows: In every township sout]i of the principal base line which closes on a standard parallel, the surveyor will begin at the southeast corner of the township and measure westward, establishing the half-mile and mile corners and noting their distance from the preestablished corners. He will then proceed to subdivide as directed under the above head. In townships north of the principal base line -which close on the standard parallel, the section lines must be closed on the standard parallel with true meridian lines instead of course lines, as directed for townships otherwise situated ; and the connections of the closing corners with the LAND SURVEYING. 703 preestablished standard corners are to be ascertained and noted. In case the surveyor is unable to close the lines on account of the standard not having been run for some reason, as be- fore mentioned, he will then plant a temporary post or con- struct a mound at the end of the sixth mile, thus leaving the lines and their connections to be finished when the standard shall have been run. 1316. Water Frontage. — Departures from the gen- eral system of dividing land have been authorized by law, especially in the case of water frontage. In surveying the public lands of Louisiana, which border on rivers, streams, lakes, and bayous, surveyors were author- ized to divide the land with water frontages of fifty-eight poles and running back four hundred and sixty-five poles in depth, "and of such shape and bounded by such lines as the nature of the country will render practicable and most con- venient. " Later, authority was given to survey lands with two acres water frontage and running back a depth of forty acres, tracts so surveyed to be offered for sale entire in- stead of in half quarter-sections. In localities where it would best subserve the interests of the people to have fronts on the navigable streams and running back into the uplands for timber, surveyors were authorized to increase the quantity of land so as to give four acres frontage and forty acres in depth, giving tracts of 160 acres, but in so doing they were only to survey the lines between every four lots (or 640 acres), establishing the boundary posts or mounds in front and in rear, at the distances requisite to secure the quantity of 160 acres to each lot, either rectangularly where practicable or at oblique angles where otherwise. The angle is not important so long as the principle is adhered to of making, as far as possible, the rear lines square with the regular sectioning. 1317. Meandering. — This name is applied to the usual mode of traversing or surveying a navigable stream. The instructions for this work are in part as follows: Both 704 LAND SURVEYING. banks of navigable rivers are to be meandered by taking the courses and distances of their sinuosities and the same are to be entered in the meander field book. At those points where either the township or section lines intersect the banks of a navigable stream, posts, or, where necessary, mounds of earth or stone are to be established at the time of running these lines. These are called " meander corners," and, in meandering, the surveyor will commence at one of these corners on the township line, coursing the banks and measuring the distance of each course from the commencing corner to the next "meander corner " upon the same or another boundary of the same township, carefully noting intersections with all the intermediate meander corners. By the same method meander the opposite banks of the river. The crossing distance between the meander corners on the same line is to be ascertained by triangulation, in order that the river may be protracted with entire accuracy. The particulars are to be given in the field notes. The courses and distances on meandered navigable streams are the bases for the calculation of the true areas of the tracts of land (sections, quarter-sections, etc.), known to the law as fractional and bounding on such streams. The surveyor is also to meander, in manner aforesaid, all lakes and deep ponds of the area of twenty-five acres and upwards, also navigable bayous. As traverse tables are generally calculated to 15' angles, it is advisable to make meander courses read to quarter degrees instead of intermediate minutes, except in closing or where the extreme length of a side of a lake or stream falls in one course. The precise relative position of islands in a township made fractional by the river in which they are situated is to be determined trigonometrically. To meander islands crossed by government lines, meander corners are previously estab- lished at opposite points on the shore of the island, and the meanders run from one to the other. Should the island not be crossed by a line, measure a special base line from the LAND SURVEYING. 705 meander corner nearest to the island, triangulating to and establishing at any convenient point on the island a special meander corner from and to which the meanders of the island start and close, 1318. Marking Lines. — All lines on which are to be established the legal corner boundaries are to be marked after this method, viz. : Those trees which may intercept the line must have two chops or notches cut on each side of them without any other marks whatever; these are called sight trees or line trees. A sufficient number of other trees standing nearest to the line on either side of it are to be blazed on two sides diagonally or quartering towards the line, in order to render the line conspicuous and readily traced, the blazes to be opposite to each other, coinciding in direc- tion with the line where the trees stand very near it, and to approach nearer each other the further the line passes from the blazed trees. Due care must ever be taken to have the line so well marked as to be readily followed. 1319. Marking Corners. — After a true coursing and most exact measurements, the corner boundary is the consummation of the work for which all the previous pains and expenditure have been incurred. A boundary corner in a timbered country is to be a tree, if one be found at the precise spot; and if not, di post is to be planted thereat, and the position of the corner post is to be indicated by trees adjacent (called bearing trees), the angular bearings and distances of which from the corner are facts to be ascertained and recorded by the surveyor. In a region where stones abound, the corner boundary will be a small monument of stones alongside of a single marked stone for a township corner and a single stone for all other corners. In a region where neither timber nor stone is available, the corner will be a mound of earth of prescribed size varying to suit the case. When posts are used, their length and size must be pro- portional to the importance of the corner, whether township, section, or quarter-section post. 706 LAND SURVEYING. Township corner posts are three inches square and set at least twenty-four inches above ground. Where a township post is at a corner, common to four townships, it is to be set in the ground diagonally, as shown « in Fig. 311, and the cardinal points of the compass indicated by lines cut or sawed out of its top at p^-^ least one-eighth of an inch deep, as shown in the figure. On each face of the post is to be marked Fig. 311. the number and range of the particular township which it faces. Thus, if the post be a common boundary to four townships, viz., one and two south of the base line and range two west, and also one and two south of the base line and range three west, the face markings will be as follows : ( R. 2 W From N to E ^ T. 1 S ( S31 / 3 W From N to W - 1 S 1 36 1 2 W From E to S - 2S 1 6 ( 3 W From W to S - 2S ( 1 R3W TIS R2W TIS R3W R2W T2S T2S Pig. 812. The position of the post which is here taken as an example is shown in Fig. 312. These marks are neatly chiseled into the wood, and are also marked with red chalk. The number of the sections which they respectively face will also be marked on the township post. • Section or mile posts, being corners of sections, when they are common to four sections, are to be set diagonally in the earth (in the manner provided for township posts), and with similar marks cut in the top to indicate the car- dinal points of the compass, while on each side of the post is LAND SURVEYING. 707 cut the number of the particular section which the side faces. Also, on one side is to be marked the number of its township and range. To make such marks more conspicuous and durable, red chalk is applied. A quarter-section or half-mile post is to have no other mark than ^ S to indicate what it stands for. Township posts are to be notclicd with six notches on each edge or angle corresponding to the cardinal points of the compass. All mile posts on township lines must have as many notches on opposite angles as they are miles dis- tant from the corresponding township corners. Each of the posts at the corners of sections in the interior of a town- ship must have on their four angles, corresponding to the cardinal points, as many notches as they are miles distant from the corresponding township corners. The four sides of the post will indicate the, numbers of the sections which they respectively face. Should a tree be found at the place of any corner it will be marked and notched in the manner before described and will serve in place of a post; the kind of tree and the diameter must be given in the field notes. The position of all corner posts or corner trees of what- ever description, which may be established, is to be perpet- uated in the following manner, viz. : From such post or tree, the courses shall be taken and the distances measured to two or more adjacent trees in opposite directions as nearly as may be, which are called bearing trees, and are to be blazed near the ground with a large blaze facing the post and hav- ing one notch in it, neatly and plainly made with an ax, square across, and a little below the middle of the blaze. The kind of tree and the diameter of each are facts to be clearly set forth in the field book. On each bearing tree the letters B. T. must be distinctly cut into the wood in the blaze a little above the notch or on the bark, with the number of the range, township, and section. At all township corners and at all section corners on range or township lines y<7//r bearing trees are to be marked in this manner, one in each of the adjoining sections. 708 LAND SURVEYING. At interior section corners four trees, one to stand within each of the four sections to which such corner is com- mon, are to be marked in the manner aforesaid if such be found. From quarter-section and meander corners, two bear- ing trees are to be marked, one within each of the adjoining sections. Stones at township corners (a small monument of stones being alongside thereof) must have six notches cut with a pick or chisel on each edge or side towards the car- dinal points; and where used as corners in the interior of a township, they will also be notched with a pick or chisel to correspond with the directions given for notching posts similarly situated. Stones when used as quarter-section corners will have \ cut on them, on the zvest side in nortJi and soutJi lines, and on the nortJi side in east and zvcst lines. Wherever bearing trees are not found, mounds of earth or stone are to be raised around posts on which the corners are to be marked in the manner aforesaid. Wherever a mound of earth is adopted, the same will present a pyra- midal shape. At its base on the earth's surface a quadran- gular trench will be dug ; a spade deep of earth being thrown up from the sides of the line outside the trench, so as to form a continuous elevation along its outer edge. In mounds of earth common to four townships or four sections, they will present the angles of the quadrangular trench diagonally to the cardinal points. In mounds common only to two townships or two sections, the sides of the trench will face the cardinal points. Prior to piling up the earth, in a cavity, formed at the corner boundary point, is to be deposited a stone, or a portion of charcoal; or a charred stake is to be driven twelve* inches down into such center point to be a witness for the future. The surveyor is further specially enjoined to plant midway between each pit and the trench seeds of some tree, those of fruit trees adapted to the climate being always to be preferred. Double corners are to be found nowhere except on the standard parallels or correction lines whereon are to appear LAND SURVEYING. 709 both the corners which mark the intersection of the lines which close thereon and those from which the surveys start in the opposite direction. The corners which are established on the standard parallel at the time of running it are to be known as ^'- standard corners,'" and in addition to all the ordinary- marks (before described) they will be marked with the letters S. C. The closing corners will be marked C. C. 1320. Field Books. — There are several field books, viz. : 1. Field Books for the meridian and base lines, show- ing the establishment of toiunship, section, or mile, and quarter-section, or half-mile boundary corners thereon ; with the crossings of streams, ravines, hills, and mountains; the character of the soil, timber, minerals, etc. These notes will be arranged in series by mile stations consecutively from number one to number . 2. Field Books for the standard parallels or correction lines, showing the establishment of the township, section, and quarter-section corners, besides exhibiting the topography of the country on line as required on the base and meridian lines. 3. Field Books for exterior lines of townships, showing the establishment of the corners on line, and the topography as aforesaid. 4. Field Books for the subdivision of townships into sections and quarter-sections; at the close whereof will follow the notes of the meanders of navigable streams. Those notes will also show by ocular observation the estima- ted rise and fall on the line. A description of the timber, undergrowth, surface soil, and minerals upon each section line is to follow the notes thereof, and not be intermixed with them. 5. The Geodetic Field Book, comprising all triangulations, angles of elevation and depression, leveling, etc. 1321. Retracing Old Lines. — The original surveys of lands in the older States of the American Union were 710 LAND SURVEYING. imperfectly made and full of errors. This was owing to two principal causes; viz., the cheapness of the lands and the lack of skill in the surveyors. Boundary lines described in deeds and shown in maps as straight are found to be crooked on the ground; tracts contain less or more land than called for in descriptions. Records of adjoining tracts make one to overlap another or leave an unclaimed gore between them. These discrepancies and blunders often render the work of the surveyor, when retracing old boundaries or establishing corners, exceedingly difficult, and great tact and judgment are often necessary in making amicable and satis- FiG. 318. factory adjustments of contending claims. In general, old boundaries, such as line trees, stone monuments, and fences are accepted as holding ; but, before retracing lines the surveyor should, if possible, secure the consent of adjacent owners to abide by such monuments and boundaries, irre- spective of the lines or quantities called for in contracts or deeds. It must be borne in mind that the bearings of lines are each year undergoing a slight change which, in a long period, amounts to several degrees, and if the lines were re- run according to original bearings as given in descriptions, they would enclose a tract differing widely from that in- cluded in the original survey. The surveyor must accord- LAND SURVEYING. 711 ingly determine the amount of magnetic variation or change which has taken place between the time of the original survey and the date of the survey about to be made, and having determined such change or variation, he must make the original bearings conform to the calculated variation before commencing the survey. Fig. 313 illustrates the effect of magnetic variation in altering the direction of lines. The figure A B C D Ogives the outline of a tract according to the original survey, and A B' C D' E' the relative directions of the boundaries when resurveyed with the original bearings, there having been during the intervening time a change in magnetic variation of 3° west. Let columns 1, 2, and 3 in the accompanying diagram give the courses, original bearings, and distances, and col- umn 4 the cor- rected bearings which the original boundaries will have, when allow- ance has been made for the mag- netic variation. When the north end of the needle has been moving westerly, i. e., when the variation or chatige is west, the corrected or present bearings will be the sums of the change and the old bearings which were northeasterly or soiitJnvesterly and the differences of the change and the old bearings which were northwesterly or southeasterly ; when the variation or change is easterly^ the corrected or present bearings will be the differences of the change and the old bearings which were northeasterly or southwesterly and the sujus of the change and the old bearings which were north- westerly or southeasterly. It will be seen, by reference to Arts. 1211 and 1212, that declination is the reverse of i>ariation, i. e. , a west decli- nation results when the variation or movement of the N end 1 2 3 4 Courses. Bearings. Distances. Corrected Bearings. A B N68°00' E 210 N7r00' E B C S 73° 00' E 200 S 70° 00' E CD S 8° 00' E 162 S 5° 00' E D E S 87° 00' W 326 S 90° 00' W EA N 28° 00' W 176 N 25° 00' W 712 LAND SURVEYING. of the needle is to the east, and <'rtj/ declination results when the movement of the N end of the needle is to the west. By this rule the bearings given in column 4 are obtained. Before commencing the survey, the surveyor should cor- rect all the bearings and write them out together with the original bearings in their proper order. 1322. How to Determine Magnetic Variation. — If the date of the original survey is known, the amount of variation may be determined from published tables giving the yearly variation for different sections of the country, but the date of the survey is often omitted. The date of the deed must not be taken as the date of the survey. If one of the original boundaries remains unchanged, the magnetic variation can be determined at once by taking the present bearing of the line. The difference between the present bearing and that of the original survey is the re- quired correction. The corrections are then to be made in the original bearings and the resulting courses run out. Where the measurements fall short of or overrun the original measurements, corrections must be made, locating the original corners if they can be found or establishing new ones, and, if possible, to the mutual satisfaction of adjoining proprietors. 1323. Establishing New Boundaries. — Where the description and map show a boundary to be a straight line and the actual boundary is found to be crooked, it is a good policy to establish a new and straight boundary by the prin- ciple of "give and take," providing adjoining owners will agree to the adjustment. Fig. 314 illustrates the principle which is frequently em- ployed in correcting such boundaries. M^ D c Fig. 314. Let A and E be two corners and let the boundary line joining them be described and shown in the map as a straight LAND SURVEYING. 713 line. Let the irregular line A B CD £' represent the actual boundary. It is evident that the dotted straight line A E may be substituted for the irregular line A B C D E, and would equitably divide the adjoining properties. The prin- ciple of give and take is applied, the adjoining owners ma- king exchanges .of equal areas. The location of the new boundary is determined by ma- king a careful survey of the old boundary and platting it to a large scale; a fine thread is then stretched on the plat and a line of division made as closely as may be estimated by the eye. The areas of the equalizing triangles are then calcu- lated by scaling their dimensions, and if they do not balance the dividing line can readily be shifted until the desired result is obtained. The line is then measured on the ground and permanent corners established. Where the boundary is in woodland, careful search must be made for line and bearing trees. Blaze marks are very enduring, being easily recognized on some varieties of trees after a lapse of a quarter of a century. 1324. Lost and Obliterated Corners. — Corner monuments of perishable material, such as wooden posts, decay and in time become obliterated. A pile of stones, which is commonly used as a corner, may become scattered, and, unless permanent witnesses remain, it may be a difficult matter to restore the landmark. The most enduring wit- nesses are live trees which are disposed as shown in Fig. 315. Three trees facing the corner are chosen ; in each tree three notches are cut in the side facing the corner, and the bearing and distance from each to the corner are recorded in the notes. A sketch is made in the note book giving the relative positions of the corner and the witness trees. When the corner is lost, but the witness trees still remain, the cor- ner is restored by describing intersecting arcs from the wit- ness trees as centers with radii equal to the given distances from the original corner. Where both corner and witnesses are gone, it is best to run from both directions towards the missing corner, placing the corner at the intersection of the 714 LAND SURVEYING. lines. The surveyor need not expect to find his measure- ments agree with those in original surveys, but he can save his successor much annoyance and trouble by careful and accurate work. He should always give both in map and in description the exact date of the survey; the direction of Fig. 315. courses should also be given both in writing and figures, and the corners should be fully described. A stone monument is the best corner, and should always be used where the material is available. AREAS. 1325. The area of a surface is its superficial content. In the surveying of public lands all measurements are made with the surveyor's chain, commonly known as Gunter's chain, from the name of the inventor. It is GO feet in length and contains 100 links, each 7.92 inches long. At each interval of ten links a brass tag is attached with tally points similar to those on the engineer's chain described in Art. 1214. Tables of surveyor's linear and square measure are given in Arts. 209 and 211. For land areas the unit of measurement is the square foot = 144 square inches, though LAND SURVEYING. 715 areas of considerable extent are usually expressed in acres. An acre contains 43,500 square feet of surface. Rectangular areas are determined by multiplying the length in feet by the breadth in feet, and dividing the product by 43,500, which gives the area in acres. In surveys of farms or larger tracts, dimensions are given in chains and links. The product of such dimensions is in square chains, which, divided by 10 (the number of square chains in an acre), gives the area in acres. Example. — A rectangular piece of land is 1,060 feet in length by 820 feet in breadth ; required, the area. Solution.— 1,060 x 820 = 869,200 sq. ft. 869,200 -h 43,560 = 19.954 acres. Ans. DIFFERENT METHODS OF COMPUTING AREAS. 1326. By Dividing the Plat into Triangles.— Farms, especially in the older States of the Union, are com- monly of irregular form. The readiest and — where the measurements have been accurately made — a sufficiently accurate method of determining areas is as follows : Make an accurate plat of the tract to as large a scale as may be conveniently used. Divide the resulting figure, an irregular polygon, into triangles, making their sides of as nearly equal length as possible. It is evident that the sum of the areas of the several triangles into which the polygon is divided is equivalent to the area of the polygon. This mode of calcu- lating area is illustrated in Fig. 316. Let the irregular polygon A B C D E Fhe the outline of a tract of land the area of which is required. Draw the diagonals B F, C F, and C E, dividing the figure into four triangles, the combined area of which is equal to the area of the polygon. From the vertexes A, B, D, and E drop the perpendiculars A G, B //, D K, and E L upon the opposite bases of the triangles. The lengths of the several bases and altitudes are measured with the scale and the areas of the several triangles calculated by the rule : the area of a trian- gle is equal to one-half the product of its base and altitude. 71G LAND SURVEYING. The sum of the areas of the several triangles is equal to the area of the polygon. Fig. 316. 1327. By Dividing the Plat into Trapezoids. —A plat of the area having been made, it may be resolved into trapezoids by either of the methods shown in Figs. 317 and 318. In Fig. 317 the line A N is drawn parallel to B C, and the lines B M, K H, and E L are drawn perpendicular to A H, dividing the figure into trapezoids and the triangle H D K. The area of each trapezoid is equal to one-half the sum of its bases multiplied by its altitude, and the sum of their areas together with the area of the triangle is equiva- lent to the area of the polygon A B C D E F. In Fig. 318 a base line H Pis drawn, and from each angle of the polygon perpendiculars are drawn to it. The sum of the areas of the three trapezoids A B K H,B C N K, C D P N is found, and LAND SURVEYING. 717 from that sum, the sum of the areas of the trapezoids A G L //, G F M L, F E O M, and E D P O \s subtracted. The difference of these sums is the area of the polygon A B C D E FG. LATITUDES AND DEPARTURES. 1328. Definitions. — The latitude of a point is its distance north or south of some '^parallel of latitndc" or line running cast and lucst. The longitude of a point is its distance east or west of some meridian or line running north and south. The meridian from which the longitude of a point is reckoned is the magnetic meridian. The distance which one end of a line is due north or south of the other end is called the latitude of that line. The distance which one end of -a line is due east or west of the other end is called the departure of that line. The latitude and departure of a line and its determination are explained in Fig. 319. Let A B he the given line whose length and angle with the magnetic meridian A^ 5 is known, and whose latitude and departure are required. From B draw B C perpen- dicular to N S^ forming the right-angled triangle A C B,'\x\. which the sides C A and C B about the right angle are, re- spectively, the latitude and the departure of the line A B. Then, A C ^=- A B y, cos bearing, and B C ^ A B X sin bearing; that is, the latitude is equal to the product of the cosine of the bearing and the length of the course; and the departure is equal to the product of the sine of the bearing and the length of the course. Let A />' = 400 feet and the bearing of A B, i. e., the angle B A C= 30°. Then, latitude A C= co.) 30" X 400 = Fig. 319. 718 LAND SURVEYING. .86G03 X 400 = 346.412 ft., and departure B C = sin 30° X 400 = .50000 X400 = 200 ft. If the course be northerly, the latitude will be north, marked + , and be additive; if southerly, it will be marked — , and be subtractive. If the course be easterly the departure will be east, marked +, and be additive; if westerly, the departure will be west, marked—, and be subtractive. 1329. Traverse Tables. — The latitude and departure of any distance for any bearing can be found by a table of natural sines and cosines, but for facilitating work special tables, called traverse tables, have been prepared. They usually give the latitude and departure for any bear- ing to each quarter of a degree and for distances from 1 to 9. To t(se the tables (see traverse tables, or Latitudes and Departures of Courses), find the number of degrees in the bearing in the left-hand column if the bearing be less than 45°, and in the right-hand column if the bearing be greater than 45°. The numbers on the same line running across the page are the latitudes and departures for that bearing and for the respective distances, 1, 2, 3, 4, 5, 6, 7, 8, 9, which appear at the top and bottom of the pages, and which may be taken to represent links, rods, feet, chains, or any other unit. Thus, if the bearing be 10° and the distance 4, the latitude will be 3.939 and the departure .G95; with the same bearing, and the distance 8, the latitude will be 7.878 and the departure 1.389, or double the latitude and departure for the distance 4. Any distance, however great, can have its latitude and departure readily obtained from this table, since, for the same bearing, the latitude and departure are directly proportional to the distance because of the similar triangles which they form. Hence, the lati- tude and departure for 80 is ten times the latitude and departure for 8, and is found by moving the decimal point one place to the right; that for 500 is 100 times the latitude and departure for 5, and is found by moving the decimal LAND SURVEYING. 719 point two places to the right, and so on. By moving the decimal point one, two, or more places to the right the latitude and departure may be found for any multiple of any number given in the table. In finding the latitude and departure for any number such as 453, the number is resolved into three numbers, viz.: 40 and the latitude and departure 5 for each taken from the table 3 and then added together. 453 We thus obtain the following Rule.— Write dozvn the latitude and departure, neglecting the decimal points, for the first figure of tJie given distance; write under them the latitude and departure for the second figure, setting them one place further to the right; under these place the latitude and departure for the third figure, setting them one place still further to the right, and so continue until all the figures of the given distance have been used ; add these latitudes and departures and point off on the right of their sums a ?iumber of decimal places equal to the number of decimal places to which the tables being used are carried; the resulting numbers will be the latitude and de- parture of the given distance in feet, links, chains, or whatever unit of measurement is adopted. Example. — A bearing is 16° and the distance 725; what is the lati- tude and departure ? Distances. Latitudes. Departures. 700 6729 1929 20 1923 0551 5 . 4806 1378 725 6 9 6.936 199.788 Solution. — Taking the nearest whole numbers and rejecting the decimals, we find the latitude and departure to be 697 and 200. When a occurs in the given number the next figure must be set two places to the right, as in the following example: Example. — The bearing is 22° and the distance 907 feet; required, the latitude and departure. 730 LAND SURVEYING. Solution. — Distances. Latitudes. Departures. 900 8 34 5 3371 7 6490 2 622 907 840.990 3 3 9.722 Here the place of in both the distance column and in the latitude and departure columns is occupied by a dash — . Rejecting the deci- mals, the latitude is 841 feet ^■"' and the departure 340 feet. When the bearing is more than 4~)°, the names of the columns must be read from the bottom of the page. The latitude of any bearing, as 60°, is the departure of its complement, 30'; and the departure of any bearing, as 30°, is the latitude of its complement, 60\ This will be readily understood from an inspection of Fig. 320, in which if A' 5 be the mag- netic meridian and BOA = 60^ the bearing, then A O \s the latitude and A B the departure. If, now, 6> C be made the meridian and i? 0(7 =30° (the complement of BOA) the bearing, then O C (the equal of A B) is the latitude, and B C (the equal of A O) the departure. Example. — Let O B = 1,326 feet, and its bearing = 60°. Solution. — Distances. Latitudes. Departures. 1,000 0500 0866 300 1500 2598 20 1000 1732 6 3 00 5196 1326 Fig. 330. 663.000 1148.316 of and The required latitude is 663 feet and the departure 1,148 feet. Where the bearings are given in smaller fractions degrees than is found in the table, the latitudes departures can be found by interpolation. Traverse tables are chiefly employed in testing the accuracy of surveys, platting them, and calculating their content. 1330. Testing a Survey. — When a surveyor has completed the survey of a field or farm by taking bearings LAND SURVEYING. 721 and measuring courses, it is evident that he has gone as far north as south and as far east as west. The sum of the north latitudes shows how far north he has gone, and the sum of the south latitudes shows how far south he has gone. The sum of the east departures shows how far east he has gone, and the sum of the west departures shows how far west he has gone. Hence, if the survey has been correctly made these sums will be equal or will balance. The entire operation of testing a survey is illustrated in the following example: Latitudes Departures. N + S - E + w - 1 N 34i°E 273 226 154 2 N 35i° E 128 10 128 , 3 S 56i° E 220 121 184 4 S 34i° W 353 292 199 5 N56i" W 320 177 267 34r 273 56r 220 413 5786 2480 112 6 3940 1 68J 225.640 153.688 1097 1097 12 0.6 7 1673 1673 184.03 5 6i° 320 1656 1104 176.64 413 35r 128 34r 353* 2502 166! 466. 0079 0157 0621 266.88 466 0997 1994 7975 10.098 12 7.615 2480 • 1688 4133 2814 2480 1681 291.810 198.628 Adding up the north and south latitudes we find them to exactly balance each other, as do the east and west departures, which proves the survey to be correct. On account of the inherent defects of the compass and the errors which are 7%2 LAND SURVEYING. liable to occur in measurement, especially on rough and extensive areas, it is but rarely that the survey will exactly balance. A moderate discrepancy, which would indicate what may be called unavoidable errors, will be allowable, and the survey accepted as correct. How great a difference in the sums of the columns may be allowed is a doubtful question. Every surveyor of experience knows the average degree of accuracy of his work, and will readily distinguish between a serious error and an allowable inaccuracy. 1331. Balancing a Survey. — When the sums of the latitudes and of the departures do not equal each other, and yet the difference does not indicate any error, the different latitudes and departures are modified so that their sums shall be equal. This process is called balancing the survey. The error is distributed among the different courses in proportion to their length by the following Rule. — As the sum of all the courses is to any separate course^ so is the ivJiole difference in latitude to the correction for that course. A similar proportion corrects the departures. An example illustrating the process of balancing a survey is given below. In this example four separate columns are given for the corrected latitudes and departures. In prac- tice, however, the corrected latitudes and departures are written in red ink directly above the original ones, which are crossed out with red ink. The distances given are in chains: sta- tions. Bearings. Dis- tances. Latitudes. De- partures. Corrected Latitudes. Corrected De- partures. N + S- E + W- N-f-l S- E-l- W - 1 2 3 4 N 53° E S 29rE S 31f ° W N 61= W 10.63 4.10 7.69 7.13 6.54 3.46 3.56 6.54 8.38 2.03 4.05 6.24 6.58 3.48 3.55 6.51 8.;m 2.01 4.08 6.27 29.55 10.00 10.10 10.41 10.29 10.06 10.06 10.35 10.35 LAND SURVEYING. 723 The corrections are made by the following proportions; For Latitudes. For Departures. 29.55 . 10.63:: 10 : 4 links. 29.55 : 10.63:: 12 : 4 links. 29.55 4.10:: 10: 1 link. 29.55 4.10:: 12 : 2 links. 29.55 7.69:: 10 : Slinks. 29.55 • 7. 69:: 12: Slinks. 29.55 : 7.13::10:2 1inks. 29.55 7.13:: 12: 3 links. 10 12 This rule should not always be strictly followed, especially if one line has been measured over rough and broken coun- try, while the others have been measured over smooth and open ground. In such a case the greater part of the error will probably lie in the rough line, and, consequently, it should receive the larger share of the correction. A slight alteration of a bearing will sometimes balance a survey. This may be done where an obstructed sight has probably caused an error in the bearing. 1332. Application of Latitudes and Departures to Platting. — Rule three columns, one for stations, the next for total latitudes, and the third for total departures, as shown in the following diagram. To obtain the total latitudes, begin at any station, the extreme east or west one is preferable, and add up algebra- ically the latitudes of the following stations, observing that north latitudes are plus (+)» and south latitudes minus ( — ). In the same manner find the algebraic sum of the depar- tures for the different stations, placing each successive sum opposite its proper station. In the example given in Art. 1330, beginning at Station 1, we obtain the fol- lowing results. The work is proved to be correct by the latitudes and depar- tures for Station 1 coming out equal to 0. To apply these total latitudes and de- partures in platting, Stations. Total Latitudes from Station 1. Total Departures from Station 1. 1 0.00 0.00 2 + 2.26 + 1.54 3 + 2.36 + 2.82 4 + 1.15 + 4.66 5 -1.77 + 2.67 1 0.00 0.00 7U LAND SURVEYING. we draw a meridian through the point taken as Station 1, Fig. 321. Scale off from Station 1 upwards on this meridian the latitude 2.26 chains to A and to the right from A, and perpendicularly lay off the departure 1.54 chains to Station 2. Join 1-3. From 1 again lay off the latitude 2.3G ( = 2.26 + 10) chains to B, and to the right perpendicularly the departure 2.82 (= 1.54 + 1.28) chains to Station 3. Join 2-3, and proceed in like manner to locate Stations Fig. 321. .^ and S, laying off + latitudes above Station 1 and + departures to the right of the meridian, and — latitudes below Station 1 and — departures to the left of the merid- ian. The principal advantages of this mode of platting are rapidity of work, the fact that each course is platted independently, and the certainty of the plats closing, pro- vided the latitudes and departures have previously been balanced. 1333. Calculating the Content.— The survey of a field or farm having been made and platted, the content can always be found by dividing the plat into triangles, and LAND SURVEYING. 725 scaling off their bases and perpendiculars from which the contents are calculated. This and other methods previously mentioned are only approximate, the degree of accuracy depending upon the largeness of the scale and the skill of the draftsman. The method of calculating content by latitudes and departures is perfectly accurate, and does not require the previous preparation of a plat. 1334. Definitions. — If a meridian be passed through the extreme east or west corner of a field, the perpendicular distance from any station to that meridian is the longitude of that station, additive or plus if east and subtractive or Fig. 322. minus if west. The distance of the middle point of any line, such as the side of the field, from the meridian is called the longitude of that side. The difference of the longitudes of the two ends of a line is called the departure of the line; the difference of the latitudes of the two ends of a line is called the Uititude of the line. 72G LAND SURVEYING. 1335. Longitudes.— Let N S, Fig. 322, be the meridian passing through the extreme westerly station of the field A B C D E. From the middle and ends of each side draw perpendiculars to the meridian. These perpendicu- lars will be the longitudes and departures of the respective sides. The longitude F G of the first course A B is evi- dently equal to one-half its departure H B. The longitude / K of the second course B C '\'& equal to J L -\- L M -\- M K equal to the longitude of the first course plus half the de- parture of the first course plus half the departure of the course itself. The longitude F^of some other course E A, taken anywhere, is equal to IV X — V X— U V, or equal to the longitude of the preceding course minus half the de- parture of that course minus half the departure of the course itself, i. e., equal to the algebraic sum of these three parts, remembering that south latitudes and west longitudes are negative, and, therefore, to be subtracted when the instructions are to make an algebraic addition. To avoid fractions, the preceding expressions are doubled, whence we deduce the following Rule for Double Longitudes : The double longitude of the first course is equal to its departure. The double longitude of the second course is equal to the double longitude of t lie first course plus the departure of that course plus the departure of the second course. The double longitude of the third course is equal to the double longitude of the second course plus the departure of that course plus the departure of the course itself. The double longitude of any course is equal to the double longitude of the prcccditig course plus the departure of that course plus the departure of the course itself. The double longitude of the last course {as well as of the first) is equal to its departure. This result, when obtained by the above rule, proves the accuracy of the calculation of the double longitudes of all the preceding courses. LAND SURVEYING. 727 Fig. 323. it is equal to the product 1 336. Areas. — The following is an application of the rule for finding areas by double longitudes. See Fig. 323. Let A B Ch& 2l three-sided field, of which A is the most westerly- station. Through A draw a meridian, and from the stations B and C and the middle points of the three sides of the field draw perpendiculars to the meridian. It is evident that the area of the field A B C is equal to the area of the trapezoid D B C E less the triangles A D B zxi6.A E C. The area of the triangle A D B \s equal to the product oi A Dhy F G, i. e. of the latitude of the first course by its longitude. The area of the trapezoid D B C E is equal to the product oi D E hy half the sum oi D B and E C, or H K, i. e., it is equal to the product of the latitude of the second course by its longitude. The area of the triangle A E C is equal to the product oi A E by half E C, ov L M, i. e. , it is equal to the product of the latitude of the third course by its longitude. The bearing of the course A Bis^ E, and that of C^i is N W. Their latitudes are, therefore, north. The bearing of the course .5 C is S E, and its latitude is south. Calling the products in which the latitude is north, north products, and the products in which the latitude is south, south products, we find the area of the trapezoid to be a south product and the areas of the triangles to be north products. The difference of the north products and the south prodifcts is, therefore, the area of the three-sided field ABC. Using double longitudes, to avoid fractions, in each of the preceding products, their difference will be double the area of the field ABC. Take, now, a four-sided field, A B C D, Fig. 324, and drawing a meridian through its most westerly station A, 728 LAND SURVEYING. and longitudes as in the preceding case, it will be evident from inspection that the area of the field A B C D is equal to the trapezoid F C D G, diminished by the area of tri- angles A G D, A E B, and the trapezoid E B C F. The area of the triangle A E B is equal to the product of the latitude A E of the first course by its longitude H K. Its product is north. The area of the trapezoid E B C F is equal to the product of the latitude E F of the second course by its longi- tude L M, and is also :i north product. The area of the trapezoid F C D G is equal to the product of the latitude F G oi the third course by its longi- tude N (9, a south product. The area of the triangle A G D'\s equal to the prod- uct of the latitude A G oi the fourth course by its longi- tude P Q, a north product. Subtracting the sum of the north products from the sum of the south products the difference is the area of the field A B C D. If double longi- tudes had been used, as in the previous case, the difference would have been double the area of the field. Fig. 324 1337. The Application of I>oul>le Longitudes to the FindinK of Areas. — Whatever the number or direc- tions of the sides of a field or any surface enclosed by straight lines, its area will always be equal to half the dif- ference of the north and south products arising from multi- plying together the latitude and double longitude of each course or side, whence the following LAND SURVEYING. ' 729 General Rule for Finding Areas : 1. Prepare ten columns, headed as in the following exam- ples, and in the first three write the stations, bearings, and distances. 2. Find the latitudes and departures of each course by the traverse table, as directed in A rt. 1329, placing them in the four following columns. 3. Balance them as in Art. 1331, correcting them in red ink. If. Fifid the double longitudes as in Art. 1335, zvitJi refer- ence to a meridian passing through the extreme east or west station, and place them in the eighth column. 5. Multiply the double longitude of each course by the corrected latitude of that course, placing the north prod- ucts in the nintli column and the south products in the tenth column. 6. Add the last two columns ; subtract the smaller sum from the larger, and divide the difference by two. The quotient will be the content required. 1338. To Find the Most Easterly or Westerly Station of a Survey. — Make a rough hand sketch of the tract, giving the sides, their approximately true direction, and length. The most easterly or westerly station may then be determined from an inspection of the sketch. Example 1 of this article refers to the five-sided field, a plat of which is given in Fig. 321, and the latitudes and de- partures of which were calculated in Art. 1330. Station 1 is the most westerly in the plat, and the meridian will be passed through it. The double longitudes are found by applying the rule for double longitudes, given in Art. 1335. As the additions are made algebraically, due attention must be paid to the signs. The double longitudes are marked D. L., as shown in the marginal diagram. These double longitudes are ob- tained by the following operation. As stated in- the rule, the double longitude of the first course is equal to the 730 LAND SURVEYING. stations. D. L. 1 + 1.54D.L. + 1.54 + 1.28 2 + 4.36D.L. + 1.28 + 1.84 3 + 7.48D.L. + 1.84 -1.99 4 + 7.33D.L. -1.99 -2.67 5 + 2.67D.L. departure. By reference to the given example, we find that the departure of the first course is 1.54 chains, an cast departure, and, there- fore, positive. We record this in the column headed D. L., opposite Station 1. The D. L. of the second course is equal to the D. L. of the first course plus the departure of that course plus the de- parture of the second course. Accord- ingly, we place under the D. L. of the first course, the departure of that course, viz., + 1.54, and the departure of the second course, viz., + 1-28, as given in the east departure column of the exam- ple. This sum, viz., -|-4.36 is the D. L. of the second course and placed opposite Station 2. The D. L. of the third course is equal to the D. L. of the second course plus the departure of that course plus the departure of the third course. Accordingly, we place under the D. L. of the second course the departure of that course, viz., + 1.28, and the departure of the third course, viz., + 1.84. This sum, + 7.48, is the D. L. of the third course, which we place opposite Station 3. In a similar manner we find the D. L. for the fourth and fifth courses. The double longitude of the last course is equal to its de- parture, which proves the work. The double longitudes of the courses are then multiplied by their corresponding lati- tudes, and the content of the field obtained as directed in the given rule. Had the meridian been supposed to pass through Station Jt, the most easterly station, all the longitudes would have been west or minus, but the difference in the double areas would have been the same, giving the same content as before. The following examples will give the student some prac- tice in the use of traverse tables, and in applying latitudes and departures in the calculation of areas: LAND SURVEYING. 731 o5 £ 3 9 <5 1 o CO «c o Ort< oji-; "^ CO -4 CI ^^ CO + ■* O OS so ■ n5 CO CI ?D 00 V 1 . a «c so -* 10 !0 .-; ^ t-' {^ -i* lO SO -4 eo CO 00 O CO »ffl at 3 •1-H d CO Tj< lO TH (1, J J J J Q Q Q Q >-] o?oeo ioeo-«J* ^3^ ci CO CO l-OO CO 00 aoci X eor-i * ci t> la OQ t- u * »c eo. t-05 1 CO P9. so CO ^ Tj 1 iC cs. 00 • CO eo eo «a do y—* T™i •0 3 ^ eocs. y^ eo t- + icaa. »o 00 z edesL eo do T-l 1—1 eo c.H ■ oS Cl CO en be WW ^ ^ sfXOO OS?} t- CO coo iO Q eo ecco d «o w osos ^ © T-iOD © X iO (NWOJ ■«t l-OO C(N 00 eo<»os i-Hoo 5> «o» cr 1/1 V ^ 3 u OS a + lO*"*. 00 to 00 CJ Q QOOR JO t- 1—1 T-l M ■*^ '"' t-^t- I eo"«)<.i-jo ss i-n-COOt-03 i« tfl eosii-i * CO CO •0 3 M ^ + »0 ©» 00 «o w^ J?S Tj< CQ 00 00 «D «Sk Z ■ ,-; ■ ■ (N>i CO CO a: 00 c = t- -^ eo OS 10 -^ 00 s ^ d 3 t-CJOOC^T-iOiO T-H |5 mcJT-^r-irHOJ'-^'-! CO t pi Q © < s> w^^^^^w^ w q c 00 c ~*f-\,^alpto -+♦-•»• t^CDOdOOOOCQ^ 10 CC CO t- « >ffl sc to CO II CO c » C/372 7)C/)Z^^!2; ^ c • 09 5g rH (N CO Tjt 10 » C- 00 « u cfl^ ■M LAND SURVEYING. 733 The notes of the survey given in Example 3 by total latitudes and total departures from Station 1. A plat of the survey is given in Fig. 325 and the total lati- tudes and departures in the accompanying table. From an inspection of the plat it will be seen that Station 2 is the most easterly, and the double longitudes given in Example 3 are reckoned from a meridian passing through that station. are platted Total Total Stations. Latitudes from Departures from station 1 . station 1. 1 0.00 0.00 2 -3.13 "t- 4.85 3 -4.94 + 3.52 4 -5.71 + 2.89 5 -6.06 + 1.91 6 -5.61 + .76 ■ 7 -4.39 -1.06 8 -3.51 - .48 9 -2.66 -1.76 1 -0.00 0.00 Fig. 325. TOWN SITES AND SUBDIVISIONS. 1339. First Considerations. — In laying out town sites the consideration of first importance is the location of the streets rather than the greatest number of lots obtainable. The custom of laying out town sites in rectangular lines, 734 LAND SURVEYING. without reference to topographical conditions, prevails almost universally throughout the United States. This is largely owing to two principal causes, viz., first, the sup- position that the rectangular method or plan will yield the greater number of lots, and, hence, the greater profit, and, second, the haste in surveying, platting, and placing the property on the market does not admit of a thorough study of the ground. The town site should be considered as a whole, the loca- tion of its main streets and thoroughfares being determined by traffic considerations chiefly. These considerations will necessarily involve the questions of grades, drainage, and railway communications. Without the latter there is small excuse for a town. Where possible a main avenue should be laid Qut, parallel with the railroad, leaving one tier of lots between the street and track. This avenue may then be used as a base from which to lay out the adjoining streets and avenues, which may be parallel with and at right angles to it if the surface be generally level, or at oblique angles if the surface be rolling or hilly. 1340. Grades, Drainage, and Topography. — Grades and drainage should be so arranged that surface water will tend to form main channels, i. e., the surface water of several streets will find its way into some particular street where special provision can be made for its control and discharge. The streets in the residential portion of the town should, so far as possible, conform to the existing topographical con- ditions. This will greatly reduce the cost of grading the streets, give easy grades, and so promote comfort of pedes- trians and the efficiency of teams. There is no loss in front- age from the employment of curves instead of straight lines, and there is no question of the advantage of the former from an artistic standpoint. The accompanying plan, Fig. 326, is made to meet the following conditions, viz., two lines of railroad, a main line and branch, meet at the junction of two streams. The land LAND SURVEYING. 735 bordering on the smaller stream, which is followed by the branch road, rises rapidly from the stream, reaching a height of 200 feet, and then falls gradually until an elevation of 50 feet above the stream is reached, when the surface remains generally level. The land bordering the larger stream, which is followed by the main line of the railroad, rises gradually until a height of 50 feet above the stream is reached, beyond which the surface is generally level. 1 ^^Pj ^ / 1 i ' L ■a " if — 1» 1 I -l'^ 90' t i 1 '230' • .._t_ Avert lOO' Fig. 326. That part of the given surface which is generally level will be laid out in rectangular blocks. The unaided eye will readily determine whether a town site is well adapted to rectangular divisions. If it is so adapted the order of survey will be as follows: 1341. General Directions for Preliminary Sur- vey. — Run a line enclosing the entire area, giving location of prominent features, such as railroads, highways, streams. 736 LAND SURVEYING. houses, etc., and accurately plat to a scale of 200 feet to the inch. For cities, avenues are made 100 feet in width be- tween building lines, and streets 60 feet, the avenues being parallel to each other and the streets at right angles to the avenues. City lots usually have fronts of 25 feet and depths of 125 feet. Part of New York is laid out in blocks of 200 feet by 800 feet, the 200 feet facing the avenues. Lots are 100 feet in depth, each block containing 64 lots. Having deter- mined the dimensions of the streets and blocks, lay out the principal base line so that it will form the center line of a street or avenue running parallel with the general direction of the railroad, providing for overhead or sub-crossings where practicable. If crossings must be at grade, the fewer of them the better. Provide easy and safe access to railroad stations and freight depots. Lay out the plat in rectangular blocks, accurately scaling all dimensions. Arrange the plan so as to interfere as little as possible with existing lines of travel, at the same time giving due regard to the future needs of an increasing popula- tion. If the ground is wooded or sight obstructed by under- brush, but one additional base line can be used. It should be about midway between the extremities of the principal base line and at right angles to it. If, however, the ground is open with nothing to interfere with long sights, two base lines should be laid out, one at either extremity of the main base and at right angles to it. 1342. Measurements. — All measurements should be made with a standard steel tape and plumb-bob and care- fully checked. The base lines especially should be measured with great care, as the correctness of all the subsequent measurements depends upon the degree of accuracy with which these primary lines are measured. 1343. Base Lines and Subdivisions. — The rect- angular method of surveying town sites is illustrated in Fig. 327, in which A B is the principal base, and the aux- iliary bases A D and B C are laid off from the extremities of A B. The avenues are at right angles to A B, and the LAND SURVEYING. 737 streets parallel to A B. Avenue A is parallel to the railroad, 90 Ti \V \ W o— o— o * o-^o A E O T Fig. 327. or from which it is separated by a 25-foot alleyway and one tier of lots 125 feet deep. Avenues are 100 feet in width, 738 LAND SURVEYING. streets GO; blocks 250 feet by GOO feet, fronting 250 feet on the avenues, and the lots are 25 feet by 125 feet. The initial point A of the principal base A B is the center of an avenue, and should be fixed by a plug 2' X 2' X 18' driven flush with the surface of the ground and the center marked by a tack, with a guard stake beside it, and num- bered 0. Drive a temporary plug at X to be used as a fore- sight in giving the direction of A B. Set up the instru- ment at A and sight to X, frequently checking the foresight. Measure from A ox\. A B b'd feet, and drive a 12' plug, care- fully centering the same. This point marks the north side of Avenue B. Continue measuring on the line A B, driving a stake at each hundred feet, marking the exact measure- ment by a tack, and number in .regular succession from A. At G50 feet from A set a 12" plug with tack center, marking the south side of Avenue C\ 50 feet further, at Station 7, set a 12" plug with center. This point will be in the center of Avenue C', at 7 -j- 50 a plug with center is set, marking the north side of Avenue C. In like manner locate the center and sides of all avenues lying between A and X, always checking the foresight before setting tack centers. At B set a plug 2' X 2' X 18". At each station remeasure the last 100 feet, so as to secure accurate results. The measure- ment of the main base line A B being completed, take a foresight on Jfand turn off an angle of 90°, setting a tem- porary plug at Y. Mark the center at Fwith a pencil point and repeat the angle five times, marking a center at V for each angular measurement. These points will vary slightly in position, though two of them may fall at the same place. Take the mean or average of these points, and mark the point with a tack. Then, commencing at A measure the line A V, setting stakes at each 100 feet, as in A B, and set hubs on the side lines of Avenue A and at centers and side lines of the streets parallel to it, checking the foresight at V and the measurement of each station before setting plug centers. On this line the measurements will be, first 50 feet, next 250, then GO, 250, GO, etc., the streets being 60 feet and the blocks 250 feet in width. At D set a plug LAND SURVEYING. 739 2' X 3* X 18", In a similar manner locate the base line B C and the street centers and side lines on B C. Then set up at D, which is a permanent point, and foresighting to C set points on centers and sides of avenues on D C. Next set up at £", foresighting to F. Provide a supply of plugs 1" X 1' X 8' and measure from E, 50 feet in both directions on the line E F, and mark the points with pins. These points will be on the north and south lines of Avenue B. On either side of these pins in the line E F, and about two feet from them, set plugs, leaving two inches of their length above the surface of the ground. Center these plugs, dri- ving tacks half their length into each one. In the same manner set plugs on both sides of each street line as indi- cated by the small circles in the figure. In this example B C '\?> 2,800 feet distant from A D, too great a distance for the accurate setting of plug centers; therefore, the measure- ments from A D to B C should terminate on the south line of Avenue D. In the same manner locate plugs on the lines G H, I K, L M, etc. Having set all plugs between the base A D and the south line of Avenue Z?, move the instru- ment to F and, foresighting to E^ set plugs on both sides of all avenues between Avenue /^and Avenue Z>, including the north side of D. In like manner locate plugs on H G, K I, ML, etc. Move the instrument to the point U; stretch pieces of cord between the plugs on both sides of the line X T; foresight to T, and at each intersection with the cord, as at V, IV, etc., drive a 12" plug, and center with a tack. This method of locating street corners by intersections has the advantage of bringing all corners on the same street in perfect line, a result which it would be practically impossible to obtain by direct measurement. The measurement of all angles is referred to the base lines where special care is taken in checking them, 1344. Permanent Monuments. — The street and avenue centers located on the base lines should always be rendered permanent by setting stone monuments at those points. MAPPING. INTRODUCTION. 1345. The object of this section is to furnish the stu- dent thorough, practical instruction in mapping. Having previously mastered the section on Geometrical Drawing, he should by this time be familiar with the various instru- ments employed in the drafting room, and be accustomed to their use. All the principles and methods here described are fully il- lustrated by drawings, which comprise six plates, found at the end of the volume on Mechanical Drawing. These plates the student will be required to draw, and the degree of pro- ficiency, as shown by his work, will determine his standing. The examples given in the plates are similar to those met with in practical field and office work. 1346. A map is a series of lines and angles so com- bined as to represent the true outlines, proportions, and character of any required surface. 1347. Lines are either boundaries or divisions of the required surface. They have only the properties of direction and length. DRAWING THE PLATES. PLATE, TITLE: PLATTING ANGLES I. 1348. This plate contains six angle lines, three of which are comprised by Fig. 1 and three by Fig. 2. The three lines a, b, and c, under Fig. 1, will be drawn to a scale of 200 feet to the inch, platting the angles with a protractor, the 742 MAPPING. NOTES FOR LINE a. use of which was fully explained in the section relating to Geometrical Drawing. The student will plat these lines according to the follow- ing directions, being careful to give to each line approxi- mately the same position it occupies in the plate. This statement also applies to all the plates which are to be drawn from the data given in thjs section. In these examples, distances are expressed in sta- tions of 100 feet each, as in the section on Surveying. The direction of each line is referred to that of the immediately pre- ceding line, which line is pro- duced and the angle recorded as being to the right or left of that line. In practical office work, the lines produced are drawn lightly in pencil and erased as soon as the angles are laid off. In the lines a and b, Fig. 1, the lines produced are dotted and the angles written in dotted arcs, in order that the student may clearly and fully understand the method. The dimensions of the following plates and the di- rections for drawing the border lines are the same as for the plates on Geometrical Drawing. The notes for line a in Fig. 1 are as shown. Stations. Angles. 25 + 84 End of Line. 21 + 94 L. 32° 35' 15 + 53 R. 44° 10' 11 + 72 L. 60° 30' 5 + 25 L. 25° 15' 1349. The starting point A of the line is numbered 0. The first angle turned is at Sta. 5 + 25, which we denote by B. Locating the starting point A about three-fourths of an inch from the lower and left-hand border lines, we draw a straight line, giving it the same direction as that given to it in the engraving. Scale off from yi, to a scale of 200 feet to the inch, the first course, 525 feet in length, locating the point /)'. Produce A B to C, being sure to make B C a. little greater than the diameter of the protractor. At Sta. 5 + 25, B, an angle of 25° 15' is turned to the left. Now, MAPPING. 743 placing the center of the protractor on the point B, with the zero point on the line B C, lay off the angle 25'' 15' to the left of/) C, marking the point of angle measurement /?with a needle point. Through the points ^and Z>draw a straight line. The angle C B D is 25° 15', and the line B D is the direction of the next course. The second angle, 00° 30', is turned to the left at Sta. 11 + 72. The length of the second course is found by subtracting 525 from 1,172, giving a dif- ference of 647 ft. Produce B D and scale off the second course 647 ft., locating the point E2X Sta. 11 + 72. Produce B Eto F, and lay off to the left oi E F the angle 60° 30', lo- cating the point G. Join E and G. The angle /^£ 6" is 60° 30', and the line ^ 6^ is the direction of the next course. The third angle is R. 44° 10', and is turned at Sta. 15 + 53. The length of the third course is found by subtracting 1,172 from 1,553, giving a difference of 381 feet. Produce E G and scale off from E the distance 381 ft., locating the point H at Sta. 15 + 53. Produce E H to K, and to the right of H K lay off the given angle 44° 10', locating the point L. The line joining the points H and L forms with // A'an angle of 44° 10', and gives the direction of the next course. The next angle is L. 32° 35', and is turned at Sta. 21 + 94. The length of the course is found by subtracting 1,553 from 2,194, giving a difference of 641 ft. Produce H L and scale off from // the distance 641 ft., locating the point M at Sta. 21 4- 94. Produce H M to N, and to the left of M N lay off the given angle 32° 35', locating the point O. Draw M O. The angle N M O is 32° 35', and M O is in the direction of the next and last course of line a^ whose length is found by subtracting 2,194 from 2,584. The difference is 390 ft. We produce the line M O, and from M scale off the last course of 390 ft., locating the point P at Sta. 25 + 84, At each angular point in the line an arc is described, giving as a center, with a radius O P, describe the indefi- MAPPING. 747 nite arc P Q. The chord of 37° 20' is .6401, which, multi- plied by 400 ft., gives 25G.04 ft., the length of the required chord. From P as a center, with a radius of 256.04 ft., describe an arc intersecting the arc P Q \n R. Join O and R, forming with O P the angle P O R — 'iT 20'. The end of the line 5 is at Sta. 25 + 80, making the length of the last course 542 ft. In a similar manner, plat the notes for lines b and c^ which are given in Art. 1353. 1352. To Lay Off an Angle by its Bearing.— By this method of laying off angles, the direction of each line is referred to the magnetic meridian, which maintains a con- stant direction, being a north and south line. The bearing of a line is the angle which the line makes with the magnetic meridian. In platting a land or railroad survey, a pencil kE rQ Fig. 329. line giving the direction of the magnetic meridian is drawn through each station at which a bearing is taken. The direction of the meridian may be given by means of the ordinary T square and triangles, and the angles laid off either by a protractor or by tangents. The use of T square and triangles in laying off angles by bearings is illus- trated in Fig. 329. A sheet of paper is fastened to a draw- ing board. It is well known that if the head of the T square 748 MAPPING. be kept firmly pressed against the side of the drawing board, as shown in the figure, the lines drawn along the straight edge will be parallel; hence, the lines drawn perpendicular to this straight edge by means of the triangles, as shown in the figure, will be parallel. Either the parallels drawn along the straight edge of the T square or of the triangle may be used as the magnetic meridian, though the latter is preferable, as it brings the north end of the meridian at the top of the map, which is its proper position. Let* it be required to plat a line having a bearing of N G0° E. As in Fig. 329, a point A is assumed as the station at which the bearing is taken. Through the point A, a line A B \?, drawn perpendicular to the straight edge of the T square. This line will represent the direction of the mag- netic meridian. As the bearing is east, the angle of 60° will be to the right of A B. Place a protractor with its center at A and its zero point in the line A B. Lay off the angle 60°, and mark the point of measurement C with a needle point. Draw a line joining the starting point A with the point of angle measurement C. The line A C will then form an angle of 60°. with the meridian, and its course will be N 60° E. From the notes find the length of the first course, and measure on the line A C to some convenient scale the length of that course, locating the point D, where the next bearing N 30° E is taken. Slide the T square upwards, and with the triangle draw through D another meridian D E. From Z?as a center lay off from the right of the meridian D E the bearing N 30° E. Let F mark the measurement of this angle. The line joining D and F will have a bearing of N 30° E. PLATE, TITLE: PLATTING ANGLES IL 1353. This plate contains five angle lines, the angles of the three lines given in Fig. 1 being platted by magnetic bearings, and those in Fig. 2 by tangents. In Fig. 1, line «, the distances are given in stations of 100 feet each ; in the lines /^ and r, the distances are given in chains. The student MAPPING. 749 will draw line a to a scale of 200 feet to the inch, and lines d and r to a scale of 2 chains to the inch. The notes of line a are given below. Let A be the starting point of the line, which we num- ber Station 0. Let the arrow iV S give the direction of the magnetic meridian. Through A draw a meridian A B parallel to NS. The bearing of the first course is N 10° 15' E. From the meridian passing through A lay off this bearing angle with a protractor, as directed in Art. 1352. The first course is 375 ft. Draw a line through A having the given bearing, and scale the distance 375 ft. This will bring us to Sta. 3 + 75, which we de- note by the letter C, where a bearing of N 60° E is taken. The end of this course is at Sta. 6 + 90. The length of the second course will, therefore, be the difference between 6 + 90 and 3 + 75, which is 315 feet. Through C draw a meridian C D, from which lay off the bearing angle of 60° and draw a line marking the second course. Scaling the distance 315 feet we reach Sta. 6 + 90, which we call E. Here a bearing N 83° 30' E is taken. Through E draw a meridian E E, and from it lay off the bearing N 83° 30' E. The end of this course is at Sta. 10 + 40. Its length will, therefore, be the difference between 10 + 40 and 6 + 90, which is 350 ft. Scale off this distance from E, locating Sta. 10 + 40, which we call G. The bearing at 6^ is S 81° 20' E. Through G draw the meridian G H. As the bearing is S E, the meridian will fall below the station, from which lay off the bearing S 81° 20' E, and draw a line in the direction of this course. The next bearing is taken at NOTES FOR LINE a. Stations. Bearings. 28 + 15 End of line. 23 + 55 S 45° 00' E 18 + 92 S 70° 45' E 14 + 20 N 80° 30' E 10 + 40 S81° 20' E 6 + 90 N 83° 30' E 3 + 75 N 60° 00' E N10° 15' E 750 MAPPING. Sta. 14 4- 20. The length of the course is, therefore, the difference between 14 + 20 and 10 -f- 40, which is 380 ft. Call Sta. 14 +20, K. Through A' draw the meridian K L. The bearing here is N 80° 30' E. From the meridian K L, lay off this bearing and draw a line in the direction of the course. In a similar manner locate the remaining stations and lay off the remaining bearings of the line. The bearing of each course should be distinctly written above it, the letters reading in the same direction in which the line is measured. The notes for the lines b and c are as follows: NOTES FOR LINE b. Stations. Bearings. Distances. 1 2 3 4 5 N 40^° E N 65i° E S 75i° E S 45i° E S 20i° W 4.22 chains 6.75 chains 8.70 chains 6.60 chains 5.18 chains NOTES FOR LINE c Stations. Bearings. Distances. 1 2 3 4 5 S 47° E N 20^° E S 80° E S 20° E N 65i° E 6.60 chains 8.80 chains 4.32 chains 6.54 chains 7.48 chains 1354. The regular 100-foot stationing is used in rail- road and highway surveying, but in land surveying the lengths of the courses are given in surveyors' chains. As the fractional parts of chains are given decimally, the MAPPING. 751 length of each course is readily scaled on the plat with a decimal scale. The notes of line b are platted as follows: The starting point is called Sta. 1, and so marked on the plat. Call Sta. 1, A. Through A draw a meridian A B, and from it lay off the first bearing, N 40^° E. The first course is 4.32 chains in length, which lay off. to a scale of 2 chains to the inch, locating Sta. 2, which call C. Through C draw a meridian C D, and lay off the given bearing N 65^° E. The course with this bearing is 6.75 chains in length, which scale off, locating Sta. 3. In similar manner plat the remainder of line b, and also line c. Mark dis- tinctly each course, giving its direction and length, being careful that the figures and letters shall read in the same direction in which the line is being run. 1355. To Lay Off an Angle by its Tangent.— In laying off an angle by its tangent, the line from which the angle is turned is prolonged to a distance equal to the length of the assumed radius. The length of the tangent of the given angle is then found in terms of the assumed radius and the tangent platted. A line joining the angular point with the extremity of the calculated tangent will give the direction of the required line, which is then measured to the given scale. Let A B, in Fig. 330, be the given line, from which an angle of 30° 15' is to be laid off to the right at the point B. Produce A B to (7, ma- b B^4 00' king BC= 400 feet, the length of the assumed radius. The tangent of 30° 15' in terms of a radius 1, is. 58318, which, ^'^- ^• multiplied by 400 feet, the length of the assumed radius, gives 233.27 feet, the length of the required tangent. At C erect a perpendicular to B C 233.27 feet in length, equal to the calculated tangent. Denote the end of this tangent by C. Join B and C. The angle C B C = m° 15', the given angle, and the line B C is the required line. 752 MAPPING. The following notes which are platted in Plate, Title: Platting Angles II, Fig. 2, the student will plat to a scale of 200 feet to the inch : NOTES FOR LINE a. Stations. Angles. Bearings. 25 + 00 19 + 97 13 + 22 5 + 00 End of Line L. 40° 10' R. 32° 15' R. 43° 30' N 78° 45' E S61°05'E N 86° 40' E N 43° 10' E The notes for line a are platted as follows: Having ad- justed the paper to the drawing board and drawn a merid- ian iV 5, fix the starting point A, which number 0. The first course is 500 feet in length, which plat by drawing a meridian A B through Sta. 0, and scale oflE 400 ft. equal to the length of the assumed radius A C. The bearing of the first course is N 43° 10' E. The tangent of 43° 10' is .93797, which, multiplied by 400, the length of the radius, gives 375.19, the length of the required tangent. Erect a perpendicular \.o A B txX. C, and on this perpendicular scale off to the right, the tangent 375.19 ft., calling the extremity of the tangent D. Draw A D. The angle CAD will be 43° 10'. The first course is 500 feet in length, which scale off on the line A D 2it 200 ft. to the inch, locating Sta. 5 + 00 at E. The angle at Sta. 5 + 00 is 43° 30' to the right. Produce A E and scale off the radius E 7^=400 ft. The tangent of 43° 30' = .94896, which, multiplied by 400, gives 379.58 ft., the length of the required tangent. Erect a per- pendicular to E F at F, and scale off, to the right, the tan- gent 379.58 ft., locating the point G. Draw E G. The angle F E G '\s 43° 30', and the line E G the required line, the bearing of which is N 80° 40' E. Produce E G to H, making /: //= 1,322 - 500 = 822 ft. in length. MAPPING. 753 The line changes direction again at Sta. 13 -f 22, where an angle of 32° 15' is turned to the right. Denote Sta. 13 + 22 by H. Produce E H 400 feet, equal to the assumed radius, calling its extremity K. The tangent of 32° 15' = .63095, which, multiplied by 400 feet, gives 252.38 feet, the length of the required tangent. Erect a perpendicular to H K 2X K and on that perpendicular scale off, to the right, the tangent 252.38 feet, locating the point L. Join H and L. The angle K H L \s 32° 15' and the bearing oi H L is S 61° 05' E. The line changes direction again at Sta. 19 + 97. Call this station AT. The angle at this point is 40° 10' to the left. Produce H M 400' to yV, and at N erect a perpendicular to M N. The tangent of 40° 10' is .84407, which, multiplied by 400, gives 337.63 feet, the length of the required tangent. On the perpendicular to AT N sc2i\& off, to the left, this tan- gent, locating the point O. Join>/and O. The end of the line is Sta. 25 + 00. The length of the last course is readily found by subtracting 19 + 97 from 25 + 00. The difference, 503 feet, is scaled off on M O, locating the point P, the end of the line. The bearing of M Pis N 78° 45' E. In a similar manner plat the notes of line b. NOTES FOR LINE b. Stations. Angles. Bearings. 27 + 47 End of Line 20 + 97 R. 42° 20' S34° 25' E 13 + 73 R. 49° 10' S76° 45' E 7 + 63 L. 62° 15' N54° 05' E 0. S 63° 40' E 1356. To Lay Off an Angle by Latitude and Departure. — The subject of latitudes and departures was discussed in the section on Land Surveying, and the theory needs no explanation in connection with this subject. 754 MAPPING. Suppose the bearing of a line is N 40° E, and its length is 300 feet. Its latitude and departure are calculated as follows: Distances. Latitudes. Departures. 3 ft. 22 9 8 19 2 8 ft. 0000 0000 Oft. 0000 0000 3 ft. + 22 9.8 ft. + 192.8 ft. Departure 192.8' The student should bear in mind that north latitudes and east departures are +, and south latitudes and west departures are — . ^^ Let A, in Fig. 331, be the station at which the bearing is taken. Through A draw the meridian A^ S. From A upwards scale the calculated latitude 229.8 ft., marking the ex- tremity B. At B erect a perpen- dicular to the meridian N S, draw- ing it from left to right, as the bearing is east. On this perpen- dicular scale off the calculated de- parture 192.8 ft., locating the point C. Join A and C. The angle BAC is 40°, equal to the given bearing, and A C is equal to the length of the given course, viz., 300 ft. Example. — Calculate the latitudes and departures of the following courses, and plat them by means of total latitudes and total departures from Sta. 1. Fig. 331. Bearings. Distances. Latitudes. Departures. Stations. N + S - E + W - 1 2 3 4 N 10i° E N 41i" E N 84i' E S 25^" E 250 ft. 123 ft. 215 ft. 210 ft. 246 ft. 91.76 ft. 20.64 ft. 189.94 ft. 44.5 ft. 81.92 ft. 214.03 ft. 89.57 ft. MAPPING. 755 Solution. — Distances. 250 ft. 200^ ft. 50 ft. Oft. Latitndes. 1968 4920 0000 Departures. 0356 0890 0000 250 ft. 246.000 ft. 44.500 ft. 123 ft. 100 ft. 2 ft. 3 ft. 0746 1492 2238 0666 1332 1998 1 2 3 ft. 91.758 ft. 81.918 ft. 215 ft. 200 ft. 10 ft. 5 ft. 0192 0096 0479 1991 0995 4977 215 ft. 2 0.63 9 ft. 214.027 ft. 2 1 ft. 200 ft. 10 ft. Oft. 1809 0904 0000 0853 0427 0000 2 1 ft. 189.940 ft. 8 9.5 70 ft. Stations. Total Latitudes from Station 1. Total Departures from Station 1. 1 2 8 4 5 0.00 ft. + 246.00 ft. + 337.76 ft. + 358.40 ft. + 168.46 ft. 0.00 ft. + 44.50 ft. + 126.42 ft. + 340.45 ft. + 430.02 ft. The platting of the courses is as follows: On the merid- ian A'^ 6\ Fig. 332, take a point which call Sta. 1. The total latitude of Sta. 2 is + 246 feet, and, as it is a plus latitude, it must be scaled off on the meridian above Sta. 1, locating 756 MAPPING. the points. The total departure of Sta, 2 is +44.5 feet. This departure will therefore be to the right of the merid- ian N S. At A, erect a perpendicular to the meridian, and upon it scale off the total latitude 44.5 feet, locating Sta. 2. The line joining Stas. 1 and 2, i. e., the first course, will have a bearing of N 10^° E. Its length, viz., 250 feet, we write on the plat, the figures reading in the same direction in which the line is being run. N k Total Lat+368.4(f^ TotalLat+33r.76t Total Lai.+246' TotalLat.+J68.46! Total Dejk +340.45' ^ Total Dep^ B +126.42^ /3 Total ^/V Dep. +■ Fig. 332. The total latitude of Sta. 3 is +337.76 feet, which we scale off on the meridian above Sta. 1, locating the point B, and on a perpendicular to the meridian at B, we scale off the total departure of Sta. 3, which is + 120.42 feet, locating Sta. 3. The line joining Stas. 2 and 3 has a bearing of N 41f° E, and length of 123 feet. The total latitude of Sta. 4 is + 358.4 feet, which we scale off on the meridian above Sta. 1, locating the point C, where we erect a perpendicular to the meridian and upon it scale off the total departure of Sta. 4, MAPPING. 757 viz., + 340.45 feet, locating Sta. 4. The line joining Stas. 3 and 4 will have a bearing of N 84^° E, and a length of 215 feet. The total latitude of Sta. 5 is + 1G8.46 feet, which we scale off on the meridian locating the point Z>, where we erect a perpendicular to the meridian and upon it scale off the total departure of Sta. 5, viz., -j- 430. 02 ft., locating that point. The line joining Stas. 4 and 5 has a bearing of S 25^° E, and a length of 210 ft. This method of platting bearings or angles is more accurate than either of the foregoing methods, as each course is platted independently. Great care must, however, be observed in making the additions by which total latitudes and departures are obtained. Tables of latitudes and departures are commonly calculated to quarter degrees. See table of Latitudes and Departures. Where angles are read to single minutes, a table of sines and cosines may be used to advantage. The two following formulas should be memorized : Latitude = distance X cos bearing. (9^») Departure = distance X sin bearing. (98.) 1357. In preliminary railroad work, angles are com- monly platted by tangents, but on difficult parts of the line where all dependence must be placed on a paper location, latitudes and departures should be used and the line platted to a scale that will admit of full topographical details. For practice in platting lines by latitudes and departures, the following examples are given. The notes of Example 1 are platted in Fig. 333, and those of Example 2 are platted in Fig. 334. The student should carefully study the different steps given under Art. 1356, and illustrated in Fig. 332, before undertaking to plat the following notes. He should cal- culate the latitudes and departures for each course, compa- ring his results with those given in the text and likewise with the total latitudes and departures for platting. These plats he will submit for inspection, together with Plate, Title: Platting Angles II. 758 MAPPING. .J 1 5R ^ ^— ^— •— H ^-^ »— « r— < <— ^ V-i 1-1 o o: 00 00 05 T— 1 CO Ol T— t "rt 2 6 o ^ ^ 1— 1 (?i X 00 ^ Q u p rH (N CO '^ CO T-H i> o ^ rt .1- (U -4^ (N i> r- (N C5 t- cc 1—1 ^ + + - r- ^ + + + + Q + + «5 tH '^ U3 ;d •,;; 3 o c c 1— CC cc cc cc "z; i i3 i> «C «; «c -r? oc c (N rt ^ cc '^ -<*■ T-H CO cc l-H CO hJ C/2 + + + I 1 _l 1 1 •~^ 1— « 1 oc QO T— ^ '* d i> C to •c CO '«*■ i> (N C/3 C cc • • oc 1) <£ • «: •d 3 ■>-> rt • ^ ,._J yA + a- cr. • a ) ->* oc en JZ x: X rC x; x' -C -C o c C c c o a o a u rt cc t- t- c 1— o »c »c 3J tn c<: — c "* »— (M QC oc T-" >? CC »c C X o Ol ♦-> MAPPING. 759 . (» 4- ■)-J ' I f 4- 4- 4J 4- ' 1 1 4J 4-J VM £ ■rH 00 00 Ci ■<* 1—1 »o ^ "* "rt 2 6 a, C o ci 5^ ci 05 d as CO CO O C5 »c oc »o •<* CO ^ 00 en a ?-H o c: '^ C5 rH »o 1 Q C/3 1 1 1 1 ' I— 1 1 ^ 1 1 C/3 ■M -J +j -M 4-> 4-1 4-> 4J i> oc o CO c cc »o rt 5 i> J> Tt^ -u -M 4-1 1 vm MH VM VM VM 1 oc c T-^ i> -^ CA o: cc i> c itC c • 1 H c CO J> i 1 cc o- »c »o -* VM vm 4- VM 4-J VM 4-> VM 1 «: ,- (N »o Ci Oi c i> • c cc d en c- c- !> • cc CO •a 3 *-> -1- 4- + <+. 1 VI- vt_ , «C > c- ir. ) ^ i »- • 5 i • 4 CO ■t- Vt- Vm V|_ 4- V|- 4- vt_ 4- V|- > 4- 1 V|_ a ) W tr. a ) C i> ' a ) iC i i to a > >C ^ c t oc '^j i T- s i> • ^ ''t cr ) w: ) cc cc ) CC ' a VM CO ^ : ^ ^ {X 1 ^ ^ &: pi: ' -S _C o o c o £3 at ^ H 0* * "*■ * «( * -4 N -t ^ -4 * 5 w < cr > C > C > c c; ) a S I- 1 QC ) 'i «I > «> . cc cr > '^ < pq ^ ; ^ tr. 1/ } !/ ! c/: cr J ^ ( 1 en 5 § r- < CO ' cc Tt >« «c i> • a cs c« -H 760 MAPPING. A piece of drawing paper one-half the size of an ordinary drawing plate will be large enough to contain plats of both lines. The total latitudes and departures in both examples are reckoned from Station 1, which in Fig. 333 is the most westerly station, and in Fig. 334 the most easterly one. Plat the courses of Example 1 to a scale of 2 chains to the inch, and those of Example 2 to a scale of 200 feet to the inch. N.89tK Fig. 888. In Fig. 333, a magnetic meridian is drawn through Sta. 1, which we call A. We find in the column for total latitudes and departures from Sta. 1 (see Example 1), that the total latitude of Sta. 2 is+ 375.9 links, which we scale off on the meridian above ^ to a scale of 2 chains or 200 links to the inch, locating the point B. The total departure of Sta. 2 is + 214.9 links, which we scale off at 2 chains to the inch on a MAPPING. 761 perpendicular to the meridian at B, locating Sta. 2, which we call C. A line joining A and 6" will have the given length and bearing of the first course, viz., length 4.33 chains, and bearing N 29|° E. The total latitude of Sta. 3 is -f- 461.2 links, which we scale upon the meridian above A at 2 chains or 200 links to the inch, locating the point D. The total departure of Sta. 3 is -\- 724.8 links, which we scale off on a perpendicular to the SSf. Fig. 334. meridian at D, locating Sta. 3, which we call E. A line -joining C and E will have the given length and bearing of the second course, viz., length 5.17 chains, and bearing N 80^° E. In a similar manner plat the remaining courses, bearing in mind that positive latitudes are measured on the meridian above Sta. 1, and positive departures on perpen- diculars to the right of the meridian, while negative latitudes 762 MAPPING. are measured on the meridian below Sta. 1, and negative departures, if there were any, on perpendiculars to the left of the meridian. The notes for Example 2 are similarly platted, excepting that the meridian passes through the most easterly station, as all the departures from Sta. 1 are negative. The lengths of the courses in this example are given in feet, and are to be platted to a scale of 200 feet to the inch. Write the bearing of each line distinctly, being careful that the letters read in the same direction in which the line is run. The student is expected to accompany each drawing with a brief description of the successive steps taken in the work. 1358. Parallel Rulers. — A parallel rule is a straight edge carried on milled rollers of equal diameter, having a common axis. They are of great service in drawing meridian lines. A magnetic meridian is drawn the entire width of the sheet which is to contain the plat. The straight edge of the rule is then made to coincide with the meridian line and then rolled across the paper until the straight edge passes through the point where the angle is to be measured. A line is then drawn following the straight edge ; this will be a meridian line. 1359. The Line of Survey. — The line of prelim- inary survey is a succession of straight lines and angles, or an angle line, as it is commonly called, while the located line is a succession of straight lines and curves. 1360. Tangents and Curves. — Though this subject has been considered in the section on Surveying, yet some additional matter may be of advantage in connection with the subject of mapping. 1361. Map of Final Location. — In mapping a final location the measurements should be made from inter- section point to intersection pomt, and the angles platted either by tangents or by latitudes and departures. The points of curve are then located by scaling the tangent distances from the intersection points. The curve centers MAPPING. 763 o v^* FIG. 3.35. 764 MAPPING. are best determined by describing intersecting arcs from the tangent points as centers, with radii equal to that of the given curve. Let it be required to plat by tangents the following location notes: Stations. Degree of Curve. Intersection Angle. Tangent. Magnetic Bearing. 25+50 20+ 10 14+ 55 10 + 80 P. T. P. C. 5° L. P. T. P. C. 6° R. N 1° 00' E 27° 00' 275.20 ft. N 28° 00' E 22° 30' 190.03 ft. N 5° 30' E The tangent distances are found by the formula r= Tetany/. (See Art. 1251.) The first curve is 6° R. ; the intersec- tion angle / is 22° 30'. The radius of a 6° curve is 955.37 feet. See table of Radii and Chord and Tangent Deflec- tions. i 7=11° 15'. Tan 11° 15' = .19891; then 955.37 X .19891 ft. = 190.03 ft. = T; which we place in the column headed "tangent," opposite the intersection angle 22° 30'. The second curve is 5° L; the intersection angle is 27° 00'. The radius of a 5° curve is 1,146.28 feet. ^ 7=13° 30'. Tan 13° 30' = .24008, and 1,146.28 ft. X .24008 = 275.2 ft. = T, which we place in tangent column opposite the intersection angle 27° 00'. A plat of these notes is given in Fig. 335. The order of work is the following: First we select a starting point A, which we number 0, and through this point draw a meridian A B with its north point at the top of the plat. The first course has a bearing N 5° 30' E. From Sta- tion 0, scale off on the meridian 600 feet, the length of our radius for platting angles. The bearmg angle is 5° 30' and MAPPING. 765 its tangent .09629, which, multiplied by 600, the radius, gives 57.77 feet, the length of the required tangent. Call the extremity of the radius C. At C erect a perpendicular to A B, and on it lay off the tangent 57.77 feet, locating the point D. Join A and D. The angle C A D = 5° 30'. The P. C. of the first curve is at Station 10+ 80. The tangent distance, as given in the preceding table, is 190.03 feet. Hence, the distance from the starting point to the first in- tersection point is the sum of 1,080 and 190.03 feet, which is 1,270.03 feet. Produce A D, making a total distance of 1,270.03 feet to the point of intersection £, and 600 feet additional for the radius by which the next angle is platted. Call the extremity of this radius F. The intersection angle of the first curve is 22° 30'. Its tangent is .41421, which, multiplied by 600, the given radius, gives 248.52 feet as the required tangent for platting the angle. At F erect a per- pendicular to the radius F F and scale off the tangent FG= 248.52 feet, locating the point G. Join F and G. The angle F F G is 22° 30', and the bearing of the tangent F G is "N 28° E. Next, from the point of intersection F, scale off on the lines F D and F G the tangent distance 190.03 feet, locating the P. C. at H, Station 10 + 80, and the P. T. at K, Station 14 + 55. Now, from H and K as centers with a radius 955.37 feet = radius of 6° curve, de- scribe arcs intersecting at the point L. Then, from Z, as a center with the same radius, describe a curve joining the points H and K. The curve H K will be a 6° curve and will be tangent to the lines H D and A' G" at the points of curve H and K. The next intersection point M is in the line E G produced. The distance between these intersection points is made up of three parts, viz., the tangent of pre- ceding curve, which we know to be 190.03 feet; the inter- mediate tangent, i. e., the distance from the P. T. of the first curve to the P. C. of the second curve, and the tangent of the next curve following. The P. T. of the first curve is at Station 14 + 55; the P. C. of the second curve is at Station 20+10; the intermediate tangent is, therefore, the difference between 14 + 55 and 20 + 10, which is 555 feet. 766 MAPPING. The tangent of the second curve is 275.2 feet. Hence, the distance from the intersection point E of the first curve to the intersection point M of the second curve is the sum of 190.03, 555, and 275. 2 ft., which is 1,020.23 ft. Produce E G so as to contain 1,020.23 ft., and 600 additional feet for a radius, the extremity of which call N. The intersection angle of the second course is 27° 00' L., tan 27° = .50953. Radius 600ft. X .50953 = 305.72 ft., the length of the re- quired tangent. Accordingly, at A'' we erect a perpendicular to the radius M N^ and on that perpendicular, scale off the tangent 305.72 feet, locating the point O. Join 3/ and O. The angle N M O \% 27° 00', equal to the given intersection angle, and the bearing of the tangent yl/ (9 is N 1° E. From M on the lines M K and M O scale off the tangent distance 275.20 feet, locating the P. C. at P, Sta. 20+10, and the P. T. at (2, Sta. 25 + 50. Then, from P and Q as centers with radii of 1,146.28 feet, the radius of a 5° curve, describe arcs intersecting at R. From /? as a center with the same radius describe the curve P Q, which is a 5° curve, and is tangent to the lines Af K and M O 2it P and Q. Write the bearing of each tangent in its proper place, being careful that the bearings shall read in the same direction in which the line is being run. PLATE, TITLE: MAP OF RAILROAD LOCATION. 1362. This plate contains two maps of railroad loca- tion. Figs. 1 and 2, the notes for which are given in the fol- lowing pages. All the angles are laid off by tangents and the notes of the alinement given in detail, all of which the student must carefully go over and check. The student, before commencing these drawings, should first note that the magnetic meridian (by means of which the direction of the first tangent of each line is determined) is parallel to the right and left border lines of the plate. He must also determine by measurement from the border lines the location of the starting point of each line MAPPING. 767 Without these precautions, the lines are liable to run off the paper, necessitating a repetition of the work, and involving the erasure of lines, which always soils the paper and mars the appearance of the drawing. He will make the drawing to a scale of 300 feet to the inch. If his scale reads only 200 feet to the inch, he will reduce the distances given to a scale of 300 feet to the inch, to their equivalent to a scale of 200 feet to the inch. The process of reduction is simple and may be readily understood from the following: A line which measures 300 feet in length to a scale of 300 feet to the inch will measure but 200 feet to a scale of 200 feet to the inch. Hence, in chang- ing a scale from 300 feet to 200 feet to the inch the distances and dimensions will scale but f of the original distances and dimensions. Example. — A line measures 963 feet to a scale of 300 feet to the inch. What will it measure to a scale of 200 feet to the inch ? Solution. — | of 963 = 642, i.e., to a scale of 200 feet to the inch, the line will measure 642 feet. 1 363. The order of platting the notes is as follows : First draw a meridian as indicated by the arrow. Next, having located the starting point A, Fig. 1, which is numbered 0, draw through that station a parallel meridian A B. We find from the notes that the direction of the back tangent A A' (which we will consider a part of a line of railroad already con- structed) is due north and south, and that Sta. is the P. C. of an 8° R. curve with a central or intersection angle of 63° 10'. The tangent distance we find by the formula T== R tan \ /, is 440.7 feet. This distance we scale off on the meridian above the point ^ to a scale of 300 ft. to the inch, locating the point C, which is the intersection point of the back and forward tangents. Next, from Con the same meridian, we scale off the radius C D oi 400 feet for laying off the angle of the first curve. The angle of this curve is 63° 10'. The tan of 63° 10' is 1.97681. The radius 400 ft. X 1.97681 =790.7 ft., the length of the required tangent. At D erect a perpendicular to 7G8 MAPPING. NOTES FOR FIG . 1. Station. Deflection. Total Angle. Magnetic Course. Calculated Course. 40 12° 00' 6° 00' 18° 00' 12° 00' 6° 00' P. C. 12° L. 89 38 + 00 36° 00' 37 36 35 + 00 34 33 + 04.9 33 10° 40.3' P. T. 10° 30' 7° 00' 3° 30' 7° 14.7' 3° 44.7' 0° 14.7' P. C. 7° R. 35° 50' S 36° 30' E S 36" 40' E 32 31 30 14° 29.4' 29 28 27 + 93 24 21 20 + 54.9 20 10° 38.8' P. T. 9° 00' 6° 00' 3° 00' 11° 31.2' 8° 31.2' 5° 31.2' 2° 31.2' P. C. 6° R. 44° 20' S 72° 30' E S 72° 30' E 19 18 17 23° 02.4' 16 15 14 13+ 16 12 11 10 9 8 7 + 89.6 7 15° 35' P. T. 12° 00' 8° 00' 4° 00' 16° 00' 12° 00' 8° 00' 4° 00' P. C. 8° R. 63° 10' N 68° 00' E N 63° 10' E 6 5 i 4 82° 00' ! 3 j 2 1 1 North North MAPPING. NOTES FOR FIG. 1. 769 Remarks. June 28, 1894. Int. Ang. = 72° 00' From intersection to intersection. 12° curve, L. R. = 478.34 ft. Tan preceding curve = 264.8 ft. T. = 347.5 ft. Tan between curves = 195.1 ft. P. C. Length curve P. C. C. Def. 100 ft. Def. 1 ft. = 35 + 00 = 600 ft. = 41 + 00 = 6° 00' = 3.6' Tan 12° curve = 347.6 ft. Total, = 807.5 ft. tan 72° 00' = 3.07768 400 ft. X 3.07768 = 1,231.1 ft. Int. Ang. = 35° 50' From intersection to intersection. 7° curve, R. R. = 819.02 ft. Tan preceding curve = 389.2 ft. T. = 264.8 ft. Tan between curves = 738.1 ft. P. C. = 27 + 93 Tan 7° curve = 264.8 ft. Length curve P. T. = 511.9 ft. = 33 + 04.9 Total, =1,392.1 ft. Def. 100 ft. = 3° 30' tan 35° 50' = .72211 Def. 1 ft. = 2.1' 400 ft. X .72211 = 288.8 ft. Int. Ang. = 44° 20' From intersection to intersection. 6° curve, R. R. = 955.37 ft. Tan preceding curve = 440. 7 ft. T. = 389.2 ft. Tan between curves = 526.4 ft. P.C. = 13+16 = 738.9 ft. Tan 6° curve = 389.2 ft. Length of curve Total, =1,356.3 ft. P. T. = 20 + 54.9 tan 44° 20' = .977 Def. 100 ft. = 3° 00' 400 ft. X .977 = 390.8 ft. Def. 1 ft. = 1.8' Int. Ang. = 63° 10' Radius 1 = 400 ft. 8° curve, R. R. = 716.78 ft. tan 63" 10' = 1.97681 T. = 440.7 ft. 400 ft. X 1.97681 = 790.7 ft. P.C. = Length of curve = 789.6 ft. P. T. = 7 + 89.6 Def. 100 ft. = 4° 00' Def. 1 ft. = 2.4' 770 MAPPING. NOTES FOR FIG. 2. Station. Deflection. Total Angle. Magnetic Course. Calculated Course. 13 + 41.7 13 10° 15' P. T. 9° 00' 6° 00' 3° 00' 6° 00' 3° 00' P. C. 6° R. 32° 30' S 79° 00' E S 79° 00' E 13 11 10 + 00 12° 00' 9 8 + 00 5 3 S 46° 30' E NOTES FOR FIG. \— Continued. Station. Deflection. Total Angle. Magnetic Course. Calculated Course. 69 + 10.1 61 + 65.1 61 15° 40' p. T. 12° 44.1' 8° 14.1' 3° 44.1' P. C. 9° R. End 31° 20' of Line. N 39° 45' E N 39° 40' E 60 59 58 + 17 55 54 53 52 51 50 + 00 49 17° 30' P. T. 14° 00' 10° 80' 7° 00' . 3° 30' 14° 00' 10° 30' 7° 00' 3° 80' 18° 00' P. C. C. 7° L. 63° 00' N 8° 15' E N 8° 20' E 48 47 46 45 28° 00' 44 43 42 41 + 00 72° 00' N 71" 15' E N 71° 20' E MAPPING. NOTES FOR FIG. 2. 771 Remarks. June 28, 1894. Int. Ang. = 32° 30' 6° curve. L. R. = 955.37 ft. T. = 278.5 ft. P. C. = 8 + 00 Length curve = 541.7 ft. P. T. =13 + 41.7 Def. 100 ft. = 3° 00' Def. 1 ft. = 1.8' Radius 1 = 400.0 ft. From Sta. to P. C. = 800.0 ft. Tan 6" curve = 278.5 ft. Total from P. C. to P.I. = 1,078.5 ft. tan 32° 30' = .63707 400ft. X. 63707= 254.8ft. NOTES FOR FIG. \— Continued. Remarks. June 28, 1894. Int. Ang. = 31° 20' curve, R. R. = 637.27 ft. T. = 178.7 ft. P. C. = 58 + 17 Length curve = 348.1 ft. P. T. = 61 + 65.1 Def. 100 ft. = 4° 30' Def. 1 ft. = 2.7' Int. Ang. = 63° 00' 7° curve, L. R. = 819.02 ft. T. = 501.9 ft. P. C. C. = 41 + 00 Length curve = 900 ft. P. T. = 50 + 00 From intersection to intersection. Tan preceding curve = 501.9 ft. Tan between curves = 817.0 ft. Tan 9° curve = 178.7 ft. Total, = 1,497.6 ft. tan 31° 20' =.60881 400ft. X. 60881 = 243.5 ft. From intersection to intersection. Tan preceding curve = 347.6 ft. Tan between curves = 0.0 ft. Tan 7° curve = 501.9 ft. Total, = 849.5 ft. tan 63° = 1.96261 400 ft. X 1.96261 = 785 ft. 772 MAPPING. NOTES FOR FIG. ^—Continued. Station. Deflection. Total Angle. Magnetic Course. Calculated Course. 57 + 40 47 + 19 47 8° 46.3' P. T. 8° 15' 5° 30' 2° 45' 8° 13.7' 5° 28.7' 2° 43.7' 14°01.7'P.C.C. 5°30'L. 14° 00' 10° 30' 7°00' 3° 30' 11° 58.2' 8° 28.2' 4° 58.2' 1° 28.2' P. C. 7° L. End 34° 00' of Line. N ir 15' E N 11° 20' E 46 45 44 + 00 16° 27.4' 43 42 41 + 00.8 41 52° 00' N 45° 15' E N 45° 20' E 40 • 39 38 37 + 00 23° 56.4' 36 35 84 33 + 58 32 30 + 36.6 30 13° 27.8' P. T. 12° 00' 8° 00' 4° 00' 10° 37.2' 6° 37.2' 2° 37.2' P. C. 8° L. 48° 10' S 82° 80' E S 82° 40' E 29 28 27 + 00 21° 14.4' 26 25 24 + 34.5 24 23 22 + 14.4 22 9° 39' P. T. 9° 00' 4° 30' 12° 36' 8° 06' 3° 36' P. C. 9° L. 44° 80' S 84° 20' E S 84° 80 E 21 20 + 00 25° 12' 19 18 17 + 20 17 15 MAPPING. 773 NOTES FOR FIG. 2— Continued. Remarks. June 28, 1894. Int. Ang. = 34' 00' 5°30', L. R. = 1,042.14 ft. T. =318.6 ft. P. C. C. = 41 + 00.8 Length curve = 618.2 ft. P. T. = 47 + 19 Def. 100 ft. = 2° 45' Def. 1 ft. = 1.65' Int. Ang. = 52° 00' curve, L. R. = 819.02 ft. T. = 399.5 ft. P. C. = 33 + 58 Length curve = 742.8 ft. P. C. C. = 41 + 00.8 Def. 100 ft. = 3° 30' Def. 1 tt. = 2.1' Int. Ang. 8° curve, L. R. T. : P. C. Length curve P. T. Def. 100 ft. Def. 1 ft. ; Int. Ang. 9° curve, R. R. T. P. C. Length curve P. T. Def. 100 ft. Def. 1 ft. : 48° 10' : 716.78 ft. : 320.4 ft. 24 + 34.5 602.1 ft. : 30 + 36.6 : 4° 00' 2.4' 44° 30' 637.27 ft. 260.7 ft. 17 + 20 494.4 ft. 22 + 14.4 4° 30' 3.7' From intersection to intersection. Tan preceding curve = 399.5 ft. Tah between curves = 0.0 ft. Tan 5° 30' curve = 318.6 ft. Total, = 718.Tft. tan 34° 00' = .67451 400 ft. X .67451 = 269.8 ft. From intersection to intersection. Tan preceding curve = 320.4 ft. Tan between curves = 321.4 ft. Tan 7° curve = 399.5 ft. Total, = 1,041.3 ft. tan 52° 00' = 1.27994 400 ft. X 1.27994 = 512 ft. From intersection to intersection. Tan preceding curve = 260.7 ft. Tan between curves = 220. 1 ft. Tan 8° curve = 320.4 ft. Total, = 801.2 ft. tan 48° 10' = 1.11713 400 ft. X 1.11713 = 446.8 ft. From intersection to intersection. Tan preceding curve = 278.5 ft. Tan between curves = 378.3 ft. Tan 9° curve =260. 7 ft. Total, = 917.5 ft. tan 44° 30' = .98270 400ft. X. 98270 = 393.1 ft. 774 MAPPING. A B, towards the right, as the curve is to the right, and upon this perpendicular scale oflf the calculated tangent 700.7 ft., locating the point E. A line joining the points C and ^ will give the direction of the forward tangent. On the line C E, scale off from C the tangent distance, 440.7 ft., locating the point /', which is the P. T. of the first curve. From A and /"as centers, with radii of 716.78 ft., the radius of an 8° curve, describe arcs intersecting at G. Then, from G as a center, with the same radius, describe a curve joining the points A and F. The curve A F\s zn 8° curve and tan- gent to the lines A A' and F £ a.t the points A and F. We find from the notes that the next curve is 6° R. Its P. C. is at Sta. 13 + 16, and its central angle is 44° 20'. We find its tangent distance is 389.2 ft. We next calculate the distance from the intersection point of the first curve to the intersection point of the second curve. The distance is com- posed of three parts; viz., the tangent of the preceding curve, which is 440.7 ft. ; the intermediate tangent, i. e., from the P. T. of the preceding curve at Sta. 7 + 89.6 to the P. C. of the second or 6° curve at Sta. 13 + 16, a distance of 526.4 ft., and the tangent of the 6° curve, which is 389.2 ft., making a total distance of 1,356.3 ft. Produce the line CE, and scale off from Con that line a total distance of 1,356.3 ft., locating the point H, which is the intersection point of the second or 6° curve. Produce C H 400 ft. to A" for a radius in laying off the central angle, 44° 20' R., of the second curve. The tangent of 44° 20' is .977, which, multiplied by 400, gives 390.8 ft. At A" erect a perpendicular to H K, and upon it scale off the tangent 390.8 ft., locating the point L. The line joining //and L gives the direction of the forward tangent of the second curve. Next, from the intersection point H, scale off on both back and forward tangents the tangent distance 389.2 ft., locating the P. C. of the second curve at J/, Sta. 13 + 16, and its P. T. at N, Sta. 20 + 54.9. Next, from J/ and A^as centers, with a radius of 955.37 ft., the radius of a 6° curve, describe arcs intersecting at O. Then, from (9 as a center, with the same radius, describe a curve joining the points M and A^. The curve M N is a 6° MAPPING. 775 curve and tangent to the lines F H and H L zX the points of curve M and N. The student will draw the tangent distances and the radii and tangents for laying off angles in dotted lines, as they are simply construction lines. The line of survey he will draw in a full, bold line, as shown in the plate. The inter- section points and the points of curve and tangent are marked by small circles, the latter being more fully described by their station numbers. Dotted radial lines are drawn from the center of each curve to its P. C. and P. T. On one of these radial lines the length of the radius of the curve is written, and the amount of the central angle written with- in the radial lines. The student will need no further direc- tions to enable him to plat the balance of the line and also the notes for Example 2, a plat of which is given in Fig. 2. 1364. Office Curves and Beam Compass. — Office curves are curves of different radii, whose principal object 10 Scale 100 ft=' 1 in 12' Pig. 836. is to enable the engineer to readily select a curve which shall best fit the ground lying between tangents, as shown in the topographical map. They are commonly made of pasteboard, each piece containing arcs of two different radii, the degrees of curvature of which, together with the scale of each, being distinctly written, as shown in Fig. 336. A 10° curve to a scale of 100 feet to the inch will serve for a 5° curve to a scale of 200 feet to the inch, or a 2° 30' curve to a scale of 400 feet to the inch. In the same way, a 12° curve to a scale of 100 feet to the inch will serve for a 6° curve to a scale of 200 feet to the inch, or a 3° curve to a 776 MAPPING. scale of 400 feet to the inch. Office curves are applied directly to the contour map upon which a grade line has been platted, and the curves fitted to ground and tangent. Compound curves are as readily fitted as simple curves. A satisfactory line being decided upon, the tangent distances are calculated and the curves struck with a compass. When the radius is of considerable length, it is difficult to describe a true circle with the ordinary compass and length- ening bar. An accurate substitute is found in the beam compass, which consists of two upright legs; one pointed and fixed at the center of the circle; the other leg carrying either pencil or pen, with which the circle is described. Both legs B o o p Fig. ,337. are clamped to a horizontal arm called a beam, which is lengthened or shortened to suit the radius. A cut of a beam compass is shown in Fig. 337. A B is the beam, to which is clamped the needle point at C and the pen or pencil at D. At ^ is a milled-headed screw, which gives slow movement to the pen or pencil at D and adjusts it to the required radius. TOPOGRAPHICAL DRAWING. 1365. General Definition. — Topographical drawing consists of the representation of the different features of any portion of the earth's surface. The different features will comprise all its inequalities of surface, such as hills, hollows, streams, lakes, valleys, and plains; the location of towns, highways, canals, and railroads. Detailed topographical maps give individual dwellings, boundaries of fields, their owners, the charactei of the vegetation, etc. MAPPING. 777 1366. Systems. — There are three principal systems of representing topographical features, viz. : 1. By level contours or horizontal sections. 2. By lines of greatest slope perpendicular to contours. 3. By shades from vertical light. 1367. Ridge Lines and Valley Lines.— Ridge lines are the lines which divide the water falling upon them and from which it passes off on opposite sides. They are the lines of least slope when looking along them from above downwards, and the lines of greatest slope when looking along them from below upwards. They can be readily determined by the slope level. On these lines are found the projecting or protruding bends of the contour lines. Valley lines are the reverse of ridge lines. They are indicated by the water courses which follow or occupy them. They are the lines of greatest slope when looked at from above and of least slope when looked at from below. On these lines are found all the receding or reentering points of the contour lines. 1368. Forms of Ground. — It will be found from a general examination of any surface that ground exists under one of the five following conditions, viz. : 1. Sloping down on all sides ^ i. e., a hill, as shown in Fig. Fig. 338. Fig. 839. 338, the direction in which water would flow being indicated by the arrows. 778 MAPPING. 2. Sloping up on all sides, i. e., a hollow, as shown in Fig. 339. 3. Sloping dozvn on tJirce sides, i. e., shoulder or prom- ontory; the end of a ridge or watershed line, as shown in Fig. 340. Fig. 340. Pig. 841. 4. Sloping up on three sides and down on one side, i. e., a valley, as shown in Fig. 341. 5. Sloping up on two sides and down on two sides, alternately, called a saddle, and shown in Fig. 342. 1369. Clear and Intelligi- ble Maps. — No pains should be spared in making maps clear and intelligible. All water courses, whether occupied or dry, should be accurately sketched, and gaps should be left in the contour lines at suitable intervals, with the eleva- tion of the contours written in them. Where time and cost are not to be considered, the lower sides of the contours may be hatched as though water were draining off them, and the valleys and low places tinted with a light shade of India ink. Sometimes the spaces between the contour lines are tinted with India ink, increasing the tint as the depth increases. Ground under water is commonly so represented. Begin- ning at low water-line, the space to the depth of G feet is covered with a dark shade of India ink ; from feet to 12 feet Fig. 342. MAPPING. 779 with a lighter shade ; from 12 feet to 18 feet with still lighter, and from 18 feet to 24 feet with lightest of all. Greater depths are marked in fathoms. 1 370. Uses of Contours : 1. To locate roads. 2. To obtain vertical sections — profiles. 3. To calculate excavation and embankment. In both railroad and highway location, the contour map is used in platting a grade line to which the final location should closely approximate. The paper location is then made, conforming as closely as possible to the grade line in the contour map, and from that location a final profile is platted. When the contour map is to be used as a basis for the cal- culation of excavation and embankment, a hill or hollow is conceived to be divided into horizontal sections. The areas of the upper and lower bases of any section are then calcu- lated and their average is multiplied by the altitude of the section, which gives the content of that section. PLATE, TITLE : CONTOURS AND SLOPES. 1371. This plate contains three examples in topograph- ical drawing. Each example affords practice in drawing shore lines. Fig. 1 is an example under the first system in which the topography is represented by level contours, and affords the student excellent practice in contour mapping. Figs. 2 and 3 are examples under the second system in which topography is represented by lines of greatest slope or hatchings. First System — By Level Contours. — In Fig. 1 the situation is a steep hillside bordering upon a lake. The en- gineer before commencing the field work should examine the ground thoroughly in order that he may intelligently choose a method of work well suited to the situation. In the case in hand, the surface of the water in the lake is adopted as the datum plane. 780 MAPPING. It is a common and excellent practice to divide the area to be contoured into squares, the dimensions of which will de- pend upon the area to be treated and the degree of detail required in the work. Large areas are usually divided- into squares containing 100 ft. on a side. The division lines serve as guides to those taking the levels. The intersections of the division lines being 100 ft. apart, they render the loca- tion of any intermediate point an easy task. These inter- sections are called stations, and are usually numbered consecutively or distinguished in some other way. In Fig. 1 the area is divided into squares 100 ft. on a side. Base lines A X and A H are first established where distant and well-defined targets may be set up and the lines carefully meas- ured. The importance of an accurately measured base line, and of a distant fixed target can not be overestimated. The lines of division are determined by laying off lines at 90° to these bases, and are supposed to be parallel, a difficult thing to accomplish in rough country where short sights are fre- quent, and impossible if the initial angle of each line is not turned from the same backsight, and that a comparatively distant one. The base lines being established, the lines of division are carefully run. The vertical division lines, i. e., those parallel to general direction of the lake shore, are des- ignated by the letters of the alphabet, the first being de- scribed as line A^ the next as line B^ the next as line C, and so on. The horizontal division lines are numbered consec- utively, commencing with the bottom line, which is num- bered 0, the next parallel to it 1, the next 2, and so on. The intersections of the division lines locate the succeeding stations on each line. This greatly simplifies the keeping of the notes, and enables the engineer to readily locate any point and brieflly describe it. Thus, the starting point of line A is called line A^ 0; the next intersection is called line A, 1; the next line A^ 2, etc. The engineer determines the form of notes best suited to the situation. He will find a leveling rod 20 ft. in length of great assistance when work- ing in a locality where changes in elevation are frequent and abrupt. The form of notes best adapted to the work in MAPPING. 781 hand is the following, the notes being a record of the levels which are taken at each intersection of the division lines: LEVELS OF LINE A. Station. Rod Reading. Height of Instrument. Elevation. B. M. + 8.80 56.05 47.25 7.20 48.80 1 13.70 42.30 T. P. - 19.72 36.33 + 4.20 40.53 2 5.70 34.80 3 14.80 25.70 T. P. - 18.63 21.90 + 3.53 25.43 4 7.10 18.30 5 9.30 16.10 T. P. - 18.55 6.88 + 3.22 10.10 6 9.60 0.50 6 + 05 Edge of Lake. 1372. The contour map is made as follows: First we draw the outlines of the given area, 1,100 ft. in length by 750 ft. in width, to a scale of 100 ft. to the inch. These boundaries are then divided into equal spaces of 100 ft. each, as shown in the engraving, and the lines of division drawn, the boundaries being drawn full and the division lines dotted. The vertical division lines, as before stated, are designated by the letters of the alphabet, and the horizontal lines by numerals. From the level notes we find the elevations of the stations on lines A and B. These elevations we mark on the map at their proper stations, and then locate the contour lines as follows: Beginning with line A, we find that the elevation of Station is 48.8 ft. ; that of Station 1 is 42.3 ft. ; hence, 782 MAPPING. the difference of elevation between these stations is 48.8 — 42.3 = 6.5 ft. The distance between these stations is 100 ft., and the rate of fall between Stations and 1 is equal to —— = 0.5 15.4, which is called a descending slope of 1 to 15.4. The contours are 5 ft. apart, and, therefore, the elevations of each contour will be some multiple of 5 ft. Contour 45 ft. will come between Stations and 1 of line A. As the eleva- tion of Station is 48.8 ft., we must, to reach contour 45, go LEVELS OF LINE B. Station. Rod Reading. Height of Instrument. Elevation. 10.10 7 + 12 Edge of Lake. 7 8.00 2.10 T. P. - 1.24 8.86 + 19.84 28.70 6 8.30 . 20.40 T. P. - 1.65 27.05 + 19.91 46.96 5 15.00 32.00 4 9.20 37.80 3 1.70 45.30 T. P. - 2.21 44.75 + 18.88 63.63 2 6.90 56.70 T. P. - 2.24 61.39 + 18.31 79.70 1 15.50 64.20 4.40 75.30 towards Station 1 far ienough to descend an amount equal to 48.8 — 45.0 = 3.8 ft. As the rate of fall is 1 in 15.4, to fall 3.8 ft. we must go 15.4 x 3.8 = 58.5 ft., which brings us MAPPING. 783 to contour 45. This distance we scale off to a scale of 100 ft. to the inch, marking the point where contour 45 crosses line y^ by a small dot. The next two lower contours are 40 and 35. As the elevation of Station 1 is 42.3 and that of Station 2 is 34.8, both of these contour lines will cross the line between these stations. The total fall between Stations 1 and 2 is 42.3 - 34.8 = 7.5 ft., and the rate of fall is ^ = 13.3. To reach contour 40 we must fall 2.3 ft. below Station 1, and the distance will be 2.3 X 13.3 = 30.6 ft. To reach contour 35 we must fall 5 ft. more, and the additional dis- tance will be 5 X 13.3 = 66.5 ft. We accordingly locate those contours at 30.6 ft. and at 30.6 + 66.5 = 97.1 ft. from Station 1. The difference of elevation between Stations 2 and 3 is 34.8 — 25.7 = 9.1 ft., and equivalent to a de- scending slope of 1 to 11 between them. Contour 30 will come at 4.8 X 11 = 52.8 ft. from Station 2. The difference of elevation between Stations 3 and 4 is 25.7 — 18.3 = 7.4 ft., which gives a descending slope of say 1 to 14. This is not the exact rate of slope, but where decimal fractions are small and slopes easy the fractions may be ignored, as they will not to a perceptible degree affect the accuracy of the work. Con- tour 25 will come at 14 X .7 = 9.8 ft. from Station 3, and contour 20 at a point 70 ft. farther, or at say 80 ft. from Station 3. The difference of elevation between Stations 4 and 5 is 18.3 — 16.1 = 2.2, but no contour line passes between these points. The difference of elevation between Stations 5 and 6 is 16.1 — .5 = 15.6, which gives a slope of 1 to 6.4. This brings contour 15 at 7 ft., contour 10 at 39 ft., and contour 5 at 71 ft. from Station 5. 1373. The usual custom is to -work up the notes, as it is called, before commencing the platting of the contours, and when a considerable portion of the ground has been covered, plat them, and thus avoid the delay incurred by frequent changes of work. Each engineer decides upon that form of notes best suited to the character of the work in hand. The following is a clear and simple form of notes 784 MAPPING. in which is given the location and elevation of the con- tours on line B and on the cross-section lines between lines A and B: Line B. Contours Between Lines A and B. Sta. to 1. from A to B 0. + 3 to contour 75 5 ft. to contour 50 + 48 to contour 70 24 ft. to contour 55 + 93 to contour 65 43 ft. to contour 60 62 ft. to contour 65 81 ft. to contour 70 97 ft. to contour 75 Sta. 1 to 2. A 1 to B L 1 + 56 to contour 60 12 ft. to contour 45 34 ft. to contour 50 57 ft. to contour 55 79 ft. to contour 60 Sta. 2 to 3. A 2 to B 2. 2 -f- 15 to contour 55 1 ft. to contour 35 2 + 59 to contour 50 23 ft. to contour 40 46 ft. to contour 45 68 ft. to contour 50 91 ft. to contour 55 Sta. 3 to 4. A 3 to B 3. 3 + 04 to contour 45 21 ft. to contour 30 3 + 70 to contour 40 46 ft. to contour 35 71 ft. to contour 40 96 ft. to contour 45 MAPPING. 785 Line B. Contours Between Lines • A and B. Sta. 4 to 5. A ito B i. 4+48 to contour 35 9 ft. to contour 20 34 ft. to contour 25 59 ft. to contour 30 84 ft. to contour 35 Sta. 5 to 6. A 5 to B d. 6 + 17 to contour 30 24 ft. to contour 20 5 + 60 to contour 25 55 ft. to contour 25 86 ft. to contour 30 Sta. G to 7. A 6 to B 6. 6 + 02 to contour 20 22 ft. to contour 5 6 + 29 to contour 15 47 ft. to contour 10 6 + 56 to contour 10 72 ft. to contour 15 6 + 83 to contour 5 97 ft. to contour 20 Sta. 7. ^ 7 to B 7. 7 + 12 to contour 0, 95 ft. to contour 0, at edge of lake. at edge of lake. 1374. The student having worked up these notes can, with a little practice, plat them rapidly, using a decimal scale. A small offset scale is very convenient in locating contours. The examples given in working up notes will enable the student to similarly treat the others. He should be systematic in his calculations and platting, completing all the calculations on one line before commencing another, and do likewise in his platting. Otherwise, confusion is sure to follow. 786 MAPPING. The elevations of the ground at the intersections of the division lines are given in the engraving. This is done for the convenience and assistance of the student. In regular office work the elevations of these points are taken from the level book, and the only elevations given in the map are those of the contours, which are written in gaps left in the contours for that purpose. These elevations should be distinctly written, and, unless the slopes are very steep, bringing the contours very close together, the elevations should be written successively one above the other. In drawing the shore line, avoid the drawing of straight, regular lines. All shore lines, and especially those of lakes, are very irregular. A heavy line is first drawn outlining the shore, then a lighter one, at a small distance from, and parallel to, the first; then another line, at a greater distance from the second than the second is from the first ; and so on until the shore line is clearly defined. The contours themselves are to be drawn free-hand with an ordinary writing pen. 1375. Second System — By Lines of Greatest Slope. — Their direction is that which water would take in running off them. They are drawn perpendicular to the contour lines^ and are called hatchings. An example of this system is shown in Fig. 343. In sketching topography by this system, the topographer should hold the book directly in front of him so as to corre- spond with his position on the ground, drawing the lines towards him. If at the top of a hill, begin by drawing the lines from the bottom, and vice versa. To guide the hatch- ings, he should lightly sketch in the contour lines. Hatch- ings must be drawn truly perpendicular to the contour lines. Where the contour lines curve sharply, it is often well to draw in hatchings at considerable intervals as a guide to the main body of those drawn afterwards. Hatchings in adjoin- ing rows should not be contimious, but so drawn as to break joints. They must not overlap, and should be drawn in MAPPING. 787 slightly ivavy lines. In drawing a hill where the slopes are steep and irregular, it is often well to draw auxiliary contours. An example of this system is given in Fig. 3 of Plate, Title: Contours and Slopes, which represents an abrupt promontory. Its base marks the channel of a river. The ground on the opposite side of the river is generally level with occasional undulations. The degree of the slope is indicated by the spacing of the contours and the correspond- ing lengths and number of hatchings. The more abrupt the slope the closer together the contours and hatchings. Fig. 3-13. The preliminary work necessary for such a topographical map is as follows: A traverse or meander line is. run, mark- ing the windings of the stream. Having platted this meander line, the topographer takes his book containing the sketch, and from the promontory itself sketches in the main features of the surface. A hand level is of great ser- vice in determining relative elevations. From these notes the final map is made up, the work being done in the office. Fine topographical drafting should not be attempted in camp. The facilities of a well-equipped office are necessary to rapid and satisfactory work. The student is not expected 788 MAPPING. to reproduce the exact outline of the figure^ but it is expected that his work will show a proper understanding of the sub- ject. Having drawn the outline of the river, he should draw in the contours in light pencil lines, spacing them to conform to the different slopes. It will be evident to the student that within the space represented by Fig. 2 the sur- face of the river at C and D will be practically the same. Hence, if the distance from the summit A to the river at E is but half the distance from A to F, the slope A E must be twice as abrupt as the slope A F. Hence, the contours which mark equal heights will be twice as far apart on the slope A F as on the slope A E. He should draw all the contours, outlining the summits at A and B^ before com- mencing the hatchings. The short hatchings on either side of the river mark its banks. On the promontory side they are shorter than on the opposite side, as the former has the more abrupt banks. Fig. 3 of the same plate represents an irregular and abrupt sea coast. The survey for such an area would embrace a traverse of the entire shore line — of the island as well as the mainland. This traverse line should be used as a base line for auxiliary traverse lines, by means of which the summits A, B, C\ D, and E, and any other important objects could be located. . The heights of these summits could be determined either by triangulation or by the aneroid barometer. With this information as a basis, the shore line is located, the contours sketched in, and the hatchings drawn. As in the case of Fig. 2, the student is not expected to produce a literal copy, but to show his proficiency by furnishing a clear and finished drawing. Hatchings should have their thickness and distance apart proportional to the steepness of the slope. The lines are made heavier as the slope is steeper, being fine for gentle slopes, and for very steep slopes the blank spaces are but half the breadth of the lines. 1376. Third System— By Shades from Vertical I^ight. — The steeper the slope the less light it receives. In practice, the difference in color is much exaggerated. MAPPING. 789 Various governments have prepared tables establishing the ratio of color to different slopes. The shading is applied in various ways. A rapid method, and a sufficiently accurate one for many kinds of work, is to sketch in the contours and then apply the shading in the form of India ink. Each varying tint is applied with its particular brush, care being taken not to allow any tint to dry before the succeeding tint is applied. By this means the tints are blended, giving a smooth and finished effect to the work. The tints are made light for gentle slopes and dark for steep slopes, a slope of 60° being black and one of 30° being midway between black and white, and so on. 1377. Shades by Contour Lines. — This is accom- plished by interpolating additional contour lines between the regular contours. Confusion is likely to result from this method, especially where the slopes are steep, as the numerous contours are liable to run together or be confused with roads or boundaries. CONVENTIONAL SIGNS. 1378. Sand, Rock, Etc. — Sand is represented by fine dots made by the point of a pen ; gravel by coarser dots. Rocks are represented by angular, irregular masses, as would appear when seen from above and drawn in their proper places. 1379. Signs for Vegetation. — Woods are repre- sented by scalloped circles, irregularly placed, closSr or ttU %^^ 44i^ ; i. / > ill 11 ft %%.%%% ^*% ^^ "^V^^ Ms %%<^<^^. %'«=« \ ,yA \~^'''--i \^-\^ Fig. 354. at the point of junction, as at A or B. This simplifies the work of fitting the sheets and greatly promotes accuracy. 1389. Lettering. — Legibility and uniformity are the requisites for good lettering. Ornamental letters, ex- cepting for titles, are entirely out of place, and they are only admissible for titles of very elaborate maps. All let- tering in the body of the map or details should be in italics. Small letters should be two-thirds the height of capitals, ordinary capitals | of an inch in height, and small letters f of ^ or -^^ i^^h in height. Uniformity in spacing letters is as important as uniformity in size. There is no work where practice is more essential, if skill is to be ac- quired, and nothing adds more to the finish of a drawing than good lettering, while poor and slovenly lettering will rob of all merit an otherwise perfect drawing. 1390. General Instructions. — If the entire map is to be contained on a single sheet, judgment is required in fixing the direction of the first course so as to attain that result. The points of the compass must also be in their MAPPING. ■ 811 natural order, viz., North at the top of the map and South at the bottom. The outline of the map will determine the position of the title. Yery fine lines are a blemish rather than a merit, and heavy lines are likewise to be avoided except when used for shading or boundaries. Boundaries of private property are represented by bold, full lines, and those of state, county, or municipality by heavy broken and dotted lines. All dimensions should be expressed in figures, and all impor- tant lines and objects briefly but accurately described. RAILROAD LOCATION. 1391. Need of a Railroad. — This subject presup- poses that there is, beyond a doubt, need, both present and prospective, for the railroad whose location is to be decided upon. 1392. Available Capital.— The first duty of the Chief Engineer is to know how much money those having the direction of the enterprise, commonly known as tJic company, have or can command, as all subsequent operations will be governed by that fact alone. Having obtained that infor- mation, he collects all available maps of the country to be operated in, and from them derives a general knowledge of the mountain ranges, valleys, rivers, together with their tributaries, and the location of all towns and villages lying within that territory, their relative size and importance. 1393. Terminals. — The terminals or extremities of the proposed railroad are known, and the first problem be- fore the engineer is to determine the general route which the line connecting them should take. A careful study of the maps in hand will indicate to him the different possible routes whose comparative merits he can know only by care- ful investigation. The number of these possible routes will probably be further reduced by the location of certain towns which must be reached for traffic considerations. These towns will divide up the line into two or more sections, each offering considerable range in choice of location, which in- dicate to the engineer the scope of the country to be covered by the reconnaissance. 1394. Important Considerations. — The engineer should preserve an optimistic habit of mind, believing noth- ing to be too difficult to be overcome, and fully expecting 814 RAILROAD LOCATION. to find a line in every way superior to that which had been regarded as possible. It is of the highest importance that he should regard the proposed line from a business point of view, and be able to distinguish between what is commer- cially important and physically important. He should keep constantly in mind this vital fact, viz., that a line of rail- road is built for the pifrpose of making money for its project- ors; that any expenditure which will add proportionately to the earning power of the road is wise^ and that any which will not is criminal zaaste. 1395. Relative Economy. — The engineer must, however, be able to distinguish between wise and unwise economy. Because a line is brought to sub-grade cheaply, it is not necessarily economical grading. It requires an average continuous cut and fill of 7 feet, with the usual proportion of masonry, to equal the cost of the superstructure, i. e., ties, rails, fastenings, and ballast, while the cost of rolling stock, machinery, buildings, etc., of an active road, cost nearly as much as roadbed and track complete. 1396. Towns and Terminals. — Towns, which are always the main sources of traffic, and terminals, which, besides being sources of traffic, are the main points of traffic exchange, are considerations of vital importance to the road. No expense within the possible reach of the com- pany should be spared in reaching the heart of towns and in providing the best traffic facilities. A small saving in time and a small increase in comfort will, other things being equal, secure the traffic. Where the new line comes into competition with old and favored lines, no pains which tact or ingenuity can devise should be spared to induce favor and patronage. It is at such a juncture that tact and enterprise count. No source of business, however insignificant, should be overlooked, and every point gained should be held at any reasonable cost. Provide ample terminal grounds at any possible cost; with them a new road will have a hard fight, while the lack of them places the road at a great disadvan- tage from the first, and may cause its ruin. RAILROAD LOCATION. 815 1397. Comparative Cost of Different Lines. — In order that the engineer may correctly estimate the com- parative cost of different lines, he must know the actual cost of work of various kinds, and be able, from his exami- nations of the country, to properly classify it. Experience in the location and construction of other lines will alone enable him to decide between the comparative merits of the different routes. The almost universal fault of engineers is to underesti- mate cost, a fault common to all persons who are about to undertake construction of any kind. Experienced engineers make it a rule to add 10 per cent, to the estimate which is intended to cover all possible cost. 1398. Considerations Which Determine the Route. — Traffic and engineering considerations will usually reduce the possible routes to tivo if not to one^ thus narrow- ing the field of operations. The work of reducing the traffic and engineering possibilities of a section of country to their lozvest terms is emphatically the work of the chief engineer, and is embraced in that most important, though much mis- understood, term, viz., the reconnaissance. Let the young engineer keep prominently before his mind that the largest half of a railroad survey is the reconnaissance. Let him ponder well the varied interests and problems which con- front him, and let him know his country before he drives a stake. This knowledge can be had only by hard work and a good deal of it. RECONNAISSANCE. 1399. General Directions. — Having provided him- self with the best available map of the section immediately in hand, an aneroid barometer, and a guide who is familiar with the section, the engineer is ready for a start. He should avoid highways if he is to acquire the knowledge he is seeking, as they give the traveler an erroneous impres- sion of the character of the surrounding country. He un- consciously believes because the " walking is good " that the 816 RAILROAD LOCATION. surrounding country is smooth and tractable, and obstacles to railroad building few and insignificant. On the other hand, by taking a cross-country route, he will be likely to exaggerate those obstacles, simply because they have im- peded his travel. All experience goes to prove that in America, at least, the railways avoid the highways; not through the intent of the engineer, but, as it were, in silent condemnation of the incapacity of those who directed their building. The engineer should keep constantly in mind that his examinations are not to be confined to the strip of country within his immediate vision, but are to cover a range of several miles on either side of his line of march. Much information he can obtain from his guide; more he must find out for himself — taking nothing for granted where a doubt is raised. Very often an apparent obstruction which, did it really exist, would effectually bar the way, will disappear upon a careful inspection of the country, or at the worst prove an insignificant obstacle compared to those already passed. Obstacles to travel are not neces- sarily obstacles to railway building. Narrow defiles, ob- structed by boulders, underbrush, and timber will, when cleared, appear comparatively smooth. 1400. Use of the Hand Level.— The hand-level is of the greatest value, and should be in constant use. The unaided eye is of little use in estimating comparative elevations. The hand level determines relative heights, constantly affording needed information and saving much time, which, without it, would be spent in useless tramping. 1401. Keeping Notes. — A careful record should be kept of all streams encountered; their direction, and of what larger streams they are tributaries. The sizes of different streams in the same section, to a certain degree, determines their relative elevations. The larger the stream the lower its elevation. The velocity of its current, in a measure, indicates the grade of a stream, though a fall which would make a torrent of a river Avould give but a feeble current to a shallow stream. The recon- RAILROAD LOCATION. 817 naissance should cover a complete section of the proposed line before the work of actual survey is commenced, though it is not to be considered as complete until the final location is fixed. 1402. Deceptive Appearances of Country. — The natural eyesight is easily deceived, and rarely gives to objects their true relative proportions.. Two reasons for this deception are the following: First, the eye foreshortens the distance in an air line, and exaggerates a lateral offset. This fact is illustrated by Fig. 355, in which let the points A a.ndB, which are 10,000 ft. apart, be in an air line between two towns, and suppose this line to cross a ridge, the highest point of which is at C, and that the ridge flattens out at D, 2,000 feet from C, the middle point of A B. To the inexperienced, the offset C D, as seen on the ground, will be greatly exaggerated, appear- ing to be fully one-half the straight line A B, and the con- viction will follow that in passing from A to B hy way of C, not only will a great deal of curvature be introduced, but the length of the line will be so greatly increased over that of A B as to make a careful consideration of the route out of the question; even though the line A Z>' should require steep grades and a heavy cut at C. This exaggeration is apparent when we find by calculation that the distance from A to B hy way of D is only 770.33 ft. greater than the direct line between A and B. This illusion of the eye ex- plains the aversion to sivinging the line, too common among engineers, and the undue importance attached to good alineinent. The chances are four to one that the line A D B is immensely superior to the line A B, both in cost 818 RAILROAD LOCATION. and grades, while the increase in distance of the line A D B over the line A B vs, less than 8 per cent. Frequently a deflection, which will not, in reality, add more than 15 per cent, to the length of a line, will appear to double it, and the deplorable mistake is often miade of adopting the air line, even though it cost 25 per cent, in excess of what the deflected line would cost. Second, the eye exaggerates the sharpness of projecting points and spurs and the degree of curvature necessary to pass around them. All slopes when looked at from in front, are exaggerated by the eye. Few mountains have slopes exceeding 1^ to 1 or 33^°, yet the eye will estimate such a slope at from 45° to 50°. In running the line A B C D, Fig. 356, the engineer, if he were to accept his natural estimate of the angles at B and C, Fig. 356. would make the angle at C about twice as large as the angle at B; even though he had walked over the line. The reason for this is that while standing at any point on the line B C, his view of the line C D is cut off by the profile £ C of the hill in front, and, in spite of himself, the unseen will be distorted and invariably magnified. Nowhere is the proverb, "appearances are deceiving," so true as in an apparently smooth or gently rolling country. The undulations are so gradual that their aggregate is rarely suspected. Abundant experience goes to prove that an air line in such a country is only possible at the cost of heavy grades and long and heavy cuts and fills. To avoid them, frequent deflections must be made, introducing curvature in proportion, though the increase in length of line is in no RAILROAD LOCATION. 819 degree proportional to the saving in cost of construction and operation. 1403. Discredit All Unfavorable Reports. — An unfavorable report of a locality, more than any other, should challenge a careful examination. The inexperienced are easily daunted by obstacles which are really insignificant. A section heavily timbered and covered with boulders, and appearing to them as forbidding in the extreme, would likely show an alinement and grades incomparably better than the line of their choice. In reconnaissance it is the unexpected which happens, and the line which appears least promising will often prove, by far, the best. 1404. Choice of Lines. — Never believe that only one line is possible. There are always two, and generally sev- FIG. 357. eral. The important question is, which line is the best, and 820 RAILROAD LOCATION. that is the one to settle upon. The following instance well illustrates this point. The facts in the case are shown in Fig. 357. The line had followed the river A B for several miles, keeping a uniform grade of about 30 feet per mile. It became necessary to leave the river valley and climb a ridge in order to reach a town lying in another valley. The entire country was thickly covered with timber and undergrowth, and consisted of abrupt, irregular hills, called hog-backs. The brook C was known to the engineer, who endeavored to trace it to its junction with the river, but the brook lost it- self in a cedar swamp at Z>, and it was impossible to find the outlet. After repeated effort to find the outlet and encoun- tering each time the ridge E which lay between the river and the valley D C, he continued the line up the river, crossing it at B, where a precipitous ledge prevented further progress along the river, and crossing the neck of land /% and the river at G, commenced to climb the ridge doubling about the sharp headland at //, . and then swinging backwards, making the line K L with a heavy fill at M. This seemed the only possible line, but it was so rough and crooked that the engineer determined to make another trial. He spent two days in hard tramping during a continual downpour of rain, discovering the narrow opening at N through which the brook found its way. He also found the brooks /*and Q, and blazed a line through from E \.o K. A line was then run, following this course with the most satisfactory results, saving two river bridges and three miles in distance, though getting through the ridge at E entailed a heavy cut. The railroad company was opposed to any further investigation after the completion of the first line, as a month of hard work had been expended upon it. Yet the saving in first cost accomplished by the adoption of the second line over the first would have paid the engineering expenses of the entire line of 100 miles. In general, a better line than the one already in hand can be found by looking for it. 1405. Advantages of Valley Lines. — Wherever possible, stick to the valleys. Bottom lands, though low- RAILROAD LOCATION. 821 lying, are generally above flood line, or, if below it, are only covered by back-water, else they would have been long since washed away. Though a crooked channel may necessitate frequent and sharp curves, yet they are more than compen- sated for by the low grades fixed by that channel. As fre- quently happens, the bends in the channel are caused by projecting heads of hills. These sharp and often rocky points usually require but short cuts, and furnish the best of material for the adjacent embankments. Notes should be kept of all important information gained. Points where two promising lines diverge should be so marked as to be readily recognized. The reconnaissance being completed and all economical and topographical questions settled, the next duty of the engineer is the preliminary survey. The party should be organized and all ready for service the moment the recon- naissance and general route is decided upon. 1406. Organization of Party. — The size of the party will depend upon the character of the country in which the work is to be done. If thickly settled, smaller; if thinly settled, larger. A well-equipped party in ordinary country should number sixteen men, as follows: The transit party, comprising chief of party, transitman, two chainmen, three axmen, one stakeman, and one back flagman; the level party, com- prising the leveler, rodman, and one axman, and the topo- graphical party, comprising the topographer and two assist- ants. The last to be named, though not the last in point of importance, is the teamster, who should be provided with a strong, active team, and spring wagon that will not break down. It is a most wasteful economy to require a party to walk from two to five miles before commencing work, and then to quit work in time to make another long tramp be- fore reaching shelter. A chief of party who does not know the necessity for a team and insist upon having it, is not fit for the work in hand. No company will refuse to provide it, if the matter be properly presented, yet many parties are 822 RAILROAD LOCATION. deprived of this important part of the outfit. If the party are living in camp, a team is an absolute necessity for moving the camp, which will be done at least once a week, and usually once in three or four days. 1407. Caqip Outfit. — For camp work the following outfit will be necessary: Two wall tents with flies, or extra roofs, for the accom- modation of the men, and, if the work is to be carried on during the winter season, a tent must be provided for the team ; a sheet-iron stove and provision chest for the com- missary ; a cook who can prepare wholesome food and plenty of it, and keep himself and belongings clean and orderly; a drafting table, which is nothing more than a large draw- ing board, a straight-edge and triangles, an ordinary pocket case of drafting instruments, together with a beam com- pass, will answer for all preliminary drafting. Drawing and profile paper, note books, etc., are carried in a camp chest. Each man provides his own bedding, which consists of blankets alone. The field instruments will comprise the following, viz. : A surveyor's compass, plain transit, and transit poles, Y level and Philadelphia leveling rod, aneroid barometer, clinom- eter, slope rod, chain, axes, marking crayons, tacks, and stake straps about the width and length of ordinary trunk straps. A supply of stakes should be kept constantly on hand. If possible, have these of light, well-seasoned wood (pine is best) and of the following dimensions: Length 2 ft. 6 in., width 2 in., thickness ^ in., and planed on one side so as to admit of easy and plain numbering. Special conditions may require additional equipment, but the above outfit will meet all ordinary requirements. 1408. The Compass for Preliminary Work. — If the section be comparatively free from iron deposits, the preliminary line should be run with the compass, for in spite of small inaccuracies in alinement due to errors in reading the needle, the average accuracy of a number of readings will closely approximate to those read with the transit RAILROAD LOCATION. 823 vernier. The comparative advantages of compass and tran- sit for preliminary railroad surveys was discussed in Art. 1217. Suffice to say, that where the conditions warrant it, the compass is always the more economical and expedi- tious instrument. If, however, iron exists in quantities sufficient to hinder the perfect freedom of the magnetic needle, the compass must be discarded for the transit, with the injunction to never record an angle without first check- ing it ; and after recording, read the angle a second time. The assurance of accuracy is worth many times the labor and care of checking work. FIELD WORK. 1409. The Starting Point.— In general, the start- ing point of the survey will be at an extremity of one of the sections into which the proposed line is divided. If it is to connect with some already existing line, a point on that line is taken; if not, a street line or some other fixed boundary is chosen and the line tied into it. The chief of party ac- companied by a flagman, goes ahead and fixes the points where the angles are to be taken. The flagman carries, be- sides the transit pole, an ax for making plugs, one of which he drives flush with the ground at every transit point. A galvanized tack, or, better still, a small galvan- ized nail, is driven in the center of the plug and the transit pole (flag) held on the point while the transitman reads the angle. A point having been fixed, and the flag set up, the transitman measures the angle between the boundary at Station and the first course. The angle and bearing of the line being recorded, the transitman walks rapidly to the point where the flag is standing and sets up the instrument at that point. The head flagman should carry about a dozen pieces of red flannel to be used as targets. As soon as a transit point is set and the transitman has signaled that the angle is read, the flagman should tie a piece of target flan- nel to a light stake of about the same length as the transit pole, and plant the pole firmly in line directly behind the 824 RAILROAD LOCATION. plug or transit point. This affords the chainman a good target for liJiing in, and allows the flagman to join the chief of party who has gone ahead to select another transit point. The transit being set up, a backsight is taken to a flag held at the starting point (Station 0). The bearing is then checked and the angle turned to the next point ahead. The chainmen having come up with the transit, they report the number of the station of the transit point to the transitman, who records it in the transit book. He then directs the chainman on the next course, reads the forward angle and records it together with the bearing of that course, and then moves up to the next transit point. 1410. The Level Party. — The level party follows the transit party as closely as possible. The levels of the proposed line and the line with which it is to connect should be referred to the same datum plane, so as to secure a con- tinuous profile; especially if the levels of the established line are referred to the sea level. If such a base is not practicable, an elevation for the starting point must be as- sumed, but of such a. height as will bring all elevations of the proposed line above the assumed datum plane. In case the country is wooded, with the added hindrance of thick underbrush, the transit party will of necessity move slowly, and the level party will consequently have much spare time on their hands. They should provide themselves with profile paper and keep the profile platted as the work progresses. 1411. Bench Marks. — Bench marks are established at intervals of from 1,000 to 1,500 feet, according as the line is rough or smooth. At every stream which the line crosses the elevation of the surface of the water and of the bed of the stream should be taken. If there are any marks indica- ting the elevation of high water, a rod reading should be taken at such point and a record made of it. 141 2. The Topographical Party. — The topograph- ical party follows the level party, though their rate of progress will be more uncertain than either of the parties preceding RAILROAD LOCATION. 825 them. Where the slopes are uniform, they need not be taken oftener than every third or fourth station. If, how- ever, the country is broken and rough, it may be necessary to take them .at each hundred feet, and with great minuteness. 1413. Office Work. — At the conclusion of each day's work, the field notes, both transit and level, are carefully checked, and a plat of the line is made, either by tangents or by latitudes and departures, carefully marking the cross- ings of streams and highways, and noting any important point which would enable the chief engineer to readily locate any particular section of the line. Where the coun- try is smooth the line may be platted to a scale of 400 feet to the inch. Rough parts of the line may not exceed a scale of 200 feet to the inch, and where difficult country is encountered, involving detailed topographical maps, a scale of 100 feet to the inch is advisable. Plat the line on sheets 24' X 30' in size, numbering them in regular order, each sheet containing a part of the line on the immediately pre- ceding sheet, so that by matching and pinning them together, there may be had a continuous map of the line. So arrange the line on the different sheets that when the paper location is made they shall contain as many curve centers as possible. The topographer will do his proportional share of the work, which will consist mainly in a detailed explanation of the notes of the day's work to the draftsman, whose princi- pal work is the contour maps. The leveler will plat the day's levels on the continuous profile kept in the office, the rodman reading the notes. This profile will contain as full information as possible, especially relating to highways and watercourses. Some engineers prefer to wait for a rainy day in which to do the office work, but more make it an invariable rule to plat each night the work of the day. This practice enables the chief of party to have a complete record of his work always ready for the inspection of the chief engineer, who 626 RAILROAD LOCATION. is liable to appear at any time. If he is his own chiefs per- sonal interest in the work would warrant him in making such a rule. Notes which are platted when/V^.f// are always of more value than when stale, and the daily office work unites the different parties which are separated during the day, sustaining a common interest in the work. If the con- tour maps are to keep pace with the survey, the draftsman must be an expert. Each day he plats the work of the pre- ceding day, and under the direction of the topographer, every point is covered. 1414. Spur Lines. — At certain points of the main line, two and sometimes three different routes will present Fig. 368. RAILROAD LOCATION. 827 themselves for reaching another point of that line, and re- quire the running of spur lines to determine the most advan- tageous route. The main line being run, the spur lines are tied into it, designating them by different letters, as liney^, line B^ etc. The comparative advantage of the different alinements will show themselves in the plat. Their com- parative profiles are commonly shown by platting them in different colors. A case requiring spur lines is shown in Fig. 358. Here the general direction of the main line is C D E F, D being the point where the spur lines A and B diverge from the main line, and E where they again unite. It will be evident from an inspection of the map that the main line is superior to both the spur lines in point of alinement. Their comparative lengths are already known. With the comparative profiles before the engineer, he, knowing the nature of the ground on the different lines, will have no difficulty in making a judicious choice of lines. Sometimes where the merits of the different lines are nicely balanced, it becomes necessary to locate on two lines and base a decision upon actual estimate of cost of construction. 1415. Gradients. — The preliminary survey having been completed, a careful study of the profiles will enable the chief engineer to establish a gradient whose maximum will limit the train loads passing over it. The character of the expected traffic will greatly modify this maximum. If the road is to do a passenger business principally, the gradient may be raised, but if the bulk of the business is to be freight, the gradient must bcplaced at the lowest possible limit which the finances of the company and the nature of the country will permit. Should all the heavy grades occur on a short section of the line, it may be policy to mass them within the smallest pos- sible limits and proportionately reduce the gradient of the remainder of the line. In such an arrangement of grades, an assistant engine would be used on the summit section, and so cover the entire line without any change of train loads. 828 RAILROAD LOCATION. 1416. Curvature. — There is no absolute rule for limiting curvature. The approximate limit will depend upon the topography of the country and upon the character of the expected traffic, a freight traffic admitting a higher and a passenger traffic requiring a lower degree of curvature. For all ordinary traffic conditions, i. e., where freight and passenger traffic will be about equal, the invariable rule is use such curves as zvill best conform to the existing topographical conditions. Any curve up to 10 degrees will be no obstacle to a speed of 30 miles per hour, the average speed of passenger trains. This affords a range in curvature which will meet the requirements of most localities. Curvature is no blemish to a line, if it secures the great advantages of low gradients and moderate cost. At points Fig. 359. where moderate curves are possible only at great cost, it is often a wise policy to build a temporary line, using sharp curves, and put off the expensive work until the financial strength of the company warrants its undertaking. RAILROAD LOCATION. 8'29 An instance where a temporary line is expedient is shown in Fig. 359. Here the track follows the windings of a stream in a narrow valley, whose sides are steep and rough. Unless the company is financially strong, it will be much better policy to build the line A B C D £, using curves as high as 15°, and reducing cost to a minimum, than to build the line A F B, giving a single curve of G°, but requiring a heavy rock cut at /% or perhaps a tunnel at that point. The line A F £ is always possible, and when the road has built up a paying traffic and finances are easy, the cut or tunnel at F can be made without interfering in any way with traffic, and, in all probability, at much better prices than when the. temporary line was built. The question of gradients being decided, a preliminary profile is made, which will serve as a basis for a paper location. 1417. A Paper Location. — The paper location is substantially the one which takes permanent form in the final or located line. It is laid down on the contour maps, which contain all the information accumulated by the pre- ceding surveys. The grade for each station is taken from the preliminary profile and marked on the contour maps opposite the corresponding station. This is readily done, as the contours are but five feet apart, and intermediate eleva- tions can easily be estimated. These grade points are com- monly marked by small red dots enclosed in small circles of the same color, and show where the plane of the grade would cut the surface of the ground. A piece of fine thread is then stretched, covering as many of these points as pos- sible, and a pencil line drawn in place of the thread. This pencil line will locate a tangent on the map. In the same way any number of tangents may be located. A set of office curves will be of great assistance in fitting curves to the tangents, the curves like the tangents fol- lowing the grade line as nearly as possible. Having determined the degrees of curve uniting the tangents, the intersection angles are calculated by tangents and the 830 RAILROAD LOCATION. Fig. 360. tangent distances accu- rately scaled from the intersection points. 1418. Field Notes from the Paper Lo- cation. — In taking notes from the paper location for actual field work, the points of curve and points of tangent should be care- fully referred to fixed points in the preliminary line (either stakes or plugs, the latter are pref- erable) so that if, upon the completion of any curve, the following tan- gent does not take the position prescribed for it in the notes, it may be stvnng into that position. It is impossible, especial- ly in a rough country, to make the actual measure- ments agree with the cal- culated measurements, hence small inaccuracies need cause no concern. The platting of a paper location is illustrated in Fig. 300. Here the grade of the line is determined by the grade of the stream, which it closely follows. The grade averages . 5 per cent. The preliminary line is shown dotted, and RAILROAD LOCATION. 831 the located line is drawn full. Let the grade for Sta. 1 be 11.0 feet. The grade for Sta. 2 will, therefore, be 11.0 feet plus. 5 foot, or 11.5 feet. The grade for Sta. 3 will be 11. 5 + .5, or 12 feet. By the same process we find the grade for each of the stations given in the plat. The grade for each station is then marked on the contour map opposite the correspond- ing station of the preliminary line by a small dot enclosed in a circle. Straight lines A B and C D, which are to form tangents in the paper location, are then drawn, covering as many of these small circles as may be, and produce, until they intersect at E. The line ^ ^ is then produced to F, making E F = 300 feet or any other convenient length of radius suitable for measuring the intersection angle by its tangent. At /^ erect the perpendicular F G, which will be the tangent of the intersection angle F E G. Meas- uring F G hy scale F G = 140 feet, though by calculation 139.89 feet. Dividing 140 by 300 we have a quotient of .4667 = tan 25°. We find By trying different curves that an 8° curve will most nearly cover the grade points between the tangents A B and C D. From formula 9 1 , 7" = /? tan \ I (Art. 1251), we find the tangent distance = 158. 9 feet. Scaling from the intersection point E on both tangents this distance we locate the P. C. and P. T. The station of the P. C. we determine by scaling from the P. T. of the last curve. The station of the P. T. is, of course, found by, calculation. 1419. Paper Location Profile. — A profile, called a paper location proflle, is made from elevations taken from the contour map at each station of the paper location, and a grade line drawn on it which should be substantially that of the final location, and if the preliminary work has been thoroughly done, the discrepancy will be but slight. 1420. Actual Location. — The location party has the same organization as the preliminary party, excepting the topographer and his assistants. Their work is supposed to be completed. The chief of party carries, besides the notes of the location, which is to be run in on the ground^ the map 832 RAILROAD LOCATION. covering the section immediately in hand, as not infre- quently it is necessary to slightly modify the paper location. He will need in addition a short scale and compass carrying a pencil point. Where the country is open, it is good practice to locate the tangents by offsets from the preliminary line and make the intersections on the ground ; but if the ground is covered with brush or timber, the paper location must be strictly followed, and the results will generally fulfil all reasonable expectations. PROBLEMS IN LOCATION. 1421. Problems in Location. — The tangents being fixed in the paper location, the purpose is to so fix the point of curve, the P. C, that, the curve being run, its tangent shall coincide with the following tangent as laid down in the paper location. Frequently, the actual tangent fails to coincide with the theoretical tangent, in which case it must be swung- into place. Sometimes the tangents not only fail to coincide, but form an angle with each other, in which case the central angle of the curve must be either increased or diminished, as the case demands. These modifications of the paper location give rise to the following problems, which will cover all ordinary cases: 1422. Problem I. — To change the P. C. of a curve so that the curve shall terminate in a tangent parallel to a given tangent and at a given distance from it: Let A />', Fig. 3G1, be a curve terminating in the tangent B C, and it is required to change the P. C. of the curve from A to A' , so that it shall terminate in a tangent B' C parallel to B C and at a fixed distance from it. The angle B B' D = I, the angle of intersection of the tangents. We have sin B B' D = -rm, whence B B' = —. — ,. B B sm / B B' ■= O O' = A A\ the required distance to move the P. C. of the curve either backwards or forwards, according RAILROAD LOCATION. 833 as the required tangent is within or without the given tangent. Substituting A A' ior B B' we have A A' = -. — j. In the figure the required tangent is within the given Fig. 361. tangent. Let the intersection angle be 68° and the distance 40 B D = iO feet. Sin G8° = .92718, whence A A' = —z^^ = 43.14 feet. That is, the P. C. of the required curve must be moved backwards 43.14 feet from the P. C. of the given curve. • 1 423. Problem II. — To change the point of compound curvature, the P. C. C, so that the second curve shall ter- minate in a tangent parallel to a given tangent, and at a given distance from it. Case I. When the second curve is of shorter radius than the first curve: Let A B D, Fig. 362, be a compound curve terminating 834 RAILROAD LOCATION. in the tangent D H, and let it be required to change the P. C. C. from B to some point E, so that the curve shall terminate (as shown in the figure) in a tangent F G, parallel to and at a given distance H G from D H. To determine the point E (the new P. C. C. ) the angle ELF must be determined, and sub- stituted for the known angle B K D. From C, the center of the larger curve, let fall upon F G the perpendicular C G. From K and L let fall upon C G the perpendiculars K M and L N. Call the longer radius C B,R\ the shorter radius K D, r; the distance I F or its equal H G, D; the angle B K D ox its equal K C M,x, and the required angle ELF or its equal L C N, y. Then, MN Fig. 362. {R — r) COS x-\- D cos y = ^ ^_^ ^ • (99.) That is, //le distance I F or H G measured rectangularly between the two tangents, being added to the difference of the radii times cos x, and the result divided by the difference of the radii, tvill give the cosine of the angle ELF, or y, to be turned on the smaller curve. Subtracting the angle j' from the angle.!', will give the angle B C E, to be added to the larger curve; and dividing this angle by the degree of curvature in ^ .5 we find the distance from B to E, the required P. C. C. \i E F h^ the second curve located, and the required tangent lies within, i. e., D H '\s the required tangent, it is evident that instead of advancing on the curve A B, we must retreat on it to find the required P. C. C. Accordingly, we subtract D instead of adding, as in the preceding case. Example. — A B, Fig. 362, is a 4° curve to the right, located and compounding at B into a 7'" curve, the latter being continued through an angle of 38°. At the P. T. we find that the proper tangent is 46 ft. RAILROAD LOCATION. 835 to the left, i.e., without the actual tangent, so that the curve will be thrown out to meet the required tangent. How far must the 4° ciirve be continued? Solution. — The radius of a 4° curve is 1,432.69 ft. ; the radius of a 7= curve is 819.02 ft., hence, R - r= 613.67 ft. The cosine of 38° = .78801. Substituting known quantities in formula 99, (/? - r) cos X 4- Z? 613. 67 X . 78801 + 46 ^ _„. . ^^^■^ = -R^r = 613:67 = '^^^^^ Hence, angle y — 30° 21'. Subtracting this angle from 38" 00', there remains a difference of 7° 39', which must be added to the 4° curve. 7° 39' reduced to decimal form is 7.65' -e- 4 gives 1.9125 stations = 191.25 feet, which must be added to the 4" curve to reach the correct P. C. C. Ans. In the above example, it is evident that, had the required tangent been within the given tangent, it would have been necessary to move the P. C. C. backwards instead of advan- cing it. This will increase the angle y of the second curve, and, consequently, its cosine will be reduced. The distance D will, therefore, be subtracted and the formula will read^ {R — r) cos X — D Q,o^yr=- '^ — . (lOO.) K — r 1424. Problem II. — Case II. When the second curve is of longer radius than the first curve: Let A B F,in Fig. 363, be a compound curve terminating in the tangent FH, and it is required to change the P. C. C. from B to some point £ so that the curve shall terminate in the tangent D G parallel to F H and at a given distance H G from it. Let the required tangent D G ho. without the given tangent F H. Calling the perpendicular distance H G between the tangents D\ the radius of the larger curve, /?, and the radius of the smaller curve, r; the given angle B O F oi the second curve, ,r, and the required angle E C G of the second curve j, we have, as in formula lOO, _ (/? — r) cos X — D cos J R-r That is, the distance // 6^, measured rectangularly between the two tangents, should be subtracted as in formula lOO. 836 RAILROAD LOCATION. It will be seen that the required tangent is without the given tangent, consequently, it will be necessary to move E Fig. 363. the P. C. C. backwards on the first curve, i. e., the angle of the first curve must be reduced. Example. — A ^ is a 6° curve compounding at B into a 3' curve whose angle is 42° 30', and whose tangent F H is 52 ft. within the required tangent. How far backwards must the P. C. C. be moved ? Solution. — The radius of a 6° curve is 955.37 ft., and the radius of a 3° curve is 1,910.08 ft.; hence, /?- r = 1,910.08 - 955.37 = 954.71. Cos x= cos 42° 30' = .73728. Substituting the known values in formula ^„„ , 954.71 X. 73728 -52 ._„. . _ , lOO, we have cos y ~ -., „^ = .68281 ; whence, we find •^ 9o4.71 y = 46° 56'. Deducting 42° 30' from 46° 56', we have a diflference of 4° 26', which must be deducted from the first curve. 4° 26' in decimal form is 4.433; 4.433 -¥■ 6, the degree of the first curve, gives a quotient of .739 of a full station = 73.9 ft., the distance backwards from B to the correct P. C. C. at E. Ans. If the required tangent were within the given tangent, the P. C. C. would be advanced and the angle y would be RAILROAD LOCATION. 837 reduced. The distance D would then be added and the formula would read cos J 1425. Problem III. — To avoid obstacles on a curve : Let it be required to run a curve A DEC between the points A and C, and suppose an obstacle lies directly in the path of the curve. The obstacle may be avoided by tracing a parallel curve FG HI, and from the stations on this par- allel curve, the corresponding stations on the required Fig. 3&4. curve may be located. The process is as follows (see Fig. 364): Having determined either P. C. or P. T., erect a per- pendicular A F to the tangent A K. Now, io the curve FGH I it is evident that while the angle AO C remains constant, the chords F G, G H, and HI shorten as we approach the center of the required curve. L,etAF = 838 RAILROAD LOCATION. 90 ft., and the radius A (9 = 819 ft. The chords of the required curve being 100 ft. in length, we have the follow- ing proportion : O A : O A — A F::100 : F G, Xhe^ length of the chord of the parallel curve. Substituting known values in the proportion, we have 819 : 729:: 100 : FG; whence, /^ 6' = 89.01ft. Set up the in- strument at Fand trace the curve F G H I, setting a transit point at each station of 89.01 ft. Then set the transit at each of these points, as at 6", and turn to a tangent of the curve as run. Then, turning a right angle, set a stake 90 ft. from G, locating the point D. In a similar manner locate each of the stations upon the required curve. 1426. Problem IV. — Having given two angles of intersection Z? -5 E and G F H, and the distance ^/'between the points of intersection (Fig. 365), it is required to find the radius of the easiest reverse curve which will unite Fig. 365. the tangents A D and FK. The angle D B E \s equal to the angle A O E, half of which is B O E. The angle G FN is equal to the angle J5" CG, half of which is EC F. Then, (tan B O E -\- X.z.n E C F) \\.2.n BO E\\ BE : BE. But E F — BE— BE. Reducing the proportion, we have _ tan BO Ex BE tan B O E -\- tan ECF' Now, BE is the tangent distance 7^ of the curve A E, and RAILROAD LOCATION. 839 substituting known values in formula 91, T=R tan |/ (Art. 1251), v^e have B £= O £ tsin B O £; whence, B£ EF radius O E =z and radius C E = tan B O E' ^<^^^^^ ^ ^ - ^^^ ^f-p- Example.— Let the angle D B E, Fig. 365, = 40° 00', the angle G F H=m° W, and the distance i? 7^= 922 ft. Find the radius of the reverse curve. Solution.— The angle BOE=\DBE = 20°, and the angle ECF= iGFH= 31° 15'. Tan 20° = .36397; tan 31° 15' = .60681. The sum of these tangents is .97078, and we have the proportion .97078 : .36397:: 922 : B E\ whence, we find ^ £"= 345.68 ft. Substituting the value oi BE in the formula, T = B tan i /, we have 345.68 = OEx -36397 ; 345 68 whence, we have radius 0E= ,^"^-, =949.75 ft. Substituting this . ooo9 I 50 value of ^ in the formula, B = -. — = (Art. 1249), we have sin D = sin D ' 50 x-T7r-=rr, whcncc, sin D = .05264 and Z> = 3° 01', which, multiplied by 2, 949. 75 gives 6° 02', the required degree of the curve A E. To show the student that the curve EG is of the same degree as the curve A E, we complete the calculation as follows : B F= 922 ft. and E F = 922 — 345.6» = 576.32 ft. Substituting the value oi EF'in the formula T = 576 S'> R tan \ I, we have radius CE= Z'JZ = 949.75 ft. Ans. " .60681 50 Substituting this value of R in the formula, R = —. — ^, we have 50 sin D = „,_ ... , whence sin D = .05264, and Z> = 3° 01' ; this, multiplied 949. 7o > r by 2, gives 6° 02', the required degree of the curve EG, which is the same as that of the curve A E. Ans. 1427. Problem V. — To find the radius of a curve which will be tangent to three given straight lines: Let A B, B C, and C D, in Fig. 366, be the given lines, then the required radius will be equal to BC^ tan \ E B C + tan \ E C B' Example.— Let ^C = 428 feet, the angle ^^^ C= 23" 20, and the angle EC B = 'i>^° 20'. Find the radius of the curve that will be tan- gent Xo A B, B C, and CD. Solution.— Tan i EBC=. 20648, and tan i i5"Cy? = .22475. The sum of these tangents is .43123. Substituting these values in the 840 RAILROAD LOCATION. equation, radius = — „ _ ^^ . ^^ „ , we have radius = tan i £B C + tan ^ ECB' .43123' whence the required radius = 992.51 ft. Substituting this value of Ji 50 in formula 89, Art. 1249, we have sin Z> = p^-^ = .05038, and Z> = 2° 53.3', which, multiplied by 2, gives 5° 46.6', the required degree of the curve. Ans. The required degree of curve may be found by the following and simpler operation, viz.: Dividing 5,730 ft., the approximate radius of a 1° curve, by the given radius, 992.51 ft., we obtain a quotient of 5.773° = 5° 46.38', a result amply close for practical work. The angle of intersection C£Fis equal to EBC+ECB = 48° 40'. Having found the radius and angle of intersection, the tan- gent distance is calculated by formula 91, T= R tan | /. (See Art. 1251.) 1428. Problem VI. — To swing a tangent so that it will pass through a given point: Let A B^ in Fig. 367, be a curve whose tangent .5 ^ passes through the point C, and it is required to swing the tangent B X into the position B' X\ so that it shall pass through the point C . With the instrument at B measure the angle C B C. Divide this angle by the degree of the curve A B. The quotient will be the distance, in stations, which must be added to the curve A B to bring the P. T. at B\ and the tangent will pass through the required point C. Example. — Let A B he a. 6° curve, and the angle C B C = 4" 30'. Swing the tangent .5 C so as to pass through the point C Solution. — Reducing 4° 30' to decimal form and dividing by 6, the 4 5 degree of the curve A B, we have-^ = .75 of a full station = 75 ft., which we must add to the curve A B, bringing the P. T. at B', and the tangent B' X' will pass through the point C. Ans. It will be evident that, had B' X' been the given tangent and C the required point, it would have been necessary to RAILROAD LOCATION. 841 move the point of tangent B' backwards to B, i. e., to subtract 75 ft. from the given curve. 3130 1 429. Problem VII. — To find the distance across a river in a preliminary survey: Let the line A B, Fig. 368, cross a river, too wide for direct measurement. With the instrument at A^ sight to a flag held at B, and turn a.n 2ing\e B A C = \° . Seta plug at C, opposite B in the line A C, and measure the distance B C. The required distance ^ C" X 100 ^^= 1.745 Example 1.— If BC- Fig. 368. 10.6 ft., how long is A B7 Solution.— y? B = ^^f^)^^ = 607. 45 ft. Ans. 1.745 842 RAILROAD LOCATION. Example 2.— If /)'t" = 8.8 ft., how long is A B? 8.8 X 100 Solution. — A B ■ 1.745 = 504.3 ft. Ans. 1430. Engineers' Field Books. — The problems given cover the cases which are liable to arise under ordi- nary conditions, and the explanations have been fully given. The engineer must necessarily carry a field book containing the usual tables of reference. All standard field books con- tain demonstrations of problems covering all those special cases which do not properly come within the scope of this work. 1431. Relative Position of Preliminary and Located Line. — The relative position of the preliminary and of the located line, where the work has been intelligently per- formed, is shown in the following sketch, Fig. 369, in which the pre- liminary line is shown V' The location is in dotted and the loca- ^^ practically fixed tion in full lines. fV X \ \ by the preliminary line, leaving little to do but to run in the curves. The slight changes in the direction of the tan- gents and the degrees of the curves will be determined by an inspection of the contour map, which is the basis of every intelligent location. 1432. Field Profiles.— The profile is kept plat- ted as fast as the line is located, in order that the chief of party may know how nearly the actual profile ap- proximates to the theoretical one (the one that is made from the paper location) and what changes may be necessary. Fig. 3C9. RAILROAD LOCATION. 843 1433. Final Location. — After the right of way has been cleared, affording an unobstructed view of the ground, it will frequently be seen that slight changes in the located line will greatly reduce the cost of construction ; and not until such changes are made will the engineer have made the fitial location. None but experienced engineers can understand how a Area^4.5 Sq.ft. Fill 30ft T Fig. 370. slight change in location, especially on a side hill line, can so greatly affect cost; and it is first cost which generally de- termines the success or failure of the enterprise. The accompanying sketches will afford some light where it is oftenest needed. Fig. 370 is an example of poor location more often met with than that of any other kind, and yet one where a little conscientious work, together with common nil 5.8ft Fig. 371. sense, would have produced amazing results, as shown in Fig. 371, which is decidedly good location. Side hills afford op- portunity for almost the cheapest form of construction. A 844 RAILROAD LOCATION. grade line, i. e. , where the grade coincides with the surface of the ground on the center line, as in Fig. 371, can, unless rock is encountered, be graded with pick and shovel alone, the men casting the material taken from the cut directly into and making the fill. The area of the cut in Fig. 370 is 49.8 sq. ft., while the area of the fill is but 4.5 sq. ft., leaving an excess of excavation of 45.3 sq. ft., or ten times the area of the fill. There is no way by which this excess of mate- rial can be utilized ; it must, therefore, be wasted, as has been the labor of excavating it. By moving the center line 4 feet to the right, we obtain the cross-section shown in Fig. 371, in which the calculated areas of cut and fill are as fol- lows: Cut, 19.2 sq. ft. ; fill, 20.3 sq. ft. ; a difference of less than 1 sq. ft., and the excess is on the right side, for a ditch should be made four feet from the top of the upper slope to prevent the washing down of the slope, and this material will more than equal the excess of the fill over the cut. 1434. Referencing Transit Points. — Having com- pleted the final location, the points of curve and points of tangent must be referenced, and also intermediate points where a change of grade requires it. Such an intermediate point is shown in Fig. 372. Fig 372. The line ABC from the P. T. at A to the P. C. at C is straight, but the transit pole at C can not be seen through the transit SitA on account of the change of grade at B. It is, therefore, necessary to establish an intermediate point at B on the line ABC. The transit being set up at B, both P. T. and P. C. are in full view. A good example of referencing is shown in Fig. 373. The reference points consist of plugs driven flush with the ground and protected by substantial guard stakes, which are RAILROAD LOCATION. 845 marked with the letters JR. P. Where the located line trav- erses timber or brushwood, the ordinary stakes on the center line should be replaced by much larger ones. They are best cut from saplings about 3 feet in length and from 2^ to 3^ inches in diameter. A place for the stake is made with an iron bar, and the stake driven at least one foot in the ground with a sledge hammer. Special care is taken in *lug and Guard Stake Plug and Guard Stake £C Fig. 373. guarding points of curve and tangent. While the right of way is being cleared a man is detailed to look after the stakes and hubs on the center line, as many will be disturbed or torn out of the ground while hauling logs and timber from the right of way. When the clearing and burning is completed, the center line should be rerun, restoring all lost or disturbed stakes. Transit points, if well set, will rarely be disturbed. When the center line is restored the transit points are referenced. A little care and judgment will enable the engineer to select reference points which will remain undisturbed during the work of construction. Where the work is heavy these points will be further re- moved from the center line than at points where the work is light. When the grading is completed, the original points of curve and tangent can be restored and the center line run in from both ends of the curve. Any small error in aline- ment due to inaccuracies in the measurement of the original line will then be thrown on the middle of the curve, where 846 RAILROAD LOCATION. they will not in any way affect the excellence of the work, and the tangents will remain unchanged. 1435. Final Levels. —While the transit points are being referenced, the leveler takes the final levels^ reading all turning points with the target and correcting all bencli marks. He need not hurry, as accuracy is all important. An error in final levels is unpardonable, as the work of con- struction is based upon them. Most errors in field work are directly chargeable to carelessness. A bench mark is estab- lished at each bridge site, and at all points of the line where permanent structures, such as arch culverts, trestles, water tanks, stations, etc., are to be built. The final profile is platted from these levels and the grade line drawn in pencil. The points of curve and tangent are marked in small cir- cles on one of the horizontal lines at the bottom of the pro- file. That portion of the line corresponding to tangents is drawn in a full line, and the balance, representing the curves, in broken line. The stations of the points of curve and tangent are also numbered on the profile. The compensations for curvature are then calculated, and the final grade line drawn in ink. 1436. Compensation for Curvature. — From .03 to .05 ft. per degree is the compensation or reduction in grade, made for the added resistance due to curvature, i. e. , where the established grade for tangents is 1 per cent., the grade on a 6° curve, allowing a compensation of .03 ft. per degree, would be LOO— (.03 ft. x 6) — .82 per cent. Where a compensation of .05 ft. per degree is made, the grade on a G° curve would be 1.00 — (.05 X n) = .70 per cent. 1437. Final Grade Lines. — The establishing oi final grade lines is illustrated in Fig. 374, where the uncompen- sated grade is 1.3 per cent., and the compensation for curvature as shown in the final grade line is .03 ft. per degree. The location notes for the line included in the diagram are as follows: I* RAILROAD LOCATION. 847 Stations. Intersection Angles. 52 + 00 End of Grade. 49 + 75 P. T. 44 + 25 P. C. 9° R. 49° 30' ~ 42 + 00 P. T. 37 + 50 P. C. 6° L. 27° 00' 33 + 00 P. T. 29 + 00 P. C. 8° R. 32° 00' 27 + 00 Beginning of Grade. The profile is made to standard scales, viz., horizontal 400 ft. = 1 in. ; vertical, 20 ft. = 1 in. The elevation of the grade at Sta. 27 is fixed at 120 ft., and at Sta. 52 at 152.5 ft., giving between these stations an actual rise of 32.5 ft. and an uncompensated grade of 1.3 per cent. These grade points we mark on the profile in small circles. The total curvature between Sta. 27 and Sta. 52 is 108^°. The resistance due to each degree of curvature being taken as equivalent to an in- crease of .03 ft. in grade, the total resistance due to 108. 5° is equal to .03 ft. X 108.5 = 3.255 ft., and is equivalent to adding 3.255 ft. to the actual rise between Sta. 27 and Sta. 52. Hence, the total theoretical grade between these stations is the sum of 32.5 ft., the actual rise, and 3.255 ft. due to curvature, which is 35.755 ft. Dividing 35.755 by 25, the 35 755 number of stations in the given distance, we have^ — ^-- — = 25 + 1.4302 ft., the grade for tangents on this line. The starting point of this grade is at Sta. 27. The P. C. of the first curve is at Sta. 29, giving a tangent of 200 ft. = 2 stations. As the grade for tangents is + 1.4302 ft. per station, the rise in grade between Stas. 27 and 29 is 1.4302X2 = 2.8604 ft. The elevation of the grade at Sta. 27 is 120 ft., and the elevation of grade at Sta. 29 is 120 + 2.8604 = 122.8604 ft., which we record on the profile as shown in Fig. 374, with the 848 RAILROAD LOCATION. rate of grade, viz., -j- 1.4302 written above the grade line. The first curve is 8°, and as the compensation per degree is .03 ft. for 8°, or a full station, the compensation is .03 ft. X 8 = .24 ft. The grade on the curve will, therefore, be the tangent grade minus the compensation, or 1.4302 — .24 ft. = + 1.1902 ft. per station. The P. C. of this curve is at Sta. 29, the P. T. at Sta. 33, making the total length of the curve 400 ft. = 4 stations. The grade on this curve is -|- 1.1902 ft. per station, and the total rise on the curve is 1.1902 X 4 = 4.7608 ft. The elevation of the grade at the P. C. at Sta. 29 is 122.8604; hence, the elevation of grade at the P. T. at Sta. 33 is 122.8604 + 4.7608 = 127.6212 ft., which we record on the profile together with the grade, viz., + 1.1902, written above the grade line. The P. C. of the next curve is at Sta. 37 + 50, giving an intermediate tangent of 450 ft. = 4.5 stations. The grade for tangents is + 1.4302 ft. per station; hence, the total rise on the tangent is 1.4302 X 4.5 = 6.4359 ft. Adding 6.4359 ft. to 127.6212 ft., we have for the elevation of grade at Sta. 37 + 50, 134.0571 ft., which we record on the profile, to- gether with the rate of grade for tangents. The next curve is 6° and the compensation in grade per station is .03 ft. X 6 = .18 ft. The grade on this curve will, therefore, be 1.4302 — .18 = 1.2502 ft. per station. The length of the curve is 450 ft. = 4.5 stations, and the total rise in grade on this curve is + 1.2502 ft. x 4.5 = 5.6259 ft. The elevation of the grade at Sta. 37 + 50, the P. C. of the curve, is 134.0571. The elevation of the grade at Sta. 42, the P. T., is, therefore, 134.0571 + 5.6259 = 139.683 ft., which we record on the profile together with the rate of grade on the 6° curve, viz. , + 1. 2502. The P. C. of the next curve is at Sta. 44 + 25, giving an intermediate tangent of 225 ft. = 2.25 stations. The total rise on the tangent is, therefore, 1.4302 X 2.25 = 3.21795 ft. The elevation of grade at the P. T. at Sta. 42 = 139.683; therefore, the elevation of grade at Sta. 44 + 25 = 139.683 + 3.21795 ft. = 142.90095 ft., which we record on the profile together with the grade, viz., + 1.4302. The last curve is 9° and the compensation in RAILROAD LOCATION. 849 30 grade per station is .03 ft. X 9 = .27 ft. The grade on 9° curve is, therefore, 1.4302 — .27 = 1.1602 ft. per sta- tion. The length of the curve is 550 ft. = 5.5 stations, and the total rise on the curve is 1.1602X5.5 = 6.3811 ft. The elevation of grade at Sta. 44 + 25, the P. C. of the 9° curve, is 142.90095 ; hence, the elevation of grade at the P. T., at Sta. 49 + 75, is 142.90095 + 6.3811 = 149.28205 ft., which we record on the profile to- ? ^q gether with the grade, % + 1.1602. The end of the line is at Sta. 53, giving a tangent of 225 ft. = 2.25 stations. The rise on this tan- gent is 1.4302x2 25 = 3.21795 ft., which we add to 149.28205, the elevation of the P. T. at Sta. 49+75. The sum, 152.5 ft., is the eleva- tion of grade at Sta. 52. The sum of the partial grades should equal the total rise be- tween the extremities of the grade line. 60 850 RAILROAD LOCATION. The points where the changes of grade occur are marked on the profile in small circles, which are connected by fine lines which represent the grade line. These points of change are projected on a horizontal line at the bottom of the profile. Those portions of this line representing curves are dotted, and those portions representing tangents are drawn full. The points of curve P. C. and P. T. are marked in small circles on this horizontal line, and lettered as shown in the figure. Where the grades are light and the curves easy, there will be no need of compensation for curvature. Where the grades exceed .5 per cent, and the curves 5°, compensation should be made. 1 438. Changing of Grade Lines. — Unforeseen diffi- culties sometimes arise during construction which warrant the changing of grade lines, but these occasions are rare. If the final grade line has been properly considered, it would better remain unchanged. The engineer should learn to make up his mind and stick to it. 1 439. Vertical Curves. — Vertical curves are used to round off the angles formed by the meeting of two grade lines. Let A C and C B, Fig. 375, be two grade lines meeting at C. These grades are given by the rise per station in going in some particular direction. Thus, starting from A, the grades A C and C B may be denoted by g and g' \ that is, the grade for any station on y^ (7 is found by adding the RAILROAD LOCATION. 851 rate of grade g to the grade of the preceding station, and the grade for any station on C ^ is found by adding the rate of grade g' to the grade of the preceding station. But C B is a descending grade. Therefore, the rate^', to be added to each station, is a minus quantity and^' is negative. The parabola furnishes a simple method of putting in a vertical curve. 1440. Problem.— Given the grade ^ of A C, Fig. 375, the grade ^' of C B, and the number of stations n on each side of C to the tangent points A and B, to unite these points by a parabolic vertical curve : Let A £ B he the required parabola. Through B and C draw the vertical lines F K and C H, and produce A C to meet F K in F. Through A draw the horizontal line A K and join A and /?, cutting C H \n D. Then, if a represents the vertical distance of the first station M on the curve from the corresponding station 7" on the tangent, the ver- tical distance at the second station will be the square of 2, or 4 «, and at the third station the square of 3, or 9 «, and at B, which is 2 « stations from A, the vertical distance to the curve will be the square of 2 « or 4 «" « ; that is, F B =^ FB 4 «' a, and a = - — j. To find a, it will first be necessary to find F B. This may be done by means of the following formula, in which g and g' are the grades mentioned in Art. 1439, and n is the number of stations between A and C: 4 n (lOl.) Having determined the value of a, the distances of the several stations in A C and C B from the curve, viz., a, 4 a, 9 a, 16 n, etc., are readily known. Let T and F' be the first and second stations on the tangent A C, and if from T and T' perpendicular lines T P and T' P' be drawn to the horizontal line A K, T P, the height of the first station T above A, equals^, and 7 ' P' equals 2^, and for succeeding stations we shall find the heights 3 g, 4 g, etc. We have 852 RAILROAD LOCATION. already found T M—a, T' M' = A: a, etc. The heights of the curve above the level of A will, therefore, be as follows: K\.M, heights TP- T M=g- a; at J/', height = T' P' — T' M' = 2g-Aa, and at E, height =C H - C E^Zg — 9 rt, and for succeeding points A g — 16 «, etc. To find the grades for the curve at successive stations from A, that is, the amount which must be added to the grade or height of one station'to equal the grade of the following station, we must subtract each height from the next following height. Thus, calling the height of A 0, we have (^ — «) — = ^ — a^ the height of M above A K, called the grade of M; (2^—4 a) —{g — (i) = g — 3 a, which must be added to the grade of J/ to find the grade of J/' ; (3^ — 9 «) — (2 ^ — 4 «) = g— 5 a, which must be added to the grade of Af to find the grade of E. The succeeding quantities are (4^ — 16 a) -{3g-9a)=g-'7 a,{5 g- 25 a) - (4^-16 a) = g - 9 a, and {& g —ZQ a) — {5 g — 2b a) = g — \l a. The suc- cessive grades or additions for the vertical curve. Fig. 375, are ^ - ^, g-Z a, g- 5 a, g-7 a, g-d a, and g-lla. In finding these grades, strict regard must be paid to the algebraic signs. The results are then general. 1441. Example 1. — Let the number of stations on each side of C, Fig. 375, be 3, and let A Che an ascending grade of 1.2 feet per station, and C B a. descending grade of .8 ft. per station. Assume the elevation of the grade at Sta. A to be 120 feet, and find the grade at each station from A to B. Solution. — Here « = 3, ,^ = + 1.2 ft., and ^' = — .8 ft. Substitu- -^' 1- 1.2-(- -i-2-,we have a — . ^ ^ — 1 AAA ft- onH fVio crfiir1*»c frf\rr\ A \r\ 12 p— z' 1 2 — (— .8) ting known values in formula 1 Ol , a = , ,we have a — 4« 2 Yq = .1666 ft., and the grades from A to B will be Heights of Curve above A. g- a =1.2- .167= 1.033 ft. 1.033 ft. g- Za = 1.2 - .500 = .700 ft. 1.733 ft. ^-5^=1.2- .833= .367 ft. 2.100 ft. ^- 7a =1.2-1.166= .034 ft. 2.134 ft. ^- 9a =1.2-1.500=- .300 ft. 1.834 ft. g - 11a = 1.2 - 1.833 = - .633 ft. 1.201 ft. RAILROAD LOCATION. 853 Since the elevation of the grade at Sta. A, Fig. 375, is 120.00 feet, the grades for the following stations of the vertical curve will be : Elevation of „^ ^. Elevation of tation. „ . Station. „ . Grade. Grade. A 120.000 ft. O 122.134 ft. M 121.033 ft. M' 121.733 ft. E 122.100 ft. Ans. R 121.834 ft. B 121.201 ft. Example 2. — Let A C, Fig. 376, be a descending grade of 1.0 ft. per station, and C B an ascending grade of .5 ft. per station. Let the vertical curve include 2 stations each side of C. Find the grade at each station from A \.o C. Solution.— Here g =— 1.0 ft., ^' = + .5 ft., and « = 2. Substituting GTade=120.0 Fig. 376. these values in formula lOl, a=.'^^ — ^— , we have 4 « -1.5 a^-\.0-{.h) _ = — .IS'* 5, and the four grades required will be: Ans. g- a = g-Za = g -oa = g-'7a = 1.0 -(- .1875) = 1.0 -(- .5625) = 1.0 -(- .9375) = 1.0 -(-1.3125) = 1.0+ .1875 = -.8125 ft. 1.0 + .5625 = - .4375 ft. 1.0+ .9375 =- .0625 ft. 1.0 + 1.3125= + .3125 ft. It will be seen that after finding the first grade, the suc- ceeding grades are found by a continual subtraction of 2 a. Thus, in the first example, each grade after the first is .333 ft. less than the preceding grade. In the second example, a is a negative quantity, and each grade after the first is. 375 ft. greater than the preceding grade. The grades in the foregoing examples are calculated for whole stations, and are sufficient for all purposes except for track laying or ballasting, when- grade stakes on the vertical curve should be driven at intervals of 25 feet, and the grades must be calculated for these sub-stations. To do this, let g" 854 RAILROAD LOCATION. and^' represent the grades for a sub-station of 25 feet, and 11 the number of such sub-stations on each side of the intersection of the grade lines. Example. — In the last example divide the curve into sub-stations of 25 ft. each. Assume the grade at A to be 130 feet, and find the grade at each sub-station. Solution.— Here ^=—.25 ft, ^' = +.125 ft., and « = 8. Sub- stituting these values in formula lOl, ', Fig. 376, is 400 feet divided into 16 sub-stations of 25 feet each. Since the grade of A is 120.0 feet, the grades of the fol- lowing stations will be: f Stations. Grades. Stations. Grades. A 120.000 9 118.699 1 119.762 10 118.672 2 119.547 11 118.668 3 119.355 12 118.688 4 119.187 13 118.731 5 119.043 14 118.797 6 118.922 15 118.887 7 118.824 16, i5... 119. 000 8 118.750 The purpose served by vertical curves will be at once ap- parent to the student. The sudden and severe stress upon the rolling stock caused by passing from one grade to another results in great harm to rolling stock and much discomfort to passengers. Vertical curves should always be put in the grade during construction. Where the meeting grades are very slight, no curve is necessary. 1 442. Preliminary Estimates. — Having established the final grades, the next work of the engineer is the pre- liminary estimate. This estimate gives in detail the approx- imate quantities of all material to be handled in the work of Ans. kAILROAD LOCATION. 856 construction, and of all probable cost attending such work. Work and materials to be furnished, together with the prices ruling in the locality where the work is to be done, are classified as follows: 1 443. Classification of Preliminary Estimates. — 1. Clearing per acre $20.00. ^ Earth, per cubic yard 20c. } Loose rock, per cubic yard. . 40c. ■ ' ' ' ( Solid rock, per cubic yard. . . 80c. Overhaul exceeding 1,000 feet, per cubic yard Ic. Piles, per lineal foot 25c. to 30c. 3. Trestling. \ Frame, per 1,000 ft. bd. meas- ure, Ga. pine $35.00. Ist-class rock-face range work, per cubic yard $10. 00 to $12 00. '2d-class good lime mortar rubble, per cubic yard. . . . $8.00. Dry rubble, per cubic yard. . $4. 00 to $4. 50. Riprap per square yard, in place $1.50to$2.50. Wooden [ron and steel 4. Masonry.. ■< 5. Bridgmg . -j ^^ Classification not only affects price, but quantity. Cuts in solid rock, which are the most costly, stand at a slope of ^ horizontal to 1 vertical, while earth ordinarily requires a slope of 1 horizontal to 1 vertical, and sometimes as flat a slope as 1|^ horizontal to 1 vertical. All materials excavated, and all masonry, are estimated by the cubic yard. Trest- ling is estimated by the 1,000 feet, board measure, and piling by the lineal foot. Wooden bridges, of moderate span, are sometimes estimated at a fixed price per 1,000 feet for lumber, and a fixed price per lb. for iron, but generally a special estimate is made for each bridge. The cost of bridges increases rapidly as the span increases. In metal bridges the cost will increase about as the square of the 856 RAILROAD LOCATION. span, i. e., if one bridge has twice as great a span as another, the first will cost the square of 2 or 4 times as much as the second. 1444.* Quantities. — The material to be handled in grading the roadbed is generally estimated by level cuttings, which process assumes that the cross-section surfaces are 1/ 9.0 ft t 4.4ft Fig. 377. ' level, and the areas are calculated from the center cuts and Ji//s. Let Fig. 877 represent the actual cross-section at a given station, and Fig. 378 the cross-section based upon the center cut. The area of the section A B C D m Fig. 377, calculated from the actual cross-sections, is 160.78 sq. ft. The area of the section A' B' C D\ in Fig. 378, calculated Cut 6.4 ft Cut 6.4 ft JS.4- -i 15.4.^- > 1^ 6^ 1— Fig. 378. Cut 6.4ft V 6d . from a level section, with the same center cut, viz., 6.4 feet, is 156.16 sq. ft., giving a discrepancy of 4.62 sq. ft. ; that is, the area of the section, calculated by level cuttings, is 4.62 sq. ft. less than the area calculated from the actual cross- sections. This deficiency is about 3 per cent., but where the slope is very steep, the difference increases rapidly. As the invariable custom is to add 10 per cent, to the estimated RAILROAD LOCATION. 857 rt o -t-> Vh OJ • > m I— 1 ^ o NH H 03 O O > O l-i o 03 NJ ffi X » 1-H ^ > a; o 03 » o nJ xn 4J b C TJ 172 &Q ^ o n4 -!-> fe ffl M-1 > CO o o d 1-H 00 •6 ^ 3 »0 o CO 1—1 t-; ^ 00 3 "* o o T— 1 o o o ^ CO 3 -* o T— t r-l I— 1 00 1—1 tn 3 CO O CO o l-H 00 aj 00 T—l "* ^ CO 3 5^ CO I— 1 00 03 T3 CO 3 3' O 00 CO T—l o •d ^ O 3 o d 1—1 00 1—1 Depth of Cut in Feet. O i-H « 858 RAILROAD LOCATION. cost, such addition will fully cover any deficiency resulting from table calculations. Where time is not an object, it is good practice to take the slopes with a clinometer and plat them on cross-section paper. The estimate thus obtained will be a close approximation to the actual quantities handled in the work of construction. For work in the Northern and Middle States the following rates of slope are standard: For embankments, H horizontal to 1 vertical; for earth cuts, 1 horizontal to 1 vertical, and for rock cuts, ^ horizontal to 1 vertical. In Western and Southern States it is the usual custom to give to cuts the same slope as to embankments, viz., 1^ horizontal to 1 vertical. 1445. Traut^vine's Engineers' Pocket Book con- tains complete tables of level cuttings for standard widths of roadway, both single and double track. The slopes are given for earthwork, both excavation and embankment. The quantities are calculated for sections 100 feet apart. If the sections are taken oftener than each 100 feet, the quan- tities will be proportionally less. The table of Level Cut- tings shows the arrangement for single-track excavation, roadway 18 feet wide, slopes 1 horizontal to 1 vertical. The use of this table is explained as follows: Suppose the center cut at vStation 10 is 1.5 ft. and the center cut at Station 11 is 3.0 ft. The sum of these two center cuts, 1.5 -|- 3.0 = 4.5 ft. The mean or average center cut at 4 5 these stations is, therefore, -jr- = 2.25ft. As the nearest tenth is always used, we will call the average cut between Stations 10 and 11, 2.2 ft. Referring to the table, we find in the column headed depth of cut in feet, the figure 2, and on the same horizontal line, under the column headed .2, we find 1(54.0, which is the number of cubic yards of material to be excavated between Stations 10 and 11. The quantities are given for center cuts from .1 foot to 60 feet. For cuts greater than 60 feet, the quantities are calculated for only even feet. RAILROAD LOCATION. 859 1446. Sections. — The line is divided into lengths of one mile each, called sections, which are numbered in regu- lar order, the first mile of the line being section 1, the second mile section 2, and so on. At the division points, i. e. , where one section ends and another begins, posts are set up with boards at- tached, facing in both directions, with the number of the section towards which they face written in large figures. See Fig. 379. The section boards enable one to readily locate any particular part of the line. 1447. Right of Way.— Before construction can be commenced, the ., right of way must be secured, a matter always attended by more or less difficulty. The standard width of right of way is 100 feet, though, in some cases, but 4 rods or 66 feet is adopted, with additional widths wherever needed. Where the local needs for the road are great, and the enterprise popular, much right of way is often donated, a nominal sum, usually one dollar, being paid as considera- tion. The ordinary mode of securing right of way is by direct purchase. The company employs an agent specially fitted for his business, who makes the most advantageous bargains possible with the different owners. When there is failure to agree on price, a common alternative is to leave the question to three arbitrators, each of the parties to the transaction choosing one and agreeing together upon the third. The arbitrators unite upon a valuation-which the contracting parties have agreed to accept. Occasionally, an owner, taking advantage of the situation, attempts extor- tion, in which case the only recourse is to the laxv of euii- nent domain. Articles of condemnation are taken out and appraisers appointed by the court, who fix the amount of 800 RAILROAD LOCATION. compensation. The process is always attended by expense, delay, and vexation, and should only be a last resort. 1448. Right of Way Maps. — A careful survey is made of each separate piece of property bought for right of way or station grounds, and stone corners established for future reference. These surveys should be platted in a "right of way" book in the same order in which they occur on the line, and a copy of the contract for and description of the property written on the same page or that adjoining the plat. The plat should specify content, boundaries, corners, and any information which may be of future use. A copy of the contract and a tracing of the plat is delivered to the person or persons from whom the property is bought. 1449. Specifications. — Specifications describe the manner in which the work of construction is to be con- ducted and the materials to be used in structures. Specifications are of two kinds; \\z., gc7ieral, those de- scribing the different general classes of work, and special, those referring to a particular structure or other work requiring special plans or processes. In this work only general specifications will be given. A., B., & C. R. R. GENERAL SPECIFICATIONS FOR GRADING AND BRIDGING. 1. Clearing. — The surface is to be cleared the full width of right of way and such additional width as the engineer in charge shall direct, of all trees, bushes, and other perishable matter. 2. Grubbing. — In cuttings, and in embankments where the fill is two feet and less, all trees and stumps between the slope stakes must be grubbed out; where the fill is more than two feet, all trees and stumps must be cut down even with the surface of the ground. No payment will be made for grubbing. RAILROAD LOCATION. 861 3. Grading. — Under this head will be included all ex- cavations and embankments required for the formation of the roadbed, side tracks, and station grounds; the founda- tion pits for bridges, culverts, and cattle-guards; the cutting of ditches and drains contiguous to the roadbed; all excava- tions and embankments in constructing farm and highway crossings, and in the changing of channels for streams. 4. Borrow Pits. — The embankment shall be con- structed from material borrowed from the right of way. No embankment shall be constructed from material de- posited by casting without special permission of the engineer in charge. If borrow pits are required outside the right of way, they shall be procured by the railroad company. 5. Provision for Settling. — Cuts and ditches shall be measured in excavation; all other work shall be measured and paid for in embankment. The embankments shall be made from 5 to 10 per cent, higher than the established grades. This additional percentage is an allowance for shrinkage, and shall be fixed by the resident engineer. No allowance for such shrinkage shall be made in the estimate. 6. Single-Track Work. — In single-track work the roadway shall be eighteen feet in width at sub-grade in cuts, and fourteen feet in width on embankments. The side slopes of earth cuts shall be one horizontal to one vertical, and of rock cuts one-quarter horizontal to one vertical, un- less otherwise specified by the engineer in charge. The side slopes for embankments shall be one and one-half horizontal to one vertical. A berme six feet in width shall be left between the slope stakes and the edge of the borrow pits. 7. Double-Track Work. — In double-track work the roadway shall be twenty-eight feet in width at sub-grade in cuts, and twenty-four feet in width on embankments. Side slopes of earth cuts shall be one horizontal to one vertical; of rock cuts, one-quarter horizontal to one vertical, unless otherwise specified by the engineer in charge. The side slopes for embankments shall be one and one-half horizontal m RAILROAD LOCATION. to one vertical. A berme six feet in width shall be left between the slope stakes and the edge of the borrow pit. 8. Borrow Pits. — A space three feet in width shall be left between the borrow pits and the right-of-way lines. The slopes of borrow pits shall not be steeper than one and one-half horizontal to one vertical, and shall generally be of such depth as will secure proper drainage. 9. Ditches. — All excavations shall be finished with side ditches of such dimensions as the engineer shall direct, and to prevent the washing of slopes, ditches shall be cut on the up-hill side, such ditches to be not less than four feet from the top of the slope. 10. Excavation. — The classification for all excavated material will be as follows: Earth will include clay, sand, gravel, loam, decomposed rock, and slate, and all other matters of an earthy kind, how- ever hard, stiff, or compact, and all boulders containing less than three cubic feet each. Loose rock will include all stone and detached rock found in separate masses, containing not less than three cubic feet nor more than one cubic yard; also, all slate, coal, or other rock, soft or loose enough to be removed with- out blasting, although blasting may be resorted to; also, stratified limestone ip layers eight inches thick and under, separated by strata of clay. Solid rock will include all rock in masses of more than one cubic yard which can not be removed without blasting. 11. Foundation excavation above the general water level at the time shall be excavated by the contractor and paid for at his grading prices. The residue of foundation work will be executed by the contractor, and paid for by the company at actual cost, with ten per cent, added for contractor's supervision, use of tools, etc. The price per yard bid for masonry will include centerings, scaffoldings, and all other expenses connected with the work, excepting the foundation work above specified. RAILROAD LOCATION. 863 12. Tunnel Excavation. — The price for tunnel ex- cavation will include all excavation between the portals of the tunnel proper, and within the area of the cross-section, as determined by the engineer, and it will include also all temporary supports, scaffolding, etc. The area of the cross- section for tunnel excavation will be measured six inches outside the wall and arch, and all excavation outside of this cross-section will not be paid for unless in the opinion of the engineer such irregularities could not be prevented by the exercise of proper care and judgment in excavating, and paid for at such prices as the engineer shall determine, 13. Masonry. — Masonry shall be built according to plans furnished by the engineer, and estimated and paid for by the cubic yard. Masonry in which mortar is required shall be kept well wet while being laid, and every stone shall be clean and thoroughly wet when laid. Arches shall be built on substantial centers extending the entire length of the arch, and the mode of construction, as well as the plan, shall be approved by the engineer. Centers shall not be removed or loosened without the direction of the engineer. The price per yard shall in all cases include the furnishing of centers, scaffolding, and all other cost and expense incidental to the completion of the work. All joints of face walls of masonry laid in mortar shall be suitably pointed, and the work finished to the satisfaction of the engineer. Tunnel Masonry. — The masonry for tunnels and all bridge piers and abutments shall be of Rock Face Range Work. All of the arch stones shall be well and smoothly cut on the beds, ends, and face, and shall be laid so that their beds shall be at right angles to the tangent of the curve. The beds of each stone shall have full and solid bearings, and the joints shall be close and straight. Walls and arches shall belaid in regular courses of uniform thickness. No course shall be less than four inches in thick- ness. The faces shall be Rock Face with edges pitched to straight and true lines. The vacancies behind tunnel walls and above tunnel arches 864 RAILROAD LOCATION. shall be filled with concrete or dry packing, at the discre- tion of the engineer. All packing must be well rammed in place as the work progresses. First-Class Masonry. — In all first-class masonry the stones of each course shall be gauged to the same thickness, and after each course is laid and grouted or filled with mor- tar, the tops of the stones shall be dressed so as to bring the top of the course to a common level. Stretchers shall be not less than three feet in length, with bed not less than sixteen inches. Headers shall be not less than eighteen inches in width, nor less than three times the thickness of the course in length. Stretchers and headers should be in the proportions of 3 to 1. All face stones shall be dressed full to the square for their entire length and width, and shall be so cut and laid as to have a full bearing for their entire bed. All joints shall be close and straight, and be so broken as to make a perfect bond. Backing shall be of good-sized and well-shaped stones and so dressed that each stone shall lie firmly on its bed. The backing shall be laid with reference to each succeeding course, affording good header bearers and so bonding the whole into one solid mass. All stones shall be laid in mor- tar, and if the engineer shall so direct, the vertical joints shall remain open until the course is finished. All unfilled parts of the wall shall be filled with mortar or grout. The tops of the walls shall be coped with large broad stones, not less than three feet in length, the same to be well-dressed on the top and ends, and all face joints pointed with good mortar. Culvert Masonry. — Arched and box culverts shall be built of good-sized and well-shaped stones, and laid dry unless otherwise directed by the engineer in charge. Stones shall be straightened on faces and ends with fair proportion of headers, and laid with joints broken so as to form a com- pact and substantial body. Covering stones shall be of such length and thickness as the engineer in charge shall direct. RAILROAD LOCATION. 8G5 The top courses of wing waits shall be of wide stones with good joints, so as to form a good and smooth coping. 14. Pavement. — Between the side walls and at the ends of culverts and bridges where required, paving will be laid of good smooth stones set on edge and well fitted, so as to make a close, smooth surface. Paving shall be of such thickness as the engineer shall direct, and it shall be secured at ends and sides by curb stones not less than two feet in depth. To prevent undermining, broken stone shall be deposited outside the curbing. Paving will be paid for by the cubic yard. 15. Mortar and grout shall be made of clean sharp sand and fresh slacked lime, in the proportions of one part of lime to two of sand. Mortar shall be thoroughly mixed and allowed to stand until all particles of lime are thoroughly slacked. Hydraulic cement to be substituted for lime at the discretion of the engineer, the difference in actual cost to be refunded to the contractor. The proportion of the ingredients of mortar and grout may be varied at the dis- cretion of the engineer. 16. Protection. — When required by the engineer, em- bankments will be protected by cribbing built of round logs and filled with stone, or riprap laid with beds at right angles to the slope of embankment, affording a close and generally smooth surface. Contractors shall hold themselves in readi- ness to perform such work with promptness and dispatch. Cribbing will be paid for by the lineal foot, and riprap by the cubic yard — both to be measured in place. 17. Piling. — Piles shall be of white or burr oak, long leaf pine, or other suitable timber, sound and without loose or rotten knots. They shall measure not less than seven inches in thickness at the small end, and average not less than eleven in thickness. The bark must be removed before driving. 18. Driving. — Piles must be driven at the places staked out for them by the engineer in charge, and they must be 866 RAILROAD LOCATION. driven, if the engineer so desires, to such a depth that a hammer weighing 2,000 pounds, falling upon the pile from a height of twenty feet, will not sink the pile more than one inch. 19. Timber. — All timber shall be of sound, straight- grained white or long leafed southern pine or other suitable timber, free from rotten knots or shakes, and with no sap extending more than two inches from any edge. 20. Framing. — The framing shall be done in the most workmanlike manner and in accordance with plans furnished by the engineer. 2L Inspection. — The kind and quantity of all material in the work shall be subject to the approval of the engineer in charge. Timber shall be estimated in place and paid for by the thousand feet,, board measure. All iron used in structures will be paid for by the pound. 22. Montlily Estimates. — During the progress of the work, on or about the first of every month a monthly esti- mate shall be made of the kind, quality, amount, and value of work done during the preceding month, eighty-five per cent, of which value will be paid to the contractor on or about the fifteenth of said month, and when the work is completed and accepted there shall be a final estimate made by the engineer of the quantity, character, and value of the entire work, according to the terms of the contract, and the balance, after deducting the several monthly payments, and upon the contractor giving release to the company from all claims or demands whatsoever, will be paid in full. 23. The contractor shall render an account monthly, through the proper superintending engineer, of any extra work which he may have been authorized to do; and to pre- vent disputes hereafter, it is hereby understood that no bills for extra work will be allowed unless authorized and ordered in writing by the engineer in charge, and the bill for said extra work presented at the end of the month in which the work was done, and approved by said engineer. RAILROAD LOCATION. 867 24. During the progress of the work and until it shall be completed and accepted by the company, it shall be the duty of the contractor, at his own expense, to sufficiently guard and protect the same by barriers, fences, or otherwise, so as to prevent travelers or other persons from sustaining injury to themselves or property by falling into any excava- tion or running over any dangerous fill or embankment, or over or against stumps, timber, or any material, or in any other way whatsoever; and in blasting stone, the contractor shall use the utmost precaution and care to avoid injuring persons or property, and the contractor shall save and keep the company free and harmless from the payment of any damage for injury to persons or property arising from any malfeasance or negligence of the contractor or of any of his sub-contractors, agents, or servants. 25. The contractor shall not let or transfer his contract or any part of it, or withdraw his personal attention there- from, without the consent of the engineer. 26. The contractor shall put on and maintain night forces at such points and to such extent as the engineer shall direct. 27. In all disputes the decision of the engineer shall be final. 28. By engineer is meant the chief engineer. 1450. Advertising for "Work. — A classified estimate is made of the amount of work in each section, and the road is advertised for contract. These advertisements name a date for the opening of bids. Contractors are provided with a printed copy of the general specifications and of the esti- mated quantities in each section, and are allowed to take such notes as they may require from the map and profile. In walking over the line they can readily locate any par- ticular section from the section boards. 1451. Reservations. — The company should invari- ably reserve the right to reject any or all bids, in order that 8G8 RAILROAD LOCATION. they may shut out irresponsible men or prevent a combina- tion of contractors from charging exorbitant prices for work. 1452. Bond. — Contractors should be required to fur- nish a bond signed by two responsible parties to insure the proper fulfilment of their contract. This bond is usually to the amount of ten per cent, of the estimated cost of the work undertaken. The contract specifies the date on or before which the contractor shall complete the work, and often specifies a forfeit to be imposed in case of any default on the part of the contractor to fulfil the conditions of his contract. RAILROAD CONSTRUCTION. 1453. The Engineer Corps. — The engineer corps in charge of construction differs in organization from that in charge of location. In general, when construction is com- menced, it is prosecuted with vigor throughout the entire line, and, as the work requires constant inspection, the force of engineers is considerably augmented. 1454. Subdivisions of the Line. — The entire line is divided into sections of about 30 miles each, called divi- sions, each division being placed in charge of a division engineer. The divisions are further divided into lengths of about 10 miles each, called residencies. Each residency is placed in charge of a resident engineer. 1455. The Division Engineer, His Authority and Duties. — The division engineer has general charge of an entire division and is directly accountable to the chief engineer, from whom he receives general orders relating to the work of his division. He should go over his entire division twice each week, giving particular directions to the resident engineers for the conduct of the work and main- taining a general supervision of the whole. His office should, if possible, be so situated as to afford prompt mail service. Telegraphic communication with the chief engineer is important, though not always possible. Plans of all the important structures on a division, excepting large bridges, are made at the division office and forwarded to the chief engineer for approval. The monthly estimates made by the resident engineers of his division are inspected by the divi- sion engineer, a careful record of them kept at his office, and forwarded by him to the chief engineer for approval. 870 RAILROAD CONSTRUCTION. 1456. The Resident Engineer, His Corps, and Their Duties. — The corps in charge of each residency, comprises the resident engineer, instrument man, rodman, tapeman, and axman. The resident engineer has immediate charge of all work on his residency, a profile of which is given him with the grade lines drawn upon it, with the gradients and compensation for curvature clearly stated. At each watercourse shown in the profile, a brief descrip- tion is written, giving the character and dimensions of the structure required at that place. He is given a copy of the specifications which are to guide him in making a proper inspection of the work. A suitable office is provided him at or as near the middle of his residency as possible, and fur- nished with drawing table, drawing materials, field books, pads, and official stationery. A horse and strong two-seated buckboard are an important part of his outfit, especially when in thickly settled country, where the line of road is readily accessible from public highways. The first duty of the resident engineer is to check the alinement and levels on the line of his work, transferring bench marks from trees or rocks, which are liable to be dis- turbed, to permanent objects far enough from the center line to be outside of the slope stakes. 1457. Setting Slope Stakes. — His next work is set- ting slope stakes, commonly called cross-sectioning, which consists of setting stakes in the ground at the points which will mark the top of the cut or foot of the slope of the finished roadway. The following dimensions are suitable for cross-section stakes: Length, 2 feet; width, 2 inches, and thickness, 1 inch. They should be planed on one side to admit of easy marking, and sharpened for driving. In a country of average smoothness, the level, rod, and tape are used in locating slope stakes; but in very rough locali- ties, the Y level is used to carry the continuous line of levels, while the side elevations, from which the slope stakes are located, are determined by means of the hand level and rods. RAILROAD CONSTRUCTION. 871 ^ 1^ 8 The process of setting slope stakes is illustrated in Figs. 380 and 381. In Fig. 380, the elevation of the grade is 103.0 feet. The height of in- strument A is 97.5 feet, and, hence, the instrument is 5.5 feet below grade. The rod read- ing at the center line is CO feet, hence, the surface of the ground at the center line is below grade, i. e., there must be a fill, the amount of which is made up of two quantities, viz. : First, the difference between the elevation of grade and the height of instrument ; and, sec- ond, the rod reading at the center line. The first of these quantities is 5. 5 feet, the second 6.0 feet, and their sum, 11.5 feet, is the amount of the fill at center. If this cross-section is taken at a full station, there will already be a stake in place, and the Jil/ is marked on the back of the stake F. 11.5. If the section is taken at an intermediate point, i. e., a sub-station, say 20 + 50, the center line is located by rang- ing in from the stakes at the regular stations and the stake is marked 20 -j- 50 on one side and the fill, F.11.5, on the other side, and the stake driven with the numbering facing Station 20. The s/ope stakes are located by holding the leveling rod where, in the judgment of the rodman, the foot of the slope of the completed embankment will be. In Fig. 380, 872 RAILROAD CONSTRUCTION. the rod reading at the right of the center line is 9.5 feet, which, added to 5.5 feet, the difference between the height of instrument and ^ grade, gives a fill of «; 15 feet. The natural slope of earth is one and one-half horizon- tal to one vertical, called a slope of 1^ to 1. Therefore, in a fill of 15 feet, the foot of the slope will be 1^ times 15, which is 22.5 feet from the top of the slope, to which must be added one-half the width of the roadway, viz., 8 feet, making 30.5 feet from the center line. The rod is ac- cordingly held at 30.5 feet from the center line. If the rod read- ing at this distance is the same, i. e. , 9.5 feet, it marks the foot of the slope, and a stake marked F. 15.0 is driven in the place of the rod. Usually the rod will not read exactly the * same when held at the calculated dis- tance, and another calculation will be necessary, two trials generally proving sufficient. In Fig. 381, the right slope stake is fixed in the same way. The left slope stake is -Fill 16:2- RAILROAD CONSTRUCTION. 873 located by means of rods and a hand level. First, a point C is found where the line of sight from the level A cuts the surface of the ground. A cross-section rod, which is similar to a transit pole, is held at this point, which is 5.2 feet below grade. At 5.2 feet above C, a rod is held in a horizontal position, and the point D where it meets the ground marked by a stake. This point is at grade, i. e., where the plane of grade cuts the ground. The stake is marked by two ciphers 0.0, and its location recorded in the note book. By means of the rods, the left slope stake at£"is located. As the left slope is in excavation, the left half of the roadway will be one foot greater in width than the right half, viz., 9 feet. As the slopes in excavation are but one horizontal to one vertical, called a slope of 1 to 1, the dis- tance of the slope stake from the center line is the sum of sta.eo Fig. 382. one-half the width of the roadway, viz., 9 feet, and the depth of cutting. In Fig. 381, the cut is 6.8 feet; consequently, the slope stake is set at 9 + 6.8 = 15.8 feet from the center line. When the cross-section is irregular, intermediate readings are taken as shown in Fig. 382. In this section, besides finding the center fill, 6.8 feet at A, and the fill 14.4 feet at foot of right slope at B, and a fill of 3.8 feet at C at foot of left slope, intermediate read- ings are taken at D and E where the slope of the cross- section changes. These readings are recorded in the note books, but no stakes are driven at the points of change of slope. 874 RAILROAD CONSTRUCTION. 1458. Form of Cross-Section Notes. — The levels are carried continuously from bench mark to bench mark, the level notes being recorded on the left-hand page of the note book and the cross-section notes recorded on the right- c o 1 c •S o Pi c 1— 1 > >- 2 c u o 4-> o ■(-> C O C Left Line. Right Line. 20 40 60 6.0 2.7 97.5 114.8 • 91.5 112.1 103.0 120.0 11.5 7.9 6.8 F. 9.0 21.5 C.G.8 0.0 15.8 5.0 F.3.8 F.6.8 F.15.0 30.0 F.16.2 32.3 F.7.0F.14.4 13.7 8.0 8.0 29.6 hand page. The above form of cross-section notes is simple and complete, and contains the notes for Figs. 380, 381, and 382. The cross-section notes are recorded in the form of frac- tions, the amount of cut or fill being the numerator of the fraction, and the distance of the slope stake from the center line, called the side distance, being the denomi- nator. It will be seen in comparing the notes for Station 20 with Fig. 380 that the rod reading at the center stake is 6.0 feet, which gives a center fill of 11.5 feet. The figure shows at the foot of the right slope a rod reading of 9.5 feet. The in- strument man instead of determining the elevation of the ground at this point by subtracting the rod reading from the height of instrument and then calculating the fill by subtracting the elevation of the surface of the ground from the calculated grade for that station, calculates the fill in this way. If a rod reading of G.O feet gives a fill of 11.5 feet, a rod reading of 9.5 feet must require as much more filling than 11.5 feet as 9.5 feet \% greater \h2in 6.0 feet. The RAILROAD CONSTRUCTION. 875 «5l or O "S^" *« «- «■ •5" - -*H- 2 6 -C- difference 9.5 — 6.0 = 3.5 feet; 11.5 + 3.5 = 15.0 feet, i, e., a rod reading of 9.5 feet requires a fill of 15.0 feet. In the notes for Sta. GO, corresponding to Fig. 382, it will be observed that the inter- mediate readings taken at D and £ are re- corded in the same order in which they are taken. The calculations of the side dis- tances are simple problems in mental arith- metic, and, with a little practice, they can be made with great rapidity. A tape especially adapted to cross-section work is graduated on both sides, one side giving the varying fills from 1 foot to 28 feet, and the other side being graduated to feet and tenths of a foot. Fig. 383 illustrates the principle upon which the tapes are made. As shown in the figure, the eight-foot mark on the right side of the tape corre- sponds with the zero mark on the reverse side. The reason for this is that, whatever the fill, the slope stake must be placed at least eight feet from the center line in order to afford sufficient width for the road- way. Each division representing tenths of feet of filling is equivalent to 1^ tenths of feet of lineal measurement, that is, a fill of 1 foot, as marked on the reverse side of the tape, corresponds to the division 9.5 feet on the right side of the tape. In using the tape, a man stands at the center stake holding the tape case. The rodman holds the end of the tape besides carrying the rod. The man at the center stake lines in the rodman, that is, he places him as nearly at right angles to the center line as he can estimate by the eye. The rodman 876 RAILROAD CONSTRUCTION. first holds the rod at where he judges will be the foot of the slope. The instrument man calculates the fill and calls the amount of the fill to the tapeman, who finds on the reverse side of the tape the numbers corresponding to the given fill, and holds the tape at that point on the center stake, causing the rodman to approach or recede from the center line according as his calculation has differed from the true one. Again, a rod reading is taken and the amount of the fill called out, and the corresponding fill being found on the tape, the rodman is checked again by the level. Two trials, unless the slopes are very irregular, will generally be sufficient. 1459. Clearing. — All trees, logs, and bushes are cleared from the right of way. Ordinarily, this work is let by contract at a fixed price per acre to experienced woods- men. A skilful axman will fall and trim more trees in one day than five inexperienced men, and the work will be bet- ter done. The resident engineer should require the con- tractor to clear the right of way immediately after his taking charge of the work, as the work of staking out must be deferred until after the clearing is completed. As all timber on the right of way belongs to the railroad company, the resident engineer should require the contractor to avoid unnecessary destruction of merchantable timber while clear- ing the right of way. Timber suitable for cross-ties should be worked up at once, the ties being piled in safe places and in such form as will admit of rapid seasoning. Logs large enough for boards and square timber are piled well out of reach of the work of construction. Clearing will cost from $20 to $50 per acre. 1460. Grubbing. — Grubbing includes the removing of all trees and stumps lying within the slope stakes in cut- tings and in embankments where the fill is two feet or less. Formerly all trees and stumps were grubbed by digging about the stump and exposing the roots, which were cut off with an ax. After the large roots were severed, a long RAILROAD CONSTRUCTION. 877 lever was used to complete the work by overturning the stump. A better method succeeded this very slow and expensive work of grubbing. The trees were left standing and as soon as the large roots were cut, horsepower was employed as follows: A strong rope was fastened to the trunk high above the ground. A strong team (often two teams) were then hitched to the rope at a safe distance from the tree. The leverage gained was great, and the tree could often be overset with half or even less than half the grubbing that was required by the older process. In mod- ern practice dynamite is almost exclusively employed. The trees are first felled and their trunks and branches removed. A round-pointed bar of steel 2 inches in diameter is driven at an angle beneath the stump, penetrating far enough to bring the explosive directly beneath the stump. The bar is then removed, and the hole loaded with dynamite, precisely as in blasting rock. A little experience will enable one to gauge the amount of the charge. The execution of the powder is thorough, generally blowing the stump, together with the roots, completely out of the ground and splitting the stump into several pieces, which greatly facilitates the work of handling them. In grubbing stumps with dyna- mite, the gain in first cost over other methods is great, but the gain in time is greater still. Grubbing is sometimes paid for by the acre, oftener by the stump, and in some cases the cost of grubbing is in- cluded in the price paid for excavation. As stated in Art. 1433, the clearing of the right of way will often afford opportunity for slight changes in the line which will considerably reduce the cost of construction. It is important that the work of cross-sectioning be completed at the earliest possible date after construction has com- menced, as the demands upon the engineer's time multiply when construction is well under way. Where the line traverses open and timbered country in about equal propor- tions, the cross-sectioning on the open stretches can be pushed while the clearing is being done; in this manner the work can be kept well in hand. 878 RAILROAD CONSTRUCTION. CULVERTS. 1461. Classification of Culverts. — Culverts are of three classes, viz., box, tile, and arched. The dimen- sions of a culvert will depend upon the amount of water to be discharged. This amount will depend upon the area and character of the water shed. The engineer can approxi- mately determine this area either from an inspection of county maps or from personal examination of the country. Local records of high water will be of great service to him. Culverts should always be made large enough to meet the requirements of the greatest freshets. The following for- mula is used by some engineers in determining the area of a culvert opening : A=c^^, (102.) in which A is the area of the opening of the culvert in square feet, M is the drainage area in acres, and c the vari- able coefficient depending upon the nature of the country, 1.6 being used for compact hilly ground, 1 for comparatively level ground, and being raised to 4 for abrupt rocky slopes. For example, under average conditions, a drainage area of 200 acres with a coefficient of 1.6 will give the following cross-section area for a culvert : A = l.Gi/200- 22.62 sq. ft. In this situation a double-box culvert would be suitable, with openings three feet in width and four feet in height, separated by a wall two feet in thickness. 1462. Box Culverts. — Foundations will be prepared as follows: Excavate a pit, including the entire area of the opening and the side walls, to a depth of 1 foot. Cover this area with a paving of stones set on edge 1 foot in depth, with a curb two feet in depth at each face of the drain, and start the walls on this paving. The paving, after being laid, should be well rammed, in order to afford a firm foundation for the superstructure. If the fall of the drain does not exceed 9 inches, drop the upper end to a level with the lower end. When the fall is greater than 9 inches, RAILROAD CONSTRUCTION. 879 make a sufficient number of drops of 9 inches each to equal the difference in the elevation of the two ends of the drain. At each drop, place a cross-sill 2 feet in depth. Box culverts are not made of greater span than 3 feet. When a wider opening is required, a double-box cul- vert is built with a division wall 2 feet in thickness. A general plan for a single-box culvert is shown in Fig. 384. The distance marked 10 ft. is termed the height of the embank- ment at center line. Box culverts are gen- erally constructed of dry rubble masonry. The stones in the abutments (also called side walls, and having a height of 3 ft., in Fig. 384) should be of good size, faced with beds roughly dressed and laid with joints well broken. Binders reaching through from face to face of wall must be used in sufficient numbers to insure a com- pact and stable structure. Covering flags (4 ft. 6 in. wide and 1 ft. thick, in Fig. 384) must be of com- pact stone free from seams ,20' 121. 'I2f ■t 880 RAILROAD CONSTRUCTION. and with faces dressed so as to insure a complete cov- ering. Mortar is used at the discretion of the engineer in charge. The parapet, 1 ft. thick, is laid on the covering flags. In soft, marshy soils, a 1-foot paving will not afford a se- cure foundation, especially if quicksand be present. A pit 2 feet in depth and filled with stone, leaving only sufficient depth for the 1-foot paving, and well rammed, will, together with the paving, bear any ordinary box culvert. In wet, boggy soils, a secure foundation may be obtained by exca- vating a pit of double the area of the superstructure to the depth of 2 feet and laying a course of logs of uniform size over the entire bottom of the pit. A layer of broken stone is then spread over the logs of sufficient depth to secure a uniformly level surface. The paving is laid upon this surface, and the foundation is then in readiness for the abutments. Rule I.— To Lay Out a Box Culvert on the Ground.— Take the height of the top of the parapet from the height ,of the embankment at the center line. With this difference as height of embankme7it, find the side distance as in setting slope stakes. To these side distances add 18 inches, and if the embankment is 10 feet in height or over, add I inch on each end for each foot in height above the parapet. The covering flags are 1 foot in thickness and the parapet 1 foot in height, making the top of the parapet 2 feet above the top of the abutment or side walls. The height of the parapet is, therefore, the height of side walls -|- 2 feet. The thickness of side walls must never be less than 2 nor more than 4 feet in thickness. Rule U. — To Find the Length of Wing Wails. — Add to the height of side tea I Is the thickness of the covering fiags. One and a half times this sum plus 2 feet will give the dis- tance from the inside face of the side wall to the end of tving. The wing walls (marked 8 ft. long, in Fig. 384) must be parallel to the center line of the road. RAILROAD CONSTRUCTION. 881 Example. — The roadway is 16 feet in width, the height of the embankment at the center line is 22 feet, the abutments are 4 feet in height, the covering flags 1 foot thick, the parapet is 1 foot in height ; what is (a) the distance from the center line to end of abutment wall, and (d) the distance from face of abutment wall to end of wing wall ? Solution. — (a) Applying rule I, we have 22 — (4 + 2) = 16. 16 X H + 8 4- 1 ft. 6 in. + 1 ft. 4 in. = 34 ft. 10 in. Ans. ((5) Applying rule II, we have 4 + 1 = 5. 5 X li + 2 = 9ft. 6 in. Ans. 1463. — Tile Culverts. — In localities where stone is scarce and costly, culvert pipe furnishes an economical and efficient substitute. Culvert pipe is made of clay, which is subjected to a high degree of heat, when it is known as vitrified pipe. The manufacture of culvert pipe is carried on extensively in most of the chief American cities, the range in sizes being sufficient to meet all requirements. The pipes vary in length from 24 to 30 inches, and in di- ameter from 12 to 24 inches. They are fitted with socket or bell joints similar to those on cast-iron water pipes. The thickness of the shell is -^^ the diameter of the pipe, and the width of the socket ^ the diameter. The pipe is laid on a concrete foundation with sufficient fall to prevent water from standing in the pipes. A shallow pit is dug to receive the concrete, the pipes being laid as soon as the con- crete is in place and brought to a grade. The pipes are laid with joints of cement mortar, and covered with concrete to one-half their height; the latter are held in place by side boards, secured by banking with earth or by stakes driven in the ground. The concrete affords a secure foundation and prevents leaking at the joints, which is the chief cause of failure of pipe culverts with earth foundations. The parapet walls are of rubble masonry laid in cement mortar, and carried far enough below the bottom of the pipe to prevent undermining. In alluvial soils, such as are traversed by many of our western lines, it is frequently necessary to carry the parapet walls to a depth of six and even eight feet to guard against the undermfning of the embankment. The parapet walls need not be built until after the completion of the road, when the stone may be 882 RAILROAD CONSTRUCTION. hauled by construction trains, thereby saving the great cost of transporting building stone by teams. A general plan C^ Wii^H-:.)-] :o5 J Ql \^A^- ^^^ of pipe culvert is given in Fig. 385. When a single pipe is not sufficient to pass all the water, two or more pipes are placed side by side, with concrete well rammed between. RAILROAD CONSTRUCTION. 883 1464. Open "Water Culverts. — These are generally of 2 feet span, with walls 2 feet thick, and of not greater depth than 3 feet. The foundation is of 12-inch paving placed as in foundations of box culverts. The walls, directly under the stringers, should be capped with large well-finished stones, so as to afford good bearings for the stringers, and properly distribute the loads of passing trains. Both stringers and cross-ties should be of sawed timber. 1465. Cattle Guards. — These are placed on each side of a public road crossing when the crossing takes place at grade. Formerly they were built like open culverts, with spans of from 3 to 5 feet and from 3 to 4 feet in depth. The abutment walls, upon which the wooden track stringers were laid, were from 2 to 2^ feet in thickness. The rails were laid directly upon the stringers, thus dispensing with cross-ties and leaving the space between the rails and abut- ments entirely open. Although possible for stock to get into these pits it was almost impossible for them to get out, and they often proved a cause of instead of a protection against accident. The modern cattle guard dispenses with both masonry and excavation. It consists of two strips of 3-inch plank laid on cross-ties at a distance apart of 8 feet. Triangular strips of either wood or iron laid parallel to the rails are spiked to these pieces of plank, completely covering the space between the rails excepting space for the wheel flanges. A space 2 feet in width outside the rails is similarly covered, the whole closely resembling a gridiron, which is the name given to this form of cattle guard. It is quickly and cheaply made and thoroughly efficient. 1466. Open Passage W^ays. — These are passage ways for public roads which cross the railroad below grade. The walls in part serve the purpose of retaining walls, and should have a thickness at their base of about y%- of their height. The coping of the walls is arranged in the form of steps, as shown in the general plan of highway culvert; see Fig. 386. The height A B oi the embankment is 15 feet. 884 RAILROAD CONSTRUCTION. The steps CD, etc., are so arranged that the natural slope E F of the embankment will just touch the back of the steps. The steps are not car- ried down to the level of the ground, but stop at G where the wall has a height be- tween 4 and 5 feet. The section shows the thickness of the walls, which are 2^ feet thick on the line of slope where the steps chow. The thickness at the base is at all points about ^ of the height of the embankment at that point, giving a thick- ness of about G feet where the embank- ment attains its full height, and finishing at the top with a thickness of 2^ feet. The back of the wall is indicated by the line 77 A". The stringer L consists of two timbers 8 inches wide by IG inches deep by 17 feet in length, sep- arated by cast-iron RAILROAD CONSTRUCTION. 885 spools M, and called a packed stringer. The stringers rest on wooden bed-plates N^ N^ 12 inches wide by 3 inches thick, and are notched down 1 inch on the bed-plates. They are spaced 1 ft. 8 in. from the center line of the track, and are held in place by a strut (7, 3 in. by 12 in, by 3 ft. 4 in. Stringer bolts P oi \ in. round iron pass through both stringers, one on each side of the strut, and are fastened with nuts fitted with cast washers. The cross-ties (2? 8 in. wide by 7 in. deep, are spaced 18 in. between centers and notched down 1 in. on the stringers. The guard-rail 7? is 7 in. by 7 in. bj' 17 ft., and notched down 1 in. on the cross-ties and bolted to every fourth or fifth cross-tie with \ in. bolts. The bridge seat 5 for the stringers is 18 in. deep. The abutments behind the bridge seat are built up to the top of the embankment, thus keeping the earth from falling down upon the bridge seat. The spool M and a device for holding the strut O in position are shown in detail at T. In ordinary open culvert masonry the bridge seat and steps are the only dressed stone used in the structure, the body of the walls being built of well-scabbled rubble. Large stones with good beds should compose the bulk of the walls, and when under-sized stones are used they must be thoroughly bonded by large ones. The wall plates should be placed as nearly over the center of the wall as possible, so that the shock and load of the passing train may be equally distributed throughout the abutments. 1 467. Arched Culverts. — When the volume of water is too great to be discharged by a double-box culvert with openings 3 X 4 feet, an arcbed culvert is substituted with a single opening of the required area. In determining dimensions of culvert openings, the greater danger lies in making them -too small. The volume of surface water discharged from a given area depends on widely differmg conditions, and is often in apparent violation of all pre- scribed rules. It is not within the province of the engineer to attempt to meet phenomenal conditions, but he should meet common extremes, and there is no branch in railroad 886 RAILROAD CONSTRUCTION. construction where he so often blunders as in the matter of culverts. 1468. Parts of an Arch. — Fig. 387 represents an arched culvert in which the distance D £ is called the span, O F the rise, the lower boundary line D F E the soffit or intrados, the upper boundary G B H the back or extrados. The end of the arch included between the lines Fig. 387. D F E and G B H is, called the face. Lines level with D and E and at right angles to the face of the arch are called springing lines or springs. The blocks of which the arch is composed are called arcti stones or voussoirs. The center one B F is the keystone, and the lowest ones A and C the springers. The parts B G and B H are the baunclies. The spaces BGNK and B H ML are the spandrels. The material deposited in these spaces is the spandrel fllling. It is sometimes earth and sometimes masonry or partly of both. Arches according to their forms have different names. RAILROAD CONSTRUCTION. 887 That in Fig. 387 is a semicircular arch, and is the form commonly adopted in culvert building. A circular arch containing an arc of less than 180° is called a segmental arch (see Fig. 388). The arch shown in Fig. 389, composed Fig. 388. Fig. 389. of three circular arcs, is called either an elliptical or a three-centered arch. 1469. To Find the Depth of Keystone. — For cut stone arches, whether circular or elliptic, find the radius O D, Figs. 387, 388, and 389, which will touch the arch at Z>, F, and^. Rule I. — Add together this radius and half the span D E. Take the square root of the sum. Divide this square root by Jf. and add to the quotient -^ of a foot. Or, by formula, depth of keystone in feet = {r^dt^i±M^j^,^foot. (103.) For second-class work, increase this depth of keystone about I part; for brickwork or fair rubble, about \ part. Example. — The radius (9 D\% 18 feet, the span Z> .£"36 feet; required, the depth of an arch of cut stone for second-class work and for brick- work. Solution. — Applying formula 103, we have 4/18 + 18 For cut stone, depth of arch = r +.2 foot = 1.7 feet. Ans. 888 RAILROAD CONSTRUCTION. For second-class work, increase depth of cut stone arch | = 1.7 + iX 1.7 = 1.91 feet. Ans. For brick or fair rubble, increase depth of cut stone arch ^ = 1.7 + iX 1.7 = 2.12 feet. Ans. Rankine's formula for depth of keystone in feet is, dcptJi of keystone in feet = \^.1'Z radius. (104.) The latter formula may serve where all conditions are theoretically perfect, but, under ordinary conditions, the re- sults given by this formula are too small. The arch stones of a 3G-foot arch should be at least 1 ft. 9 in. in depth, for considerations of appearance as well as security. To find the radius O D, Figs. 387, 388, and 389, whether the arch be circular, segmental, or elliptical: Rule II. — Square half t/ie span; square the whole rise ; add these squares together and divide the sum by twice the rise. The quotient is the required radius O D. Example. — The span is 30 feet; the rise 10 feet; required, the radius O D. -, „ ,. 15» + 10' 325 ,«o..* * A Solution. — Radius = -^ — = -^ = 16.25 feet. Ans. 1470. To Proportion the Abutments for a Stone Arch, whether Circular or Blliptical : Rule. — Find the radius O D, Fig. 387, in feet which will touch the arch at D, F, and E. Divide this radius by 5. To the quotieyit, add -^^ of the rise afid 2 feet. The sum ivill be the thickness D N or E M of each abutment at the springing line for any abutment whose height E T does not exceed li^ times its base T U. If of rough rubble, add 6 inches to E M to insure full thickness in every part. Or by formula. Thickness of abut- ment at spring line in feet, when the height does not exceed 1\ times the base radius in feet , rise in feet , ^ ^ , ^ ^^ (106.) Mark the points M and A'^ thus obtained. Next, from the RAILROAD CONSTRUCTION. 881) center 6> of the span or chord D E, lay off O F(Fig. 387) equal to ^^ of the span, and join F and V. Through the point J/ draw the line R 6^ parallel to F V, which will mark the back of the abutment E T U M. In the same way, draw the line 5 NX , marking the back of the other abutment. Now on the lines MR and A^ 5 mark the points R and 5, their height above the line M N being half O B, the full height of the arch. Produce the line B O, and upon that line as at P locate a center from which an arc may be described, passing through S, B, and R. This arc will mark the top of the masonry filling above the arch, except when the rise is about \ of the span or less, in which case the masonry back- ing must be carried up solid to the level K L oi the top of the arch. Ordinarily, the height E T oi the abutment will not exceed 1^ times the base T U. Incase the height should exceed E T, a.s E ]', make the base V Z equal to T 6^ in- creased by \ the additional height T Y. Then, from ^ draw a line parallel to U R, which will mark the back line of the abutment. It is a common practice to give to the faces of the abutment a batter of from ^ inch to 1 inch to the foot, shown in the dotted line^ T' V. This considerably in- creases the base of the abutment, and, proportionately, its stability. An arc struck from the center P' with a radius P' R', R' being level with R, will mark the top of the masonry filling above the arch. 1471. Foundations for Arch. Culverts. — As arch culverts usually require a greater amount of masonry than box culverts, their foundation must be proportionally stronger. The general directions given for box culvert foundations will answer for arch culverts of small span, say from 4 to 8 feet. For greater spans, unless the natural foundation is firm and secure, such as hard clay, sand, gravel, or rock, a deep trench must be dug to receive the founda- tion. If the soil is soft or marshy, it may be necessary to drive piles and cut them off at a uniform elevation below the water-line, and fill between and to the depth of one foot above tops of piles with concrete made with hydraulic cement. 800 RAILROAD CONSTRUCTION. The trench should extend outside the lines of the founda- tion at least 12 inches, in order that the pressure of the superstructure may be sufficiently distributed. The first course of masonry should project at least inches outside the main body of the abutment for the same reason, and should be composed of much larger stones than those which form the main body of the superstructure. The paving be- tween the abutments and curbing at ends of arch should be of the same dimensions as adopted for box culverts. A partial section of arch culvert with concrete foundation is shown in Fig. 390. The stones forming the impost course at A, in a culvert of 16 feet span, should be from inches to 12 inches thick. 1472. Concrete. — The concrete for the foundations should be composed of the following ingredients: Cement, 1 part; sand, 3 parts; broken stone, 5 parts. If the con- crete is to be deposited below the water level, Portland cement should invariably be used. If the pit is free from water at the time of construction, though ordinarily below water level, Rosendale or any other good American cement may be used. The value of concrete depends much upon the quality of the sand and broken stone used and the man- ner of mixing. Sand containing loam should never be used, RAILROAD CONSTRUCTION. 891 and if none other is available, the sand should be washed in a slight current of water, which will remove all the loam. The stone should be broken to a fairly uniform size, and con- tain no piece which will not pass through a 2^-inch ring. If suitable stone is not available, hard-burned brickbats, broken to the requisite size, form an excellent substitute. For mixing concrete a level platform of rough boards is pre- pared, convenient to the foundation pit. A suitable quantity for mixing is the above given proportions in barrels of material, viz., 1 barrel of cement, 2 barrels of sand, and 5 barrels of broken stone. The broken stone is deposited in a regular pile, 12 inches in thickness. Upon the same plat- form the sand and cement are mixed in a dry state, after which water is added to them and they are worked into a mortar of uniform consistency. The mortar is then spread evenly over the stones, and the whole mixed with shovels, commencing at the outside of the pile and working towards the middle; which when reached, the shovelers reverse the movement, working towards the outside and casting the con- crete towards the middle, so that when the outside of the pile is reached, the whole will be thoroughly mixed. It is injurious to work the concrete over repeatedly. Twice handling with the shovel, if thoroughly done, is sufficient. The concrete should be deposited in the foundation pit without delay, before setting commences; and with quick setting cements, especially in summer weather, the process is rapid. It is most conveniently handled in wheelbarrows, and can be deposited directly from them into the pit. In marshy situations, it is a common practice to confine the concrete by inclosures of rough boards held together by stakes driven in the ground. As soon as the concrete is de- posited from the barrow, it must be spread with hoes or shovels into uniform layers, the thickness of which will de- pend upon the depth of concrete to be deposited. If only 12 inches of concrete, it should be deposited in two layers of 6 inches each, and each layer well rammed as soon as deposited. Rammers of about 35 pounds weight, similar to those used in street paving, are recommended. They are of wood 4 892 RAILROAD CONSTRUCTION. feet long, G to 8 inches in diameter at foot, with a lifting handle. Ramming, when properlj' done, consolidates the mass of concrete about 5 or 6 per cent., rendering it less porous and increasing its strength. Water collecting upon the surface of the concrete gives evidence of sufficient ram- ming. The surface of the concrete should be brought to a uniform level, and sufficient time be allowed for setting before the abutments are started. 1473. Mortar. — Cement mortar should be exclusively used in the construction of arch culverts, the cement to be well tested and approved before being allowed to go into the work. Cement which does not show a tensile strength of 40 pounds to the square inch after remaining in water 2-t hours should be rejected. The common American cements, if of good quality, mixed in the proportion of 1 part of ce- ment to 2 parts of sand, will afford a mortar suitable for any ordinary engineering structure. Mortar should never be mixed in large quantities, lest its strength be impaired by setting before using. The proper practice is to mix only such quantities as can be used immediately, thus keeping the supply perfectly fresh and insuring the highest results. The cement and sand should always be mixed dry, the water being added afterwards, and the whole thoroughly worked with a hoe before using. The use of cheap brands of cement is false economy. Ordinary cement will admit of sand in the proportion of tzuo parts of sand to one of cement. The best Portland cement, especially for work not requiring rapid setting mortar, will bear four parts of sand. Hence, the latter may be used with the same economy as the former, even at twice the cost per barrel. 1474. Pointing of Joints. — Arch culverts for water- ways are invariably rubble masonry, but of the best of its kind. Sometimes the corner stones of the abutments, as well as the arch stones of the faces, are of cut stone. The joints of these should be left open at the faces until the work is well advanced or completed, when they should be pointed RAILROAD CONSTRUCTION. 893 with mortar made of the best cement in the proportions of 1 part of cement to 1 part of sand, and neatly dressed with a pointing tool. The joints of the rubble masonry are simply struck, i. e., the trowel is pressed against the mortar and drawn the full length of the joint, forming a water- shed for each joint. The joints are struck as the stones are laid, the same mortar being used at the faces as in the interior of the walls. There are two principal methods used in pointing cut stone, as shown in Figs. 391 and 392. Fig. 391 shows the form in most general use. It is not so ornamental as that Fig. 391. Fig. 39~'. shown in Fig. 392, but it is less exposed to the weather, and, hence, is more enduring and a more certain protection to the joints. Mortar intended for pointing must be used immediately after mixing, and the pointing tool repeatedly run over the joint or bead, under considerable pressure, in order to compress the mortar and give it a smooth surface and uniform groove or projection. 1 475. Centers for Arches. — A center is a temporary wooden structure for supporting an arch while it is being built. Centers are built lying flat on a fixed platform, to a full-sized drawing, and vary widely in design, according to the type and dimensions of the arch. The different parts of a center are given in Fig. 393, which is a standard type of centering for all arches of moderate span, say from 6 to 16 feet. 894 RAILROAD CONSTRUCTION. The frames A, A are made of ribs of 1^-inch plank and united as shown in the figure, breaking joints and fastened together with spikes. The ribs are fitted to the drawing as the frames are built. The ribs are 4 ft. 1 in. in length, 8 in. in width at ends, and 10 in. in width at middle, the edge being trimmed down to fit the curve of the arch. The chord B is composed of two planks, each \^ in. thick by 10 in. in width and 1(5 ft. in length, spiked securely to the frames. The upright strut C is 3 in. thick by 10 in. in width, placed ' 1 pr 1 \ I 1 1 1 I 1 1 I 1 Ij^ 1 1 jCD I directly under the crown of the arch and fastened to the frame by two cleats D securely spiked to both frame and strut. Its foot passes between the planks forming the chord to which it is spiked. The brace E is fastened at top to the strut with spikes. Its foot passes between the chord planks and is shaped to abut against the rib at the spring line, being securely spiked to the chord. The frames are spaced 3 feet from center to center, and rest on G in. by G in. caps / which are supported by 6 in. by G in. posts G. These posts rest on 4 in. by G in. ground sills H which rest on the stone paving. On the caps directly under each frame are striking or lowering wedges K, by means of which the frames are raised in case any of the posts should settle. RAILROAD CONSTRUCTION. 895 1476. Striking Centers. — Upon the completion of the masonry, the lowering wedges are removed, which per- mits of the removal of the centering. This process is called striking the centers. There is great difference of opinion as to the length of time which should elapse after the comple- tion of the masonry before the centers are struck. In the case of brick and rubble arches where the mortar forms a considerable part of the mass, a period of two or three months should elapse before the centers are struck. This will allow the mortar to harden and prevent undue com- pression of the joints and consequent settlement of the arch. 1477. General Directions for the Building of an Arch. — All arch stones must be laid with beds in radial lines. The joints at the intrados, or soffit, will, therefore, be thinner than at the extrados, or back. All rough pro- jections must be removed from the beds of the stones, and the stones laid in firm beds with broken joints. Until the arch is half built, the backing need not be started, as an ex- cess of weight on the haunches is liable to cause a lifting of the crown. In arches of large span it is a common practice to load the centering at the crown until 45° of the arch above the springing line is completed. When the 45° line is passed and the pressure on the centering becomes more nearly vertical, the backing must be carried up to take the pressure. The continuance of the centering will be no hindrance to traffic over the bridge. 1478. Wing Walls. — Wing walls are generally built with faces diverging at an angle of 130° from the face of the arch. Their foundations are prepared at the same time as the abutment foundations, and varied to suit the different heights of wall above them. Abutments and wing walls are carried up together, the stones of both walls interbonding so as to form one solid mass of masonry. The thickness of the wing walls at foundation line should ordinarily be y*g- of the full height of the wall at that point, with faces battered from 1 to 1^ inches to the foot and having a thickness of 2^ feet at the top. 896 RAILROAD CONSTRUCTION. When y\ of the height of the wall (allowing a batter of 1 inch to the foot) does not give a thickness of 2^ feet at the top, the thickness of foundation must be sufficiently in- creased to insure that thickness at the top. Where wing walls attain a height of 12 feet and over, make the thickness of the foundation ^ of the height. Sometimes the slope of the back of the wall is broken up into steps instead of being uniform. Some advantage is gained from such treatment, as the weight of the back filling bears directly upon the pro- jecting stones. Any attempt to give the back a smooth, uniform slope should be avoided. It adds nothing to the appearance of the work, as it is covered by the embankment, and lessens the friction of the filling against the back of the wall, which tends to prevent its overturning. It is far better to increase, the size of the stones, allowing their rough edges to project from the rear face. The large stones act as binders for the smaller ones, greatly increasing the sta- bility of the wall, and the projections afford the necessary friction to the filling. A general plan of a semicircular arch culvert, including parapet and wing walls, is given in Fig. 394. The span A B is m feet, and the rise CD 8 feet. The thickness of arch D £ is found by applying formula 103, Art. 1469, » / /- F • /- i^ radius 4- half span , ^ ^ , aeptli of keystone tn feet = -^—^ (- . 2. foot. ^ ^ . . . ^. . , 4/8 feet -4- 8 feet Substitutmg given dimensions, we have — 4 .2 foot = 1.2 feet, which is the depth of key given for cut stone. As the rule calls for \ greater depth for arches of rubble, which is the material supposed to be used in the 1 2 feet arch under consideration, — ^ — = .3 foot; 1.2 + .3 = 1.5 4 feet = required depth of keystone. The length of the soffit A D F is equal to half the circumference of a circle whose diameter is 10 feet. Its length is, therefore, 25.13 feet. The number of stones in an arch should always be an odd number, which will place the keystone in the center of the RAILROAD CONSTRUCTION. 897 arch and give an equal number of arch stones on both sides of the key. If now we make the thickness of the arch stones 12 inches from center to center of joint on the soffit, the arch will contain 13 such stones on each side of the key and leave 13|- inches for the thickness of the keystone. The height of the abutments F F' we take at 6 feet. The thickness F G oi the abutments at spring line we find by applying formula 105, Art. 1470. Thickness of abut- " mcnt at spring line in feet, when height of abutment does not ex- ceed 1^ times its base Substituting given dimensions, we have thickness of abut- 8 8 jnent at spring line in feet = — -f- — -|- 2 ft. =4.4 feet. radius in feet . rise in feet , „ ,. ^ = 5-^+ j/-+2A^'. 898 RAILROAD CONSTRUCTION. This thickness of abutment is for first-class masonry. As our structure is of rubble, we add ^ foot to 4.4 feet, which gives 4.9 feet.. We further increase the thickness of the abut- ments to 5.0 feet, which will insure perfect stability without any excess of masonry. We give to the back of the abut- ment wall a batter of 1 inch to the foot, making the thick- ness of the abutments at the ground line X Y 5 feet 6 inches. The height of the points L and J/ above the spring line is 4 feet and 9 inches, equal to one-half the full height C £ of the arch. The arc L E M which limits the top of the backing or spandrel filling is struck with the radius W L^ 18 feet 9 inches in length, found by trial. The wing walls O and Pare shown in plan at Q and R. A section of wing wall at 5" 7" is shown in full at U. The top N of the parapet is 1 foot 9 inches above top of arch. The parapet and wing walls have a coping of dressed stone 6 in. in thickness. 1479. General Directions for Building Rubble Walls. — Small stones, excepting for back filling, should not be used, provided those of suitable size can be had at reasonable cost. Stones of too great size are equally objectionable unless they have full beds and reach from face to face of wall. Many rubble walls are built, as shown in Fig. 395, of large stones showing on one face, but extending only a short distance into the wall, while the back and body of the wall are composed of small stones. The back of the wall, having so much greater proportionof mortar than the front, will in high walls settle considerably more than the front, producing cracks in the masonry. The almost total lack of binders is an even greater source of weakness. Such a wall is objectionable in any situation, but when serving as a retaining wall for a Fig. 395. Fig. 396. RAILROAD CONSTRUCTION. 899 railroad embankment where the back filling is subjected to the constant vibrations caused by passing trains, its ultimate failure is almost certain. A full proportion of large stones should show on both front and back and extend well into the wall, binding the wall compactly together, as shown in Fig. 396. RETAINING WALLS. 1480. A retaining wall is one for sustaining the pressure of earth, sand, rock, or any other substance deposited behind it after it is built. The material deposited is called filling or backing. Retaining walls are much used in railroad construction, especially in sections where the natural slope of the ground approaches closely to that Fig. 397. of the angle of ordinary earth filling, viz., 1^ horizontal to 1 vertical. Railway tracks entering towns, especially where they cross or crowd other lines, terminal grounds, etc., invariably require retaining walls. The pressure exerted by the backing will vary greatly, depending upon the slope of the ground behind the wall, the nature of the material composing the backing, and the manner of depositing it; but chiefly depending upon the height of the backing. The usual form of retaining wall is shown in Fig. 397. There is 900 RAILROAD CONSTRUCTION. no invariable rule for determining the dimensions of retain- ing walls, and the rules of various authors differ widely. The following rule by Trautwine is based upon careful experiments and is widely adopted. The back of the wall is vertical, and the foundations not more than 3 ft. deep. Rule. — 1 V lie 71 the backing is deposited loosely, being du mped from earts, barrows, etc., zuall of cut stone or first-class large ranged nibble in mortar, base C D equals .35 of the vertical height D B; wall of good common scabbled mortar rubble, or brick, base C D equals .Jf. of the vertical height D B; wall of well-scabbled dry rubble, base C D equals .5 of the vertical height D B. When the backing is deposited in layers and well rammed, these dimensions may be somewhat reduced, but there is no fixed rule. In general, the additional cost of spreading and ramming will quite equal the saving in masonry. In Fig. 397, the height B B is 6 feet. The wall, supposed to be of dry rubble, has a base of 3 feet 4 inches. The foundation is laid in a trench about 1 foot in depth, with a footing or offset F G 6 inches in width. The face is battered 1 inch to the foot, which gives the wall a more sub- stantial appearance, though clearly adding nothing to its stability. Earth and sand are the materials commonly used for backing. When broken stone, gravel, boulders, or clay are to be used, additional weight must be given to the wall. By inclining the base A B of the wall (see Fig. 398), the friction of the wall against the foundation is increased and the danger of overturning lessened. As was stated in Art. 1478, the rough bat- tered back of the wall also *''0' 896. RAILROAD CONSTRUCTION. 901 increases the friction of the backing, tending to prevent overturning. The batter of the face should not exceed 1^ inches to the foot. Any increase is liable to catch water running down the face and carry it into the wall. This danger is increased where the joints of the masonry are in- clined backwards, as in Fig. 308. To obviate this danger, the face stones are sometimes laid in mortar. 1 481 . Guarding Against Frost. — Where deep freez- ing occurs, the back of the wall should be sloped forwards, as shown in Fig. 399 at ad, and smoothly finished to lessen the hold of the frost, which might otherwise displace the masonry. The foot of the slope d should be at the frost line, usually three or four feet below the surface a. 1482. Bulging. — Where walls are too thin, Fig.399. they usually first manifest their weakness by bulging out- wards at about one-third of their height above the ground, as at a, Fig. 400. This effect is sometimes owing to the yielding of fresh mortar, and if not more than \ inch for each foot in thickness of wall at a, it need not cause apprehension. Sometimes retaining walls fail on account of the com- pression of the backing, causing settlement and in- creased pressure against the wall. This is especially fre- quent where the backing supports railway tracks car- rying heavy and rapidly moving trains. In design- ing walls for such situa- tions, this heavy additional weight must be provided for by additional weight in the wall. Fig. 400. 902 RAILROAD CONSTRUCTION. 1483. Offsetted Back. — Having proportioned a re- taining wall abdc in Fig. 401, by the foregoing rule, we can, by offsetting the back, as shown in the figure, considerably increase its stability without adding to the volume of the masonry. The offsets are determined as fol- lows: Through ^', the middle point of the back, draw any line f g. From /"erect the perpendicular ///. Divide g Ji into any even number of parts, in this instance 4, and draw through these points of division lines parallel to/" //. Then divide/// into 1 great- er number of equal parts than gJi, and through these points of division draw lines at right angles to f h, forming the offsets as shown in the figure. By increasing the thickness Fig. 401. Fig. 402. Fig. 403. of the wall at the base, the center of gravity is lowered and the stability consequently increased. The backing included by the lines ^/z and /// exerts only vertical pressure against the offsets, which tends greatly to prevent the overturning of the wall. RAILROAD CONSTRUCTION. 903 1484. Surcharged Walls. — When the backing is higher than the top of the wall and slopes upwards from its inner edge a, at the natural slope a b oi 1^ to 1 (see Fig. 402), the dimensions given in Art. 1480 will be inadequate for the increased pressure. The following table prepared by Trautwine gives dimensions of walls for all probable heights of backing: TABLE 29. ^ a ^•g- 4> C o u 3. c o •o" 8i> 33 ^ en '^ J5 t^m 0;0 "JB t: m O J2 J3 O S 03 n o S o 3 ® l3 rt OO ^ o 3 Total Height ing as Comp Height of W ffi tn x: If a T3 9i Thick Pari ness of \ .8 of Hei Vail in ght. Thickness of Wall in Parts of Height. 1.0 .35 .40 .50 2.0 .58 .63 .73 1.1 .42 .47 .57 2.5 .60 .65 .75 1.2 .46 .51 .61 3.0 .62 .67 .77 1.3 .49 .54 .64 4.0 .63 .68 .78 1.4 .51 .56 .66 6.0 .64 .69 .79 1.5 .52 .57 .67 9.0 .65 .70 .80 1.6 .54 .59 .69 14.0 .66 .71 .81 1.7 .55 .60 .70 25.0 1.8 .56 .61 .71 or more .68 .73 .83 When the slope a b oi the backing starts at the front a of the top of the wall (see Fig. 403), additional thickness is required. The triangle a c d showing section of earth above top of wall exerts only vertical pressure against the top of wall, and, hence, increases its stability. When the backing reaches above the top of the wall, as in Figs. 402 and 403, the wall is surcharged. The following table by Poncelet gives thickness of walls surcharged with dry sand from the outer edge a, Fig. 403: 904 RAILROAD CONSTRUCTION. TABLE 30. i§^ c o 0) c o *^ ll kl m & ■^ c u ^1 a 1- 03 "^ tn 3 t o h «? iJl o ^ ° rt « "^ i bo o o ^ c - J= 6 L^ bo o o .2 c *S O *i rt ^ 'v o z. 03 3^ffi Thickness of Wall in Thickness of Wall in o - Parts of Height. Parts of Height. 1.0 .350 .452 2.0 .707 .930 1.1 .393 .498 2.4 .762 1.020 1.2 .439 .548 3.0 .811 1.110 1.3 .485 .604 4.0 .852 1.180 1.4 .533 .665 6.0 .883 1.250 1.5 .579 .726 11.0 .909 1.280 1.6 .617 .778 21.0 .922 1.310 1.7 .645 .824 31.0 .926 1.320 1.8 .668 .847 Infinite .934 1.340 1.9 .690 .903 The table is applied as follows : If the height of the backing is 20 feet and the retaining wall 10 feet, the tabular height of backing is given as 2, and the thickness of the re- taining wall, if of cut stone, should be 10 X .707 = 7.07 feet. 1485. To Prevent Sliding. — ^ retaining ivall may slide from its foundation ivithout losing its vertical position. Where the wall is built on a timber platform or a smooth rock surface, the danger of sliding is great, owing to insuf- ficient friction between the wall and foundation. To pre- vent this, strong projecting beams are built into a timber platform running at right angles to the direction in which the wall would slide, as shown in Fig. 404. On wet clay the friction is about ^ the weight of the wall ; on dry earth, from \ to I, and on sand or gravel, from f to f the weight of the wall. RAILROAD CONSTRUCTION. 905 The friction of masonry on a timber platform is about ^jj of its weight if dry and f- of its weight if wet, i. e., a retain- ing wall under the above given conditions will not slide under a pressure of ^, f, f, etc., of its total weight. 1486. On the Theory of Retaining ^Valls. — Let a bdc. Fig. 405, be a retaining wall with battered face and vertical back. The top b e oi the back- ing is level with the top of the wall. Let d e represent the natural slope of the material com- posing the filling, — « g ^ viz , 1^ horizontal fig. 405. to 1 vertical, which is the average of materials used for back filling. It is assumed that the wall a b d c\s heavy enough to re- sist sliding along its base, and that it can fail only by over- turning, i. e., rotating about its toe c. Now, if the angle 906 RAILROAD CONSTRUCTION. ode between the vertical line o w turnmg. Drag scrapers are rarely used for a longer haul than 400 feet. 922 RAILROAD CONSTRUCTION. RAILROAD CONSTRUCTION. 923 The number of trips in a day for a 400-foot lead will, there- 600 (number of minutes in day) _600_ 600 _ ' number of 75 feet length in lead -|- 15 ~~ 415 5.53~ 108.5 trips at ^ cu. yd. per trip = 21.7 cubic yards, the amount of material hauled by each team per day. As the team and driver cost $3.50 per day, the cost of hauling per cubic yard will be -^^t-^ = 16.13 cents. Other charges will be the same for drag scrapers as for wheeled scrapers, and we have the items giving total cost to contractor fof delivering material at the dump, as follows: Loosening with plow. 1.00 cent per cubic yard. Loading and dumping 1.00 cent per cubic yard. Hauling 16.13 cents per cubic yard. Maintaining road, yVcent for each 100 feet of lead. . . .40 cent per cubic yard. Superintendence, water car- rier, and spreading. ... 2.00 cents per cubic yard. Total cost to contractor, exclusive of profit. .... 20.53 cents per cubic yard. Add 15^ for contractor's profit 3.08 cents, per cubic yard. Total cost to R. R. Com- pany 23.61 cents per cubic yard. The above figures are only approximate, and will vary largely with conditions. Much depends upon the material handled, the situation, and the weather; but far more upon the energy, skill, and judgment of the contractor and fore- man. 1497. Work with a Steam Excavator and Dump Cars. — In cuttings from 8 feet upwards, a steam excavator may be employed to great advantage. A first-class exca- vator, such as is shown in Fig. 415, will excavate and load into dump cars 600 cubic yards per day. 924 RAILROAD CONSTRUCTION. The excavator stands on a track a, and as the material ahead of the machine is cut away, the track is extended and the excavator is advanced by means of its own machinery. This is accomplished as follows: The car axles b, b are fitted with sprocket wheels driven by pitch chains c. These chains work on sprocket wheels d^ fixed to the countershaft e. The countershaft carries a pinion, not seen in the drawing, which is driven by the large spur/', which is itself driven by a pinion attached to the main shaft g. The main shaft also carries another pinion which drives the spur //, and the drum attached to its shaft. This drum carries the chains k which give to the crane / its lateral motion. The boom m is formed of heavy steel angles, between which the dipper handle n works. The power for crowding the dipper out- wards is applied through the steel rack and the pinion attached to the dipper shaft, and derived from the hoisting chain q, where it passes over a pocket sheave r. This pocket sheave drives the intermediate shaft s by friction clutch and steel pitched chain. The dipper / holds from 1 to If- cubic yards. The teeth are of heavy pointed steel and attached so as to be renew- able. The handle is of oak with racking of heavy cast steel. Steam is generated in the boiler w, and the machinery is driven by the engine v. The reversing levers are shown at w. The excavator crew consists of three men, viz., an engineer, foreman, and craneman. The duty of the latter is to see that the excavator does full work, i. e., that the dipper is filled at each cut of the machine. Six pitmen are required to lay track, see to the shifting of the machine, and help in shifting cars and making up train loads. The bulk of the work connected with the shifting of cars and making up of trains is performed by horsepower. A pit foreman takes charge of all work not immediately connected with the working of the excavator. The cost of an excavator is about $6,000. For interest on same and wear and tear of machine, charge 110.00 per day. The several items of cost to be charged to the excavator will be the following: RAILROAD CONSTRUCTION. 925 Cost of. excavator $10.00 per day. 1^ tons coal @ 16.00 per ton 9.00 per day. Water 4.00 per day. Oil, waste, etc 3.00 per day. Engineer 4. 50 per day. Fireman 2.00 per day. Craneman 3.00 per day. 6 pitmen @ $1.50 9.00 per day. Foreman 3.00 per day. Horse and driver for shifting cars. . 2.25 per day. Total ; $49.75 At 600 cubic yards per day, the cost per cubic yard for $49 75 excavating will be ' = 8.29 cents. Teams will haul 6 cars holding 1^ cubic yards each and travel at the rate of 3 miles per hour, or an average of about 260 feet per minute, which will bean average of 130 feet go- ing and coming, i. e., 130 feet of lead per minute. About 3 minutes are consumed in stopping, dumping, and chang- ing team for return to the excavator. It will require about 1:^ minutes per car to load, making 9 minutes per train of 6 cars. The number of trips per team per day will, there- fore, be equal to 600, the number of minutes in a working day of 10 hours, divided by 9 minutes, the time of loading + 3 minutes, the time of unloading + the number of 130 feet lengths of lead. Calculating upon a haul of 1,300 feet equal to ten 130 feet lengths of lead, we have the number of trips per team per day = -————— = 27.3. Deducting for de- y — |— o ~j~ j-U lays caused by defective track, derailed cars, etc., 3.3 trips, we have 24 trips per day for each team. As each train car- ries 9 cubic yards, the total yardage per team per day is 24 X 9 = 216 cubic yards. The team and driver will cost $3 75 $3.75 per day. The cost for hauling will, therefore, be ' ' = 1. 74 cents per cubic yard. Five men are required to main- tain the tracks and take charge of the dump, 4 men at $1.25 926 RAILROAD CONSTRUCTION. per day and foreman at $2 per day, making 17.00 per day. The cost per cubic yard for track and dump charges will, therefore, be -^— = 1.17 cents per cubic yard. It will re- quire 24 cars to handle the materials, at a cost of 50 cents per car per day, making a total daily charge of $12.00, which, divided by 600, gives an additional charge of 2 cents per cubic yard for use of cars. The total cost to the contractor for excavating, loading, hauling, dumping, and spreading will, therefore, be as follows: Excavating and loading 8.29 cents per cubic yard. Hauling 1.74 cents per cubic yard. Care of track, dumping, and spreading 1.17 cents per cubic yard. Use of cars 2.00 cents per cubic yard. Total cost to contractor 13.20 cents per cubic yard. Adding 25;^ for contractor's profit 3. 30 cents per cubic yard. Cost to R. R. Company 16.50 cents per cubic yard. On account of the great cost of plant and heavy contin- gent expenses, the contractor should calculate on a profit of 25 per cent, when making estimates on this class of work. 1498. Rock Excavation. — A cubic yard of hard rock in place, i. e., before being blasted, weighs on an average 1.9 long tons, or 4,256 lb., equal to 158 pounds per cubic foot. A cubic yard of hard or solid rock w/irn broken up by blasting so that it may be loaded into carts will occupy about 1.8 cubic yards of space, or 48.6 cubic feet of space. Each cubic foot of broken rock will, therefore, weigh ' = 87. 6 lb. A cart will carry about -^ of a cubic yard of solid rock, i. e., 9.7 cubic feet of broken rock, which will weigh on an average 850 lb., which is only 50 lb. more than an average cartload of earth. A horse may, therefore, be expected to haul as many loads of broken rock as of earth. It will cost on an average 40 cents per cubic yard in place to cover the cost of loosen- RAILROAD CONSTRUCTION. 927 ing, including sharpening tools, drilling, powder, etc. It will cost an average of 10 cents per cubic yard in place to load the stone into carts. As the number of cubic yards of rock handled per day is less than the number of cubic yards of earth, the cost of superintendence and of water carrier will be greater, say 3 cents per cubic yard. Repairs of road will cost ^ cent for each 100 feet of lead. Dumping and spreading will cost 2 cents per cubic yard. Carts will cost same as in earth excavation, viz., $1.50 per day. It will require an average of 5 minutes to load and dump carts. Example. — For a lead of 600 feet, what will be the cost to the con- tractor for delivering solid rock on the dump ? Solution. — The number of cart trips per day will be 600, the number of minutes in a working day, divided by 5 + the num- ber of 100 feet lengths of lead. We have, accordingly, number of cart trips per day = ;; ^ = 54.5 trips. At ^ cubic yard per cart, the 54 5 number of cubic yards hauled per cart per day will be —^ = 10.9 cubic yards in place. The cost of hauling will, therefore, be $1.50, the cost per day per cart, divided by 10.9, the number of cubic yards hauled per cart, which gives 13.76 cents per cubic yard in place, that is, of solid rock. We have then for handling solid rock with carts, the following items of cost, viz. : Loosening 40.00 cents per cubic yard. Loading 10.00 cents per cubic yard. Hauling 13.76 cents per cubic yard. Dumping and spreading 2.00 cents per cubic yard. Superintendence and water car- rier 3.00 cents per cubic yard. Repairs of road 1.20 cents per cubic yard. Total cost to contractor 69.96 cents per cubic yard. Add 15 per cent, for contractor's profit 10.49 cents per cubic yard. Cost per cubic yard to the R. R. Company 80.45 cents per cubic yard. All stone and detached rock found in separate masses, con- taining not less than 3 cubic feet nor more than 1 cubic yard, and all masses of rock, slate,, or coal, or other rock soft enough to be removed without blasting, are classified as 928 RAILROAD CONSTRUCTION. loose rock and may be handled at about half the cost of solid rock. 1 499. Hand Drilling:. — Hand drilling is performed in two ways, viz., by churn drilling and by Jumping. A churn drill is made of a round iron bar about 1^ inches in diameter and from 6 to 8 feet in length, having a piece of tool steel a little wider than the diameter of the bar welded to one end of it. This, after being properly hardened and sharpened, forms the cutting edge. In ordinary work, the holes are from 1^ to 3 inches in diameter and from 2 to 4 feet in depth. Holes drilled with the churn drill are usually vertical. In drilling the bench in tunnel work the drills are inclined slightly backwards from a vertical line. In drilling, the churner raises the drill a few inches, turning it slightly in the hole and allowing it to fall. The drill in a free, hole rebounds so that but little effort is required by the driller in lifting the drill. An experienced driller will in a working day of 10 hours drill from 5 to 12 feet of 2-inch hole, de- pending upon the character of the rock. In granite or hard limestone from 7 to 8 feet of If-inch hole is a fair day's work and from 9 to 10 feet in ordinary sandstone. When the hole is more than -4 feet in depth, two men are put to the drill. The Juniper is a short drill which is held and turned by a man in a sitting posture while blows from 8 to 12-lb. ham- mers are delivered upon the head of the drill by two other men called strikers. The average depth of a hole per man is considerably greater with the churn drill than with the jumper. The advantage of the jumper lies in its admitting of drilling holes at any angle and in many places where the churn drill could not be worked on account of limited space. In drilling with jumpers, drills of various lengths are used, depending upon the depth of hole. Drill bits re- quire sharpening at each G to 8 inches of hole. Great skill is required in tempering in order that the drills may do full duty. On surface work, good d,rillers are paid from $1.50 to $1.75 per day. In tunnel work from $1.75 to $2.00 per day. RAILROAD CONSTRUCTION. 929 1 500. Percussion Drills. — Percussion drills are usu- ally spoken of as rock drills, and are built to be driven by steam, compressed air, or electricity. They should be de- signed for hard service, such as sinking shafts and drilling tunnels in the hardest rock. They should strike a hard blow, and be so built as to stand the most severe usage, yet be readily kept in repair with the facilities available in re- gions remote from machine shops. They must stand up to the work of pounding a hole in the hardest kind of rock at the rate of 150,000 to 200,000 blows a day, with all the shocks and jars which that would mean. The blow should be an uncushioned blow; that is, in steam and compressed air drills, the exhaust, during the forward stroke, should remain open until the blow is struck, and none of the force of the blow should be taken up by a cushion of steam or air in the front end of the cylinder. The bit or drill proper must hit the rock, which is the only proper cushioning, and hit it before the pressure enters the front end. Expansive working of the steam or air in rock drills, as has been at- tempted, is a mistake. It is permissible and advisable in engines where the length of the stroke is fixed and where the weight of the machine is not of very great account, but in a rock drill the object is to get the hardest possible blow f.-om the smallest cylinder and the lightest machine. The smaller and lighter the machine, the less space required for working and the easier handled. The value of a hard blow in hard rock is well known. The average drill runner is not careful to keep his bits sharp, and it is a common sight to see a rock drill pounding away with a bit which has no edge at all. It then becomes a question of pounding the rock to pieces instead of cutting it. A hard blow will do this, while a tappet drill, which has the force of the blow materially checked by the early admis- sion of pressure to form a cushion, will run along at a lively speed, but accomplish very little in proportion to power consumed. Another quality a rock drill must have is the power to pull the bit out of the hole as well as to drive it in, and that when the hole is blocky, crooked, or muddy. 930 RAILROAD CONSTRUCTION. The best rock drills on the market are the Ingersoll- Sergeant and the Rand drills, operating by steam or com- pressed air, and the General Electric Co. 's drill, operating by electricity. Fig. 416 is a sectional view of one form of a drill using steam or compressed air, without tripod or column. The principal parts are as follows: 1 is the cylinder. At the right hand or "back" end of the cylinder there is a washer 2, and a buffer 3, to receive the piston when it strikes at this end. Immediately behind these are the "rotation washer" 4, and the "rotating ratchet" 5, both inside of the back cylinder head 6. To the left, 7 is the brass "rifle nut," 8 is the "rifle bar," and 9 is the piston. The rifle nut 7 is secured to the piston 9 and slides back .17 i» ^ Fig. 416. and forth with it over the rifle bar 8. This compels a relative rotation between the bar and the piston, but as the piston is very much the heavier, the tendency is that only the bar will rotate. It is controlled, however, by the rota- ting ratchet 5, and allowed to turn only in one direction. The piston, therefore, must turn on its return stroke, and in this way it is made to rotate a little at every blow and so drive the bit to a new place. At the extreme left, 10 is the piston bushing to take the wear off the bit. The key 11 is drawn down by the U bolt 12, and so clamps the bit. The front cylinder head 13 and the gland IJ^ are both in halves. The washer 15 and the buffer 10 ease up the blow when the piston strikes here On top we have the steam chest 17, the steam chest covers 18, valve 19, valve guide 20, valve washers 21, and buffers 22. The "goose neck " ^5 carries RAILROAD CONSTRUCTION. 931 one end of the feed screw, which is driven by the crank 25 turned by hand. Fig. 417 represents a drill mounted on a tripod and ready for work. The feed-screw A is collared at its upper end to the frame B and is thus prevented from moving longitudinally when revolved by the crank fixed to its top. Its lower end works in a nut fixed to the cylinder, which last moves longitudinally backward as the crank is turned. The drilling is begun with a short drill called a starter, the first few blows being lightly given until the hole is fairly started, when the full force of the steam is turned on. As the drill penetrates the rock, the cylinder is fed forward by means of the feed-screw A as far as the shell permits. The steam is then shut off gind the drill withdrawn by reversing the movement of the feed-screw. A longer drill is then substituted and the drilling continued. The cutting edges of the bits are necessarily worn by the drilling and constant rotation in the hole so that the diameter of the bottom of each section of hole is slightly less than that at the top ;. accordingly, at each change of drill, one is selected with a bit from ^ to -^^ inch narrower than the one removed. In tunnel driving, the drills used in the heading are usually mounted on columns, similar to that shown in Fig. 418. The column A is set in an upright position near the face of the heading, the top B of the column being forced against the roof of the tunnel by the capstan screws C which rest in special castings D on the floor of the heading. It is a common practice to place strong blocks of wood on the head of the column and under the feet of the capstan screws, which prevent the rock supports from becoming loosened by the continued jarring of the column, due to the Fig. 417. 932 RAILROAD CONSTRUCTION. working of the drills. The arm E at right angles to the column slides up or down the column by means of the collar F^ and may be clamped in any position by the clamp G. The drill is carried on this arm and revolves about it as an axis, thus giving a wide range of action. Usually two drills are mounted on each column. In sinking shafts and driving tun- nels, as well as in mine work, compressed air is used instead of steam, which loses much of its pressure through condensation. The use of compressed air greatly promotes ventilation. Percus- sion drills are tinder a pressure of from 60 to 70 lb. per square inch. In one hour one will drill a hole from 2 to 2i^ inches in diameter and from 4 to 10 feet in depth, depending upon the character of the rock, the position of the strata, and the size of the machine. The cost of drilling will vary from 8 to 20 cents per FIG. 41B lineal foot. 1501. I>rill-bits are of different shapes, being varied to suit the work to be done. For uniform hard rock, the bit is cross-shaped, with the arms of equal length and at right angles to each other. For seamy rock, the arms of the bits are of equal length, but cross each other X fashion. For soft rock, frequently a bit with a Z-shaped cutting edge is used. Fig. 419 shows the usual form of drill-bit, and Fig. 420 the tool for sharpening same. On surface work, a drill is usually worked by one man; in tunnel work, two men are RAILROAD CONSTRUCTION. 933 commonly employed. The man in charge of the drill is called the drill runner and his assistant the helper or tailer. II m Three or four men are required I I in moving and placing the larger i ■ drills. 1502. Air Compressors, — As before stated, when percussion drills are used for surface work, they are operated by steam which is usually generated in a portable fig. 420. boiler and conveyed to the drills through iron pipes. The direct connection with the drills is FIG. 419. made by means of steam Jiose. When the work is of great magnitude and confined to a small area, a sta- tionary boiler of adequate size is set up. When compressed air is required for working the drills, as in mine or tunnel work, air is forced into a receiver by an Fig. 421. air compressor and conveyed thence by iron pipes and steam hose to the drills. The receiver is a wrought-iron cylinder, from 2 to 4 feet in diameter and from 5 to 12 feet long. A cut of a light duplex compressor made by the Rand Drill Co. is shown in Fig. 421. It is so made that it can readily be 934 RAILROAD CONSTRUCTION. taken apart and transported on mule-back. A and B are the steam cylinders, and C and D are the air cylinders. E is the air delivery pipe and F the steam pipe. Some of the advantages of the duplex type are the following: Since the cranks are set at right angles, the engine can not get on a dead center. One cylinder can be detached when only half the capacity of the machine is required. The power and resistance being equalized through opposite cylinders, large fly-wheels are not necessary. A borizontal air receiver is shown in Fig. 422. The air enters the receiver at A, flows through a series of pipe coils, and discharges through B. Cold water constantly cir- FlG. 422. culates about these coils, cooling the air and drying it at the same time, the moisture dropping to the bottom of the coils. The glass gauge £ indicates the amount of moisture de- posited. When the gauge indicates too great an accumu- lation of water, it is drained off. The cooling water enters the receiver at C and is discharged at D. The gauge F shows the pressure of the air, and // is a safety valve which regulates the pressure. RAILROAD CONSTRUCTION. (CONTINUED.) TUNNEL WORK. 1503. Tunnels. — The location and construction of tunnels are so intimately connected that it has seemed best to consider them under the head of construction alone. When grading requires a cutting to exceed 60 feet, it be- comes expedient to drive a tunnel. Tunnels should, when possible, be driven on straight lines, especially for single- track roads, in order to reduce the danger of collisions. 1504. Laying Out the Surface Line. — The first work of the engineer in preparing for tunnel work is to lay out the tunnel line on the surface of the ground. If the tunnel line is a tangent, it should be run in by foresights, so far as possible, in order to obviate those errors due to defects in the adjustment of the transit, and the work repeated a sufficient number of times to insure a true line. As a per- fect line is of the utmost importance, great pains should be taken, and considerable expense may be incurred in securing long sights. Special transits, called /wwwr/ transits, of double the weight and power of ordinary instruments, are used in running the lines. Frequently, platforms of either timber or masonry, several feet in height, are erected at the suc- cessive points on the line, their elevation admitting of much longer and clearer sights. The hours of the early morning are the most favorable time for running the test line." The air is then of uniform temperature, and the rays of the sun so low as not to interfere with sights. It is useless to attempt work of this kind when the wind is blowing. A cool, cloudy morning is the best time, and in most situations it may be 93G RAILROAD CONSTRUCTION. O^ had by watching one's chances. Some engineers prefer to run the surface Hne (if it is one con- tinuous tangent) at night, using plummet lamps for sights. The center line of the Cascade tun- nel, on the Northern Pacific Railroad, was run in this way. The laying, out of the surface line is illustrated in Fig. 423. Let E B C G represent the profile of the hill or mountain to be tunneled. Setting up the instrument at A and foresight- ing to E^ a point is set at i?, the highest point on the surface line which can be seen from A. Intermediate points H, P, and 1 /fare also set ivomA. Moving 2 the instrument to B, a backsight is taken to A and a second principal point set at C, an in- termediate point being at L. Removing the instrument to C, a backsight is taken to B, an intermediate point set at Q, and a fourth principal p©int-"Bet-«rt- D in the opposite tunnel ap- proach. Intermediate points AT, N, and O are also set from C. This surface line may be from 2,000 to 10,000 feet in length, and yet not have more than half a dozen intermediate points. Frequently the surface is so broken as to require more. The instruments require the most careful and repeated ad- RAILROAD CONSTRUCTION. 037 justments. Mountainous country is especially favorable for making careful adjustments, on account of the long sights which are easily obtained in such localities. Substantial monuments should be set at each of the principal points. A short section of log, cut off square, or a section of sawed tim- ber of equal length, set on end in a pit and bedded in cement mortar rubble, answers this purpose well. The timber should extend three inches above the surface of the ground. On each monument two points are set about four inches apart. At one of these points a vertical hole one inch in diameter by six inches in depth is bored to hold the per- Fig. 424. manent target, which is set up at each of the principal points. A monument corresponding with the above description is shown in Fig. 424, and target in Fig. 425. The target is made of pine or spruce. The shank which fits the hole in the monument and the target are of one piece. The surface of the target is divided as shown in Fig. 425, the inner figures painted either red or black and the outer figures white. The target is set up plumb, the points of the squares of different colors uniting in a vertical line which coincides with the established center line denoted in both figures by the letters C L. Such a target can be readily distinguished with a good instrument at a distance of one mile, and is easily and cheaply made. 938 RAILROAD CONSTRUCTION, 1505. Measuring the Line. — After the line is estab- lished, it is measured, a work requiring great care and re- peated checking. Either of the following methods may be used to obtain horizontal or true measurement: The first method is by the use of a steel tape, plumb-bobs, and spring balance, in which the tape is held in a horizontal position and strained to the same tension at each measurement, the strain being measured by a spring balance. There will be, of course, no uniformity in the length of the sections of line measured, the varying lengths depending mainly upon the degree of the slope. Before the measuring is commenced, stakes are firmly set on line at such distances apart as will permit easy plumbing. A 100-foot standard tape is used, unless the sections are very short, when a 50-foot tape is used. Tacks with small heads are set on line in each stake. In measuring, an allowance of .0000066 part of the length per degree is made for expansion or contraction, according as the temperature at the time of measurement is above or below the normal temperature, which will of course vary in different latitudes. Example. — If a temperature of 50° is assumed as normal and at a temperature of 90° a line measures 72.421 feet, what is its normal length ? Solution.— 90° - 50° = 40°. 40 x .0000066 (the rate of expansion per degree) = .000264, the amount of expansion for each unit of length of line. The line measures 72.421 feet. The total expansion will, therefore, be .000264 X 72.421 =- .019 ft. 72.421 ft. M-.019 ft. = 72.440, the normal length of the line. For measurements of 100 feet or less a tension of 16 pounds is sufficient. This process of measuring is illustrated in Fig. 426. The head tapeman holds the zero end of the tape with the spring balance attached at B. The hind tapeman, standing at A, holds the tape above the stake until it is in a horizontal position. The tape carries a rider containing a spirit level and a small eye through which the plumb-bob cord is passed. There are two rear tapemen. One holds the tape and gives it the RAILROAD CONSTRUCTION. 939 requisite tension, which is reported by the head tapeman at B\ the other directs the raising or lowering of the tape while bringing it into a horizontal position, adjusts the plumb- bob, and reads the tape. The reading is then recorded. The rear tapemen then change places and repeat the work and record the measurements. Each man must read and ^ ""' '" liiiili i a|iMiliii^iiiiliiii|ft ®c rliiiTliiiiljiiir \ E Fig. 427. record his measurements independently of the other, in order that they may the better check each other's work. Accord- ingly they do not call out the measurements, but after each 940 RAILROAD CONSTRUCTION. has read and recorded his measurements, they compare results, and if there is any considerable discrepancy, the work must be repeated. Fig. 427 shows form of tape rider for plumbing tape. It consists of a piece of sheet brass A B, 6 inches in length, an end view being shown at C. It is bent so as to fit closely to the sides and top of the tape when stretched, and slides along the tape. An open slot a d, 2 inches in length, in the side of the rider shows the graduationson the tape. A spirit level D £ is attached to the under side of the rider. To the under side of the bubble tube at its middle point an eye c is attached, from which the plumb-bob /^ is suspended. Directly over this eye and fastened to the rider is a fine point ^, which indicates to the tapemen the precise reading of the tape. The second method of measuring is as follows: The stakes are driven as in the first method, and the slope meas- urements from center of tack to center of tack are taken, the spring balance used, and allowance for expansion or contraction made as in the first method. The levels are then taken between the different stakes, the tack in the top of each stake being taken instead of the surface of the ground, and the slope distances are then reduced to horizontal dis- tances. This method is illustrated in Fig. 428. The distance a b measured on the slope is 68.10 feet, ^^ = 75.111 feet, ^Trt'^z 57.166 feet. The difference in ele- vation between a and b \% a a' ■= 10.811 ; between b and c is (^(^' = 20.42 feet; between c and d is rr' = 20.752 feet. aa' b forms a right-angled triangle, right angled at a\ in which the hypotenuse is the slope distance, 68.10 feet, and the altitude a a' is the difference in elevation between a and ^=16.811 feet. From the trigonometrical formula side opposite , ■ u < 16.811 nAaop sm = -, i-5- , we have sm a o a =^ —r;7r^r- = .24686, hypotenuse 08.1 whence angle a ba' = 14° 17'. The base a' b, which is the horizontal distance between a and b, is obtained by apply- ing the formula tan a b a' = -^ f^ . Substituting side adjacent RAILROAD CONSTRUCTION. 941 known have tan 14° 17' = quantities, we 10.811 .16.811 a' b 1G.811 whence a! b — ,..,.^ 6G. 032 feet. By a similar process we determine the length of b' c, and find that it equals 72.242 feet, and that c' d = 53.272 feet. The total horizon- tal distance between a and d is the sum of a' b-{-b'c-\-c'd = 191.54:6 feet. This method of measurement is possible where the slopes are so abrupt as to render the ^ 1 use of the plumb-bob P J$ practically impossible. ^ ^ 1506. Stationing. — Stations are estab- lished at each 50 feet, and if the surface be very rough, at each 25 feet, in order that a correct pro- file of the surface may be obtained. 1507. Curved Tun- nel Lines. — When the tunnel line is curved, the tangents are made to intersect, if possible, and the angle of intersection is measured with the 942 RAILROAD CONSTRUCTION. transit. The tangent distances are calculated and the P. C. and P. T. located by direct measurement. The work and calculations are repeated many times, and every possible precaution taken to secure perfect accuracy of results. Orad&H-0. 75 Fig. 430. The sketch given in Fig. 429 shows the difficulties attending the laying out of the Rockport tunnel on the Lehigh Valley Railroad. • The original line A B C D followed the course of the Lehigh river, which hugs the bluff E. The tunnel line A F G H \iov\di have been adopted and the tunnel driven when the road was first constructed, but a rival line was building on the opposite side of the river, and there was a RAILROAD CONSTRUCTION. 943 race to reach the Wyoming Valley coal fields and command the coal traffic. The tunnel line was accordingly postponed and the river line adopted. After a lapse of twenty years the tunnel was driven in 1882-3. The neck F G through which the tunnel passes (a profile of which is shown in Fig. 430) reached a height of more than 300 feet. The hillsides were so steep that in places a man could hardly stand. The tangent K F \s the prolongation of the original tangent A K. The grade of the original line was about 20 feet per mile, and as there was a gain in distance of nearly 1^ miles, there resulted a discrepancy in grades at L of about 30 feet. In order to dispose of this difference, the grade on the old tangent A K and on the tunnel curve was increased to 40 feet per mile. In place of the original tangent L D, the tangent G H was substituted, and z.'a G H has a grade of 40 feet per mile against L D oi 20 feet, it will be seen that the two grade lines constantly approach each other. The difference in grade being 30 feet, it required, at a gain in grade of 20 feet per mile, a distance of 1^ miles for the two grades to meet. The tangents A K and G H being estab- lished, they were produced intersecting at M. The inter- section angle G M N measured 57°. A 5° 18' curve was decided upon, and the tangent distances M F and M G measured by direct measurement, and the P. C. and P. T. set. On account of the steepness of the slopes and the height of the hill, much difficulty was experienced in making a satisfactory intersection. Within a distance of 500 feet there was a difference in elevation of more than 300 feet, and, though taking every precaution, some of the sights contained a vertical angle of more than 60°. The lines were run principally in the early morning hours, though some of the best results were obtained on cloudy days. A large tunnel transit with powerful lenses, and of more than double the weight of an ordinary transit, was used. Common pins against a dark background were used for backsights. First an intersection was made, large plugs (6 inches square) being used. The tangent K M was then repeatedly run, 944 RAILROAD CONSTRUCTION. and each line marked on the plugs O and P, Fig. 431, with tacks, each one of which was numbered, as shown in the figure. The lines varied each time, no two coinciding. One or two fell wide of the mark and were ignored. Finally the mean of the lines (as shown by the heavy line in the figure) was adopted as final. The tangent G M was then Fig. 431. Fig. 43a. run an equal number of times, and each intersection on the line O' P' , Fig. 432, marked on the plug Q' with a tack and numbered. The mean of these intersections, as indicated by the heavy line, was taken as final. Equally great difficulty was experienced in locating the P. C. and P. T. The distance was measured many times, and each distance marked. The mean was then taken as the correct measurement. The top of the hill had the form of a plateau, and the center of the curve, O, was located by turning a right angle to the tangent A' F at .F, the P. C, and measuring the radius 1,081.44 feet, locating the center O. The central angle F O G oi 57° was then turned, and the second radius O G run out and measured. The line and measurement falling on the plug at the P. T. at G proved the work correct. The reward for all this care and pains was in the almost perfect alinement of the tunnel. The tunnel was driven from both ends, and when the headings met there was found to be less than a half inch discrepancy in the two lines. 1508. Tunnel Sections. — Tunnel sections vary somewhat, according to the material to be excavated, but the general form and dimensions are much the same. RAILROAD CONSTRUCTION. 945 The general dimensions are as follows : For double track from 22 to 27 feet wide and from 21 to 24 feet high, and Section of Double Track Ttinnel. Section of Sin-^'.r Trn-'k Tunnel. Fig. 433. Fig. 4.34. for single track from 14 to 10 feet wide and from 17 to 20 feet high. See Figs. 4;3o and 434. In seamy or rotten rock the section is sufficiently enlarged to receive a lining of substantial rubble or brick masonry laid in good cement mortar. When the material has not sufficient consistency to sustain itself until the masonry lining is built, resort is had to timbering, which furnishes the necessary support. 1509. Tunnel Driving. — Tunnels in rock are driven either by hand or machine drills. The requirements of modern railroad construction are such that hand drills play a very important part in tunnel work. There are many points in favor of hand drills and hammers, viz., portability, cheapness, and immunity from the accidents which fre- quently cause delays where machine drills are used. But the process is slow, compared with machine work, and time limitations have made the use of machine drills compulsory. 1510. Plant. — The plant for furnishing the com- pressed air used in working the drills consists of a boiler house where steam is generated, and an engine house 946 RAILROAD CONSTRUCTION. containing the engines, air compressor, and air receiver. Both houses are usually under one roof. If the tunnel is short, a single plant, situated near one of the tunnel portals, furnishes power for all the machinery used at both working faces. When the tunnel is of great length, an air compressing plant is stationed at both ends. About 12 horsepower is required to run each drill (drill cylinders 3i to 3^ inches in diameter), and as each tunnel face requires six drills, a 70-horsepower boiler and engine is required to work each tunnel face. When the air is conveyed a great distance, there is some loss of power through friction. A three-inch pipe will carry sufficient air for six drills. The pipe couplings are well leaded to prevent waste of air. 1511. Method of Driving. — When the material is rock, the mode of driving is the following : The tunnel sec- tion is divided into two parts, viz., the heading and the bench. The heading comprises from one-fifth to one-fourth of the entire section extending from the roof downward. It is from G to 8 feet in height, and is kept from 50 to 250 feet in advance of the remainder of the section, which is the bench. The drills working in the heading are mounted upon columns, two drills on each column. The drills work- ing on the bench are mounted upon tripods. The air pipe is carried to within about 50 feet of the bench, where a bench hose of equal diameter is attached to the air pipe, lead- ing directly to the bench. At the end of the hose is a metal nozzle called a manifold, containing hose connections for each of the drills. A section of heading showing arrangement of drill holes in the face is given in Fig. 435. The two middle rows of holes A B and CD converge at an angle of about 20°, nearly meeting on the center line E F oi the tunnel, and are called the center cut holes. The mass of rock included by these holes is wedge-shaped and shown in plan at A in Fig. 43G. The removing of this wedge by blasting i«j called breaking the cut. Fig. 437 shows a longitudinal section through the center cut holes. The rows of holes G, H, A', RAILROAD CONSTRUCTION. 947 and Z, Fig. 435, on each side of the center cut holes, are called side rounds. If but one row on each side, they are Fig. 435. Fig. 437. Fig. 436. Pig. 438. called single side rounds ; if two rows, double side rounds. A longitudinal section through the side holes is Fig. 439. Fig. 440. Fig. 441. FlO.442. given in Fig. 438. The cut and side rounds are loaded at the same time. 'I^he cut is fired first (see Fig. 439), followed 948 RAILROAD CONSTRUCTION. by the side rounds, which are fired either single, i.e., one row on each side of the cut (see Figs. 440 and 441), or double fired, i. e., both rows fired simultaneously, as shown in Fig. 442. 1512. Enlarging the Heading. — In that portion of the heading shown in the preceding figures, the holes are drilled directly into the face of the heading. After the holes are fired and the material removed, side holes are Fig. 444. Fig. 445. drilled at an angle of about 60° with the center line denoted by the letters C. Z., as shown in section in Fig. 443 and* plan in Fig. 444. 1513- Removing the Bench. — The bench is taken out in two sections, B and />', as shown in section in Fig. 445. The full tunnel section is shown by dotted lines. The holes in the bench are inclined backward from a ver- tical line. A longitudinal section through the center line, showing the usual mode of drilling headings and benches, is given in Fig. 440. The center cut holes in the heading // and all the bench holes at B and B' are usually fired RAILROAD CONSTRUCTION. 949 together, followed by double side rounds in the heading. The center cut offers the greatest resistance to blasting. The holes are consequently loaded with more powerful explosives than are used for either side rounds or bench. In driving the New York aqueduct tunnel, the cut was loaded with dynamite containing from GO to 80 per cent, of hitro-glycerine, while the average bench powder contained but 40 per cent, of nitro-glycerine. On some sections, where rock of special hardness was encountered, the cut was loaded with pure nitro-glycerine. This operation is .^;^-.^-~^^ Fig. 446. always attended with great danger. After several prema- ture explosions, resulting in considerable loss of life, the use of pure nitro-glycerine was abandoned. The effect of firing the cut is generally to pulverize the rock, and all tunnel blasting is intended to so break the rock as to render the use of the sledge-hammer unnecessary in reducing masses of rock to sizes convenient for loading. The execution of the powder depends largely upon the judgment used in locating the holes and the angle at which they are bored. The position of the machine while drilling holes at foot of the bench is shown at C, Fig. 446. 950 RAILROAD CONSTRUCTION. 1514. Drainage. — The grade of a tunnel must be established with reference to securing complete drainage. When the grade at both portals is the same, the grade of the tunnel is made to ascend from both ends, the grades being united by a flat vertical curve. The grade of the St. Goth- ard tunnel is 0.1 per cent. ; that of Mt. Cenis 0.05 per cent., but these grades are very light. A grade of 0.25 per cent, will insure complete drainage and need not be exceeded. If the tunnel is short, a continuous grade may be employed. In such a case, if the tunnel is driven from both ends, it will be necessary to remove the water from the descending por- tion by pumping. In tunnels of considerable length, the grade is usually made to ascend from both ends. This pro- vides complete drainage during construction and also i educes the cost of removing the excavated material, as the loaded cars will either run of themselves or with small draft. When shafts are sunk, the water is removed frorn the tunnel by pumping. 1515. Shafting. — When the tunnel is of considerable length, and dispatch in driving is of great importance, ad- ditional working faces are obtained by sinking one or more shafts, each shaft affording two additional working faces. Shafting adds very considerably to ^the cost of tunnel dri- ving; for, besides the cost of sinking the shaft, there is the constant expense of hoisting the excava:ed material to the surface, to which must be added the expense of pumping. On the New York aqueduct tunnel, which has a total length of about 33 miles, a shaft was sunk at each interval of one mile, the shafts varying in depth from 80 to 380 feet. Where shafts are employed, the greatest care and skill are neces- sary in transferring the alinement from the surface of the ground to the tvmnel at the foot of the shaft. 1516. Shaft Lining. — When the shaft is sunk through solid rock, the walls are self sustaining, and no timber lining is required except a curb at the top of the shaft. If, however, the material is earth, loose rock, or shale, the shaft must be timbered. The timbers are put in place as the shaft is sunk. RAILROAD CONSTRUCTION. 951 Frames {se/s, they are commonly called) of timber, shown at A in Fig. 447, are placed about 4 feet apart, and behind these frames, lagging^, of either sawed timber or half round poles split from young trees, is placed on end and in close contact. As each frame is placed in position it is supported by struts footing on the bottom of the shaft, or if the walls are sufficiently firm, the frames are held in place by wedges, Fig. 447. until another set is required, when timber struts C, mortised into the frames, form the permanent support. These struts are placed one above the other, and, together with the frames into which they are mortised, form continuous tim- ber columns extending from the bottom to the top of the shaft. With each set of timbers a horizontal timber D, called a bunton, is placed with ends abutting against the 952 RAILROAD CONSTRUCTION. vertical timber E. A beveled seat with a square shoulder is cut on the vertical timber for each bunton. The buntons are held in place by wedges shown at /^and F' . These wedges are forced between the bunton and the shoulder of the beveled seat. As the wedges are tightened, the bunton is forced downwards until it is perfectly rigid. Vertical tim- bers 6", G' are spiked to the buntons and to the ends of the frames, to serve as guides for the carriage. A detail of the splice of the carriage guide is shown at H and of the wedges at K. As all shafts are moist, and many decidedly wet, iron should only be used in timbering when no substitute can be found. The pressure of earth or loose rock against the timbers is usually sufficient to hold them in place, and most of the joints do not require keying. Treenails (wooden pins) should be used in place of iron. The lagging must be put in place as fast as the work progresses, and all spaces behind it filled with welUrammed earth. In very wet ground or in quicksand, special devices are employed to meet the needs of the situation. Shaft sinking in bad ground is exceedingly dangerous work, and every known precaution is essential if loss of life would be avoided. 1517. Removing Excavated Material. — The ma- terial excavated in tunnel driving is called muck. The muck is loaded into dump cars at the foot of the bench, which, when there is a sufficient descending grade, run by gravity either to the foot of the shaft, where they are hoisted to the surface, or to the dump outside the tunnel. When there is not sufficient grade to run the cars of themselves, mules are employed to haul them. A single track A^ Fig. 448 (ordinarily of 3 feet gauge), is laid on the center line of the tunnel, with passing branches at suitable intervals. At a distance of about 100 feet from the bench a simple switch is built, and two tracks C and D laid to the bench, which permit the loading of two cars at the same time, and provide for shifting cars. On a level with the top of the bench, and directly over the cars, a scaf- fold E is erected, and upon it a runway of planks F is laid. RAILROAD CONSTRUCTION. 953 extending from the scaffold to the heading. The heading muck is loaded into barrows and wheeled on this runway to the scaffold, and emptied directly into the cars. A simple and very effective bench scaffold is made of wrought iron pipe supports and shown in Fig. 448. Each support consists of two pieces of pipe, one telescoping within v^?^^-*/y///y////riu/////////Znc////^////////)i^////////ZZ'iii,'^//^^^ ¥^- .,-C^.JRsx "---■Jiitb ifrajic. -^ Fig. 448. the Other, and provided with clamps by means of which they are adjusted to any desired length. The plank is laid directly upon these pipe supports. The air for working the drills is carried from the air pipe G to the bench by means of the bench hose //. The manifold K attached to the end of the bench hose contains hose connections for all the drills. A ditch L on the opposite side of tunnel from the air pipe drains the tunnel. 954 RAILROAD CONSTRUCTION. 3 5 As the work advances from the tunnel entrance, or from the foot of the shaft, more time is required to haul away the loaded cars and bring back the empty ones. When one mule is no longer able to perform the work a second one is added, and passing branches are built in the main track at suitable intervals, where returning empty cars are switched while the loaded cars are passing outward. A passing branch contains two switches, which are made self-acting by the following simple device, shown in Fig. 449. The points of the switch rails a and b are connected by a clamp rod, attached to a spring c d, which is constantly acting, and holds the point a close against the main rail c f, and the switch is constantly set for the passing branch k I. The switch points ;;/ and fi of the second switch are kept in place by the spring op, the switch being always set for the main track q r. An outgoing car running in the direction r q finds the switch Y set for the main track. Upon reaching the switch X, the flange of the right-hand wheel, pass- ing between the rail e f and the switch point a, forces the switch point b against the rail s /, and the car passes the switch in safety. A returning empty car finds the switch X set for the passing branch k /, and in passing from the branch to the main track, the flange of the head wheel, in passing between the rail u t and the switch point ;//, forces the switch point n against the main rail c f, and the car passes safely on to the main track. The springs c ^and op RAILROAD CONSTRUCTION. 955 are elastic young saplings, kept in place by strong staples driven into the switch ties. 151S. Care of Track. — A common fault of contract- ors and their employes is neglect of track. Usually poor material is furnished, worn cut and crooked rails, poor fastenings, poor ties, and often no ties, requiring every sort of makeshift. With such material a good track is im- possible, and requires constant tinkering. Derailments are continually occurring, involving costly delays. Tunnel tracks should be built of good material and in a thorough manner. Short rails of varying lengths are required in keeping the track well up to the bench. With proper care of tracks, the cars may be kept within easy shoveling dis- tance of the bench. The foreman in charge of the muckers should keep a small stock of ties and rails constantly on hand, together with the necessary track tools, and do his own track work. 1519. Keeping Down to Grade. — The invariable tendency in tunnel work is to keep above grade. The prin- cipal cause is the unconscious effort to avoid the water which is constantly accumulating. This tendency can only be avoided by establishing grade stakes at every 25 feet and keeping the excavation on true lines. The holes drilled at the foot of the bench should penetrate a foot below grade, which will insure the removal of the entire section. Much of the muck in the bottom of the tunnel will require severe use of the pick to remove it. Wedges and a heavy sledge are often of great service in this work. 1520. Timbering. — When the material is rotten rock or earth, the tunnel must be timbered. The timbered sec- tion should be enough larger than the standard section to admit of a masonry lining. When the material is such that the side walls will stand of themselves for a time, hitches A and B are excavated near the springing line and sets of timbers placed as shown in Fig. 450. Iron clamps shown at C and D hold the timbers together while the lagging is 956 RAILROAD CONSTRUCTION. being placed. It is laid over the timbers lengthwise of the tunnel and as close together as possible. • The spaces G, H [Fig. 150. between the lagging and the roof are filled with dry rubble or cordwood. Roof timbers should be either 12 in. X 12 in. or 12 in. X 14 in. in cross-section, and placed with 2 to 4 feet clear space between each set. Where the ground is very soft with a tendency to expand, larger timbers may be necessary. Hemlock, yellow pine, or spruce is commonly used. In special cases, where great pressure is to be resisted, oak is used. When the side walls will not support the roof tim- bers, they are carried on supports arranged as shown in Fig. 451. Four posts A, C, D and i), resting on sills O, P, Q and Ry are mortised into the cap E F. The roof timbers G, H, AT are clamped together as in Fig. RAILROAD CONSTRUCTION. 957 450, and mortised into the cap at spring line. The pressure against the roof timbers is relieved by the struts Z, J/, N^ U, and V, which transfer the stress to the posts C and D and the cap E F. The dimensions of timber given in the draw- ing are such as are used where the pressure is great; they will meet the requirements of most situations. The lagging may be either sawed timber or split poles, obtained by split- FlG. 451. ting in half straight grained chestnut or oak saplings. The backing may be either dry rubble or cordwood. The latter is preferable, as it is light, portable, and uniform in shape. The side walls are all of well-scabbled rubble of good-sized stones, even beds, and laid in courses with cement mortar. The impost courses S and T should be of well-cut stone, twelve inches in thickness and of full width of wall. The arch is either' brick or rubble. The caps and roof struts 958 RAILROAD CONSTRUCTION. interfere somewhat with arching. Holes are left in the masonry where these timbers interfere until a section of the arch is complete, when they are removed and the gaps filled with masonry, the joints being thoroughly grouted. All other timbers are left in place. The spaces /f, Z, etc., Fig. 450, between the arch and roof timbers, are usually filled with concrete. When the material through which the tunnel passes is very soft, with slight coherence, all the energy and skill of engineer and workmen are required to make headway. It is considered the better practice to drive the heading at the bottom of the tunnel instead of the top, as by the time Fig. 452. the heading is driven the ground composing the remainder of the section will have become thoroughly drained, and may be taken out with much greater safety and less expense than with a top heading. The mode of driving a heading through such material is illustrated in Fig. 452, in which A represents a cross-section and B a longitudinal section of the heading, with complete system of timbering. A full section of timbers is called a set^ of which the up- right timber C is called the leg; the horizontal timber D the sill, and E the cap or collar. The short boards F, F, which extend from collar to collar, and are in direct contact with the sustained material, are caUed poling- doards. They are sharpened to a cutting edge, and are driven into the face of the heading with sledges, a wedge-shaped block G being RAILROAD CONSTRUCTION. 959 placed above them to keep them at a proper angle. The planks H which protect the sides of the heading are termed lagging. The flooring K serves to exclude the liquid mud, which would otherwise be forced from underneath by the external pressure. The horizontal cross timber Z, as well as the longitudinal timbers M and A^, are called struts. The floor O serves as a footing for the workmen while driving the poling boards. If the material penetrated is wet enough to run, it is necessary to constantly maintain a bulkhead of planks /*, called face boards, which is held in place by struts Q. As the poling boards are driven forward, the top face board is removed, allowing the released material to flow into the gangway. This forms a cavity in the face of the heading, and immediately another bulkhead is started by placing a face board R in advance of those at /*, with a strut 5 to keep it in place. When the heading is advanced half the length of the poling boards, a new set of timbers is put in place, the collar of which takes the strain from the poling boards, which would otherwise be soon broken by the great pressure above them. As the section is enlarged, other timbers are substituted, until the complete section is excavated. The masonry lining should follow immediately. The less important tim- bers may be removed as the masonry advances, and their stresses transferred to it; but the main supports should re- main in place, and the masonry be built around them, and not disturbed until the arch is keyed. They can then be removed with safety, and the vacancies in the masonry carefully filled and grouted. All open spaces between the masonry and the timber should be filled with well-rammed concrete. 1 521 . Centering. — Tunnel centers are built on much the same plan as those used in arched culverts, a full description of which was given in Arts. 1475 and 1476. 1522. Portals. — Tunnel portals correspond to the face and wing walls of an arched culvert. Usually some 9G0 RAILROAD CONSTRUCTION. regard is paid to architectural effect, the walls being of dressed stone laid in courses. 1523. Alinement and Levels. — During construc- tion, the alinement and levels must be frequently tested. At least once a week the heading should be carefully centered, and a grade stake set at the foot of the bench. In running the center line, plummet lamps are used in- stead of the transit poles used on surface lines. A plummet lamp consists of an oil reservoir of brass of the shape of an ordinary plumb-bob, the stem of which contains the wick. The lamp is suspended by a bail, at the crown of which is an eye for the cord which suspends the lamp. When sus- pended, the cord, the flame of the lamp, and the point of the plumb-bob are in the same vertical line. A man holds the cord against the roof of the heading, moving it right or left until the intersection of the cross wires coincides with the flame of the lamp. A point is then marked on the roof, and a hole accurately drilled by hand to a depth of about three or four inches. A plug of dry pine is then driven into the hole, projecting two inches below the roof. The plug is carefully centered and a screw-eye securely fastened in its center, from which a plummet lamp may be suspended. A piece of copper wire equal in length to the full height of the tunnel is attached at one end to the screw-eye and the other end fastened to the wall of the tunnel. When the full section of the tunnel is excavated, a plumb- bob is suspended from the wire, just touching the floor of the tunnel. A hole is drilled at the point, plugged, and centered, as on a surface line. For bench marks, holes are drilled in the tunnel wall about two feet above the floor, and plugs of either wood or iron are firmly driven and allowed to project far enough from the wall to allow the rod to be held upon them in a vertical position. In testing the grade of the roof, the rod is held in an inverted position, the foot of the rod being placed against the roof. In this case the elevation of the roof is obtained by adding the rod- reading to the height of instrument. For example, suppose RAILROAD CONSTRUCTION. 961 the tunnel section is 24 feet in height, the floor grade at say Station 160, is 240.5 feet and the height of the instru- ment, which is standing on the bench, is 259.6 feet, what should the rod read to give roof grade for Station IGO ? The floor grade at Station 160 being 240.5 feet, the roof grade will be 240.5 feet + 24 feet (the height of the tunnel section) which is 264.5 feet. As the height of instrument is 259.6 feet, the rod-reading for roof grade will be 264.5 — 259.6 = 4.9 feet. A common bulls-eye lantern is used to illuminate the cross hairs, and a small headlight reflector affords the best light for reading the level rod and tape, and for taking notes. 1524. Measuring Excavation. — Various methods are adapted for checking the dimensions of the tunnel sec- Pig. 453. tion and measuring up the work. The best device is the following, shown in Fig. 453. A semi-circular protractor A B oi a diameter from 8 to 10 feet, and made of light pine, 962 RAILROAD CONSTRUCTION. is set up at right angles to the center line of the tunnel. The diameter A B oi the protractor is brought into a hori- zontal position by means of the spirit level C and placed at any desired height above the floor of the tunnel. A sliding rod D E, one end of which is fastened to the center D of the protractor, measures the distances to the tunnel walls on radial lines. The angles which these lines make with the horizontal are read directly from the protractor. The tun- nel section and the actual working measurements are then platted on cross-section paper, from which the amount of excavation is readily calculated. 1525. Plumbing Shafts. — When a shaft is sunk to increase the number of working faces, the process by which the center line is transferred from the surface of the ground to the bottom of the shaft is called plumbing the shaft. Fig. 454 illustrates the process. Two pieces of plank C and D are spiked to the shaft timbers where the center line crosses, the edges of the plank projecting over the shaft wall. Slots E and E are cut in the plank on the center line. An iron plate with a carefully drilled hole in its center is placed over each slot with the center hole exactly on the center line of the tunnel. Holes are drilled in the corners of the plates for screws, by means of which the plates are fastened to the plank. Plumb-bobs weighing from 20 to 30 pounds are suspended by fine steel wire which passes through the eye-hole in the plate. On the shaft bottom a pail of oil is placed directly under each plumb-bob, which is entirely immersed in the oil to check the vibrations. When the plumb-bobs come to rest, the lines which suspend them are exactly in the center line as laid down on the surface of the ground. A transit is set up at / (the tunnel having been driven some distance from the foot of the shaft) and moved until both wires are exactly in the line of sight. A plug is then set on the line at K, after which the instrument is moved to A' and a plug set at /, thus establishing the line. ' RAILROAD CONSTRUCTION. 9G3 1526. Ventilation. — In clear weather, the gases formed by the combustion of the powder used in blasting pass rapidly from the tunnel to the outer air. In heavy weather, and especially when the heading is at a consider- able distance from the portal or shaft, several hours are required to clear the tunnel of powder smoke. Under such conditions the question of ventilation becomes an important one. In order that a man may do effective tunnel work, he should have a supply of 100 cubic feet of pure air per min- ute. And as there is an average force of 25 men in each 964 RAILROAD CONSTRUCTION. heading, the aggregate supply of pure air per heading should therefore be 2,500 cubic feet per minute. A 70-horsepower compressor will deliver to the drills about 500 cubic feet of free air per minute, and there will still be required for ven- tilation the difference between 2,500 cubic feet and 500 cubic feet, which is 2,000 cubic feet per minute. Exhaust fans with air pipes leading to the headings should provide the balance of 2,000 cubic feet per minute. A 24-inch air pipe, carrying air at a velocity of about 10 feet per second, will provide the necessary ventilation. The air pipe should reach as near to the bench as may be without injury from blasts. Contractors are invariably negligent in the matter of ventilation, causing much needless suffering to their men and much loss to themselves. Men can not and will not do full work in a tunnel reeking with powder smoke. Exhaust fans give much better results than blowers, as they remove the foul air and powder smoke direct from the heading, instead of forcing it out through the shaft or portal, as in the case with blowers. 1527. Cost of Tunnel Excavation. — The cost of tunnel excavation varies widely, depending principally upon the character of the material excavated. Firm rock of moderate hardness can be removed at from $4.50 to $0.50 per cubic yard for the entire tunnel section. The heading will cost about 40 per cent, more than the balance of the section, on account of the limited space for working drills and the greater amount of powder required in blasting. Where unusual obstacles are met, the cost may increase 200 per cent, or 300 per cent, over the above figures. Earthy material is easily broken, but the expense and delay in timbering and lining brings the cost to about the same figures as for solid rock. 1528. A Day's Work for a Machine Drill. — An average day's work for a machine drill in heading or on bench is 50 feet of 2-inch to 2^-inch hole. The great records made on the surface of the ground are not possible in tun- RAILROAD CONSTRUCTION. OCTo nels where the accumulated muck from each preceding blast must be partially removed and the roof trimmed before the columns can be set up. Before firing, drills, tripods, bench hose, and scaffolding must be removed to a safe distance, which requires considerable time. 1529. Average Progress in Driving. — Eight sec- tions of the New York aqueduct tunnel gave an average monthly progress of 127 feet for full section of about IG X 16 feet. The average weekly progress in best ten headings, using IngersoU drills, was 38.73 feet, an average of 6. 45 feet per day. Average monthly progress made by IngersoU drills at Vosburg tunnel on the Lehigh Valley Railroad was 202 feet, the tunnel section being about 24 X 26 feet. By hand drills the average monthly progress at the two ends of the same tunnel was 61 and 73 feet, respectively. Material was a hard gray sandstone. A monthly average of 150 feet for a full tunnel section is first-class work. The day is divided into two shifts of ten hours each. There is an hour's interval for changing shifts, and a dinner hour at 12 o'clock noon and 12 o'clock midnight. • 1530. Lighting. — In modern tunnel work electric lights are almost exclusively used. Oil lamps are to be condemned, as they pollute the air. Tallow candles may be used instead. 1531. Track work in Tunnels. — In laying the per- manent track, only first-class material is admissible. As the roadbed is free from the action of frost, the track, after two or three thorough surfacings, should require comparatively little attention, except that given by the track walker. Rock ballast is invariably used. Ditches should be large enough to secure complete drainage. Oak ties are to be preferred, of uniform dimensions, and spaced 18 inches center to cen- ter of tie. Tunnel ties should be of the following dimensions : Length, 8 feet; breadth, 8 inches; thickness, 7 inches. There should be at least 8 inches of rock ballast between bottom of tie and tunnel floor, giving a total thickness of 966 RAILROAD CONSTRUCTION. ballast of 15 inches. When the tunnel lining has an invert, i. e., when the section of the floor is concave, the drain is sometimes built under the track, and covered with flags to prevent clogging with ballast. Side ditches are to be preferred, as they are always accessible and easily cleared. PROTECTION WORK. 1532. Classification. — Under this head will be con- sidered surface ditches, changing channels of streams^ crib work, paving, etc. 1533. Surface Ditches. — Surface ditches are cut at the top of slopes, but at sufficient distance from them to prevent the water from breaking through and washing down the slope. Where the natural slope of the ground is towards the center line and of such a degree that a large proportion of storm water runs off, the surface ditches should be cut before construction commences. When this important precaution is neglected, it often occurs that a great amount of storm water is discharged into open cuts, effectually stopping all work until the water is drained off mi^///////////////'/////^^^^^ Pig. 455. and the ground becomes dry enough to handle. The sight of men and animals floundering in flooded cuttings is too common in railroad work. Many contractors, and especially sub-contractors, are of limited experience, financially irre- sponsible, and generally follow a penny-wise policy. In such cases, the engineer in charge must insist on such precau- RAILROAD CONSTRUCTION. 967 tions being taken as will insure a vigorous prosecution of the work. Ditches are usually paid for at the same price per cubic yard as ordinary excavation. Fig. 455 shows a section of a surface ditch which will meet the requirements of most situations. The line A B repre- sents the natural slope of the ground ; C, the surface ditch ; B D, the side slope of the cutting, and D E, the half width of the roadway. The center line of the road is denoted by E F. 1534. Changing Channels of Streams. — It fre- quently happens when the line of road is parallel to the gen- eral direction of a stream that the windings of the stream repeatedly cross the line of the road. By changing the channel of the stream at favorable points, a great saving is made in the cost of construction. A situa- FIG. 456. tion which warrants the changing of a channel is shown in Fig. 456, in which the located line ABC crosses the stream D G L a.t F and //, requiring an expensive bridge at each point. By cutting a channel across the narrow neck E, both bridges are avoided. Such instances are of frequent occurence. 1 535. Crib Work. — When the foot of an embankment is subject to the erosion of a current of water, as at L in Fig. 456, a crib work of logs and stones is built into the embank- 968 RAILROAD CONSTRUCTION. ment at the exposed point. Protection cribs are ordinarily built of round timber, so combined as to form compartments, which are filled w'th stone to give them stability and with- FlG. 457. stand the action of the current. A general plan of the crib is given in Fig. 457. Cribs serve the purpose both of retaining walls and of re- vetments. Their chief advantage lies in their adaption to situations where the cost of retaining wall foundations would be excessive. They can be readily built on wet, marshy soils or in swift running water. When weighted with stone, the structure sinks, and additional courses are added to the top until the required height is attained. The usual custom is to excavate a pit to a depth of from 12 to 18 inches, the bottom course of rangers, i. e., the logs run- ning lengthwise in the crib, being laid close together. Where there is danger of scour from the current, the outside com- partment is sometimes built with an open bottom. As the water works under the crib, the stone drops from the com- partment above, forming a rip rap which prevents further action of the current. The lower courses of the crib, being kept constantly moist, are free from decay. The earth and sand from the sustained embankment are gradually washed into the cavities in the ballast until the whole forms one compact mass of great strength and solidity. In Fig. 457 A B is the front elevation, the line A B being parallel to the RAILROAD CONSTRUCTION. 969 direction of the current, C D shows a section of the crib, and E the foot of the embankment which slopes away at the natural slope of earth, viz., 1^ to 1. A plan of the crib is shown at F and the foot of the embankment by the broken line G H. A detail of a joint is shown at K. The log Z, corresponding to r j in the elevation, is called a ranger ; and the log il/, corresponding to C Dm. the section, is called a cross-tie or tie. At each joint a drift bolt, usually a piece of f-inch round iron sharpened at one end, is driven to fasten the logs together. The bolt should be of sufficient length to pass through three logs. A hole of slightly less diameter than the bolt is bored to receive the bolt. A compartment filled with stone is shown at O. 1536. Paving. — Paving as applied to protection work consists of a stone covering laid on the surface of embank- ments where they are exposed to the action of water. The paving is usually 12 inches in depth and composed of good- FiG. 468. sized stone of fairly regular shape and even beds, the beds being laid perpendicular to the slope of the embankment, and when finished the whole to present a fairly uniform sur- face. The slope of the embankment should be smoothed and well rammed before the paving is laid. A foundation course of heavy stones A, Fig. 458, is laid at the foot of the embankment in a pit from 12 to 18 inches in depth, depending upon the nature of the soil. When the stream has a rocky bed the foundation course is laid 970 RAILROAD CONSTRUCTION. upon the surface. The profile of the surface of the ground is shown by the irregular line B C\ the earth embankment by D\ the bed of the stream by E F\ the sur- face of low water by G //, and of high water by L M, The elevation of the protected surface is shown at K, with the joints of the stones well broken. The grade of the roadway is indicated by the line N O. ROUTINE WORK. 1537. Routine Work of the Engineer Corps. — The initial work of the construction corps, viz., the checking and betterment of the alinement, the referencing of transit points and cross-sectioning, together with the location and conduct of tunnel work, have already been described. The routine work which occupies the engineers' time from the commencement of the construction to its completion will be considered under one head. 1538. To Lay Out a Culvert at Right Angles to the Center Line, W^hich is a Tangent: The rule for laying out box culverts was given m Art. 1462. The stakes for pit excavations and for neat lines of masonry are arranged as shown in Fig. 459. The broken lines show the outlines of the foundation pit, which extends from six to twelve inches outside the neat lines of the masonry, depending upon the depth of the foundation. Ordinarily six inches is sufficient. The pit should be large enough to permit a thorough inspection of the masonry. The face lines of the masonry are located with the transit. The center line X Fof the culvert being at right angles to the center line P Q oi the road, a plug is set at K, Fig. 459, at the intersection of the center line of the road and the center line of the culvert. The instrument is then set up at K and a right angle turned in the line X V for locating face lines. The height of the embankment at this point is nine feet ; the culvert opening two feet wide and two feet high ; the covering flags are one foot thick, and the parapet one foot high. Then, according to the rule for find- RAILROAD CONSTRUCTION. 971 ing the dimensions of a box culvert, given in Art. 1462, we have 9 feet — 4 feet = 5 feet; 1^ X 5 feet = 7. 5 feet; 7.5 feet + 1.5 feet = 9.0 feet ; 9 feet + 8 feet, the half-width of the roadway =17 feet, the distance from center line of road to the end of the culvert. We then measure on the line X V the distance K L = 17 feet, setting a plug at L. On the same line six or eight feet from L set a temporary point M. Then, set large stakes at A and C, twelve inches from M, in lines at right angles to L J/, estimating the angles by the eye. Measure accurately the distances MA and MC, each twelve inches, and drive a lath nail in both stakes, checking the distance ri 6^=24 inches. Then, reverse the instrument, setting a plug at ^V, 17 feet from K, and a point at O for locating the stakes at B and D, checking the measurements < ip" A tI rrHl -W'i- <^K- l=U *B P Fig. 459. iLj G* -Oo-T as at A and C. Next, set the instrument at iVand turn the angle A'A^//'= 90°. Applying the rule given in Art. 1462, for finding the length of wing walls, we have 2 feet, the height of abutments + 1 foot, thickness of flags = 3 feet; 1| X 3 feet = 4.5 feet; 4.5 feet + 2 feet =0.5 feet, the dis- tance from the face of the opening to the end of wing wall. On the line N //set a stake at H, ten or twelve feet from N, and drive a lath nail in the stake on line. Reverse the instrument, and at the same distance from N set a stake at G, with a tack on line. Next move the instrument to L, and turning a right angle to X V, set stakes at E and F. With these stakes for a guide, the engineer can locate the pit 972 RAILROAD CONSTRUCTION. ■rt t fr- \ corners with the tape alone. A stake is driven at each corner of the pit, and after the excavation is made and the paving is laid, cord is stretched from the tacks in the stakes from A to B^ C to D, E to F, and G to H , marking the face lines. All other needed lines the mason can lay out for himself. 1539. When the Center Line of the Road is a Curve. — On curves, as on tangents, wherever pos- sible, th« center line of the culvert is placed at right angles to the center line C L on the road, i. e., at right FIG. 460. angles to the tangent D E oi the curve at the center D of the culvert (see Fig. 460). The wing walls F and G are parallel to this tangent. The dimensions of a culvert on a curve are the same as those on a straight line, with the same height of embankment. 1540. When the Center Line of the Culvert Makes an Oblique Angle with the Center Line of the Road, i. e., W^hen the Culvert is Askew. — First find what the length of the culvert would be if it were at right angles to the center line of the road. This will give the base of a right-angled triangle, one of whose angles is the angle of skew. The other is easily found by subtracting the angle of skew from 90°. The hypotenuse will be the required side distance. The wing walls must, in all cases, be parallel to the center line of the road. Example. — A railroad embankment is 12 feet in height. A box culvert with opening 3 feet wide and 3 feet high must be built askew at an angle of 70° with the center line. What is the distance from the center line of the road to the center of the opening at the face of the culvert ? Solution. — Let A B, Fig. 461, be the center line of the road, and CD the center line of the culvert, .-/ K C = 70^ being the angle of skew. At A' draw E Fat right angles to A B. From the given dimensions of culvert and height of embankment, we have for a right-angled culvert, side distances as follows: 12 — 5 = 7, H X 7 = 10.5, 10.5 -h 1.5 = 12, RAILROAD CONSTRUCTION. 973 12 -h 8 = 20 feet, the side distance. Lay off on K E the distance KG = 20 feet. Draw G H perpendicular to KG, forming the right-angled triangle K G H, ot which the angle G K H =W and the side K G = Fig. 461. 20 feet. The side length, which is the hypotenuse K H, is found by the formula cos 20° 20 gA'=20feet hypotenuse K H , or hypotenuse K H . 20 cos 20° Tioki;?; - 21.28 feet = the side distance. Ans. .yoyby The wing walls for a right-angled culvert of the given dimensions would have a length of 1^x4=6; 6 + 2 = 8 feet. Their length L M for the given culvert is found by the following proportion : 20 ft. : 21.28 ft. ::8 ft. : L M, 21.28 X 8 whence the length of skewed wing wall L M =^ 20 8.51 feet. Side and wing walls are 2^ feet thick and covering stones 1 foot thick. The dimensions of the foundation pit are pro- portionately the same as in Fig. 459. The stakes for the neat lines of the masonry are located as in that figure. Skewed culverts are of greater length and contain more material than those at right angles to center line of road, and, when arched, they are much more costly to build. Considerable expense may, therefore, be properly incurred in altering a channel so as to obtain a right-angled crossing. 974 RAILROAD CONSTRUCTION. 1541. Borrow Pits. — Borrow pits are excavations made for the purpose of obtaining additional material for embankments when the regular excavation does not furnish an adequate supply. The simplest form of borrow pit is a trench dug parallel to the center line, a space of suitable width being left between the slope stakes and the edge of the pit. This space, or berme, as it is called, should be six feet in width. Formerly, much of the material taken from such borrow pits was handled with wheelbarrows. In modern practice, where the material admits of it, the wheeled scraper is invariably used. The amount of ma- terial needed for the embankment in excess of that fur- nished by the adjacent cuts is readily calculated. This excess is first excavated from side borrow pits and deposited in place, after which the material from the adjacent cuttings is added. Another means of borrowing material, and one which is always adopted where the haul is not too great, is by widen- ing the cuts. In proportion as the cut is widened, the danger of the ditches being filled up by caving embankments or snow is removed. Where embankment is made from material cast from the sides of the road, the berme is rarely more than four feet in width. When the building of a road is only possible through the exercise of the greatest economy, a berme of four feet is admissible, even though it may involve increased expense at some future time. Side work of this kind has been let on some of the cheap Dakota lines at a price as low as 12 cents per cubic yard, with an average height of em- bankment of 2 feet. These lines were built through an unsettled country, and carried the settlers who were to fur- nish the future business for the road. As the country set- tled up and traffic increased, these roads were practically rebuilt. The original grade lines, whenever practicable, followed the undulations of the prairie. In rebuilding, these grades were greatly improved by filling up the sags. On many sections the amount of material added was double that put in the original work. RAILROAD CONSTRUCTION. 975 fi^. loa 1542. Calculating the Contents of Borrow Pits. — Where the entire embankment is made from side borrow pits, the contents of the embankment with an allow- ance for shrinkage is taken as the contents of the pits. This process of measurement saves work and is more accurate than measuring the dimensions of the several pits, especially when they are made with wheeled scrapers which leave the pits in irregular shape. When the cuts are widened for borrowed material, the surface cross-sections are extended far enough to include the additional excavation. After the work is completed, the cross-sections are again taken. Both cross-sections are platted on the same sheet, which, at once, shows the amount of the excavation. Frequently the embank- ment is many times greater in volume than the tributary cuttings, involving an ex- tended borrow pit. In such cases the cross-sections some- times extend several hun- dred feet from the center line. Fig. 462 shows a bor- row pit of this character with the usual form of cross- section. In this figure the proposed borrow pit is situated on the left of the center line, and the cross-sections include an area extending in length from station 100 to station 105, and in width 250 feet from the center line. A bench mark is established at a convenient distance from the bor- row pit, to be used in taking cross-sections for monthly c: S* ® J5 »^ e« © *^ «♦ ©» *j "^ •s *^ •«< Fig. 462. 104 109 102 101 lOOtM lOO 976 RAILROAD CONSTRUCTION. estimates and final cross-sections. The surface levels are taken as follows: Stakes are driven on the center line 25 feet apart, commencing at station 100, and an equal number at corresponding points on a line 350 feet from and parallel to the center line. A rope 250 feet in length, with tags tied at intervals of 25 feet, is stretched from station 100 to the stake at A, 250 feet distant. ' A rod reading is then taken at each 25-foot tag and recorded. The line is then moved forward 25 feet, one end being held at station 100 -{-25, and the other at B, and the levels on this line taken. In the same way the entire surface is covered. This arrangement divides the surface into squares of 25 feet on a side. For monthly and final estimates the cross- sections are taken at the same points, which insures accuracy and greatly simplifies calculation. The surface sections are platted on cross-section paper, and placed far enough apart on the sheet to avoid over- lapping when the monthly and final sections are platted. The cross-sections for each monthly estimate are platted in a different color, excepting the surface and final sections, which are in black. Cross-section books, the leaves of which are ruled like standard cross-section paper, are very convenient for platting sections of borrow pits and special excavations. They may be used in the field, like ordinary note-books, the notes being recorded in pencil, and inked in at the office when leisure time permits. For platting work of this kind, cross-section books are far prefer- able to loose sheets, which are sure to become soiled from repeated use, and, in spite of the greatest care, some are lost. 1543. Checking the Center Line. — During con- struction, and especially on embankments, the center line should be frequently checked, i. e., run in on the incom- pleted embankment. All materials will not at once take the natural slope of 1^ horizontal to 1 vertical. Frequently the embankment becomes one-sided, and a line of centers reveals at once any irregularity. Contractors of ten sustain RAILROAD CONSTRUCTION. 977 a loss on account of material being wasted. It is the duty of the engineer to restore centers whenever they are needed, whether asked for or not. 1544. Grade Stakes. — When the roadway, either in cutting or on embankment, is brought approximately to grade, a grade stake is set at intervals of 100 feet. On embankments the stake is driven on the center line, with its top at grade. In cuttings the stake is driven at the side of the roadway, and a peg is driven near the foot of the stake. The elevation of the top of the peg is taken, and the amount of cutting which must be made below the top of the peg to reach the grade line is written upon the stake. 1545. Care of Stakes. — The destruction of stakes by contractors' workmen, and the disregard of them by contractors themselves and their foremen, is about universal. There is no regularly prescribed penalty for such criminal carelessness. The cost of restoring stakes should be charged to the contractor at double price. A literal enforcement of specifications in minor details, where they might be relaxed to the advantage of the contractor and with no detriment to the railroad company, has caused many a contractor to regret his carelessness in this matter. A trick of dishonest contractors is to move slope stakes nearer to the center line, and so reduce the quantity of excavation or of embank- ment. An alert engineer will soon get the true measure of the contractors under him, and detect deceit of this kind. 1546. Provision for Settling. — Embankments are raised from 5 to 10 per cent, above the established grade to provide for the shrinkage which invariably takes place in all earth embankments. The amount of this percentage is fixed by the engineer in charge, and depends upon the nature of the material composing the embankment. Com- pact clay or gravel will noL settle or shrink more than half as much as soft alluvial soils. 978 RAILROAD CONSTRUCTION. 1547. Overhaul. — Many contracts for railroad work specify the maximum distance to which material shall be transported at the given price per yard. When the distance exceeds that specified in the contract, the excess is termed overhaul, and a clause in the contract stipulates what addi- tional compensation shall be made for each hundred feet of overhaul. Free haul \s commonly limited to 1,000 feet, and for each hundred feet of overhaul an addition of 1 cent per cubic yard is made to the contract price per yard. In recent years the overhaul clause is omitted from most contracts, as it is almost sure to involve litigation. BRIDGE WORK. 1548. The Location of Bridges. — There are two important factors in the location of a bridge, viz., first, the determination of the angle which the center line of the road shall make with the general direction of the channel, and, second, the measurement of the span. In all cases it is desirable that there should be a right- angled crossing, and for bridges of large span the aline- ment is often modified to obtain that result. The amount of such modification, if any, will depend upon the impor- tance and character of the traffic. If the line is for through business where numerous passenger trains are to be run at high speed, the angle of the crossing will be subservient to the alinement; that is, a skewed bridge will be adopted rather than to introduce curvature and mar the directness of the line. Skewed bridges are always more expensive and generally less satisfactory than those crossing streams at right angles. The character of the crossing being determined upon, the next thing in order is the measurement of the span. This may be effected in two ways, and, when practicable, both methods should be used, the one serving as a check upon the other. The first method is by direct measure- ment; the second by triangulation. Before either method is applied, the center line must be accurately checked and RAILROAD CONSTRUCTION. 979 established by fixed monuments set on both sides of the stream. 1 549. Direct Measurement of Span. — The direct measurement of the span is made as follows: A light strong steel wire is stretched from monument to monument, spanning the stream. One end of the wire is fixed so that the wire is either in actual contact with the point in the monument or directly over it. To the other end a spring balance is attached, which indicates by a dial the amount of tension placed upon the wire. The wire is then stretched until the sag is practically removed, and the amount of tension noted. If the wire is not in direct contact with the monument centers, the measurement is found by plumbing from the wire to the monuments. The points of measurement are then marked on the wire and the measurement repeated. The measure- ment should be made at least three times, the wire being subjected to the same tension. As one end of the wire is fixed, any variations in measurement will show at the free end. If the measurements show any considerable variation, the process must be repeated until tJiree measurements practically agree. Two supports are then erected upon a level surface, at a distance from each other equal to the span of the stream, and of such height that the wire w/// clear the groujid when stretched between the supports at the same tension as used in the original measurement. The wire is then stretched with the proper tension, and the points of measurement transferred to the ground by plumbing. The measurement on the ground is made with a standard steel tape, and repeated three times. The average of the three measurements, providing their discrepancy is slight, may be accepted as the correct measurement of the span. 1550. Measurement of the Span by Triangula- tion. — If practicable, the same monuments used in direct measurement are used in triangulating. The first step is the establishing of a base line, which should be of approxi- mately the sajue length as the span, and laid out on as smooth 980 RAILROAD CONSTRUCTION. ground as the situation will permit. The measurement of the base line is made with the greatest care and repeatedly checked. When the ground is practically level the following method is recommended (see Fig. 463): Strong stakes are driven at A, B, C, etc., approximately 100 feet apart, their tops being on the same level and pointed, with a small tack in each stake. The spaces between the stakes are then measured with a steel tape at a tension of about 15 pounds. The measurements are made three times, and the average of them taken as correct. Greater accuracy in measure- ment is secured by having different persons read the tape for each measurement, each recording his own reading, and after the third reading place the three readings in a column and take the average for the correct measurement. The sum of the averaged measurements will be the length of the base line A G. Suppose for this case that they are as follows: 99.892 99.997 99.8963 99.957 99.9466 99.880 699.5689 feet, which gives f.or the total length of the ^<2;jf' //«^ 599. 5689 feet. Let Fig. 464 be the plan of the bridge crossing. A and G are monuments in the center line on each side of the river, and B G the base line^ whose length we have deter- termined by direct measurement to be 599.5689 feet. The angles at A, Z>', and G are measured three times, and the average of the readings taken as the correct reading. It is desirable to use a transit which will read to 10 seconds, On RAILROAD CONSTRUCTION. 981 bridges of great length the angle readings are taken in three sets of five readings each, and the average of all accepted as the correct reading. This mode of angle measurement was adopted in measuring the span of the Washington bridge over the Harlem river, at New York. Suppose that the average of three readings makes the angle at A^ 57° 29' 35"; at B, 59° 01' 03.3" and at G, 63° 39' 20". Their sum is equal to 179° 59' 58.3*, which proves the angle meas- FIG. 464. urement to be practically correct. The length of the side A G, i. e., the span, is determined by the principles of trigonometry (see Art. 1243), as follows: Sin 57° 29' 35' : sin 59° 01' 03.3' :: 599.5G9 : side A G. sin 59° 01' 03.3' = .85733 599.569 X .85733 = 514.028491 sin 57° 29' 35' =.84333 514.028491 .84333 = 609.522 ft. =side^ G. If the temperature of the air in this case were 60° Fahren- heit, it may be considered normal, so that there need be no allowance made for the expansion or contraction of the tape. The base line B G'\s practically parallel to the direction 982 RAILROAD CONSTRUCTION. of the channel current as indicated by the arrow, and the angle at G of 63° 29' 20' will be the angle of skew to which the bridge will be built. i 1551. The Location of Piers and Abutments. — The number of piers to be built will depend upon whether the stream is navigable or not, and upon the cost of founda- tions. If the stream is navigable there must be one channel span of such width as the Government authorities shall determine. When no provision is required for navigation, the cost of foundations alone will determine the number of piers. In general, the cost of bridges will increase about as the square of the span ; that is, if 07ic bridge is of twice the span of an- other, the first will cost about four times as much as the second. If the stream is shallow and its bed of rock or com- pact gravel or clay, suitable for foundations, it will be cheaper to increase the number of piers, and shorten the spans proportionately. 1552. Foundations. — This subject is too broad for any but general treatment. A bridge foundation must meet two conditions, viz., stability and security; that is, it must be able to safely support the maximum load imposed upon it, and must be protected against those natural forces which either periodically or continually attack it. The principal enemies of bridge foundations are the erosive action of the current and floating ice, both of which are most active at high stages of water. Bridge piers, with few exceptions, are of stone. Pier foundations may be divided into three classes, viz., rock ox concrete foundations, ///i" foundations, and caisson foundations. 1553. Rock and Concrete Foundations. — When the bed of the stream is rock or compact gravel, sand, or clay, the pier site is prepared as follows: When of rock, trenches equal in width to the thickness of the outside walls of the pier are excavated to a depth of 12 inches. The bottom of the trench is brought to the same general level, RAILROAD CONSTRUCTION. 983 and a layer of concrete added to furnish an even bed for the masonry. As foundations are generally built at low stage of water, the action of the current is but slight. When compact sand or hard clay forms the bed of the stream, a dam is built enclosing the foundation site. If the water is stagnant and of a depth not exceeding 4 feet, a trench is dug from 12 to 24 inches in depth, enclosing the foundation, and the trench is then filled with clay and gravel, well mixed and thoroughly rammed, forming a wall which is carried above the surface of the water. The enclosed water is then pumped out and the foundation area excavated to a depth of from 12 to 24 inches, depending upon the erosive force of the current and the weight of the proposed pier. The pit is then filled with well-rammed hydraulic concrete, and the masonry laid precisely as on shore. The two lower courses of masonry are stepped outwards, that is, they project beyond the main body of the pier, increasing the bearing surface of the foundation. These footings or offsets are made from 4 to inches wide. The foundation courses should be of larger stones than those composing the main body of the pier. The faces of the pier are usually battered from |- to 1 inch horizontal to 1 foot vertical. Where the piers must resist heavy masses of floating ice, the up stream ends are brought to an edge, forming ice breakers. 1554. Cofferdams. — For depths of stagnant water greater than four feet and for less depths having a current, the clay dam is replaced by a cofferdam. This construc- tion consists of two rows of piles which are driven enclosing the foundation site. The distance apart of these rows of piles, as well as the spacing of the piles in the rows, will de- pend upon the depth of the water surrounding the founda- tion site, and the nature of the material into which the piles are to be driven. The piles will also be required to support a platform, upon which are placed the derricks, hoisting machinery, and building material used during construc- tion. ^84 RAILROAD CONSTRUCTION. The usual form of construction of a cofferdam is shown in Fig. 465. Two rows of piles /*, P are firmly driven, enclo- sing the foundation area. Longitudinal pieces of squared timber Wy Uncalled string pieces or wales are bolted to the piles a little above the water level. Directly opposite the string pieces on the inside of the piles, guide pieces g^ g are bolted, the same bolt passing through both string piece and guide. The guide pieces serve to keep the sheet piles 5, 5 in line while being driven. Cross timbers B^ B called bind- ers are notched down on the string pieces to which they are bolted. The de- positing and ramming of the puddle tend to cause the rows of piles to spread. The bindei:s prevent this and give strength and stability to the structure. The plank flooring e supports the derricks, hoisting machinery, building material, etc. The consistency of the cofferdam filling must be such as to exclude the water, and the weight and strength of the entire structure must be sufficient to resist the pressure of the excluded water. Taking the weight of water at G2^ pounds per cubic foot, the external pressure of the water against the sides of a cofferdam is determined by the following rule (see Art. 976, Vol. L): Rule. — Tlie pressure upon atiy vertical surface due to the •weight of the liquid is equal to the weight of a prism of the liquid whose base has the same area as the vertical surface ^ Fig. 465 RAILROAD CONSTRUCTION. 985 and whose altitude is the depth of the center of gravity of the vertical surface beloiv the level of the liquid. Cofferdams are really retaining walls, which were fully described in Arts. 1486 to 1490, inclusive, and the forces acting against them are the same, though somewhat differ- ent in application. In the case of retaining walls, the backing being of earth or broken rock, only that part of the backing included between the back of the wall and the line of natural slope, extending from the inner foot of the wall upward at a slope of 1^ horizontal to 1 vertical, exerts any pressure upon the wall. In the case of water, however, the particles, hav- ing no cohesive force, all exert pressure against the dam. The center of pressure of the water, like the center of pres- sure of the forces acting against a retaining wall with backing level with its top, is taken at one-third of the depth of the water above the bottom. The direction of the water pressure is at right angles to the face of the cofferdam, and the moment of the water pressure is the product of the pressure found by the above rule multiplied by one-third the depth of the water. The moment of the resistance of the cofferdam, that is, its stability^ or resistance to overturiiing, is the product of its weight multiplied by the distance from the inner toe of the cofferdam to the vertical line drawn from the center of gravity of the cofferdam. Example. — If, in Fig. 465, the length of a cofferdam is 50 feet, its height 7 feet, its thickness 4 feet, and the 'depth of water 6 feet, {a) what is the pressure of the water against the side of the cofferdam ? (b) What is the overturning moment of the water pressure, and the resisting moment of the dam ? (r) What is the factor of safety of the dam ? Solution.— («) 6 x 50 x 3 x 62.5 = 56,250 lb., the pressure against the side of the cofferdam. Ans. ib) In determining the moments of the water pressure and of the resistance of the dam, we take a section of the dam 1 foot in length. The pressure of the water against a 1-foot section of the cofferdam is 6 X 3 X 62.5 = 1,125 lb. Its center of pressure is at one-third the depth, or 2 feet, above the bottom. The moment of the water pressure is, therefore, 1,125 X 2 = 2,250 lb. Ans. Taking the weight of the puddle filling at 130 pounds per cubic foot. 980 RAILROAD CONSTRUCTION. we have for the weight of a 1-foot section 7 X 4 X 120 = 3.360 lb. The moment of resistance of the dam is the product of its weight by the perpendicular distance from the inside toe of the dam to the vertical line from the center of gravity of the section. This peVpendicular distance is 2 feet. 3,360 X 2 = 6,720 lb. Ans. (c) This moment opposes the moment of the water pressure, which we found to be 2,250 lb. The factor of safety of the dam is, therefore, the quotient of 6,720 h- 2,250 = 2.99, nearly. Ans. In this calculation we have ignored the weight of the piles and timber composing the cofferdam, as well as the resisting power of the piles. These would considerably in- crease the factor of safety of the dam. The water pressure per square foot upon the bottom of the enclosed area will be equal to the depth of the water (G feet) multiplied by 02.5, or X 02:5 = 375 pounds. This pressure is resisted by the material composing the bed of the stream and the sheet piling. If the bed of the river is composed of compact sand or clay, little trouble need be anticipated. If, however, the bed consists of loose sand and gravel, special provision must be made to exclude the water. An effective device used by French engineers is the fol- lowing (see Fig. 400) : Two rows of piles P, P are firmly driven. Wales TF, W and guides G", G are bolted to the piles. A row of close piles C of square timber is driven and bolted or pinned to the outside guide. The foimdation area and the space to be covered^ by the cofferdam filling are dredged to the depth of 3 or 4 feet and the entire pit filled with concrete. Before the concrete has had time to set, the inside row D of close piles is driven, their feet pene- trating 2 feet into the concrete. The clay filling is deposited to the depth of one foot upon the fresh concrete and rammed, so there may be a perfect connection between the puddle and the concrete. This work must be done with dispatch. The remainder may be deposited more gradually. After sufficient time has elapsed to allow the bed of concrete to become thoroughly hardened, the water is pumped out of the enclosure. If the pressure of the water is great enough RAILROAD CONSTRUCTION. 987 to lift the concrete foundation, additional weight must be added to keep it secure until the weight of masonry insures stability. P JP Fig. 466. 1555. Pile Foundations. — When the river bed is composed of soft, yielding alluvium extending to a consider- able depth, hut underlaid by a firm soil of ample depth, a pile foundation is commonly adopted. The piles should not exceed in length thirty times their butt diameter, and should be cut from live straight trees. Oak piles are the most durable and strongest; rock elm, spruce, and yellow pine are of about equal strength and durability. The out- line of the proposed pier will to some measure determine the arrangement of the piles, but the general arrangement is always the same, and is as follows: The piles are driven in rows, spaced not less than two and a half feet, center to center, and cover the entire foundation area. In some special cases the outside row of piles is made double, the outer piles projecting beyond the outlines of the pier. The calculation of the bearing power of piles and the various methods of driving are fully explained in succeeding pages. The piles, after being thoroughly driven, are sawed 988 RAILROAD CONSTRUCTION. off at a uniform level at a suitable depth below low water level. A general plan of the pile foundation and the masonry usually adopted for bridge piers is shown in Fig. 407. The dimensions of the foundation from center to center of out- side piles are width 9 feet and length 33 feet, the pier being -*» for a standard double-track roadway. The piles are cut off 4 feet below low water. A timber platform, or grillage, of heavy timbers is built upon the piles, to receive the foundation. First, a course of cap timbers is laid crosswise upon the heads of the piles. The caps are commonly 12 by 14 inches, and notched down 2 inches upon the pile heads, leaving 12 by 12 inches of solid timber above the piles. The caps extend six inches outside the piles, to which they are fastened with 1 inch square drift bolts. Care must be taken that the tops of the caps are on a uniform level. The second course of timbers is stringers 12 by 14 inches laid lengthwise of the pier, and notched down 2 inches on the caps to which they are drift-bolted at each intersection. They are laid close together, forming a complete flooring. A third course of 12 by 12-inch timbers is laid at right angles to the stringers to which they are securely drift-bolted. The top of the grillage should be at least 1 foot below low water. Upon it the masonry is started. In Fig. 467 A shows the side elevation of the foundation and pier; B^ the elevation of the up-stream end of the foundation and pier; C, the arrangement of piles in the foundation, and Z>, the plan of the pier. The courses g and h are the coping courses, the latter forming the seat upon which the bridge rests. The foundation piles are spaced 3 feet center to center. The grillage of timber extends on all sides 12 inches from the centers of the outside row of piles. The first course of masonry is laid flush with the outside of the grillage, and extends on all sides 6 inches beyond the second course. The second course projects on all sides 6 inches beyond the main body of the pier. Beginning with the third course, the north end of the pier gradually develops into a conical-shaped ice breaker, RAILROAD CONSTRUCTION. 989 and in construction consists of the intersection of a cone with a wedge. The curve of intersection is shown in the h f—r ^ . ■; I i' ' \k'^ K.' V k ■'." L.l'.TT-T na iii^:!;:;.k:J''".L,:t-r 2SzE:~zEE^3: £.^ i ,^': :/: te:r - ^. ETE ^S& Ei5 r d a?;:':^r J"lfc-i^;'— -K^l^ - fc r.i^p^::''-^^:":. \ ^V'^^: 't''% m ^;:^x^XM^. :::' - }^ :. ::t . ,j, ,■.:. Af-.f....liy....tl'i- ..R-r.-.-. . ByvK-.-l'-a.- ,1 '; ' ." pf ; "r ;t^'"g^; '! ^::R '2?i? ;^^ lEl 'i^w K;: fe : ii ^ 'fe, !" ^ ^ g^ju-XK.r BJ^Zfey v^^:.k^^E^^ s feW-.V...^.^; IV>S4. Record of Test Holes. — A good form for keeping a record of test holes is given in Fig. 471, which shows a sectional profile, giving the thickness and character of each stratum passed through. The profile given in Fig. 471 is of a test hole driven in the bed of a river. After pass- ing through different strata of sand and gravel, a stratum of hard clay is encountered. After penetrating 9 feet into this clay, any further sinking is unnecessary, since 9 feet of RAILROAD CONSTRUCTION. 995 hard clay will afford a foundation amply strong for any ordinary bridge. 1565. Dimensions of Caisson. — The depth of the foundation stratum will affect the size of the caisson as the faces of the pier are battered, increasing the size of the plan as the depth increases. For example, suppose the neat dimensions of a bridge pier at the top are 6 feet by 30 feet, and all the faces batter at -^ inch to the foot. If the stratum upon which the caisson is to rest is 93J feet below the top of the pier, and the height of the caisson from cutting edge to deck is 13 feet 4 inches, and the deck is to extend on all sides 6 inches outside of the base of the pier, what will be the dimension of the caisson floor ? As the pier faces batter at a rate of -^ inch to the foot, the increase in each dimension will be as many inches as the pier is feet in height. The height of the pier is 93 ft. 4 in. — 13 ft. 4 in. = 80 feet. We, therefore, add 80 inches, or 6 feet 8 inches, to each dimension and we have for the base of the pier, length 30 feet 8 inches, and width 12 feet 8 inches. The caisson deck, which projects 6 inches on all sides beyond the pier base, will have a length of 37 feet 8 inches and a width of 13 feet 8 inches. The sides of the caisson are battered on all sides to reduce the friction of the earth against them during the progress of sinking. The total batter on each side is 12 inches. This batter will give to the base of the caisson the following dimensions, viz., length 39 feet 8 inches, and width 15 feet 8 inches. With the general dimensions of the caisson floor as determined above, the details may be modified to suit special conditions. All caisson plans must meet certain requirements, viz. : There must be adequate supply shafts for admitting men and materials; air pipes for the compressed air, and a con- crete shaft by means of which the concrete used in sealing and filling the caisson may be conveyed from the top of the masonry, where it is mixed, to the caisson ch-amber. Supply shafts are of boiler iron and from three feet to four feet in diameter, depending upon the size of the caisson. The 996 RAILROAD CONSTRUCTION. shafts are built in sections of from four to eight feet, the connections being made by means of exterior flanges, which are bolted together. E %=^^'^ c o ' ^^jr^ Q^ 1 566. Air Locks. — The shafts (usually two in num- ber) are fitted with air locks, by means of which men and materials pass from the outer air to the caisson chamber, and vice versa^ without the escape of the compressed air. The principle upon which the air lock is constructed is explained in Fig. 472. A is the air lock leading to the shaft B^ which extends to the caisson chamber. A person entering the cais- son finds the outer door in th« posi- tion C. He first closes the air cock D, and swings the door shut, the door taking the position E. He then opens the air cock F^ and the air in the lock A receives the pressure of the air in the caisson, forcing the door E firmly against the casing, which is usually fitted with a rubber gasket, making an air-tight joint. The pressure against the door G being removed, it opens of itself, taking the position H. The person is then in direct communication with the caisson chamber, descend- ing to it by means of the ladder K. At the bottom of the shaft is another door, which is closed when the air lock at the surface is removed for adding another section to the shaft. One of the shafts is used for admitting men and tools, the other for removing material. The air lock used in removing material is provided with a windlass, the axle of which has air-tight bearings and extends through the sides of the lock, being fitted with two cranks which are operated by laborers. Most caissons are fitted with a sand pipe, by means of which the pressure of the air in the Fig. 472. RAILROAD CONSTRUCTION. 997 caisson chamber is utilized in blowing out the sand or any fine material excavated in sinking. 1567. Plan of Caisson. — A general plan of a timber caisson is shown in Fig. 473, in which G represents the plan ; H the longitudinal section, and K the cross-section. The walls 6^ and F, enclosing the caisson chamber, are built of three courses of timber 12' X Vl' square. The outer and inner courses consist of superimposed horizontal timbers extending the full length and width of the caisson. The inner course of timbers is laid in an upright position, and extends to within 1 foot of the top of the caisson deck. The timbers in the walls are securely bolted together with drift bolts, each bolt passing entirely through two timbers and penetrating fully 6 inches into the third. As the tim- bers are laid, they are poured with hot coal tar or pitch. At frequent intervals, the horizontal layers of timber are bolted to the upright timbers with screw bolts. The bolt heads must be countersunk and the sockets filled with pitch. Rubber washers are used to insure tight joints. The cutting edge a \s oi \ inch boiler plate, 8 inches in width, and backed by 4-inch oak plank. The walls above the cutting edge increase in thickness with each course of timber, attaining their full thickness of 3 feet in the third course. When the caisson is of great size, longitudinal division walls are built dividing the caisson chamber into compartments. Openings are made in these walls to admit of free communication between the various compartments. The caisson shown in Fig. 473 has not sufficient breadth to require any interior division walls. Struts V of 12' X 12' timber placed at intervals of about 8 feet insure lateral stiffness, and 2-inch iron tie-rods Z fitted with turnbuckles prevent the walls from spreading. The deck consists of six courses of 12' X 12' timbers so laid as to render the chamber as nearly air-tight as possi- ble, and give the greatest possible stiffness and strength to the structure. The first course A forms the ceiling of the chamber, the timbers extending the entire width of the 998 RAILROAD CONSTRUCTION. RAILROAD CONSTRUCTION. 999 caisson. A layer of zinc enclosed between two layers of felt is laid over the entire ceiling course and ceiling, and floated with pitch. The timbers are laid close, with joints filled with pitch and fastened to the walls with heavy anchor bolts. Course B is laid diagonally to course A and bolted to it, a share of the bolts extending into the side walls. The diagonals stop at 6^ feet from the ends of the caisson. The balance of the course is laid longitudinally, with the alternate timbers passing between the uprights and extend- ing to the outside sheathing of the caisson. Course C is laid transversely ; course D diagonally, the diagonal timbers being at right angles to those in course B^ and stopping at ^\ feet from the ends of the caisson, as in course B, and the balance of the course laid longitudinally, as in that course. Course E is laid transversely. Course /% forming the deck of the caisson, is laid transversely, and the masonry is started upon it. An adz is used to give to the outside walls their proper batter. They are sheathed with 4-inch plank, tongued and grooved, the joints of which are filled with either hot coal tar or pitch. The sheathing affords a smooth outside sur- face, which greatly reduces the friction of the earth against the sides of the caisson. The timbers forming the inside walls and ceiling of the caisson chamber are first thoroughly calked and then covered with a layer of 1^-inch hemlock or spruce. This surface is then covered with tarred paper and a second layer of 1^-inch matched spruce boards, with leaded joints. L and M are supply shafts — L for admitting men and tools, and M for removing excavated materials. N is a shaft for admitting concrete for sealing. The small shaft shown between L and N is an air pipe for conveying air from the compressor to the caisson chamber. The pipes /*, Q, and R are sand pipes, by means of which sand and other fine material encountered in sinking may be forced out of the chamber by compressed air. The air lock connecting with shaft L is shown in plan at S, and in elevation at T. It is fitted with exterior flanges, which fit the flanges of the sections of the shaft L. 1000 RAILROAD CONSTRUCTION. Ordinarily the air lock Tis used. When, however, the masonry has reached the height of the air lock T, the air lock d at the foot of shaft L is closed. The air lock T is then re- moved, another section of shafting added, and the lock again placed in position. The air lock d is then opened and the door fastened to the caisson ceiling. The air lock for shaft Mis placed within the caisson chamber at X. This shaft is used in hoisting excavated material, which is placed in buck- ets and raised by a windlass placed on the top of the masonry. The buckets are filled and placed in the lock. Connection with the caisson chamber is then cut off, and the bucket hoisted to the surface. The caisson is usually built near the shore, and when completed it is floated to the pier site, where it is held in position by strong hawsers fastened to cluster piles. The masonry is then started on the caisson deck, and the pres- sure of the air increased as the weight of the masonry causes the caisson to sink. As the caisson approaches the bed of the stream, it must be accurately located, so that when grounded it will take the exact position prescribed for it in the plan. Though of great weight, so long as the caisson floats, its position may be readily changed, but, once grounded, only a slight change of position is possible. 1568. Sinking tlie Caisson. — Once grounded in the proper position, the sinking of the caisson should be pros- ecuted with vigor. Since all excavated material must pass through an air lock, the process of hoisting it to the surface is necessarily slow. After the enclosed area has been excavated to a depth of from 12 to 18 inches, the cutting edge of the caisson is un- dermined to an equal depth. The air pressure is then re- laxed, and the weight of the caisson, together with its load of masonry, causes it to sink until it again rests on a firm footing. When the excavated material is sand, it is usually removed from the chamber by the sand pipe. To effect this a piece of flexible hose is attached at one end to the air pipe near the ceiling. The other end is fitted with a shear valve. RAILROAD CONSTRUCTION. 1001 The sand is shoveled into piles, and the hose brought into direct contact with it. The valve is then opened, and the air pressure forces the sand through the hose and air pipe to the surface, where another piece of hose is attached, which carries the sand outside the masonry. When rock is en- countered it is broken by blasting, and removed in buckets through the shaft. The rock encountered in sinking the caisson of the Washington bridge at New York was drilled with an air drill, the compressed air being furnished by the same plant which supplied compressed air to the caisson. Dynamite was used to break the rock. The caisson was lighted by electricity generated by a small dynamo stationed in the compressor house. When the caisson is situated at a distance from the shore, the compressor plant is placed on a boat securely anchored at a short distance from the caisson. 1569. To Determine the Air Pressure in tlie Caisson. — The air pressure in a caisson must be sufficient to resist two external forces — the one due to the atmospheric pressure and the other due to the pressure of the water. The atmospheric pressure is taken at 15 pounds per square inch. The pressure of the water in pounds per square inch is found by multiplying the depth by .434. The sum of the two pressures will be the amount of the air pressure which must be maintained in the caisson in order to exclude the water. Example. — At a depth of 50 feet, what will be the working pressure in a caisson ? Solution.— .434 x 50 = 21.7; 21.7 + 15 = 36.7 lb. Ans. 1570. Sealing tlie Caisson. — When the caisson reaches a secure foundation the process of sealing at once follows. This process consists in filling the entire chamber with concrete. The concrete is mixed on top of the pier and conveyed to the caisson chamber through the concrete shaft. This shaft or pipe is from 12 to 18 inches in diameter and fitted at both top and bottom with an air-tight door. While charging the pipe with concrete the bottom door is closed. 1002 RAILROAD CONSTRUCTION. When the pipe is full the surface door is shut, the bottom door opened, and the contents of the pipe is discharged with- in the chamber. The concrete is then carried in wheelbar- rows to the extremities of the chamber, which are first filled, the concrete being forced into every cavity. The chamber is completely filled from floor to ceiling, the space about the concrete pipe and shaft being left until the last. When the space has become too small to work in, the workmen leave the chamber, and the remaining space is readily filled with material from the top of the shaft. PILE WORK. 1571. Pile Driving. — There is no subject connected with construction upon which there is so little accurate knowledge. This is partly accounted for by the fact that the material into which piles are driven lies below the sur- face of the ground, and exact knowledge of it is difficult to obtain. Nor will a knowledge of the material into which the piles are driven enable the engineer to accurately measure the forces which give to the pile its bearing power. The bearing power of a pile depends upon two things, viz. : first, the strength of the pile considered as a column, and, .f^^<7«^, the friction of the ground against the sides of the pile. 1572. Pile-Driving Formulas. ^A number of for- mulas for guiding engineers in pile work have been prepared by eminent engineers. Most of these formulas are more or less complicated. Some employ values which are difficult to obtain and are not suited to practical constructors. The fol- lowing formula, published by the " Engineering News," and known as the Engineering Nezas' formnla, is very simple, andean be safely followed under all circumstances: L = '^ (109.) in which L — safe ioadm tons, pounds, or other units; u> = weight of hammer in same unit; /i = fall of hammer in feet; 5 = penetration of pile in inches at the last blow, and as- RAILROAD CONSTRUCTION. 1003 sumed to be sensible at an approximately uniform rate (and head of pile in good condition, i. e. , not split or broomed). This formula gives a factor of safety of 6, i. e., the actual load which the pile can safely carry is only ^ of its total bearing power, and is applicable to all forms of raflroad con- struction from an ordinary trestle to a drawbridge pier or turntable foundation. 1573. Methods of Driving. — There are six methods of driving piles. First Method. — Ordinary method, in which a hammer weighing from 2,000 to 3,000 pounds or more is dropped from a height of from 20 to 30 feet, falling free upon the head of the pile. Intervals between blows, from 5 to 20 seconds. Second Method. — The same as first, except that the ham- mer is attached to rope which is slacked on the winding drum, allowing the hammer to fall. This method permits more rapid blows than the first method, but there is a loss of from 20 to 40 per cent, of the force of the blow, caused by the friction of rope on the drum and the hoisting sheave. It also admits of deliberate deception on the part of the con- tractor, who can check the fall of the hammer by the friction brake, delivering blows of not half the force which the amount of fall would indicate. This method is, however, very convenient and fair if properly used. Third Method. — By Water Jet. In this a stream of water under pressure is ejected at or near the point of the pile, the water rising along the sides of the pile and remov- ing nearly all the end and side resistance, so that the pile sinks by its own weight, though sometimes extra pressure is added. This method is specially adapted to compact sandy soils, and is often efficacious where all other methods fail. Fourth Method. — By Direct Pressure of a Constant Weiglit. This method is applicable to soils of a wet silty nature (practically saturated with water). This method is much employed in dock building at and in the neighborhood of New York. The method is sometimes 1004 RAILROAD CONSTRUCTION. knovina.s pulling down piles. In the mud of the Hudson river, it is almost impossible to drive a pile by ordinary methods, and the process oi fulling is employed by placing part of the weight of a scow as an insistent weight upon the pile, which sinks it into the mud. Fifth Method. — By Nasmyth or Other Steam Pile Drivers. In this the hammer weighs from 3,000 to 5,000 pounds. The fall is short, usually about 3 feet, but the blows are correspondingly rapid, usually about GO per minute. Otherwise the principle is the same as Method 1. Sixth Method. — By Gunpowder Pile Driver. In this each blow is a double one, the first caused by the fall of the hammer, and the second by the explosion of the powder on the head of the pile, which in turn throws the hammer upwards. By this method, there is scarcely any intermission in the downward movement of the pile. 1574. The Striking Force of the Hammer. — In calculating the striking force of the hammer, the resistance of the air and friction is not regarded. The leaders, i. e., the upright timbers between which the hammer works, are supposed to be vertical, and the hammer, held in place by well lubricated guides, falls about as freely as though uncon- fined. Thus, a 3,000-pound hammer falling a height of 20 feet will strike a blow of 3,000 X 20 = 00,000 ft. -lb. 1575. Interval of Time Between Blows. — Blows should be delivered at as nearly uniform intervals as possible, and the driving continued until the pile is completely driven. The effect of an interval of rest of even a few minutes is to permit the ground to settle about the pile, thereby greatly increasing its resistance to driving. This effect is most marked in fine, soft, and wet earth, and least in coarse gravel and sand. When driving in soft, wet soils, the penetration from last blow should not be taken for value of S, but after allowing an interval of rest, depending upon the action of the material upon the piles, the mean penetration from several blows should be taken. RAILROAD CONSTRUCTION. 1005 1576. Effects, of Broomed Heads. — According to best authorities, a broomed head will destroy from half to three-quarters of the effect of a blow, even where the broom- ing is not more than half-inch deep. To apply a formula, it will be necessary to adz or saw off the head of the pile so as to secure the full force of the hammer. Apply the formula to several cases, the average result of which may be depended upon. 1 577. Effect of Driving with Hammer Attached to Rope. — The common practice of driving with hammer attached to rope is to be condemned. The force necessary to uncoil the rope from the drum and the friction of rope on hoisting sheave rob the blow of at least one-fourth of its force. In an actual case in practice, a pile penetrated 0.5 foot with a 40-foot fall of a 2,470 pound hammer with line attached to hammer and slacked on drum; it penetrated 0.7 foot when hammer was allowed to fall free, the gain in penetration from a free fall of hammer being 40 per cent, greater than when the hammer was attached to a rope. 1578. Pile Shoes. — In cases where piles are to be driven through a stratum of boulders, old cribwork, or any substance offering great resistance to driving, resort is frequently had to shoeing the piles with either cast or wrought iron. Common forms of shoes are shown in Figs. 474 and 475. The shoe in Fig. 474 is of wrought iron, the point Fig. 474. Fig. 475. Fig. 476. Fig. 477. being fastened to the pile by spikes through the strap s. The shoe in Fig. 475 is an inverted cone of cast iron. The bolt 1006 RAILROAD CONSTRUCTION. «, which fastens the shoe to the pile, is of wrought iron, the cone being cast around it. The fiat base of the cone affords a good bearing for the foot of the pile. The practice of shoeing piles has of late years fallen into disuse. In a great many instances where shoes have failed, piles cut off square have driven fairly well. Shod or pointed piles are liable to cant or drive at an angle. In average ground a pile cut off square at the point will drive better, truer, and almost as rapidly as when pointed. There are, however, situations where either shoeing or pointing is absolutely necessary. 1 579. Pile Hoops. — To prevent the pile from splitting while driving, the head is surrounded by an iron hoop from one-half to one inch thick and from 1^ to 3 inches wide, as shown in Fig. 47G. They are, however, an uncertain security, especially in hard driving, when often the pile splits below the hoop and bulges to such an extent that it must be cut off before the driving can be continued. 1580. Slight Penetration Often Indicates Poor Driving. — When the penetration caused by a high fall of a heavy hammer is less than one-fourth inch with oak or one-half inch with soft wood piles, there is danger of over driving. A common mode of failure is shown in Fig. 477. 1581. Spacing Piles. — Bearing Piles, i. e., those used for foundations, should not be spaced less than three feet center to center; those spaced less than 2^ feet are worse than wasted. Where piles are overcrowded, the soil either becomes churned to a liquid mass or so compressed that those already driven are forced upwards while others are being driven. This effect sometimes occurs where the surface soil is underlaid with quicksand or soil of a buoyant nature, even where there is no overcrowding. A remedy for this trouble is often found in driving piles with the large end or top downwards. Where a considerable area is to be piled, those at the center should be driven first, then working towards the outside of the area. Where the reverse order is used, the soil of the enclosed area often becomes so compressed that piles can not penetrate it. RAILROAD CONSTRUCTION. 1007 1582. Computing Loads. — Calling the average weight of masonry two tons per cubic yard, piles spaced three feet center to center will carry a wall of masonry from 50 to 75 feet in height. Piles spaced 24 feet center to center will support a wall of masonry from 75 to 100 feet in height. Greater loads are not warranted by good practice. Where a greater mass of masonry is required, the founda- tions should be stepped out so as to admit another row of piles, thus distributing the pressure over a greater surface. Example. — A double row of foundation piles carries an 18-inch masonry wall. The piles are spaced 3 feet center to center, i. e., as shown in Fig. 478, and driven with a 1,000-pound hammer, until a fall of 15 feet causes a penetration of one-fourth inch. What height of wall can be safely carried by the piles ? Solution. — By formula 109, L — -^ — -, we have Z, safe load in tons; w, weight of hammer = .5 ton; h, height of fall of hammer = 15 feet; 5, last pene- tration = \ inch. Substituting these values in the formula, we have L = fig. 478. — ^ — = T^o^^ ^^ tons, i.e., each pile will safely support 13 tons. .^5 -f- 1 l./wO Each yard in length of the wall is supported by two piles, which together can safely carry 24 tons. Taking the average weight of masonry at two tons per cubic yard, such a foundation would support an 18-inch wall 72 feet in height. Ans. Modern depot buildings often carry roof trusses, which tax foundation piles to their safe limit. 1583. Trestle Loads. — In computing loads for pile trestles it is not too great an allowance to assume that the entire weight of the driving wheel base falls upon each bent, or row of piles, in succession. Suppose, for example, a bent of four piles is driven in building a trestle for heavy railroad traffic. In driving, a hammer weighing 3,000 pounds is given a free fall of 30 feet, and suppose the average penetration for the last three blows for the different piles is as follows: 1008 RAILROAD CONSTRUCTION. First pile, ^ inch; second pile, | inch; third pile, f inch; fourth pile, f inch. Applying formula 109, L = c- i i > ^^ have Of 1 A( 1. -1 r 2X1.5X30 90 tons ^^ ^ ^ Safe load for 1 st pile, L = = — — - — = 60. tons. . ~|~ X i. cf 1 A( ^A -1 r 2X1.5X30 90 tons ^_ ^ Safe load for 2d pile, L = — — = = G5. 5 tons. . O i O ~\~ X 1. o / o „ - , . , _ , ., J. 2 X 1.5 X 30 90 tons _. . ^ Safe load for 3d pile, L = — ^,^ , ^ — = ^ ^.^^ = 5o. 4 tons. .bJio -|- 1 l.u«o o i: 1 /If ^^u -1 r 2X1.5X30 90 tons „^ . Safe load for 4th pile, L ■= — = — — — — = 51.4 tons. Total safe load for four piles 232.3 tons. Taking the weight on wheel base of a consolidation engine at 48 tons, which load each bent must successively carry, and dividing the combined safe load of the four piles, viz., 232.3 tons, by 48 tons, the weight on the wheel base, we have a quotient of 4.84, i. e., the bent is able to safely carry 4.84 times as great a load as it will ever be required to carry. The above values of JS" are much smaller than can be obtained in many soils. Often the penetration from the last blow is several inches. If, however, the piles are allowed to stand 24 hours and the earth to settle firmly about them before being tested with the hammer, it will usually require two or three heavy blows to start them. Supposing the average penetration for the last three blows on the above given piles had been, respectively, 2 in., 3 in., 3^ in., and 2J in., the safe loads would have been the following, viz., 30 tons, 22.5 tons, 20 tons, and 24 tons, and the aggregate safe load 90.5 tons, which, divided by 48 tons, the weight on wheel base of locomotive, gives a quotient of 2.00 -[- , i- e., the trestle can safely carry twice as great a load as will ever be required of it. 1584. Piles Acting as Columns. — Piles penetrating through soft, yielding material into a comparatively hard, unyielding material act as columns, and should be given a RAILROAD CONSTRUCTION. 1009 factor of safety not less than six. Assuming the weight of hammer at 3,000 pounds and the fall 20 feet, we have a blow of 3,000 X 20 = 00,000 ft. -lb., and for penetration of 1 in., 2 in., 3 in., 4 in., 5 in., and 6 in., the safe load in pounds by our formula is 00,000, 40,000, 30,000, 24,000, 20,000, 17,143 lb., respectively, which is about ^ of the ultimate breaking load of a 10-inch column of wood of a height of 8 feet, 14 feet, 18 feet, 21 feet, 24 feet, and 20 feet, respectively. Where the length of the column without side support is greater than this and the safe load by the formula is less, in the same proportion will the safe load given by the formula ex- ceed the safe load of the column, i. e., the safe load indi- cated by the penetration will be in excess of the load which an unsupported column can carry. 1585. Pile-Driving Machines. — Pile-driving ma- chines are of two general classes, viz., land machines and floating machines. In both classes the framework of the pile driver is essentially the same. This framework consists of the upright timbers called the guides or leaders which hold the pile in position and between which the ham- mer rises and falls, the wooden bracing of the leaders, and the iron stayrods for the same. The machinery for hoisting the hammer may be either a simple crab-winch or a stationary engine, or horse power may be used. For all important modern work a hoisting engine is used. The land machine (see Fig. 479) rests on longitudinal sills A, A, which in turn rest on rollers^. The hoisting machinery, contained in the house C, and the coal and water supply D and £ are well to the rear of the frame- work. When a row of piles is driven, they are cut off at a fixed elevation and capped and temporary or permanent stringers laid. The pile driver is then moved forwards on its rollers, the leaders F projecting far enough beyond the last bent to reach the line of the next row of piles. The engine, boiler, coal and water supply, resting on the rear end of the framework of the machine, serve as a counterweight. The side braces 6", G extend nearly to the heads of the 1010 RAILROAD CONSTRUCTION. leaders, and foot upon the cross timber //, where they are securely braced with timber knees A', K. The back braces Z, J/, and N are bolted at top to the leaders and at bottom to the sills O and /*and to the cross timber Q. The main back braces L are fitted with rounds, forming a ladder, by Fig. 479. means of which ascent is made to the hammer sheave R. Stayrods 5 and 7", fitted with turnbuckles, extend from the heads of the leaders to anchorages in the sills at the rear end of the framework. The hammer rope ^^ winds on a drum not shown in the drawing. The brackets Fand W RAILROAD CONSTRUCTION. 1011 support cross-bars upon which the hammer rests when not working. The sizes of the timbers will depend upon the character of the work to be done and upon the length of the piles to be driven. The floating machine (see Fig. 480) is carried on a power- fully built scow A of light draught. The machine shown is of the latest model, and the heaviest in New York harbor. The hull is 56 feet 6 inches long and 23 feet 6 inches wide over all ; each of the sides of the hull is made of four pieces of yellow pine, the two lower 8 X 14 inches, the third 7 X 14 inches, the top piece 6 X 14 inches, all securely tied by through bolts. The bow planking is oak 5 inches thick ; the bottom and end plank, yellow pine 3 inches thick. The bow is further strengthened by a 16 X 16-inch cross timber at top, and at the stem is an 8 X 12-inch cross timber of yellow pine. Oak is used on the bow as being better adapted to stand the con- stant wear of the piles hauled against it. To prevent knots or inequalities on the piles from interfering with their posi- tion under the hammer, the bow planking overhangs 6 inches in its total height. The hull is especially designed to obtain longitudinal stiflf- ness so that the strain between the bow and engine may be properly distributed. To attain this end the hull is strength- ened lengthwise by four longitudinal bulkheads, or keelsons /", each 6 inches thick and braced laterally by four sets of X braces g, made of 6 X 6-inch timber. The hull is further braced in the center by two 3 X 12-inch yellow pine braces //, and tie-rods or " log chains " k of iron If inches in diam- eter. Wale pieces and fender plank / 3 inches thick protect the outside of the hull against chafing; the deck has a crown of about 6 inches in its total width. The leaders in, in are made of two pieces of 12' X 12' yel- low pine 67 feet long from out to out, with inside guides ;/ of 4 X 5-inch stuff protected by plate iron one-fourth inch thick; five-eighths inch bolts with countersunk heads fas- ten the inner guides to the main sticks and at the same time secure the iron work to the same. The bottoms of the leaders 1012 RAILROAD CONSTRUCTION. are connected with the 12 X 12-inch bed pieces o by two timber knees not shown, and are tied at the top by the cap/. The arrangement of the back braces q, r, and s is clearly shown in the elevation. Their dimensions are, respectively, 6 X 12, 5 X 10, and 5 X 12 inches. They are of yellow pine Fig. 480. and securely bolted at the top and bottom with seven-eighths inch bolts. The side braces « and v are of round timber 16 inches in diameter at butt, and each anchored to the hull by two heavy timber knees. The bed pieces o are fastened down to the hull by four bolts each one inch in diameter, the forward bolt passing through the 16 X 16-inch oak piece w on the RAILROAD CONSTRUCTION. 1013 bow, and the after bolts passing through a cross timber x^ 6 X 14 inches. The bottoms of the back braces are secured to the bed timbers by 1-inch strap bolt in each timber, the strap portion of the bolt being 2 inches x i inch in section. A seven-eighths inch through bolt ties the three braces together. The iron stayrods running from heads of lead- ers to the after part of hull are two in number, and each one inch in diameter. The hoisting sheaves on top are two in number, placed side by side. They are 12 inches in working diameter, 15^ inches from out to out, and 3^ inches wide, and the pin passing through them is 2|- inches in diameter at the sheaves and 2 inches in diameter in the boxes. These dimensions are none too great to stand the severe work frequently put upon the sheaves in hoisting heavy weights and tearing out timber. The fall or hammer rope is 2 inches in diameter, and the "runner " used in hoisting up piles is If inches in diameter. The hoisting engine is double-drummed and of nominally 25 H. P. The detail of the hammer, shown at E, gives a clear idea of its general design. The weight is 3,300 pounds. 1586. Sheet Piles. — In building cofferdams for foundations and often in protection work, piles are driven in close contact to prevent leakage. Such piles are called LXlXiOj I«g^g3 Fig. 481. Fig. 482. sheet piles. Sheet piles are always of sawed timber. Where the water is shallow and without a current, 2-in':h planks will be sufficient. As the depth of water and pressure 1014 RAILROAD CONSTRUCTION. increase, the dimensions of sheet piles increase. Usually they are thinner than they are wide, but frequently they are of square timber and as large as bearing piles, and are then called close piles. . To make sheet piles drive close together at foot, the points are sharpened as shown at/* in Fig. 481. Any lateral move- ment is prevented by the wales o, o. To keep the edges at top close to those already driven, a dog iron, such as shown at a in Fig. 482, is often used. A cut of a standard sheet pile driver is given in Fig. 483. A general plan of cofferdam illustrating the use of Fig. 483. sheet piling was given in Fig. 465, Art. 1554. The frame is light, and readily shifted by hand. The hammer A is oak. It is raised by the rope B^ which works in the single pulley C. The hammer is usually worked by hand, three or four laborers generally being sufficient. 1587. Cost of Pile Driving.— The following figures on the cost of pile driving are taken from reports published in the Engineering Nezvs : RAILROAD CONSTRUCTION. 1015 O H o a H GC o o Q PQ Q O PQ < O H :» O u a> o o c ■> o . S CO 00 c i CO J:^ CO 00 r- d CO 1— 1 '* ii rH lO - ■1 Ci T— 1 CO CO CO «& »0 r- ■t «> j>^ 1— 1 5 -t- - ^ (U o >o C > >o S o '^ a J O? T— 1 O '^ CO cj O^ CO 00 *j t- >o c : « - CO CO lO 1 > «& »0 T- ^ t- -^ r-l s * 4& "^ ;;i C 1^ o o c ; O »0 W5 li- 5 >0 -t< CO O* 1-1 2 « £J ce O ?> 00 (7? T— I T— 1 O 00 -+ CO Q •§ m lO CO -1 iio 4& i> CO i>^ >. »C (T? i^ CO o o >^ o O £- t- • ^ -H CO c^ ^ I— 1 leBr n La: GO 4-> t-> o ■M 3 Cfl C >-< ■M C ■"* tn •'"' bo _C bo C c ■1- 'S c be 'c CT C t 'rt ki 'c ■< 'S B c 4- a o Vk. ^ 'rt V u c b c D c s u c hJ _»- 3 (L) t/5 y m *^^ 'S 'c u U o CO c 1) 13 I D 4-1 C 0) <4-l *^4— t o c o 2 re k. ■4-1 •J" o ■t-t ■4- 4-> Vi _0 C 'r 'C S bo C b VM b b, C C- bo b 3 &, 3 a] .£ c ^ , rt 0, rt 3 u ^•£1 ■1- c 3 4-> o > 4- 1, > 4-> o 4-> CA Ph C XT. e ;^ e <: <: O 1 C . 1) CO C5 ti .K c (U kn ^ 3 c« bo be > > C/3 ^ 1016 RAILROAD CONSTRUCTION. Cost of Piles. — At Chicago, and points on the Mississippi river at and above St. Louis, pine piles cost from 10 to 15 cents per lineal foot, according to length and location. Soft wood piles, including cottonwood, rock elm, etc., can be had at any point for from 8 to 10 cents per lineal foot. Oak piles 20 to 30 feet long cost from 10 to 12 cents per foot ; 30 to 40 feet long, from 12 to 14 cents; 40 to 60 feet long, from "20 to 30 cents per foot. The tables of cost which follow are for various classes of work. Railroad Construction. — The accompanying table of cost is exclusive of first cost of piles and of the expense of hauling. Piles used in construction of the Chicago branch of the Atchison, Topeka and Santa Fe Railroad. Piles were driven ahead of the track by a horsepower drop hammer weighing 2,200 pounds. Average depth driven, 13 feet. Table includes cost of driving piles for foundations of Howe truss bridge, and for false work used in the erection of same. The contractor received the same price for all classes of work. . The work was varied, the piles being driven into all kinds of soil. Wages for labor were high, and as follows: Foreman, $4 per day; six laborers, at 12; two teams at $3.50; total cost for labor, 123 per day. Work in progress in the year 1887. Number of piles included in report 4,409 Number of lineal feet included in report. . . .109,578 Average length of piles in feet 24.8 Number of days employed in driving 491 Number of lineal feet driven per day 223.2 Cost of driving, per pile $2.53 Cost of driving, per foot 10.2 cents Bridge construction, Northern Pacific Railroad bridge over Red River, at Grand Forks, Dakota, constructed in 1887. Soil, sand and clay. The penetration under a 2,250 pound hammer, falling 30 feet, was 2 to 4 inches. The foreman received $5 per day, stationary engineer $3.50 per day, and laborers $2 per day. RAILROAD CONSTkT:fCTlON. 1011 In the construction of a railroad in Southern Wisconsin during 1885- 87, the contract price — the lowest competitive bid — for piles in place under the piers of several large bridges, averaged as in the following table. The piles were driven in a strong current and sawed off under water; hence, the comparatively great expense : CONTRACT PRICE FOR FOUNDATION PILES. Kind of Driving. Contract Price per Lineal Foot. Material of Pile. For Part Remaining in Structure. For Pile Heads Sawed Off. Rock Elm Pine Oak Oak Ordinary Ordinary Ordinary Hard 40 cents. 40 cents. 48 cents. 50 cents. 15 cents. 20 cents. 25 cents. 30 cents. ESTIMATES. 1588. Calculating Cross-Sections. — Cross-sections are the basis of most calculations employed in determining the amount of material handled in grading the roadway. A full description of the method of taking and recording cross-sections was given in Arts. 1457 and 1458. The cross-section notes are copied into a Qtia^ttity Book, and the total end areas of the cross-sections, together with the partial areas representing the classification of the material as determined by the excavations, are placed in regular order. On the same line, under their proper headings, are placed the quantities of the different materials excavated between .the two points of the line where the cross-sections are taken. The common practice in calculating quantities from cross-sections is to multiply the mean or average area in 1018 RAILROAD CONSTRUCTION. square feet of two consecutive sections by the distance in feet between them. Thus, let A represent the area in square feet of one sec- tion; B, the area in square feet of the next section; C, the number of feet between the sections, and Z>, the total num- ber of cubic feet in the prismoid lying between these sections. Then, by common practice, /) = ^±^XC. (IIO.) Example. — Two consecutive cross-sections are 50 feet apart. The area of one is 150.4 square feet, and of the other is 191.3 square feet. What is the volume of the included prism ? Solution. — Substituting the given quantities in the above formula. we have volume = ^^^-^ + ^^^-^ X 50 = 8.542.5 cu. ft. = 316.39 cu. yd. Ans. 1589. The Prismoidal Formula. — A more accurate result is obtained by the use of the prismoidal formula. In applying the prismoidal formula to the calculation of cubic contents, it is requisite to know the middle cross-section between each two that are measured on the ground. The dimensions of this middle section are the mean of the dimensions of the end sections. Calling one of the given sections A, the other B, the average or mean section M, the distance between the sec- tions L, and the required contents S, we have, by the prismoidal formula, S = ^{A + 4.M+B). (111.) In calculating the cubical contents of the prismoid in- cluded between the following sections, both methods of cal- culation will be used and the two results compared. The sections are represented by Figs. 484 and 485, and are denoted by the letters y^i and B. The perpendicular distance between them is 50 feet. The section given in Fig. 484 is composed of the four triangles a, hy f, and d. The triangles RAILROAD CONSTRUCTION. 1019 a and b have equal bases of 9 feet, the half width of the roadway; hence, if we take half the sum of their altitudes and multiply it by the common base we shall have the sum of the areas of the triangles a and b. The triangles c and d have a common base "8 feet, the center cut of the section, and if we take the half sum of the side distances and multiply it by 8 feet, we shall obtain Fig. 484. Fig. 485. the areas of the triangles c and d. Taking the dimensions of section A given in Fig. 484, we have Area of triangles a -{- b = — '—^ — X 9 = 80. 1 sq. ft. 21 8 -I- 14 Area of triangles c -^ d = — '-^ — X 8 = 143.2 sq. ft. Total area of section A — 223.3 sq. ft. Taking the dimensions of the section B given in Fig. 485, we have 1020 RAILROAD CONSTRUCTION. 9 7 -j_ 2 2 Area of triangles a'-^ d'= —- — f- ^ — X 9 = 53.55 sq. ft. Area of triangles c'-\- d' — — '■ — ^ — — X 5 = 74.75 sq. ft. Total area of section B = 128.3 sq. ft. AT f ^- ^ A n 223.3 + 128.3 _^ ^ Mean area or sections A and z> = ir = 175.8 ^^ sq. ft. Contents of the included prismoid = 175.8 x 50 = 8,790 cu. ft. =325.6 cu. yd. In applying the prismoidal formula we calculate the area of a section midway between the given sections, and for its dimensions we take the mean of the dimensions of the given sections. These dimensions will be as follows: Center cut, 8 + 5 = 6.5 ft. R.ight side distance, — ^^^^r — — = 12.6 ft. Left side distance, — '- — ^ — '— = 20.25 ft. With these dimensions, construct the section M shown in Fig. 486. Fig. 486. The area of section M is computed by the same method as that used with sections A and B in Figs. 484 and 485, and is as follows: RAILROAD CONSTRUCTION.* 1021 Area of triangles a' + b" = "*"' — -X 9 =66.6 sq. ft. on 9_1_ 19 R Area of triangles c' -^d" = I^ x 6.5 = 106.6 sq. ft. Total area of section M= 173. 2 sq. ft. Denoting the distance between the sections by Z, and the cubical contents of the prismoid by S, we have, by applying the prismoidal formula 111, S=^{A+4.M+B). Substituting known values in the formula, we have S = y (223.3 + 4 X 173.2 + 128.3) = 8,703 cu. ft. = 322.3 cu. yd. Ans. Comparing the results, we have By averaging end areas, contents = 325.6 cu. yd. By prismoidal formula, contents = 322.3 cu. yd. A difference of about 1 per cent. Fig. 487 represents a mixed section of which the part a b c \^ solid rock, the partcde/is loose rock and the part d e g h is earth. The slope a c in solid rock is ^ hori- zontal to 1 vertical. In a section where the excavated material is classified, the foregoing methods of computing areas can not be employed except to check the aggregate area, and when the slopes vary with the different materials other methods must be entirely used. Where there is no indication of rock, the slope stakes are set to the usual slope of 1 horizontal to 1 vertical. If rock is encountered before the rock excavation is commenced, the slope is contracted to ^ horizontal to 1 vertical. It has been customary to plat irregular sections on cross section paper. The original or surface cross-sections are first platted, and when the top material (usually earth) has been removed, a cross-section of the remaining material is taken and platted on the original sheet, the lines being 1022 RAILROAD CONSTRUCTION. drawn in colored ink. If there is still another classification of material, as shown in Fig. 487, a final cross-section is taken and platted in lines of a separate color. The different colored lines at once indicate the outlines of the various materials and assist in checking the calculations of the partial areas. The original cross-sections and the fin- ished section should be in black, the others in distinct, sep- arate colors. The partial areas are easiest calculated by dividing them into triangles and carefully scaling all dimensions not given. hyCut 13' Fig. 487. In Fig. 487 we have, remembering that the slopes of /^ and c Ji are 1 to 1 : Total. 9x3 = 18.0 sq.ft. 18.0 sq.ft. 9X1 = 9.0 sq.ft. 11X2.1 = C3.1 sq.ft. 10x2.1 = 21.0 sq.ft. Area of triangle a b c oi solid rock = Area of triangle b e /oi loose rock = Area of triangle b e k oi loose rock = Area of triangle c b koi loose rock = Area of triangle c d /& of loose rock =13.2x1. lo= 15.2 sq. ft. 68.3sq. ft. Area of triangle rt'*? ^'- of earth =27.2x1.65= 44.88 sq. ft. Area of triangle ^/^^ // of earth =34. x2.2=74.8 sq. ft. 119.7sq. ft. Total area of section 206.0sq. ft. 1590. Quantity Books. — Quantity books spoken of in Art. 1588 are of various forms. The following is rec- ommended. It contains station and cross-section notes of Fig. 487, together with the end areas: RAILROAD CONSTRUCTION. 1023 w fa *-> (U 4; 'O ^ fe tn (sj 'B 3 en ^ ^.1^ _u 3 y '+-» CJ hJ Pi C CQ 3 a j2 fa a! oj *-) 4) 4-> !- fa V' 3 cr t3 ^ U3 00 cc CO Pi I— 1 in 3 cd < 8 8 CO CO c J ^ W ji £- i^ ct! T— 1 fa 1—1 *j Si iO I— 1 Pi 2 3 J C u ^ a c 00 3 , C 3 ii CO ci u I— t 1—1 J ^ 11 ll •uoji B^S c K > 1024 RAILROAD CONSTRUCTION. This form of notes includes both left and right-hand pages of the book, and the classification of material meets the re- quirements of most railroad work. When the material in- cluded between two consecutive cross-sections is of the same character, the prismoidal formula should be used in calcu- lating the cubical contents of the. included prismoid, but when the sections are classified, as in Fig. 487, the mean area of each material shown in both sections should be taken and multiplied by the distance between the sections. When one kind of material, such as rock, shows in one section and not in the next following, the point where that particular material ends should be determined and the distance from it to the section containing rock should be measured. This mass of rock will be considered either as a pyramid or a wedge, according to its form. When of wedge form, its vol- ume is the product of its base by one-half its altitude or length, and when of pyramid form its volume is the product of its base by one-third its altitude or length. The partial and total areas of each section are placed on the same line under their proper headings. As the number of the station at which each cross-section is taken is given in the station column, the distance between any two sec- tions is readily found by subtraction. The quantities are carried out on the same line as the end areas and placed under their proper headings. Thus, in calculating the ma- terial between Sta. 50 and Sta. 50 -f- 50, place the quanti- ties on the Sta. 50 + 50 line, which is next below Station 50. When a page of the quantity book is filled, add the several columns of quantities which are given in cubic feet, and re- duce them to cubic yards by dividing by 27. At the end of each mile section a blank page should be left in the quantity book. A summary of the total yardage of each kind of ma- terial handled in the grading of the section is then made out and placed on this blank page, together with the contract price and value of the work. Wherever a trestle or cul- vert occurs, a space should be left in the quantity book at the proper station, large enough to contain a sketch and estimate of the materials for the same. Spaces should alsq RAILROAD CONSTRUCTION. 1025 be left for borrow pits and any special excavation. All these partial estimates will appear in the summary in proper order. The following will serve for a guide: SUMMARY OF QUANTITIES. SECTION lO. Excavation. Earth 10,000 cubic yards @ 20c $2,000.00 Loose rock 1,500 cubic yards® 40c 600.00 Solid rock 850 cubic yards @ 80c 680.00 Borrow 2,000 cubic yards @ 20c 400.00 Masonry. First-class .... 190 cubic yards @ 110.00 $1,900.00 Second-class ... 220 cubic yards @ 6.00 1,320.00 Rubble 270 cubic yards® 4.00 1,080.00 Rip-rap 300 cubic yards ® 60c 180.00 Paving 120 sq. yd. @ 90c 108.00 Piling. 4,000 lineal feet @ 30c .^ $1,200.00 Trestle Timber. 100,000 feet board measure, in work @$30 $3,000.00 Iron. 3,000 pounds @ 4c $120.00 Total cost of grading, masonry, and trestling on Section 10 $12,588.00 1591. Monttily Estimates. — On or about the last day of every month during the progress of construction, measurements are taken to determine the total amount of work done and materials furnished up to that date. It is frequently necessary to take measurements for both monthly and final estimates at other times than the closing days of the month. This is especially the case in foundation work where the masonry is started as soon as the excavations are completed. When the roadway has been completed, the 1026 RAILROAD CONSTRUCTION. monthly and final estimate will be the same. The quanti- ties are taken directly from the quantity book, where end areas of sections and volumes are carefully calculated and carried out in regular columns. An approximate estimate is made of all work in progress, care being taken to make it as exact as the nature of the work will allow. A special field book is used for monthly estimates, in which a description is given of the particular work or struc- ture measured, together with the date of measurement. The notes consist principally of the cross-sections of incompleted roadway. Wherever the roadway is completed to grade, the word " completed " is commonly written opposite the station and the quantities computed from the original cross- sections. Notes of foundation pits are made doubly clear by a sketch of the excavation with dimensions marked on the outlines. All special work, concerning which a misun- derstanding may possibly arise, must be particularly described. Materials, such as lumber, stone, etc., furnished by the contractor and not put into any structure at the time the estimate is taken, should be measured and the amounts placed under the head of temporary allowances^ the price allowed being somewhat less than the actual value of the material as delivered. Blank forms are used by the resident engineer in reporting monthly estimates. In these forms a column is provided for each of the different classes of material and work contained in the contract. The stations are numbered in the first col- umn in regular order, and opposite each station in the proper column the amount of excavation, masonry etc., is written. An estimate is made for each particular mile section into which the line of railroad is divided for letting. The resident engineer should keep, in a separate book, a record of each monthly estimate. The monthly estimates are forwarded to the division en- gineer, who reviews them, copying the footings of the several RAILROAD CONSTRUCTION. 1027 columns into a separate book in which the sections of his di- vision are placed in regular order. The prices are affixed to the quantities and the total amounts carried out. From the totals, the amounts of previous estimates are deducted, and the remainder is the amount due the contractor for the month. From this amount a certain percentage (usually 15 per cent.) is deducted to be reserved by the company until the completion of the contract. A summary of the monthly estimate is then forwarded by the division engineer to the chief engineer for auditing and approval. 1592. The Final Estimate. — The final estimate is a complete statement in detail of the amount of work done and the materials furnished in the construction of the road, and is the basis of final settlement between the company and the contractor. It should be commenced as soon as con- struction is under way and continued as fast as the necessary data may be collected. Full notes must be kept of each particular structure and complete measurements taken while the work is under way and the circumstances fresh in mind. This is particularly important in the case of bridge and culvert foundations and other structures, either under water or covered with earth at the completion of the work. These sketches and notes will be recorded at their proper station in the quantity book described in Art. 1590. When the work is completed, a final summary is made containing the aggregate quantities of the entire line. Full notes are kept of all classified materials and of all material affected by length of haul (providing a haul clause occurs in the contract) and arranged in the order in which the work occurs on the line. The calculations for final estimate limit the monthly estimates and guide the engineer in making approximate estimates of either work or material. TRACK WORK. TRACK LAYING. 1593. There is no department of modern railroad engineering which is receiving so much attention as the care and maintenance of the track. In the great strife for business, freight and passenger rates have been reduced to a minimum, and to meet these conditions speed and train loads have been nearly doubled. These conditions demand a good track. A track to be good must be laid on sound ties, well ballasted and surfaced, full spiked and bolted, and in perfect line and surface. 1594. New Road. — In America practically all newly constructed railroad is built of new material throughout, though the cross-ties are often cheap and the rails light. CROSS-TIES. 1595. Cross-ties are of wood. Their size and variety of timber will depend upon the locality and financial ability of the railroad company. The best ties are of white oak. The following list gives in a descending scale the com- parative values of woods for cross-ties : Hard Wood. Soft Wood. White Oak. Red Cedar. Rock Oak. Black Cypress. Burr Oak. White Cedar. Chestnut. White Cypress. Southern Pine. Tamarack. Walnut. Butternut. Cherry. White Pine. Red Beech. Hemlock. Red Oak. Spruce. 1030 TRACK WORK. It is generally accepted that hewn ties are superior to sawed ties. The surface of a well-hewn tie is a series of comparatively smooth surfaces. The effect of the ax is to close the pores as the chip is removed, which tends to exclude the moisture. The effect of the saw is exactly the reverse of the ax. While given, an average smoother surface, it tears the fiber of the wood, leaving the pores open. These minute broken fibers which cover the entire surface of the tie act like sponges in attracting and retaining moisture, and eventually hasten decay. 1 596. Importance of Seasoning. — Too little atten- tion is paid to the seasoning of cross-ties before they are laid in the track. This is especially true on newly con- structed lines where scarcity of capital and the necessity for keeping down expenses compel the use of the cheapest material and methods. Cross-ties thoroughly seasoned will last fully one-quarter longer than those used while green, and they are better in every way. Well-seasoned wood will hold the spikes better and resist the shearing tendency of the rails due to passing loads better than green ties. The most favorable months in Northern lati- tudes for cutting ties are August, December, Janu- ary, and February. Dur- FiG. 488. ing these months there is comparatively no movement in the sap of the trees. The ties should be hewn to uniform thickness and piled in square* piles about 4^ feet in height, as shown in Fig. 488, so as to admit of the free circulation of the air and to hasten the seasoning process. 1597. Specifications for and Inspection of Cross-Ties. — Specifications should include dimensions, and kind and quality of timber. Ties for standard gauge tracks should be from 8 to 9 feet in length, from 6 to 8 inches in thickness, and show not less than 6 inches of face. The TRACK WORK. 1031 standard tie is 8 feet 6 inches in length, 7 inches in thick- ness, and shows at least 7 inches of face. In the Northern, Middle, and Western States, log ties, i. e., ties cut from entire trees and showing two rounded sides, are principally used. In the Southern, Atlantic, and Gulf States, yellow pine ties are in almost universal use. They are square hewn and made of heart timber, not more than 1 inch of sap being allowed on the corners. In Southern latitudes, where the process of decay goes on throughout the year, sap timber is almost worthless. The sap timber soon softens, the spikes loosen and the rails cut into the wood, leaving the track in a dangerous state. In those portions of the South where oak is abundant, oak ties are much used. They are generally square hewn. This is a mistake, especially if the ties are cut from young thrifty trees (and no other timber should be used), since a considerable portion of the weight of the tie is sacrificed in squaring. This lost weight is all needed to give stability to the track. The ties should be cut off square and to uniform lengths, and be of a uniform thickness throughout their entire lengths. Before being inspected, they should be delivered along the right-of-way of the rail- road and piled in regular piles, each tie showing both ends. Ties are commonly graded as firsts and seconds. The in- spector carries a brush and pot of paint, marking each class of ties with a distinctive mark. Firsts are usually marked by a full circle, and seconds by a cross. PREPARATION OF A ROADBED. 1598. It is a rare thing to find a new roadbed in proper condition for track laying. Often it is in poor surface, being left by the contractors in a rough, uneven state. If the track is being laid in heavy, wet weather and .the ties are being distributed by teams, the wheels are sure to cut deeply into the roadbed, and unless some precaution is taken to bring the tops of the ties to a uniform surface, there is great danger of the rails being bent by the passage of the construction train. 1033 TRACK WORK. 1599. Track Centers. — Center stakes marking the alinement are driven at intervals of 100 ft. on tangents and 50 ft. on curves, where the degree of curve does not exceed 12°. On curves exceeding 12°, stakes should be driven at intervals of 25 ft. A tack is driven in each stake, marking the center of the track. Grade stakes for surfacing ties should be placed at intervals of 10 ft. A straight edge placed upon these stakes marks the grade for the inter- vening ties. The ties are bedded with earth taken from the roadbed and tamped with the shovel. The placing of grade stakes so close together is contrary to common practice, but the increased labor for the engineer is more than compensated for by the saving of the time or- dinarily consumed in sighting in ties where grade stakes are set at intervals of 50 or 100 ft. The surface is sure to be better where the straight edge is brought into use, and the danger of kinking rails or bending them out of surface is obviated. 1600. Track - Laying Machines. — Track - laying machines have been used to some extent. The ties, as well as rails and fastenings, are carried on cars. With some machines they are conveyed to the front on rollers; in others, on an endless belt which runs along the sides of the cars. The process of track laying is as follows: Two rail lengths are laid, bolted, and partially spiked, and the ties partially bedded. The cars are then run forwards and the process repeated. The progress of track laying with a ma- chine is limited by the amount of track which can be full bolted, spiked, and made fit for the running of trains, and ranges from 1 to 1^ miles per day, 1 mile being a common average. Economy in the force of track layers and the saving of team work are the principal advantages claimed for track-laying machines. In mountainous country, where the roadbed is difficult of access to teams, the track-laying machine has decided advantages over ordinary methods, but in open country where the roadbed is readily accessible, both ties and rails should be hauled by teams. With TRACK WORK. 1033 material distributed a considerable distance in advance of the construction train, a much larger force of men may be economically employed. If the track laying is to be rushed, the track-laying machine must take second place. 1 60 1 . Track-Laying Outfit. — Before starting out to lay new track on a new road, the boss track layer should make requisition for all the tools necessary for expeditious work. These tools are loaded on a car and shipped to the point where work is to be commenced. Everything should be in readiness for making a good beginning before the men are brought on the ground. Any lack of proper tools is cer- tain to cause awkward and often serious delay, and opera- tions must often be suspended until the lack can be supplied from headquarters. The following list of tools will amply supply a force of 100 track layers, with a reserve for extra men in case they should be needed, and will be sufficient to take the places of tools worn out or broken until a supply can be brought to the front : Hand cars 1 Steel cars 3 Push cars 2 Shovels 150 Picks 50 Lining bars 12 Claw bars 12 Tamping bars 12 Nipping bars 24 Cold chisels 24 Rail punches 6 Chopping axes 6 Hand axes 6 Striking hammers 42 Bush scythes and snaths, . each 3 Hand saws 6 Adzes 6 Track gauges 12 Covered water barrels. . . 2 Track levers 2 Chalk lines 2 Spirit levels 6 Tape lines. 6 Nail hammers 3 Monkeywrenches 3 Lanterns, red 3 Lanterns, white 3 Water pails 6 Tin dippers 6 Oil cans 2 Oilers 3 Gallons of oil 2 Pick handles 24 Nails, 10 penny, kegs ... 1 Nails, 20, 40, GO penny, kegs, of each 1 Cross-cut saws 3 1034 TRACK WORK. Adz handles 6 Ax handles 6 Maul handles 30 Red- flags 12 Sledges, 16 lb. each 2 Grindstones 1 Track wrenches 24 Iron tongs, pairs 3 Rail forks 6 Expansion shims 200 Switch locks 6 Rail drills 2 Torpedoes, dozens 4 Track jacks 4 Rail benders 2 Curving hooks 2 Post hole diggers 2 Tie poles, 30 ft. long 2 Tie lines, 1,000 ft. long. . 1 Sets double harness 1 Sets single harness 1 Sets double and single- trees, each 1 Wagon 1 Scraper 1 Horses or mules 2 Tool boxes 2 Files 6 l:J^-inch rope, feet 300 Car accommodations for track laying should be the following : One supply and office car. One kitchen car. Two dining cars. Three sleeping cars. Where track laying is being done a long distance from the base of supplies, a blacksmith with forge and tools should accompany the outfit. 1 602. Distributing Ties.— When ties are distributed along the foadbed by teams, they are strung out in proper numbers, so that the labor of carrying them to their place in the track may be as light as possible. The largest of them are reserved for joint ties, the joints being located by measuring from the ends of the rails already in place in the track. By measuring with a 30-foot pole, the joints of rails may be accurately located, a small stake driven marking each joint. This practice admits of the placing of ties several rail lengths in advance of the rail, thus affording working room for a much larger force than could otherwise be handled. A tie line for lining the ends of the ties is spaced at the proper TRACK WORK. 1035 distance from the center line and stretched taut, being fastened at suitable intervals by well-driven stakes. Joints should not be located at any considerable distance in ad- vance of the rails, as the measurements are likely to vary a little and soon accumulate an error. These inaccuracies are obviated by checking the measurements frequently from the ends of the rails already in place in the track. Care must be taken to place the ties at right angles to the center line. Ties laid askew prevent proper gauging of the track. Ties should be assorted with reference to thickness in order that those of uniform thickness may come together in the track, thus greatly reducing the labor of bedding. 1603. Bedding Ties. — As soon as the- ties are dis- tributed and lined they are bedded for the rails. The process is as follows : The straight edge is placed on the grade stakes and the faces of the ties brought to a uniform surface by first sinking those which are above grade and then raising those remaining to grade by throwing dirt or ballast under them and settling them to the correct level. It has been a general and most pernicious custom to spike the rails to the ties without bedding. Most rails will be found to carry from one to a half dozen swinging ties, some of which are sure to get skewed before the ballast secures them. The track is full of undulations and as the foundation is rough and uncertain, many of the rails are kinked or surface-bent by the passing construction train. Where ties are bedded, the spiking can be better and more expeditiously done, and the construction train can follow at once with entire safety. If the track is to be ballasted with cinders or broken stone, the ties must not be bedded, in order that the ballast may occupy all the vacant space in the roadway. Nevertheless, the dressing down of uneven places in the roadway before distributing the ties is time and money well spent. The ballasting must be kept well up with the track laying if kinking of the rails is to be avoided. 1604. Organization of Forces. — The foreman in charge of track-layers should thoroughly organize his forces, 1036 TRACK WORK. placing each man where his work will give the best results. Spikers and iron men are first choice. They should be alert, sober men, and should be paid higher wages than the rest, as upon their efficiency depends the excellence and progress of the work. The prospect of promotion which is thereby held out to the others promotes the industry and discipline of the entire force. A small surfacing gang immediately follows the track- layers. Any scarcity of men at the front can be supplied from this gang, and any extra men at the front can at any time be profitably added to the surfacing gang. 1605. Locating Joint Ties. — The foreman should detail two trustworthy men to locate the joint ties. They carry a measuring pole of the standard rail length, usually 30 feet, and locate the joints by measuring from the ends of the fixed rails. They also complete the work of spacing the intervening ties, which can not be done until after the joint ties are placed. TRACK JOINTS. 1606. There are two forms of rail joints in general use, viz., suspended and supported. Both forms have merits peculiar to themselves, but both are rarely found on the 1^ Fig. 489. Pig. 490. same road, either one or the other being used exclusively. A cut of a suspended joint is given in Fig. 489, and of a TRACK WORK. 1037 supported joint in Fig. 490. In the suspended joint there are two joint ties spaced about 6 inches in the clear. The joint is spaced midway between the ties, which should be carefully selected, have broad faces, and be of uniform thick- ness throughout. In the supported joint the tie is placed directly under the joint. The angle splices A and B, which are shown in section at C, vary in length from 24 to 36 inches. Those 24 inches in length have 4 bolts, and those from 30 inches upwards have 6 bolts. A joint to be perfect should have the same strength as the rail itself, but such a joint has not yet been devised. A vast amount of time and money has been expended upon the development of rail fastenings. Iron chairs and fish-plates, once in universal use, have disappeared. The angle splice shown in section at C, Fig. 489, is generally accepted as the best rail fastening yet invented. The prerequisite of a good rail fastening is a strong shoulder which will closely fit under the head of the rail, and a broad base closely fitting the base of the rail and extending its entire width, reaching down so as to bear upon the tie. The plates do not fit closely to the web of the rail, H 3^-0- — ->f ae FIG. 491. but are curved as shown in the section C. The holes in the plates as well as those in the rails are oblong so as to admit of the expansion and contraction of the rails due to changes of temperature. Bolts should be of a size suited to the weight of the rail, though there is small danger of getting them too heavy. Track bolts are usually fitted with nut-locks of either metal or fiber. Trackmen should avoid straining the bolts when setting up the nuts. A half turn of the wrench after the nut has come to a bearing is sufficient. Though there are still some railroad men who strongly adhere to the supported joint, yet general experience has abundantly proved the 1038 TRACK WORK. superiority of the suspended joint. The angle splice in gen- eral use on trunk lines is 3 feet in length, carries 6 bolts, and complete weighs from 40 to 60 pounds. The joint is sus- pended, and the ends of the splices also come midway between ties, as in Fig. 491. The angle splices should be slotted and spikes driven through them into the tie to prevent the creeping of the rails. In the suspended joint there are two slots in each splice, as shown in Fig. 489, and in the supported joint but one. Spike slots in the rails are not admissible, as they prevent the full expansion and contraction of the rails. RAILS. 1607. Care in Unloading Steel. — Rails are often bent in consequence of careless handling. There is no ex- cuse for either foremen or workmen for this. The rails are unfit for laying until straightened, but they are often laid in a bent state, giving a bad surface and line. The surest remedy is proper Jiandling. The rails are always loaded properly at the rolling mill, and the kinks are put in them either in transfer or in delivering on the grade. When rails are to be transferred from one car to another, rails of suit- able length should be used as skids upon which the rails to be transferred are pushed from one car to another. When from scarcity of flat cars, rails are shipped in box cars, rollers are placed in the end doors of the box car, and the rails are rolled as they are transferred. The rails should always be placed in regular order, as shown in Fig. 492. hmPs^ Fig. 492. Fig. 493. In unloading, there should be enough men to handle the rails with ease and dispatch. The rail should be lifted clear TRACK WORK. 1039 of the car floor and carried to the edge of the car. All should be ready, and at the word, the rail dropped clear of the car so that it will fall in the position shown in Fig. 493, in which position the danger of kinking is entirely avoided. Other men should stand on the ground removing each rail as soon as it drops, so that one rail shall not fall on top of another. Rails must not be dropped from the cars on rock or loose stones, but on dirt, which will insure their safety. None but the best men should be employed on the steel car. They should be strong physically, understand plain English thoroughly, and be prompt and active. When men, because of difference of nationality, fail to readily understand each other, confusion is sure and accident almost certain to follow. The same gang of men should handle all the steel. If the track laying is to be rushed, at least two, and better three, steel cars should be provided, which permits of one being constantly at the front. As soon as a load of steel is transferred from the flat car to the steel car, a team of horses should be hitched to it and the car hauled to the front. The steel men at the front, having unloaded their car, return with it until they meet the loaded car. They then lift their empty car from the rails to the side of the track, allowing the loaded car to pass. The steel men push the loaded car the balance of the way unless the grade is heavy enough to require a team. Steel cars should be light and strong, and capable of carrying a heavy load. The car should be of such weight as to be readily handled by the steel crew. The wheel base should be 8 inches in width, so that the car may pass safely over rough and poorly gauged track. 1608. Straightening Rails. — If from any cause, rails should be bent, they should be carefully straightened A Fig. 49^. before being placed in the track. If kinked, i. e., bent lat- erally as shown in Fig. 494, they may be straightened by 1040 TRACK WORK. nicking the flange of the rail with a cold chisel on the con- vex side of the rail at the point A where the bend is the sharpest. Then, laying the rail on its base, a few sharp blows with a sledge on the side of the head of the rail at the point A will remove the kink. Kinks may also be removed by means of a rail bender or Jim crow, shown in Fig. 495. The jim crow consists of two heavy hooks Fig. 495. a and d, which fit over the head of the rail. The curved barV, which unites these hooks, is drilled at its crown, and threaded to receive the screw d. The cross-bar i- unites with the two hooks a and d, and serves as a guide to the screw c/. Force is applied to the screw by means of the wrench /y having a long handle. If surface-bent, as shown at A in Fig. 496, they are easiest Fig. 496. Straightened with the jim crow. The straightening of the rails befoi;e laying will avail but little unless the ties are TRACK WORK. 1041 well bedded, and all of the rails given a good bearing when the track is laid. 1609. Curved Rails. — Rails laid on curves should always be curved before being placed in the track. When laying track on new road, it is a much better policy to curve the rails in the material yard before forwarding to the track- layers. The material foreman should have a list of the curves in the same order in which they occur in the track. He should be able to determine the middle and quarter ordinates of a 30-ft. rail for any degree of curve, and should curve each rail accordingly. His list of curves will give the station of the P. C. and P. T. of each, from which he will determine the length of each curve and the number and length of rails required for each. These rails should be marked with the number of the degree of the curve for which they are intended, and the rails for each curve should be kept separate from the other rails by pieces of board, so as to prevent any confusion when they ar- rive at the front. One 29|-foot rail is laid for each 6° of angle in the curve; hence, for a curve with a central angle of 30°, the number of 29|-ft. rails re- • J • 30 . quired is — = o. 6 In laying the track, the short rails should be equally dis- tributed throughout the curve. The rails are curved either with a rail ben- der, shown in Fig. 495, or by the aid of a track lever and curving hook, shown in Fig. 497. The latter process is as follows : A fig, 4»7. tie A is placed under each end of the rail B which is to be curved. A hook C is placed under the main track rail 1042 TRACK WORK. between two ties, at about 6 feet from the end of the rail to be curved. The track lever D is then let into the hook C^ and the men pry down upon the rail B, giving it the required curve. The quarter points should always be curved before the center, as it often happens that the center curves with the quarter points, thus saving time. The practice of curving rails by dropping them across two ties, or pounding them with a sledge hammer, can not be too severely condemned. By the former method, an angle instead of a curve is often put in the rail, and sledging is liable to break a rail outright, or, at least, put a flaw in it which may result in actual fracture when laid in the track. Some of the worst accidents on record have been caused by broken rails, weakened by hard usage while being curved. The following table contains a list of curves and tangents and the number and lengths of rails required for each. With such a list, the material foreman can forward the rails curved and assorted. His facilities for curving rails should be of the best, and with a skilled gang of men he can turn off much more and better work than would be possible at the front : MATERIAL FOREMAN'S LIST OF RAILS. No. of No. of Station. Deg. Curve. Central Angle. 30-Ft. Rails Re- quired. 29i-Ft. Rails Re- quired. Remarks. 40 + 90 End of track. 25 -f 50 P. T. 43° 12' 29 7 20 + 10 P. C. 8° L. o 35 14 + 80 P. T. 10+ 60 P. C. G^ R, 25° 12' 24 4 1610. Assorting Rail Lengttis. — Rails of different lengths should never be laid promiscuously. The short TRACK WORK. 1043 rails should be piled by themselves in the supply yard and forwarded to the track-layers in such order and numbers as they may require. On curves, as the inner rail forms a smaller circle than the outer rail, it is sure to gain, and to maintain the joints in the same relative position, this gain must be compensated by the use of short rails. A list of the curves and the number of short rails required for each should be given to the supply foreman, whose business it is to forward the track material in the order named on the list. This table shows how the material foreman makes out his list. EXPANSION AND CONTRACTION. 1611. In laying track, provision must be made for expansion and contraction of the rails, due to changes of temperature. As the temperature rises the rail lengthens, and unless sufficient space is left between the ends of the rails to allow for the expansion, the ends of the rails abut one against another with such force as to cause the rails to kink or buckle, marring the appearance of the track and rendering it unsafe for trains, especially those running at high speeds. If, on the other hand, too much space is left between the rails, the contraction or shortening of the rails due to severe cold may do equally great harm by shearing off the bolts from the splice bars, leaving the joints loose and unprotected. The coefficient of expansion, i. e., the amount of the change in the length of an iron bar due to an increase or decrease of 1° F. is taken at .00000686 per degree per unit of length. Example. — If an iron rod measures 30.015 ft. at a temperature of 90°, what is its normal length, assuming 60° as the normal tempera- ture ? The temperature of the bar must be 90' — 60° = 30° above the normal temperature. Solution.— As the increase in length is .00000686 ft. per degree for each foot in length of the bar, the total increase for 1 foot of the bar due to a rise of 30' in temperature is .00000686 X 30 = .0002058 ft., and for 30 ft. the increase in length above the normal is .0002058 X 30 =^ ,006174 ft , or about -^^ of an inch. As the rail at a temperature of 90 1044 TRACK WORK. measures 30.015 ft., of which length .00617 ft, say, .006 ft., is due to expansion, the normal length of the rail is 30.015 — .006 = 30.009 ft. Ans. To provide against the effects of expansion, an opening is left between the ends of the rails, and to provide against contraction, the holes in both rail and splice bar are made oblong, allowing about ^ inch for extreme movement. The following /ab/e of expansion is a safe guide to track-layers for most latitudes in the temperate zones: TABLE 31. Temperature When Laying Track. At 90° above zero At 70° above zero At 50° above zero At 30° above zero At 10° above zero At 10° below zero Space to be Left Between Ends of Rails. 1 T15" i 3 i 6 T6 of an inch of an inch of an of an of an inch of an inch nch. nch. To give to the track the proper opening at the joints, expansion shims are used. They are made of iron, and are of various forms. A simple and effective shim is made by bending a piece of ^-inch iron into the form of a right angle, as shown in Fig. 498. This gives a combination shim of two thicknesses, viz., y^^ and | inches. After the angle is formed, the Y^g-inch shim is ob- tained by hammering the ^-inch bar to the re- Fi«-498. quired thickness. The thickness of each shim should be clearly stamped upon it. When put in place, the shim reaches the full depth of the head of the rail, and the bent portion lies flat on the top of the rail. The shims should not be removed until the joint is TRACK WORK. 1045 full bolted, and there should be a sufficient number of them on hand to keep the track-layers constantly employed, and not require them to wait until shims can be removed from bolted joints. SPIKING RAILS. 1612. There is no part of the track laying more likely to sujffer from carelessness than the spiking. A spike, to be driven properly, should be started in a really vertical position. The spikes at the joints, centers, and quarters of the rail should be driven first. The right-hand rail is usual- ly spiked first. The gauge is then placed on the fixed rail, and the free one brought to the gauge and spiked. The common and slovenly custom of driving spikes at an angle should not be tolerated. An almost equally pernic- ious custom is to drive the spike with the track at loose gauge and then bending the head so as to give the rails their proper gauge. First see to it that the free rail is brought to the gauge. Then start the inside spike a little removed from the base of the rail, the head inclined slightly backwards. Having started the spike, a good blow will bring it to a vertical position, after which the blows should be delivered vertically upon the head. The last blow should slightly draw the head towards the rail base. AVhere the gauge is widened on curves, a special gauge should be provided and the eye not trusted to give the proper increase in gauge. Spikes should not be driven in the middle of the tie, especially in severe freez- ing weather, as they are liable to split it, but at from 2^ to 3 inches from the outside of the tie, where the wood is sure to be sound and the grain less open. The proper arrangement of the spikes in the tie is show.n in Fig. 499. Ties spiked in this fashion can not Fig. 499. 1046 TRACK WORK. become skewed, and the track, in consequence, thrown out of gauge. In spiking, the tie must be held firmly against the base of the rail. If from any cause the rail does not lie directly Fig. 500. upon the tie, the tie must be held against the rail with a nipping bar, shown in Fig. 500. The ends of the ties should be spaced at a uniform distance from the rail, both for the sake of appearance and to give to the rail a uniform foundation. A gauge made of hard wood and meeting this requirement is shown at A and B in Fig. 501. The spiker first places the gauge upon the tie with its head close against the end of the tie, as shown at A. The Pig. 501. base of the rail is then brought against the end of the gauge and the inside spike started. The gauge is then removed and the outer spike started, and both driven home. The other rail being spiked to a proper gauge will make the rails equidistant from the ends of the ties. The gauging of the ties is too often done by guesswork, as is evinced by a ragged line. 1613. Spiking Bridge Ties.— Holes should be bored in bridge ties to receive the spikes instead of driving the TRACK WORK. 1047 spikes directly into the tie. As bridge ties are sawed, they are often cross-grained and liable to split unless holes are bored for the spikes. The diameter of the spike holes should be about ^^ inch less than the diameter of the spike, so that; in driving, the hole will be completely filled with the fiber of the wood. 1614. Pulling Spikes. — When a spike is to be drawn from a tie in frosty weather, or from an oak tie at any time of year, it should always be given a light blow with a spike maul before using the claw bar. The blow breaks the hold which the wood has upon the spike, and permits of the spike being drawn with safety. Without this precaution the spike is liable to break off under the head. The instrument for drawing spikes is called a cla-w bar, and is shown in Fig. 503. Its weight is about 25 lb. The end a of the claw Fig. 502. bar is divided like the claw of a carpenter's hammer and the , bar bent into a goose-neck to increase the distance through which the opposite end b can move. In drawing a spike care should be taken that the claw is well under the spike- head before a strain is put upon the bar. When only the lip of the claw is under the head, there is great danger of the claw being broken, especially if a heavy stress is put upon it. When the spike is driven so deeply into the tie that the claw can not be forced under it, the end b of the claw bar, which is wedge-shaped, may be forced under the spike-head, lifting it so the claw may be used. 1615. Gauging Tracl«. — In track laying, no part of the work should receive more careful attention than the gauging of the track. A track gauge, to be in proper position, must be at right angles to the center line of the 1048 TRACK WORK. track, and with this fact in view the gauge shown in Fig. 503 was devised. The gauge consists of two U-shaped cast- ings connected bv a short iron pipe which is threaded at both ends, and screws into them. The castings have lugs on their under sides, as shown at A and B. The distance A B between the lugs determines the gauge. A line drawn across the faces of the gauge lugs is at right angles to a line drawn through the center of the iron pipe. To place the gauge at right angles to the center line of the track, bring both lugs shown at C against the head of the rail. A notch filed in the gauge at D marks the center of the track. G ^ ^ h ~'^ *^£' 3 C Fig. 503. Never crowd the gauge in spiking the rails. Let the rails only touch the gauge marks. Place the gauge about eight inches ahead of the tie to be spiked. This places the gauge out of danger of the spiking hammers, and insures a perfect gauge. SURFACING TRACK. 1616. As soon as the track is full bolted and spiked, it is put into surface. This is an easy matter where the tics have been bedded to grade, an3 requires much less material than where they have been placed upon the roadway and the rails spiked to them without any attempt at grade. If the track is to be earth ballasted, the material is taken from the shoulder of the roadway. If cinders, gravel, or broken stone is to serve as ballast, construction trains should furnish the material as fast as it is needed. Ordinarily, earth is used on new lines, as the finances of TRACK WORK. 1049 the company seldom warrant the use of costlier material. ^_^ T) It is only on prairie lines that sufficient ma- %Jw terial can be borrowed from the roadway IK to put the track in permanent surface, but ilNS in most cases enough is available to place Fig. 504. the track in safe condition for the full operation of the construction train. The tools used in surfacing are the fc track jack, shovel, and tamping bar. ^ The track jack, which takes the place of the ancient track lever, is one of the most economical and indispensable oi the trackman's tools. One of the best track jacks on the market is that made by Joyce, Gridland & Co., of Canton, Ohio, and is shown in Fig. 504. This jack is simply and strongly made. The foot A of the jack is placed between the ties with the lug B under the rail. By means of the lever C the toothed bar D is raised. The lug B forms a part of the bar D, the two forming one casting, and, consequently, in moving together, carry the rail with them. A tripper £ is so arranged that if desired the bar D may be made to drop instantaneously. In using the jack it should always be placed on the outside of the rail with the lever pointing from the track. Numerous acci- dents have been caused by misplaced track jacks, some of them entailing great loss of life and property. The track is raised to grade with the jack, and the ma- terial deposited with the shovel. Many trackmen use only the shovel blade in surfacing track for the first time, and this is probably the wiser policy, as the prime object of the first surfacing is to make the track safe for the 1050 . TRACK WORK. construction train, and any work which unnecessarily delays the construction train is manifestly unwise. There should be no confusion in the work as a result of changing work. Each man should be assigned to his special work and required to do it. 1617. Lining Track. — As soon as the track has a safe surface, it must be brought to line. This is done with lining bars, shown in Fig. 505. In lining, the trackmen with bars are placed at the joints, quarters, and centers of the rails nearest a center stake. <■ « • m \\ < y Weight, 27\(i lb. Fig. 505. The foreman places the gauge on the track at the center stake and orders the track thrown until the center mark on the gauge coincides with the tack in the center stake. He then moves his men to another center stake and repeats the operation. Having placed the track on center at the stakes for 300 or 400 feet, he lines in the intermediate por- tions by eye. He should then check the line at the center stakes to make sure that the track has not moved while lin- ing the intermediate portions by eye. It is needless to say that if the ties have been laid to a tie line, the track will not require any lining until after the first surfacing. 1618. Final Surfacing. — After the construction train has run over the track for a few days, the track will show numerous low places, especially at the joints. A sur- facing crew should then go over the line, putting the track in good surface. The material required for the final surfa- cing can be borrowed from the roadway or obtained by widening and ditching the cuts. That required for the track in the cuts is shoveled directly from the ditch into the track, while that required for the embankment should be hauled by the gravel train. This plan is in every way bet- ter than to borrow the material from the embankment. TRACK WORK. 1051 The freezing and thawing of the following winter will cause the slopes of most cuts to break and cave, filling the ditches with heavy mud, which must be removed to make the track safe. Hence, the removal of this material for surfacing at the time of track laying is practically clear gain In the final surfacing, all ties should be thoroughly tamped. This is best done with the tamping bar shown in Fig. 506. Fig. 506. An excellent substitute for the tamping bar is the iron- handled shovel, which serves both purposes of the shovel and tamping bar. When using them, the foreman can spread out his forces, giving to each man his share of ties, and thus obtaining equal service from all. When the ties are to be hard tamped, the tamping bar is the tool for effective service. The ballast should be tamped under the tie, throughout the entire length, but hardest at the points directly under the rails, where the load is heaviest. In case the ballast midway between rails is tamped the hardest, there is danger of the ties being broken in two at the middle by a heavy train. This danger is especially great when the ties are of soft wood. The object of ballasting track is not only to secure a firm foundation for the ties, but to so bed them that the track shall not be thrown out of line by the lateral thrust of pass- ing trains. That mode of ballasting is best which most com- pletely beds the ties and at the same time provides for the prompt removal of all water which falls upon the roadbed. In filling in the track the material should be deposited in the middle of the track and not against the rails. It should be raised to a height of about 2^ inches above the ties at their middle point A (see Fig. 507), and sloped towards the ends of the ties. Its surface at the inside line B of the rails should be such as to permit the shovel to be passed freely underneath the rail between the ties, and the slope 1052 TRACK WORK. continued to the end of the tie where it should just meet the base of the tie. Outside of the ties, the shoulder CD should continue at a slope of 1^ inches to the foot to the edge of the embankment. This insures complete drainage. Rain falling upon the roadway will run off before it can penetrate the ground. \k 8-0' Fig. 507. Provision must be made for conducting this surface water into natural channels. This is accomplished by means of side ditches. DRAINAGE. 1619. Ditching and Ballasting. — All railroad man- agers and operators are united in their estimate of the im- portance of thorough drainage. This can be effected only by a thorough system of drains and ditches. These should be of such number and size that they will not only meet the requirements of an ordinary rainfall, but also of the heaviest freshets. Ditches are of two kinds, viz., side ditches, those excava- ted in cuts on both sides of the roadway, and surface ditches, those excavated above the slope of cuts to prevent the slope from being washed down. Side ditches are partially made during the grading of the roadway; surface ditches should always be completed during construction, as they are of the first importance in affording protection to the slopes against the floods of surface water which invariably accompany a heavy freshet. The water which, during a heavy shower, falls upon the side slopes and track, is about all that ordinary side ditches can accommodate; and if the protection of sur- face ditches is lacking, great quantities of surface water are TRACK WORK. 1053 discharged at different points directly upon the unprotected slopes, soaking the roadbed, carrying with it quantities of earth and gravel which choke the side ditches, and, where the quantity of water is sufficient, producing a washout. In fact, the surface ditch is indispensable to a newly constructed road, and the question of its construction should not be open to debate. As stated above, the side ditches are partially made during the grading of the roadway, and their completion deferred until the ballasting and final surfacing of the track. All the material excavated in completing the ditching should be used in surfacing the track, and any additional material required should be obtained by widening the cuts. Wet, springy cuts are a serious annoyance and expense to any railroad, especially where the widths of roadways and slopes are limited by a fixed standard. A cut whose width and slopes are ample for sand or gravel is totally inadequate for clay. Springs in the bottom of the cut keep it constantly wet, and a firm track is impossible. Frost and rain cause the slopes to cave, filling up the ditches and often covering the ties from sight. Such a track will be full of sags in summer and badly heaved in winter, and at no time safe for trains at high speed. There is nothing to be gained from tinkering with and patching up such a track. The permanent cure is in widening the cut and reducing the slopes, so that whatever material caves in will lodge well outside the ditch line. The ditches should be from 8 to 10 feet from the rails, and so deep that the ballast will not be soaked by the water flowing through them. The cost of such work will often be heavy, but it will end the trouble and prevent the further wasting of money in useless tinkering. During the construction of the road, the slopes and zvidth of roadivay should, so far as possible, be suited to the charac- ter of the material in which the excavations are made. The dotted lines in Fig. 508 show a standard section of a through cut as made during the grading of the line, and the full lines show the section after the track has been laid, the cut widened, the ditches made, and the track ballasted. The 1054 TRACK WORK. material excavated in this work is used for ballasting the track. In establishing the grades for a new line, the com- petent engineer will make provision for the drainage of the cuts. Sometimes the grade is continuous throughout the cut, carrying all the water one way; but where the average grade is level, the drainage is effected by making the grade to ascend from both ends of the cut, uniting them by an easy vertical curve at the middle. Where the cut is short, it is a mistake to break the gradient, but rather depend for drainage upon well-constructed ditches. Where the grade of the cut is level, the ditches at the middle of the cut are made shallow, and the depth gradually in- creased towards the ends. The grades of such ditches should Fig. 508. be given by the engineer, and the excavation made to con- form to those grades. It is the continuous grade which gives to a ditch its full efficiency. Where the grade is a suc- session of levels and sudden drops, the level places accumu- late mud on account of a sluggish current, and the steep places wash badly because of a rapid current ; and in a comparatively short time a new ditch must be made. Particular attention should also be paid to the alinement of the ditch. Crooks in the ditch impede the flow of the water and tend to increase the deposit of mud. First determine the line of the ditch, with a view of avoiding any unnecessary excavation, and then cut the ditch to a true line. When gravel or broken stone is used for ballast, the section of the roadbed is somewhat altered, although its general dimensions remain the same. As stated in Art. 1603, the ties should not be bedded when cinders, gravel, or stone TRACK WORK. 1055 ballast is to be used. A section of roadway ballasted with either cinders or gravel is shown in Fig. 509. The ballast is filled in between the ties, flush with their tops, and extends to a depth of 8 inches below them, sloping from the outer top edge A of the tie to the edge of the ditch. • On some roads the shoulders at B and C are rounded off, as shown by the \m& D E, before the ballast is deposited. The effect of this is to improve the drainage. The ditch extends 12 inches in depth below subgrade; i. e., the line B C. The subgrade is the grade line laid down by the en- gineers for the grading of the roadway, and marks the bot- FlG. 509. toms of cuts and the tops of embankments. The actual Q^rade line marks the elevation of the top of the rail, and is from 15 to 24 inches above subgrade. When gravel or broken stone is used as ballast, the material excavated in ditching the cuts should be loaded on a gravel train and de- posited upon the embankments wherever needed. The more Fig. 510. material deposited on the embankments the better, as they are bound to cave more or less from the effects of frost and rain, before grass has grown in sufficient quantities to pro- tect them. A section of track ballasted with broken stone is shown in 1056 TRACK WORK. Fig. 510. The ballast extends from 10 inches below the bottom of the ties to the level of their tops, and is shouldered outwards from the ends of the ties as shown in the figure. The side ditches are 12 inches in depth, the slope of the bal- last and that of the ditch forming practically a straight line. The slopes of the cuts given in Fig. 510, as well as those given in Figs. 508 and 509, are 1 horizontal to 1 vertical This is the steepest slope at which earth will stand. The certain effect of weather is to cause the slope to cave, flat- tening it and at the same time filling up the ditches. In all recent railroad construction, where the finances of the com- pany will permit, the slopes of both cuts and embankments are made the same, viz., 1| horizontal to 1 vertical. Cuts can be widened much more cheaply before than after track- laying, but it is often a difficult question to decide where it is safest to economize. The proper time to clean ditches is in the fall, commen- cing about October 1 and finishing by or before November 1. Occasionally the slopes of a cut cave in so badly that ditches require frequent clearing. The only permanent cure is to widen the cut to such an extent that caving material can not encroach upon the ditches and track. Some writers on track insist that there should be no side ditch nearer than 10 feet from the rails, nor slopes less than 1^ horizontal to 1 vertical. This would require a roadway at least twenty-four feet in width for a single track, and involve an outlay which would prohibit the building of nearly all new lines. The roadway and track sections given in the preceding pages are entirely consistent with moderate expense and thorough construction. When the line is fully equipped, traffic connections established, and business on a paying basis, there will be ample time for betterments and a pros- pect of money with which to pay for them. The purpose of all ditches and drains is to convey the water to natural channels and thence out of reach of the track. In Arts. 1461 and 1467, mention was made of the common fault of making culvert openings too small. TRACK WORK. 1057 They should be designed to meet the requirements of the severest storms and freshets. At all low places where the water remains standing alongside the track, open culverts should be built, allowing the free passage of the water. Brooks liable to overflow and wash the track should have their channels deepened or their banks raised. After every freshet, all water passages should be thoroughly examined and all obstructions, such as sticks, brushwood, weeds, etc., removed. Brush and weeds not only obstruct the passage of water, but, when dry, are easily ignited by sparks from the engine and are a continual menace to the safety of the track. Open passages for water, built of framed timber, are to be condemned. They are likely to be undermined by a freshet, and are at best a cause for anxiety. If stone is not avail- able, the track should be carried on piles. The bents of piles next the embankment should be sheathed up with plank to prevent the washing of the embankment. 1620. Side Tracks. — The opinion still prevails on some roads that any kind of work or material will answer for a side track. This is entirely wrong. The same skill, work, and materials that go into the main track should be expended upon all side tracks. The tax upon trainmen and rolling stock is always greater on side tracks than on the main line, and it is there that time is either saved or lost. With a good track, shippers can move a loaded car with a team; whereas, if the track is rough, they are compelled to wait for a freight train, which must stop until the car can be shifted. It is admissible to use No. 2 ties in a side track, except that all joint ties should be strictly first-class. Where No. 2 ties are used they should be placed closer together in the track, so as to insure a first-class foundation for the rails. All side tracks should, as far as possible, have a switch at both ends. This permits trains to enter the side track from both directions without passing a switch and backing into the siding; it also effects a saving of time, labor, and fuel. 1058 TRACK WORK. CARE AND MAINTENANCE OF TRACK. SPRING TRACK WORK. 1621. At the first break up of winter the spring track work begins. The section foreman should plan his work so as to take advantage of each day as the season advances. As soon as the snow has disappeared from the track, which will always be a "few days earlier than from less exposed places, he should set his men to work at cleaning up the station grounds and yard. All scattering track material should be collected and neatly piled at a place convenient to the hand-car house. All rubbish which may have accumulated during the winter must be removed and used either to fill up low places in the right of way, or burned, if necessary. All switches should be thoroughly repaired and put in per- fect line. Battered rails should be replaced by good ones; guard-rails and frogs examined and defects in them rem- edied, and all ties collected, loaded on cars, and distributed along the section, where they will be ready at hand when needed to put in the track. All breaks in fences should be repaired at the earliest opportunity. The approaches to highway crossings should be made safe, and everything done in the way of repairs which the season will permit of. As the frost begins to leave the track, settlement commences, and the track should be carefully watched, thick shims being replaced by thinner ones as the settlement goes on, and all shims removed as soon as it is possible to spike the rails to their proper surface. Every joint throughout the section should be examined; all loose bolts tightened ; nut-locks or washers supplied where needed, and broken bolts replaced by new ones. As the frost leaves the track, especially in wet cuts, soft places will appear. These must be reported to the train dispatcher at once. By keeping the side ditches clear and deepening them as the frost leaves the ground, soft places can usually be made safe until the ground settles, when thorough re- pairs should be made. If the place becomes dangerous the fact TRACK WORK. 1059 must be reported by telegraph to the roadmaster, who will fur- nish the necessary men and materials to make the track safe. 1622. Washouts. — The melting snow together with the spring rains greatly increase the volume of surface water, and as the frost comes out of the ground but slowly, ditches and natural water channels are taxed to their utmost capacity. It is at this season of the year that washouts and landslides are chiefly to be feared. All ditches, culverts, and bridges must be kept clear of obstructions, and the track watched night and day so long as danger is to be appre- hended. In case of a severe storm, the section foreman should send a responsible man to one end of the section with the proper signals to stop trains in case of danger, while he goes to the other end of the section, leaving a man to guard any dangerous spot until the section is entirely covered. In case he laches the means to repair any damage done, he must report the fact by telegraph to both the train dispatcher and roadmaster, in order that the former may hold trains at convenient points while the latter can rush a construction train through to the point of danger. The foreman should include in his report the location of the break or washout, the number of the bridge or culvert, the length of thebreak,^ the number of missing bents, and any information which will aid the roadmaster in making a Correct estimate of the men and materials necessary to repair the damage. He can then set to work with his men, making such repairs as his limited force will permit of, and being ready to render every assistance in his power to the roadmaster, who assumes charge on his arrival. A foreman should never attempt any repairs of track until he has inspected his entire section, as two or more breaks may occur simultaneously, and while re- pairing one break an accident is liable to occur at another. 1623. Repairs of Track. — As soon as the frost has left the track and all shims have been removed, bringing the rails down to the surface of the ties, the section foreman should go rapidly over his section, making such repairs as will render the track safe and reasonably smooth. If the 1060 TRACK WORK. track is well ballasted with gravel or broken stone these re- pairs will be quickly made, as such track will hold a good line and surface after the severest winter. If, however, the ballast is clay, the track will show many low places and an uneven line. The track jack, shovels, and picks are all the tools needed for the first repairs. A man is set to dig block holes for the jack at the lowest points in the sags. The track is then raised until it is in average surface with the track at either end of the sag. Dirt is then shoveled under the ties, care being taken to throw it well back to the middle of the tie. No attempt should be made to tamp the ties other than to fill up the cavities formed by raising them. A part of the force will follow, dressing up the track and filling block holes. The foreman should stop raising track about two hours before quitting time, taking with him sufficient hands to line up and gauge the track surfaced during the day. The line side of the track is then given a perfect line. Either rail may be taken as the line side, but the same rail should always be used for lining. A part of the force take the gauge and spike maul and spike the track to gauge, while the rest follow, dressing up the track. This work will put the track in perfect line and fair surface, and by the time the entire section is covered the ground will be thoroughly settled and the track in shape for permanent surfacing. 1624. Lining Track. — When lining track the fore- man should stand with his back to the sun and as far from the piece of track which he is to line up as his eyesight will permit. This gives him a better view of the straight portions on each side of the crooked portion, all three of which are to be brought into the same straight line. A simple device, much practiced by trackmen when lining track, is to place small lumps of dirt on the top of the rail to be straightened. These lumps show plainly in contrast to the bright, unbroken surface of the rail, and when brought into range insure a good line. With a strong section gang the foreman can readily per- form any of the tasks which confront him ; but when from TRACK WORK. 1061 necessity his force is reduced to a minimum, he is obHged to resort to every expedient within his knowledge. He must not only direct the work, but lead in its execution. Fre- quently a foreman will have charge of ten miles of track, and have but four hands besides himself wherewith to main- tain it. It is under such circumstances that ingenuity and energy count at their full value. When a sag in the track has caused a crook in the line, and there is not sufficient force to throw the track to line, the following scheme will enable the foreman to straighten the track and hold it in place. He can only straighten one rail length at a time, and-to do that he should remove the spikes from three or four of the ties under the rail. The ties so detached from the rail are called dead ties. The lining bars are then placed under the rail upon the dead ties, which afford a far firmer foundation and leverage than ordinary ground. The track is then thrown to line, after which the dead ties are shifted to their proper position. If the track has a tendency to slip back out of the line, the rails can be temporarily spiked to the dead ties, which, being securely bedded, will hold the rails permanently in place. 1625. Straining of Track Bolts. — Reference has already been made to this serious fault, which is almost universal among trackmen and generally due to ignorance on their part. The rail splices on most American roads are fitted with nut locks of either metal or fiber, the object of which is to lock the nut and at the same time permit of the expansion and contraction of the rail. In order that expan- sion and contraction may take place, the nut should only be brought to a snug bearing on the nut-lock, whereas, the common practice is to screw on the nuts as far as the strength of the trackman will permit. This places the bolt, nut-lock, and nut under a severe strain, with the result that the rail can not freely expand and contract; the nut-lock is deprived of all power to act, and at the first abrupt change of tem- perature the nuts are liable to snap off on account of the sudden strain. One of the first duties of the section fore- man is to explain to his men the object of the slots in the 10G2 TRACK WORK. rails, expansion shims, and nut-locks. In putting in track bolts, first bring the nut to a bearing, after which a half turn with the wrench is sufficient. Track wrenches should not be longer than 16 inches for f-inch bolts. Spike slots should always be made in the angle splice. These prevent the creeping of the rails and at the Same time permit the free expansion and contraction of the rails. 1626. Removing Old Track Bolts. — In removing old track bolts they should never be battered with either hammer or wrench. The nut should not be entirely re- moved from the bolt until the bolt is loosened in the splice. When the nut is nearly off the bolt, give it a slight tap with the track wrench. This will loosen the bolt without injuring the thread. The thread of the old bolts should be oiled and the nuts well screwed on so that they will be complete and in readiness for service when needed. 1627. Loose Track Bolts. — Changes of temperature often cause the loosening of track bolts. These are most noticeable in the spring and fall of the year. Trackmen should watch for and promptly tighten all loose track bolts, as they are one of the main causes of low joints. 1628. Line and Surface of Bridge Approaches. — Special care should be taken to make the line and surface of the track on bridge approaches as nearly perfect as pos- sible. Pile bridges are liable to heave, especially when the ice surrounding them is lifted by a spring freshet. Section men should not attempt to repair bridges unless circum- stances require it. They have neither the experience nor tools for such work. Bank sills (those resting upon the embankment and supporting bridge stringers) are continually settling, and cause a bump, or lift, in the track at the bridge line. The sills should be raised and kept in perfect surface by hard tamping, and all bank ties kept well tamped. If possible, avoid placing a rail joint over a bank sill. It is almost cer- tain to be low at times; but. rather arrange the track so as to bring the center of the rail at that point. TRACK WORK. 1063 SUMMER TRACK WORK. 1629. General Repairs. — On Northern railroads, general track work commences with the month of May. By that time all frost has left the track and settlement has taken place generally. The section foreman should go to the end of his section to commence track repairs, and work towards home, finish- ing as he goes, raising all small sags and low joints to a proper surface, tightening all loose bolts, relining the track, and correcting all defects in gauge. He should fill in the middle of the track and dress it down to the track shoulder. He should allow nothing short of actual com- pulsion to call him from his work until the entire section is covered. He will then be in readiness to put in new ties, lay new steel, surface track, or cut weeds according as the work demands. In going over the track, the fore- man can correctly estimate the number of new ties needed and make early requisition for them in order that they may be on hand when needed. He should keep a record of the places where new ties are needed and distribute them accordingly. 1630. Track Ties. — Track ties constitute one of the most important items in the initial cost and maintenance of a railroad. The company should provide the best ties within their means, and, if possible, have them well seasoned before being placed in the track. Ties made from logs split in two parts should be laid with the sap side up. This brings the wide or heart side of the tie underneath, which is the position it would naturally take. Pole ties, those made from young trees, are more lasting than those made from large logs, as the older the tree, the more open and brittle the timber. Sawed ties are usually smaller than hewn ties. They are also often cross-grained, and hence more easily broken. Tie specifications should always require uniformity in length and thickness and the removal of all bark. Tie inspectors should strictly enforce these specifications. Tie contractors are quick to note any 1064 TRACK WORK. laxness in the enforcement of specifications and always ready to take advantage of it. Ties in the roadbed should be not less than 8 feet in length, 7 inches in thickness, and show at least 7 inches of face and be hewn to a uniform thickness throughout their entire length. Winding ties should be promptly rejected. They are dear as a gift. The life of a tie depends not only upon the kind and quality of its timber, but also upon the weight of the rails, condition of the roadbed, and much upon the climate. In Northern latitudes, decay is almost entirely suspended dur- ing the late fall and winter months, while in Southern latitudes decay goes on almost uninterruptedly throughout the year. The yellow pine ties of the South are best fitted to withstand the effects of the climate, and when of sound heart timber they are fairly lasting. The loss sustained from the use of inferior ties is apparent when one considers the cost of repairs and renewals. A track laid on ties with an average life of 8 years, and cost- ing 60 cents each, is vastly more economical than a track laid on ties with an average life of 5 years and costing 40 cents each. The track laid on the more expensive ties will be superior from the start to that laid on cheaper ones, and, besides requiring far less repairs, it will be in good condition when the cheap track must be entirely rebuilt. The break- age of spikes and angle splices is much greater where cheap ties are used, and accidents more frequent and severe. 1631. Placing New Ties in Traclc. — When renew- ing ties, no more material should be removed from the track than is necessary to allow the new tie to go into its proper place. Where the track is mud ballasted, remove the dirt from the sides and from the ends of the tie to a depth a little below its bed, but without disturbing the bed of the old tie. If two ties side by side need renewal, a single trench between them will serve for removing both. Remove the spikes and spring the rail up from adjoining ties, slipping a spike under it. Then knock an old tie into TRACK WORK. 1065 the trench and pull it out. Pull the new tie into the trench from the opposite side of the track and have two men slide it into place, keeping it well up against the rail until it is in place. If the track is low, throw some fine dirt under the tie and spike the tie to the rail. The ballast removed in putting in additional ties should be thrown into the trenches made when removing the first ties. When all the rotten ties are removed from one rail length, fill in and dress the track before beginning on another rail length. If, after the ties are in place, the track proves to be a trifle high, the defect will disappear after the passage of a loaded train. This method of putting in new ties does away with most of the labor of tamping, and the work is better done. A gang can put in from one-quarter to one-third more ties in this way than by any other method, but it is restricted to a mud-ballasted track alone. If the ballast is gravel or broken stone, all new ties must be tamped. The tie must be held up against the rail with a bar while it is spiked, and the ballast thoroughly tamped with a tamping bar. All new ties must be placed square across the track, and if the old ones are too widely spaced, additional ties must be put in the track with selected ones at the joints. Never spring the rails off the ties on stone or gravel-ballasted tracks, as the ballast collects under the base of the rail and prevents its proper bearing upon the ties. The prime object of track repairs is to make the track safe, and if some parts of the section are more needy than others, the foreman should first make those places safe and then go ahead with continuous repairs. 1632. Estimating New Ties for Repairs. — The proper time for estimating the number of new ties needed for repairs is in the fall of the year. In the Northern States the winter is the proper season for manufacturing ties, and most tie contracts are let in that season. If the estimates are made up and sent in to the roadmaster in the fall, he can make more favorable contracts and be sure of having a supply when needed. 1066 TRACK WORK. In making his estimate, the foreman should walk over his entire section, testing every tie of which he is in doubt and reporting the actual number needed, and no more. The renewing of ties is one of the great items of cost in the maintenance of a railroad, and a careful foreman can do much towards prolonging their life. 1 633. Disposition of Old Ties. — All labor spent in handling old ties is unremunerative, but they must be dis- posed of. In sections where timber is scarce they can usually be sold for fuel. If, however, fuel is abundant and cheap, the best way to dispose of them is to burn them. 1634. Tie Account. — The foreman should keep an accurate tie account, which will show at once the number of ties received, put in the track, and on hand. The following is a good form for tie accounts: TIE ACCOUNT FOR ONE YEAR. Months. Ties Received. Ties Put in Track. Ties on Hand. Hard Ties. Soft Ties. Hard Ties. Soft Ties. Hard Ties. Soft Ties. January February. ...... March 1,000 800 400 300 1,000 1,800 1,400 800 400 700 April 400 600 800 100 400 200 600 Mav 200 / j June Tulv August September October November December TRACK WORK. 1067 1635. Cutting Weeds. — On all mud-ballasted roads the cutting of weeds is an important item in the cost of track repairs. All weeds within a distance of 3^ feet from the rail should be kept cut clean to the surface of the ground. It is important to prevent their getting an early start; hence, when making track repairs early in the spring the surface of the ground should be shaved over either with a shovel or weed cutter. This will increase the labor of early track repairs, but it will save much subsequent labor and loss of time. A heavy growth of weeds seriously checks the speed and efficiency of a train, especially on heavy grades, besides FIG. 511. promoting decay of ties. For cutting weeds the blades of shovels or weed cutters should be ground to an edge, and a file kept handy for resharpening. The men should be dis- tributed one to each rail length to prevent crowding and insure an equal share of work from each. The weed cutter shown in Fig. 511 does inore effective work, and is less severe upon the men than the shovel. The handle of the weed cutter is considerably longer and the blade lighter than that of the ordinary track shovel. In using the weed cutter, men are not compelled to keep their backs continually bent as when using the shovel, and they can cover from one-sixth to one-fourth more ground in a day. 1068 TRACK WORK. 1636. Mowing Weeds, Grass, and Brush. — If the section force will admit of it, all weeds, grass, and brush should be cut from the right of way. This work should be commenced by July 20th, mowing first the grass and weeds about all wooden structures and burning them as soon as they are dry enough. This forms a barrier against fire, and insures the safety of these structures while burning other brush or weeds along the right of way. If possible, mow the entire right of way, burning the grass and brush as fast as they are dry enough. With the right of way clear of combustible matter there is comparatively small danger of fire being communicated to adjoining property. This as- surance is well worth the cost of the work, and it is well known that by keeping the right of way clear of weeds and brush, grass is induced to grow, which is far easier to keep in order than brush or weeds. ^^ORK ON OLD TRACK. 1 637. Combination Ballast. — A track can be better ballasted with a combination of stone and gravel than with either of these materialsseparately. Each material has ad- vantages peculiar to itself. Stone is more solid, more open, and heavier than gravel, and, hence, better suited to form the foundation of the track where solidity and drainage are of first importance. Gravel is more abundant, more elastic, and much easier handled than stone. It does not wear the ties, rails, and rolling stock like stone, and is comparatively free from weeds, and, hence, is well suited to form the top course of ballast. Where stone is used only for the founda- tion of the ballast, it need not be broken so finely as when composing the entire roadbed. Two carloads of gravel to a 30-foot rail length will make a first-class track where there is a foundation of stone 12 inches in depth. 1638. Preparing Old Track for Ballasting:. — When old track is to be newly ballasted with stone, gravel, or cinders, all dirt should be removed from between and from the ends of the ties down to the base of ties and placed on TRACK WORK. 1069 the shoulder of the roadbed. This will considerably strengthen the roadbed and afford a support to the ballast. The engineer should set grade stakes 50 feet apart, giving the elevation of top of rail for the finished track. Where sags occur, if it is intended to fill them, the material necessary for raising the track should be delivered, and the track raised to the required grade before the ballasting is begun. 1 639. Reserve the Best Ballast for Cuts. — When gravelis, the best available ballast, and that of inferior quality, select the cleanest gravel for the cuts, where drainage is most difficult and the track most affected by tlie frost. All mud ballast removed from the roadbed in cuts should be deposited upon the adjacent embankments, which are constantly being reduced in width by the action of rain and frost. If the bal- last is a mixture of gravel, sand, and loam, it should be raised a full 3 inches above the tie at the center of the track and carried out flush with the tops of the ends of the ties. All gravel beds contain streaks of clear gravel. With a little care and calculation the clean gravel can be loaded on sep- arate cars and the train made up with the selected cars by themselves. The inferior ballast should be unloaded on the embankment and the selected ballast deposited in the adja- cent cuts. Make the track shoulders of equal weight. Track with unequal shoulders is sure to work out of line. Embankments should be made at least 14 feet in width at the top before depositing the gravel ballast, and 16 feet in width if the means of the company will permit. With a 16-foot embankment there is no loss of ballast from its being crowded over the shoulder. 1640. Ballast Required for a Mile of Track. — Allowing an average length of 33 feet per car, 160 cars will cover 1 mile of track. If the trains average 8 cubic yards per car, they will form a continuous bed 12^ feet in width at bottom, 12 feet in width at top, and 6 inches in thickness. Of this amount it will require about one-half to fill in between the ties and dress the middle of the track. This will leave 1070 TRACK WORK. a bed of 3 inches beneath the ties. By unloading two cars in a place, the depth of the ballast under the ties is increased to 8^ inches, which will make a first-class track, providing the subgrade is compact and thoroughly drained. Gravel may be loaded at the pit for 75 cents per car, making the cost per mile, 2 cars to a rail length, about $250. Under favorable conditions, gravel can be loaded with a steam excavator for considerably less than the above figures. 1641. Gravel Pits. — The cost of loading gravel at the pit depends largely upon the manner in which the exca- vation is conducted. The prerequisite for cheap loading is a long, high, and regular working face. In laying out a track to a gravel pit, the ground should be well considered and the track placed so as to meet the above conditions for loading. The switch should be so placed that the turn-out curve is passed before the gravel pit is reached. If the face of the gravel bed is uneven at the start, commence loading at the projecting points and continue until the face is uni- form. With each movement of the track, excavate deeper if the depth of the gravel will permit, and so increase the height of the working face. Gravel is generally overlaid with a layer of earth. This earth mixes with the gravel in loading, and the proportion of earth grows less as the height of the working face increases. The grade of the track should be made as uniform as possible, and the track maintained in such order that an engine may draw a full train load from the pit. Under fair conditions, 10 loaded cars constitute a train. If a steam excavator is being used, there should be enough cars on hand to keep the machine constantly em- ployed. The empty cars should be placed on a spur track, connecting with the track leading to the pit, and shifted by teams as they are needed. When a train of empty cars is returned to the pit, the cars are switched to the spur track, and the loaded train hauled out. 1642. RalsinR Track. — When raising a track to a surface, the following method is recommended: Take a piece of board 1 by 4 inches and 5 feet in length. Cut two TRACK WORK. 1071 notches, each 3 inches deep, to fit over the rails, the space between the notches being equal to the gauge of the track. Place this sighting board at a high place in the track, from 8 to 10 rail lengths ahead of the point where you intend to commence track raising. Shim up the sighting board to a perfect level, giving it the same height to which the top of the rail is to be brought in the raising. Then, go to the point where you intend to commence track raising and lift the track to a proper height, bringing both rails to the same level. The spirit level is then laid aside and the intervening track brought to a surface by sighting. When sighting, stand from 50 to 75 feet from the track being raised. Raise and tamp each joint about \ inch higher than the actual surface. In raising, two jacks, a heavy and a light one, should be used, the heavy one to raise the joints, and the light one to raise the centers of the rails. Do not attempt to raise a rail center until the jack is in place at the next joint, and then raise together. This prevents the springing of the rails and insures a smooth surface. By sighting in -the rails, a more uniform surface is ob- tained, and the delay occasioned by the repeated use of the spirit level is avoided. When the sighting board is reached, it is removed, and the track brought up to the proper surface by sighting. In sighting in a curved track, sight along the inside of the rails. This permits of longer and better sights. The foreman should know the time when each regular train is due, and have the track safe for its passage. This is accom- plished by a run off, extending from the new to the old surface. This should be 30 feet in length for each G inches of difference of elevation between the old and new track surface. The amount and quality of work done will depend much upon the organization of the force. A good foreman will soon learn the good points of his men and distribute them accordingly. A gang of 14 or 16 men should be distributed as follows: Two with jacks; two to tamp the ends of the ties; four to tamp the centers, and the remaining men 1072 TRACK WORK. equally divided, one-half to be employed in filling in ahead of the tampers and the other half in dressing up the track behind them. By dividing up the men equally, placing one- half the force on each side of the track, competition, both in amount and quality of work, naturally follows. With such an organization, a foreman can effectively employ a force within comparatively small limits, enabling him to give thorough inspection to all work, and to give directions wherever needed. In raising track, both sides should be lifted together. The common custom of raising and tamping one side of the track at a time should not be permitted, as ties can not be given a uniform bearing. The centers of track ties should not be hard tamped. The greater part of the train load comes upon the ends of the ties, and if their centers are hard tamped there is great danger of the ties being broken, especially if they are sawed ties. The ties should be hard tamped only 18 inches inside the rails. This will insure a firm bed and prevent all danger of breaking. Uniformity of work is the secret of a smooth track, and the more alike the men work, the better will be the results. 1643. Yard Work. — All yard tracks should be uni- formly surfaced throughout their entire length. The grade for all yard tracks should be given by the company's engin- eer, and should practically conform to that of the main line. If possible, yard tracks should be level. Cars are then much more manageable and easier handled. Where the yard and main tracks are of the same level, the main line should be put in perfect surface first. The adjoining yard track may then be given an equal height by a level and straight-edge. In the same way, any number of side tracks can be brought to the level of the main track. It is, how- ever, much the better practice to have all elevations given with an instrument. 1644. Gravel as a Destroyer of Weeds. — One of the great advantages of gravel ballast is the saving in the TRACK WORK. 1073 cost of weed cutting. Although ballasting with gravel is a heavy initial expense, the outlay ceases when the work is complete. Weed cutting, on the other hand, is a constant and heavy expense, and one of the great arguments in favor of gravel ballast is that gravel discourages the growth of weeds and thereby saves to the company a large annual ex- pense. A railroad company should commence ballasting with gravel at the earliest possible moment, even though it is done in a fragmentary way, as every rail length of gravel is clear gain. 1645. A Day's Work.— Two rail lengths, or GO feet of finished track, ballasted and dressed, per man, is con- sidered a fair day's work. Foremen should stop raising track long enough before quitting time to line up, fill in, and dress all the track raised during the day. Track left with- out the ties being filled in and the shoulders properly dressed is easily thrown out of line. A heavy shower falling upon track which has not been properly filled in and dressed is certain to do great injury. In all cases, track should be left in a finished condition. FALL TRACK WORK. 1646. Importance of Fall Work. — On Northern railroads, the prime object of fall track work is to prepare for the ensuing winter. One day's work in the fall expended in intelligent track work is worth an entire week of repairs in winter. The section foreman should lay out his work according to the needs of his section, and, as far as possible, adhere to his program. 1647. Surfacing and Lining Track. — The most important part of the fall work is the surfacing and lining of track. In addition, the track must be put in perfect gauge and dressed down. In dressing the track, give as much strength to the shoulders as the available material will permit. With drainage provided for, the heavier the shoulder, the longer the track will hold its line and withstand frost. 1074 TRACK WORK. 1648. Seeding^ and Repairing Embankments. — It is the severe frosts of winter, followed by heavy spring and summer rains, which destroy embankments. After a heavy spring freshet, embankments are furrowed with deep gulleys, though the usual effect is the gradual wasting of the slopes. The only protection against these destructive agents is a good sod, and foremen should be supplied with grass seed of suitable variety to seed embankments whenever the conditions are favorable. Until embankments are protected by grass they must be repaired from time to time. Narrow embankments give insufficient support to the track, and sags are the result. The fall of the year is the best time to repair embankments. All the material obtained from cleaning ditches, widenmg cuts, or from any other source, should be deposited upon the embankments where there is greatest need of repair. This material the section men can transport on a push car, Fig. 612. which should be fitted with sideboards so as to carry a full load. A section foreman can do much towards keeping his embankments in proper shape, especially if he be well pro- vided with men. If there are bad sags on his section, he should not attempt to take them out until he knows how much material is required for raising the roadbed to the proper height. He can determine the necessary amount of filling by the following approximate method (see Fig. 512). Drive a stake at C against the rail at the middle point of the sag until its top is on line with the track surface at A and B. Measure the height C D oi the stake above the rail. Multiply one-half the distance A B by the top width of the embankment and by the height C D oi the stake above the rail; divide the product by 27. The quotient is the number of cubic yards of material required. TRACK WORK. 1075 Example. — A B is 200 ft., C D \%\ ft., and the top of the embank- ment is 14 ft. in width ; how many cubic yards of material are necessary to take out the sag ? Solution. — Number of cubic yards = -5- x 14 x 1 -^ 37 = 52, nearly, Ans. A push car with sideboards will carry 1 cubic yard of material. If the men and material are at hand, commence by raising the sag near the middle, extending the raising on both sides until the ends are reached. Raise the track at the middle of the sag about y^ higher than the total depth of the sag, to allow for shrinkage of the material. 1649. General Repairs. — Carefully examine all joints, tightening loose nuts and renewing bolts where they are broken or stripped of their thread. See that proper pro- vision is made for expansion, and that all ties are full spiked. Rotten ties left over from the work of the previous spring should be replaced with new ones. If new steel is required, see to it that it is laid early in the fall and the track well settled before winter begins. Thoroughly repair the right of way and snow fences. The winter season puts all fences to the test, and they should be in thorough repair if they are to do service the following summer. 1650. Building Ne-w Fence. — Though the spring is the most favorable season of the year for building fence, the more urgent track repairs fully occupy the time of every section man. Consequently, fence building is deferred until the late summer or fall. The one disadvantage to building fence when the season is well advanced is the hard- ness of the ground, which makes the digging of post holes much more laborious than in the early spring, when the ground is soft and yielding. There are, however, the fol- lowing advantages in favor of building fence in the fall season. Posts and lumber are usually much better seasoned in the fall than in the spring; streams are low, and swampy places are either entirely dry or at least accessible. It is 1076 TRACK WORK. important that posts should be peeled and well seasoned be- fore setting; and as they are usually cut in the winter season, by delivering them at the section house in the win- ter or early spring, the section men can peel and pile them on stormy days; they will thus be thoroughly seasoned when needed the following fall. The most effective fence js of barb wire with one board at the top, as shown in Fig. 513. Posts are spaced 8 feet between centers and set 2 feet 6 inches into the ground. At intervals of 500 feet on straight lines, and at every angle, braces A B should be built into the fence. The brace is mortised into the post at the top and gained into the post at the bot- tom. The wires are spaced as follows, beginning at the bottom wire, which is 9 inches above the ground : The first Fig. 51S. and second wires are 9 inches apart ; the second and third, 10 inches; the third and fourth, 10 inches apart, and the fourth is spaced 10 inches from tKe top board or rail, which is 6 inches in width. This makes the total height of the fence 4 feet 6 inches, which is a lawful fence in most of the States, and the total length of the posts 7 feet. In laying out a fence, measure from the center line of the track, one- half the width of the right of way, and set a temporary post. Place these posts from 50 to 80 rods apart on tan- gents and from 50 to 100 feet apart on curves. Then stretch a light wire between these posts, with tags at intervals of 8 feet for spacing and lining the posts. A man then takes a lining bar and spade and plumbs down from each tag with the bar, making a mark with the point of the bar. He then removes the sod from around the hole made with the bar. TRACK WORK. 1077 The hole marks the center of a post and guides the men who dig the post holes. The wire is removed while the holes are being dug, and replaced to give line for setting the posts. The diggers should be provided with a gauge giving the proper depth of hole. Those nailing on either boards or wire must be provided with a gauge giving top of fence and the spacing of each strand of wire. A handy gauge for spacing wires is shown in Fig. 514. It consists of a foot piece of pine 2 feet in length. 6 inches in width, and 1 inch in thickness. Another piece of pine 3 inches wide and 4 feet 6 inches in length, equal to the height of the fence, is nailed to the foot piece at its middle, as shown in the figure. The spacing of each wire from the ...-^ 1 .. o ^ ?.« 1 ■ ■ ground is marked by a notch cut ^'°- ^''*- into the edge of the upright piece. The foot piece, besides giving the height from the average surface of the ground, helps to keep the gauge in an upright position. In building the fence described above, judgment should be used in distributing the force if first-rate progress is to be made. With a force of a dozen men, the following dis- tribution is recommended : Two men to lay out the work, four digging holes, three setting posts, and three nailing on boards and stringing wires. A wire stretcher is necessary to first-class work and prog- ress, though good work at stretching wire can be done withi a crowbar if sufficient care and strength is used. At highway bridges and culverts, the fence usually re- turns to the ends of the abutments. The angles made in the fence by these returns must be thoroughly braced. Effective braces for such returns are shown in Figs. 515 and 516. In Fig. 515 the angle of the return is 00°, and a brace in each panel abutting on the angle is sufficient, but in Fig. 516, where the angle contains 150°, an inside brace is added. 1078 TRACK WORK. This brace abuts against a short post set in the ground to receive the thrust of the brace. Braces must be placed at each opening, such as farm and Fig. 515. Fig. 516. road crossings, and at all points where changes in direction require it. At streams crossed by pile bridges, it is customary to make a return in the fence on both sides of the stream, and to string the wires across the stream, fastening them to the piles. On tangents, and on the outside of curves, place boards and wire on the farmers' side of the posts, but on the inside of curves place them on the track side of the line of posts. 1651. Material for One Mile of Fence.— It will require 661 posts spaced 8 feet between centers to build one mile of fence. One fence board 16 ft. long, 6 in. wide, and 1^ in. thick contains 10 sq. ft. of lumber, and 330, the num- ber of boards required for 1 mile of fence, will contain 330 X 10 = 3,300 sq. ft. Barb wire, of average weight, weighs 1 lb. per rod of sin- gle wire or 4 lb. per rod of finished fence. Hence, for 1 mile, or 320 rods, it will require 320 X 4 = 1,2801b. Adding 10 lb. for splices, we have 1,280 + 10 = 1,2901b., the amount of barb wire required for 1 mile of fence. It will require ^ lb. of staples for 1 rod of fence, and for 1 mile, or 320 rods, it will require 320X^=40 lb., and we have the followin'T TRACK WORK. 10l9 TABLE OF MATERIAL FOR 1 MILE OF FENCE. Posts. Boards. Barb Wire. Staples. 661 3,300 sq. ft. 1,290 lb. 40 lb. When barb-wire fences were first introduced, the posts and braces were the only wood material used, but they proved very injurious to live stock, which, failing to see the wire, continually came in hurtful contact with the barbs. This objection is removed by placing a single board for the top rail. This board clearly marks the fence line, and, together with the barb wire, makes the most effective fence known. 1652. A Day's Work at Fence Building.—From 12 to 14 rods per man is a fair day's work at fence building, though much depends upon the hardness of the ground, the quality of the work, and the skill and industry of the work- men. Fence building requires intelligent industry. A poorly built fence is little better than no fence. 1653. Distributing Emergency Material. — In the late fall, but before any snow falls, place at each mile post, and well up from the ground, a number of rails and joint splices to be used in case of emergency, and known as emergency material. Such supplies are available when most needed, and are constantly near at hand. All track material lying about the yard should be collected and piled well off the ground. Piles of ties must be placed far enough apart to avoid catching fire from one another in case of fire. All loose spikes, splices, bolts, and nuts should be collected and placed under covef, and everything about the station made snug and safe for the winter. WINTER TRACK WORK. 1654. General Repairs. — As winter approaches, the entire section should be gone over carefully, tightening up all loose splices, correcting defects in gauge, and closing up joints which the contraction of the rails has left too open. 1080 TRACK WORK. The joints of switches are most liable to be open and the rails battered. Close up these joints and renew the rails if neces- sary. See that switch joints, rods, and frogs are in proper or- der, and that guard-rails are properly spaced and well spiked. Keep all spikes driven home, clear the snow from yard tracks and switches, flange out the main track after every snow storm, and remove ice from the ditches. 1655. Shimming Track. — There is no work con- nected with track repairs requiring more care and judgment than shimming. All mud-ballasted tracks are bound to heave from the action of the frost, and heaving spoils the surface of the track. Inequalities as small as ^ inch should be corrected by shims placed beneath the rail. Shims should be made of hard wood, slightly wedge-shaped, and driven crosswise under the rail. All shims over ^ inch in thick- ness should have a hole bored in them to receive the spike. They are easiest made by boring a hole- through the end of a straight-grained plank and cutting off a piece to the re- quired length, after which the plank may be split into shims of the required thickness. If the rail has cut into the tie, the edges of the groove must be adzed smooth before pla- cing the shims, in order that the rails may have a solid bear- ing. If the track continues to heave, thin shims must be replaced by thicker ones. Where a number of ties side by side require shimming, a plank should be placed lengthwise under the rail and spiked to the ties with boat spikes and track spikes driven through the plank to hold the rail. Where shims exceed 1 inch in thickness, spikes 7 or 8 inches in length should be used. For 4-inch shims use 1-inch shims on top of 3-inch plank, and for 5-inch shims, use 5-inch timber. Where shims ex- ceed 1 inch in thickness, old rail splices should be set with one end against the outside of the rail and the other end spiked to the tie to serve as rail braces. These braces should be spiked to every second, third, or fourth tie, according to the height of the shim. All high-shimmed track should be closely watched, and TRACK WORK. 1081 as the frost leaves the track and the track settles, thinner shims must be substituted for the thick ones. The last shim must not be removed until the frost has left the ground. When the shimmed rail is higher than the rest of the track by the thickness of the shim, you may know that the frost has left the track. All good shims, spikes, and braces should be stored in the tool house, to be in readiness when needed the following winter. 1 656. Heaved Bridges and Culverts. — Pile bridges and pile culverts require careful watching during the winter season, and whenever they are found to be heaved out of surface or line, the bridge carpenters should be promptly notified. Pile foundations, when heaved by frost, unlike earth foundations, do not resume their original position after the frost has left the track. Neither does the frost affect them equally, as one or two piles in a bent may be heaved out of surface while the others are not stirred. This places the track in a dangerous condition. To remedy the evil, either the track must be shimmed to the surface of the heaved piles or they must be cut down to the original sur- face. Where piles are driven in deep water, the ice should be cut away from them whenever a thaw is imminent, as a sudden rise in the water may lift the body of ice, and the piles, being frozen fast in the ice, must rise also. SNOW. 1657. Its Prevalence and Effects. — Nearly all roads in the Northern States are obliged to contend with snow, and, in the Northwest especially, the keeping of the track clear of snow constitutes one of the main items of cost of track maintenance. Snow must be contended with in many forms, the most common of which is drifted snow; but it is almost equally difficult to contend with it when it fills the flanges of the rails with ice, or in melting and freez- ing it fills the track ditches and flows across the track, covering the rails with ice and threatening derailment to the first passing train. 1082 TRACK WORK. 1 658. Snow Keports. — Immediately after every snow storm, the section foreman should ascertain the condition of his track, noting which cuts are clear and which are blocked, and how much snow is in each cut, and the lengths of the drifts. These facts he should report immediately by tele- graph to the roadmaster, in order that preparations may be made to clear the track. If the section is clear of snow, it should be so reported. 1659. Preparing Track for Snow Plow. — After a storm, as soon as the condition of the section has been re- ported to the roadmaster, the foreman .should take all his force and put his section in shape for the snow plow. In all cuts where the drifts are over two feet in depth, the track should be cleared of snow and flanged out to where the snow has a depth of at least 18 inches, leaving a clean face to the drift. Both ends of the cut should have the same treatment. Snow is most apt to cause derailment when it is of slight depth and hard, and so ground into the flanges that the engines mount the rail. By clearing the track of snow at the commencement and ends of drifts, this danger is avoided. 1660. Clearing Switches and Flanging Track.— As soon as the track is ready for the snow plow, the men should clear the switches of snow from heel of switch to frog, special care being taken to clear the switch rails, rods, and switch stand. The platform, track, and approaches to the station should also be promptly cleared. The section foreman should next give his attention to flanging out the main track, beginning near the summits of the hard grades, and at all points where the work upon the engines is most severe. 1 661 . Clearing Ditclies and Culverts. — If possible, keep the ditches and culverts clear of snow. If, in the fall, a tall stake is driven at both ends of a culvert opening, there will be no trouble in locating it when the culvert is com- pletely covered with drifted snow. By keeping the ditches open, all snow water can run off instead of accumulating and flooding the track, where it is bound to freeze, making TRACK WORK. 1083 the track not only hard to operate, but a continual menace to the safety of trains. The ditch for snow water should be fully 6 feet from the rails to insure the safety of the track. 1662. Snow Fences. — All railroads exposed to severe and repeated snow storms should have some protection against drifting snow. This protection is best provided in the form of fences. Their efficiency will depend upon their strength, height, position, and distance from the track. The fence should be placed at such a distance from the track that, when drifted full, the snow will not reach within 30 feet of the track. To effect this, the distance of the fence from the track should be 12 feet for each foot in height of fence. When the fence is placed too near the track, the snow will be carried to the track before the fence is drifted full ; if, on the other hand, the fence is placed too far from the track, the wind, after clearing the fence, will fall and gather up all the snow between the foot of the drift and the track, and carry it into the cut. Usually but one side of the track re- quires protection from snow, viz., that side from which snow storms most prevail. Most railroads in the snow belt of the United States run in two general directions, viz., east and west, and as most of the severe storms prevail from the north, northwest, and northeast, the north side of most tracks is the only one requiring protection from snow. At some excep- tional points on the line, the topography of the country may cause complex currents of air which may produce results at variance with general rules. At all points, fences should be built to meet the existing conditions. In general, snow fences are built parallel to the track. For fences of ordinary height, the following rule can be safely followed: Place the fence 75 feet from the nearest track rail, extending it parallel to the track the entire length of the cut. Change the direction of the fence at both ends of the cut, gradually approaching the track until the ends of the fence are 100 feet from the ends of the cut and 50 or GO feet from the track. If the cut ends abruptly at the beginning of a high embank- ment, the turn in the fence must be made before the end of 1084 TRACK WORK. the cut is reached, in order to protect the cut from head and quartering winds. Cuts which are lined on the storm side by brush or heavy timber do not require fencing, as the only snow which reaches the track is that which falls directly upon it. The brushwood and timber prevent the blowing of the snow. Cuts made in a side hill where the ground slopes off abruptly into a valley do not require fencing. But where there is a long level or gently rolling stretch of ground on the storm side of the track, the cut is liable to drift full un- less properly fenced. When a fence becomes drifted full, its height may be readily increased by adding a wall of blocks of snow taken from the inside face of the drift. So long as the weather remains cold a snow wall will serve the full purpose of a fence. A first-class snow fence, kept in perfect repair, will not last above 10 years, and it becomes a question whether to build a snow fence or grade down the cut so that it will not hold snow. The items of cost to be considered are the first cost of the fence, the annual repairs, the interest on each charge for the time it is to serve in the fence, and if these combined items equal or exceed the cost of grading down the slopes so as to keep the cut clear of snow, the grading should be done. 1663. Bucking Snow. — The clearing of the track of snow belongs to the Roadmaster's Department, but it is essentially track work and at times of vital importance to a railroad. A man should be thoroughly familiar with the best methods of bucking snow before taking charge of an outfit to open up a road for traffic after a blockade. Before starting out on the road, he should be as thoroughly informed as possible as to the condition of the road, the location, length, and depth of drifts. He should have strong, live engines and willing engineers. The snow plow should be of the best make and able to throw snow out of a 10-foot cut. There should be two engines in the outfit. The second engine follows closely, with a car, conductor, train TRACK WORK. 1085 crew, and shoveling gang. When heavy drifts are encoun- tered too deep for one engine to successfully buck, the second engine is coupled to the first, and besides doubling the momentum, serves to pull out the head engine and plow in case they are stalled. The pilot should be removed from the second engine, and the coupling made short and very strong. No car or caboose should ever be placed between the engines, as they are likely to cause a wreck. When the drifts are more than 10 feet deep, the top of the drift must be shoveled out down to that depth, and a space made wide enough that effective work may be done by the plow. When the snow is reported hard, each drift must first be carefully examined and its length and height noted. If the drift has not been faced by section men (that is, shoveled out from the end of the drift to where its depth is from 15 to 18 inches), the gang of shovelers must do the work before a run is made with the plow. Unless the drifts are properly facedj the plow is liable to mount the rails, especially on curved track, and often the engine is derailed along with the plow. All cars attached to the helper engine shpuld be left behind while bucking snow. If both engines are not necessary to buck a drift, it is better to-do the work with one. The helper engine should only be used where necessary. If the snow is not too hard, a good, heavy engine will clear a drift from 3 to 5 feet deep and from 500 to 800 feet in length at one run. There is comparatively no danger in bucking soft, deep snow with an engine at top speed. The engines with a snow-plow outfit should take fuel and water to their utmost capacity at every point reached where a supply can be obtained. Unforeseen delays and mishaps may be encountered, and there must be no risk of a short supply of fuel or water. When the road is badly blockaded, the helper engine should carry an extra carload of coal. The water supply can be readily replenished by shoveling snow into the tank. Each engine in the outfit should carry a piece of steam hose, which can be attached to the siphon cock, and reach 1086 TRACK WORK. from it to the water hole in the tender. When the water supply needs replenishing, by shoveling snow into the tender and turning on the steam, a tank full of water can be quickly made. The steam hose can also be used to thaw the snow and ice from the machinery and track rails. In plowing snow the speed of the engine should always be regulated by the length and depth of the drifts. When the drift is deep and long, the engine should back up far enough to attain full speed before striking the drift. An experienced engineer will so regulate the speed of his engine as to leave but little work for the shovelers. The engineer of the plow engine should always sound the whistle when approaching a cut, in order that section men, if working there, may be warned in time to ^et out of the cut. Failure to sound the whistle has been a frequent cause of accident. When it is necessary to buck a drift a second time, the engineer must sound the whistle and be sure that all hands are out of the cut before entering it. It is almost impossible for men to climb up out of a snow cut when first opened up. When the snow drift is of such depth and length that two runs are likely to not clear it, it is the better policy to shovel out from both ends until it is certain that two runs will leave a clear track. When the snow is both deep and very hard, the crust should be broken up and shoveled out before any attempt is made with the plow. Bucking deep, hard snow with the crust unbroken is very severe work for a locomotive, and is often attended with danger to trainmen. It is far better to insure safety even at the price of delay. It is not advisable to start out to clear a track of snow during a heavy storm, but everything should be in readiness to start the moment the storm abates. The invention of the rotary snow plow has practically solved the snow problem, especially for clearing the track of hard snow. Many roads which suffer little from snow do not yet possess rotary plows, and the old custom of bucking snow is still practised when occasion requires it. TRACK WORK. 1087 CURVED TRACK. 1664. Difference in Lengtti of Inner and Outer Rails of a Curve. — It is evident that the radius of the outer rail of a curve is greater than that of the inner rail, and, consequently, its length is greater. This difference may be taken at 1 3V inches per degree of curve per 100 feet, for standard gauge track. The difference in length between the inner and the outer rails of a curve may be found by any of the three following rules : Rule 1. — Multiply the degree of the curve by the length in stations of 100 feet, and this prodiict by 1^^ inches. The result will be the difference in length between the inner and outer rails in inches. Example. — The degree of a curve is 4° ; its length 520 feet; what is the difference in length between the inner and outer rails of the curve ? Solution.— 520 feet = 5.2 stations of 100 feet each. 4 X 5.2 = 20.8. I5V in. = 1.03125 in. 20.8 X 103125 = 21.45 in. = 1.7875 ft. Ans. Rule 2. — Multiply the distance between the center lines of the rails by the length of the curve in feet and divide the product by the radius of the track curve. Example. — A 4° curve is 520 feet in length ; the distance between the center lines of the rails is 4 ft. 10^ in. ; what is the difference in length between the inner and outer rails of the curve ? Solution. — The radius of a 4° curve is 1432.69 ft. (See table of Radii and Deflections.) lOi in. reduced to the decimal of a foot is „^„ , 4.875 X 520 , ^^ . .87o ft. - ,.^cx nr. = 1- " ft. Ans. 1,432.69 Rule 3. — Multiply the excess for a whole circumference by the total number of degrees in the curve, and divide the product by S60. The excess of a whole circumference, no matter what the degree of curve, is equal to twice the distance between rail centers multiplied by 3. II^IQ. Example. — A 4° curve is 520 feet in length ; the distance from center to center of the rails is 4 ft. lOi in. ; what is the difference in length between the inner and outer rails of the curve ? Solution. — The distance between rail centers is 4.875 ft. 4 875 x 2x3.1416 = 30.6306 ft. A 4" curve for 520 ft. contains 20.8°. 30.6306 X 20.8-^-360= 1.77 ft. Ans. 1088 TRACK WORK. For light curves laid to exact gauge, the first rule is the simpler one, but for short curves where the gauge is widened use either the second or the third method. These rules should be applied in determining the number of short rails for curves, when loading material at the sup- ply yard for forwarding to the track layers. As previously stated, a safe rule is one 29^-foot rail per 100 feet for each 6 degrees of curvature. In laying track with either even or broken joints, the required number of short rails must be laid in proper order if a first-class job is to be expected.. 1665. Curving Rails. — When laying track on curves, in order to have a smooth line, the rails themselves must conform to the curve of the center line. To accomplish this the rails must be curved. The curving should be done with a rail bender (see Fig. 495) or with a lever, as shown in Fig. 497. The rail bender is preferable. To guide those in charge of this work, a table of middle and quarter ordinates for a 30-foot rail for all degrees of curve should be prepared. The accompanying table of middle ordinates for curving rails is calculated by using the formula in = ^, (112.) in which in is the middle ordinate ; c, the chord, assumed to be of the same length as the rail, and R, the radius of the curve. Example. — What is the middle ordinate m of a 30-foot rail for an 8° curve ? Solution. — The radius of an 8° curve is 716.78 ft. Applying the formula, we have ^ = 83r7T6?78= 5773424 = ^■'^' ^'- = '^ '"• ^"^^ The results obtained from this formula are not theoreti- cally correct, yet the error is so small that it may be ignored in practical work. With a table of radii such as is given in the table of Radii and Chord and Tangent Deflections, a table of ordinates may be readily calculated by substituting the known values in formula 112. TRACK WORK. TABLE 32. 1089 MIDDJLB ORDINATES FOR CURVING RAILS. Lengths of Rails. Degree of Curve. 30 Ft. 28 Ft. 26 Ft. 24 Ft. 23 Ft. 20 Ft. In. In. In. In. In. In. 1 oi OA OtV OtV Of Of 2 Oi OtV Of OtV Oi OtV 3 OH Of OA OiV Of OiV 4 OH OH OH Of Oi OiV 5 h\ ItV Oi Of Of OtV 6 ItV U iiV 0| Of Of 7 If 1 rV u ItV Of Of 8 li If lA ItV 1 o| • 9 2i u If If If OH 10 2f 3tV If U li lA 11 2f n HI iH If If 12 m 2i 2i iH ItV U 13 3iV 2H 2tV iH If If 14 3A n 2i n If U 15 3^ 3tV 2H 2i IH iiV 16 3f 3i m 2f 2iV IH 17 4 3i 3 9 9 2iV If 18 4t\ 3H 3A 2H 2J, ''T¥ 11 19 4tV 3J 3f n 9 ' 2 20 4H 4i 3tV 3 2tV n In curving rails, the ordinate is measured by stretching a cord from end to end of the rail against the gauge side, as shown in Fig. 517. Suppose the rail .^ .5 is 30 feet in length, and the curve 8°. Then, by the previous problem, the mid- dle ordinate at a should be IJ inches. To insure a uniform curve to the rails, the ordinates at the quarters d and d' should be tested. In all cases the quarter ordinates should 1090 TRACK WORK. be three-quarters of the middle ordinate. In Fig. 517, if the rail has been properly curved, the quarter ordinates at b and b' will be f X l|in. = l^f, say If in. With practice, a man having a good eye and good judg- ment will soon find his eye measurements closely checking his table measurements. When a quantity of rails are to be curved for curves of different degrees, it is a good plan to mark the degree of the curve of each rail in white paint on the web of the rail on the concave side. There should be ample force to handle the rails with dispatch, else much time will be wasted. The use of sledges in* curving rails should under no circumstances be allowed. There is great danger of fracture, and often a flaw is caused which at the time is not perceptible, but which may, under the stresses caused by frost and heavy trains at high speed, result in a broken rail, with serious consequences. In track work it is often necessary to ascertain the degree of a curve, though no transit is available for measuring it. The following table contains the middle ordinates of a one degree curve for chords of various lengths: TABLE 33. Length of Chord Middle Ordinate in Feet. of a V Curve. 20 ft. \ in. 30 ft. iin. 44 ft. i in. 50 ft. fin. 62 ft. 1 in. 100 ft. 2tin. 120 ft. 3f in. TRACK WORK. 1091 The lengths of the chords are varied so that a longer or shorter chord may be used, according as the curve is regular or not. The table is applied as follows: Suppose the middle ordi- nate of a 44-foot chord is 3 inches. We find in the table that the niiddle ordinate of a 44-foot chord of a one-degree curve is ^ inch. Hence, the degree of the given curve is equal to the quotient of 3 -=- ^ = 6° curve. Additional examples are given as follows: 1. The middle ordinate of a 100-foot chord is 14f inches; what is the degree of the curve ? Ans. 5.G°, nearly. The degree of the curve is probably 5° 30'. 2. The middle ordinate of a 50-foot chord is 5^ inches; what is the degree of the curve ? Ans. 8.4°. The degree of the curve is probably 8° 30'. 3. Calculate by rule 1 the difference in lengths between the inner and the outer rails of a 7° curve 475 feet in length. Ans. 34.29 in. =2. 857 ft. 4. Solve Example 3 by rule 2. Ans. 2.827 ft. 1666. Springing Rails into Curve. — Rails should never be sprung and spiked to a curve; the elastic force of the steel is constantly acting, and is sure to force the track out of line. Each passing train, through its centrifugal force, aids the rails to regain their original form. The re- sult is that in a short time the curve, especially it a sharp one, will show an angle at each joint. The effect at these angles is to cause a sudden lurch of the car at each joint, causing not only discomfort to passengers, but serious and constant wear and strain upon the roiling stock. 1667. Widening Gauge of Curves. — In passing over curved track, the car wheels bind hard against the out- side rail at the curve. The reason for this is that the differ- ence between the gauge of the track and the gauge of the wheels is taken up by the wheel base, which forms a chord to the curve of the track, instead of being parallel to the rails, as is the case on a straight line. To lessen this friction, 1092 TRACK WORK. the gauge is usually widened on curves to the amount of y^^ inch per degree, but never to exceed 1 inch on any curve. The increase in gauge is usually made in quarter-inches, that being the amount allowed for 4 degrees. The necessity for widening the gauge on sharp curves is still more apparent when we consider that provision must be made to accommodate cars of both standard gauge (4 feet 8^ inches) and for those of 4 feet 9 inches gauge, com- mon to Southern roads. When the gauge is not widened, a wide-gauged car is liable to mount the rail, especially if the flanges of the wheels are badly worn and sharp. The effect of all curva- ture is to increase the train resistance, and on sharp curves, this resistance, due to friction, becomes so great as to largely reduce the train load. All train loads are limited by the maximum resistance which they must overcome. This maximum resistance may be concentrated upon a single curve, and it is at once apparent that a railroad com- pany might well incur heavy expense in reducing this curv- ature, if by so doing they could add one extra car to each train load. Another charge against curvature is the loss of time to passenger trains which can not run over sharp curves, except at reduced speed. All curves exceeding eight degrees, besides their resistance to trains, cause a direct loss of time to all fast passenger trains. 1668. Guard Rails on Short Curves. — On straight track, laid to exact gauge, the guard rail is spaced 1|^ inches from the gauge rail; but when the gauge is widened, as on sharp curves, the amount of the increase in gauge must be added to the space between the gauge and the guard rail, 1 669. LiniuK Curves. — A common habit of trackmen when lining curves is to throw the curve outwards to line. The effect of this, in time, is to reduce the degree of curva- ture at the ends of the curve and sharpen it at the cen- ter, besides crowding the roadway on the outside of the curve. TRACK WORK. 1093 A safe rule is to always throw the track inzvards^ i. e. , tow- ards the center of the curve. It is at once apparent that the effect of the cen- trifugal force of the train in passing over a curve is to throw the track outwards, and in lining curves, the track should be thrown inwards, if for no other purpose than to (Overcome this effect of the trains. The effect of throw- ing the track out- wards when lining a curve is shown in Fig. 518, in which fig.sis. ABC represents the true line of the curve and A E C the position of the tracks due to improper lining. When track is first laid, there should be a track center stake driven at every 50 feet and carefully centered with a tack. Before and after ballasting, the track should be care- fully lined to the center stakes, and if the rails have been properly curved the track will hold its line, with occasional retouching, for years. In the case of a badly lined curve, select a piece of track 60 feet in length, which appears to be in good line. There are few curves, however badly out of line, but will show at least 60 feet of good line. At each end of the 60 feet of good track set an accurate center stake, and one in the cen- ter of the track midway between them. In Fig. 519, A and B represent the center stakes 60 feet apart, and C the stake midway between them. Stretch a cord from A to B, and measure the distance from Z, its middle point, to C. The distance C L\s the middle ordinate of a 60-foot chord. Next, mark the middle point L of the chord, and move the end A of the chord to C. Measure from B the 1094 TRACK WORK. distance B M— C L, and carry the measuring cord forwards, stretching it taut, and in the line C M, as determined by the offset B M. The forward end D of the cord will mark the spot for another track center. Then, move ahead as before, measuring another offset and stretching the cord to locate another center stake at E. In this way a perfect curve may be run in without the use of an instrument. It is better policy to set the track centers in line with the faces of the stakes for line rather than the tack centers, as the cord is sure to line properly to the faces of the stakes, but in order E Pig. 519. to line their centers they must be practically of the same height, which is sometimes difficult to obtain, especially if the ballast contains stone. Having set all the track centers, select a track gauge which is square and true, and mark a point midway between the gauge lines. Then, place the gauge on the track close to the track center, and direct the men to move the track until the middle point of the track gauge coincides with the track center. Line up the track at each track center until the entire curve has been moved to line; then, repeat the operation, giving the final touches, as a second lining should be sufficient. 1 670. Elevation of Curves. — To counteract the cen- trifugal force which is developed when a car passes around a curve, the outer rail is elevated. The amount of elevation will depend upon the radius of the curve and the speed at TRACK WORK. 1095 which trains are to be run. There is, however, a limit in track elevation, as there is a limit in widening gauge, beyond which it is not safe to pass. When we consider that the centrifugal force of a car in- creases as the degree of curvature, and as the square of the speedy we readily see how a slight decrease in speed will equalize a great increase in curvature. To illustrate: A car passing around an 8-degree curve will have double the centrifugal force of a car passing around a 4 degree curve at the same speed. But to neutralize the eflfect of sharpening the curve from 4 to 8 degrees, it is not necessary to halve the speed, but only to reduce it in an inverse proportion to the square root of the degrees of curvature. Thus, if a speed of 60 miles per hour is admissible on a 4-de- gree curve, the speed on an 8-degree curve is obtained by the proportion 60 : a' = |/8^ : 4/4, or .r = 42.43 miles per hour. If we again double the degree of the curve to 16 degrees, we only reduce the admissible speed of equal safety to 30 miles per hour. Hence, it will be seen that the centrifugal force developed by an increase in speed is not proportional to the centrifugal force developed by an increase in curva- ture. In consequence of this varying relation between curva- ture and speed, no fixed rule can be followed for elevating the outer rail of curves. It is a safe rule to elevate all curves to suit the highest speed of trains passing over that part of the track. Ordi- narily freight trains require the same track elevation as pas- senger trains. All railroad men know that freight trains repeatedly run at passenger train speed. The aim of every freight train conductor is to "make time, " and he makes it whenever the grades and train loads permit. On rolling grades it is often necessary to run down a grade at top speed in order to acquire sufficient momentum to carry the train to the summit of the following grade. Every day fast running is necessary in order to make up for time lost through unavoidable delays; hence, if a curved track is elevated to meet the requirements of passenger trains, freight trains will be equally well served. All curves, when possible, 1096 TRACK WORK. should have an elevated approach on the straight main track, of such length that trains may pass on and off the curve without any sudden or disagreeable lurch. The length of the approach should be in proportion to the elevation of the curve and not to its degree. A good rule for curve approaches is the following: For each half-inch or fraction thereof of curve elevation, add 30 feet or 1 rail length to the approach ; that is, if a curve has an elevation of 2 inches, the approach will have as many rail lengths as ^ is contained in 2, which is 4 times. The approach will, therefore, have a length of 4 rails of 30 feet each, or 120 feet. The following formula by Searles, viz. , c = 1.5S7V, (113.) gives the length of the chord c, whose middle ordinate is equal to the proper elevation of the outer rail of the curve for any velocity V in miles per hour. Example. — The curve is 8°, and the velocity 40 miles pei hour ; what is the proper elevation for the outer rail of the curve ? Solution. — Substituting the given values in formula 113, ^ = 1.587 V, we have c — 1.587 X 40 = 63.48 feet, the length of the required chord. To find the middle ordinate of this chord, we apply formula 112. We have just found c — 63.48 feet, and R — the radius of an 8° curve = 716.78 feet. Substituting these values of c and R in the above formula, we have 63.48* 4,029.7 ^ = 83<-7T6:78 = 57734:2 = -'^^'-"^^'"^y = ^^'"- ^"^- This result is too great. The best authorities on this subject place the maximum elevation at \ the gauge, or about 8 inches for standard gauge of 4 feet 8^ inches. The gauge on a 10° curve elevated for a speed of 40 miles an hour should be widened to 4 feet ^d\ inches. The following table for elevation of curves is a com- promise between the extremes recommended by different engineers. It is a striking fact that experienced trackmen never elevate track above 6 inches, and many of them place the limit at 5 inches: TRACK WORK. TABLE 34. 1097 Degree of Curve. Length of Approach. Elevation. Width of Gauge. Speed of Trains. 1 60 ft. 1 in. 4 ft. 8| in. 60 m] . per hr. 2 120 ft. 2 in. 4 ft. 8^ in. 60 mi . per hr. 3 150 ft. 2^ in. 4 ft. 8f in. 60 mi . per hr. 4 180 ft. 2f in. 4 ft. Si in. 55 mi . per hr. 5 180 ft. 3 in. 4 ft. 8| in. 50 mi . per hr. 6 210 ft. Biin. 4 ft. 8| in. 45 mi . per hr. 7 210 ft. 3iin. 4 ft. 9 in. 40 mi . per hr. 8 240 ft. 3iin. 4 ft. 9 in. 35 mi . per hr. 9 240 ft. 4 in. 4 ft. 9 in. 30 m . per hr. 10 270 ft. 4iin. 4 ft. 9 in. 25 m . per hr. 11 270 ft. 4iin. 4 ft. 9i in. 20 m . per hr. 12 270 ft. 4f in. 4 ft. 9i in. 15 m . per hr. 13 240 ft. 4i in. 4 ft. 9i in. 10 m . per hr. 14 240 ft. 4iin. 4- ft. 9iin. 10 m 1. per hr. 15 240 ft. 4 in. 4 ft. 9^ in. 10 m I. per hr. 16 240 ft. 4 in. 4 ft. 9^ in. 10 m . per hr. Many persons overrate the objections to sharp curves, especially where the grades are low. Their great objection is not in their being an obstacle to high speed, but in their great resistance to traction. Freight trains, which are usually heavily loaded, are much more impeded by sharp curves than passenger trains, which are generally lighter and made up of cars which more readily adjust themselves to irregularities in line and surface. No curve exceeding 10 degrees should be placed in the main line of any railroad. The additional cost of operating and maintaining a sharper curve would pay for tne addi- tional outlay necessary to bring the degree within the 10- degree standard. Many roads place the maximum curve at 6 degrees, and though beyond the reach of many roads, it is a safe standard. 1098 TRACK WORK. Besides the loss of time necessitated by running slowly on short curves, there is a much greater loss due to the wear and tear on rolling stock and upon the rails themselves. The friction of the wheel flanges against the rails rapidly wears them out, and the continual lurching and rolling of the cars detract greatly from the comfort of passengers. Most of the trunk lines in the United States have been greatly improved since their first construction, especially in their alinement, some of them being practically rebuilt. The Pennsylvania R. R. between Philadelphia and Harris- burg is a striking instance of the great improvement, both in alinement and grade, of a line originally cheaply and poorly built. Many of the original curves have been re- moved, and all of them lightened. In many places the original line has been entirely abandoned, and a new and better one adopted. This road is, however, an exceptional case, as few lines in the world could afford to make slight changes involving so great cost. 1671. The Elevation of Turnout Curves. — The speed of all trains in passing over turnout curves and cross- overs is greatly reduced, so that an elevation of ^ inch per degree is amply sufficient for all curves under 16 degrees. On curves exceeding 16 degrees, the elevation may be held at 4 inches until 20 degrees is reached, and on curves ex- ceeding 20 degrees, -^ of an inch of elevation per degree may be allowed until the total elevation amounts to 5 inches, which is sufficient for the shortest curves. 1672. Curve Approaches liet^'een Reverse Curves. — If possible, there should be a level piece of track, at least 60 feet in length, between reverse curves, besides the elevated approaches to the curves. When the whole of the intermediate tangent is required in making the elevated approaches to the curves, commence at the middle of the intermediate tangent, if both curves are of the same degree. If, however, they are of different degrees, make the ap- proach to each curve in proportion to its degree. In ele- vating the approaches to the curves, give to the first rail TRACK WORK. 1099 length an elevation of ^ inch, after which give ^ inch addi- tional elevation per rail length, or, if necessary, 1 inch additional elevation, so as to make the total elevation of the approach equal to the elevation of the outer rail of the curve. When a curve is compounded, commence to increase or decrease the elevation far enough back from the point of compound curvature to give to the second branch of the compound curve the elevation which it requires. This in- crease or decrease in elevation is made at the rate of ^ inch per rail length, precisely as in elevating the approach to a regular curve. When the changes in a compound curve are frequent and abrupt, it is best to elevate the outer rail for the highest degree of the curve and carry this elevation uniformly throughout the curve. 1673. Putting the Elevation in Curves. — If the track is in good surface, first catch up all the low joints on the inner rail of the curve. The elevation of the outer rail is determined by means of the track level shown in Fig. 520. For leveling track, the edge a boi the track level is Fig. 520. placed upon the rails, and when perfectly level the bubble c of the spirit level will rest in the middle of the tube. The steps d, e, etc., of the track level are made 1 inch in height, so that when the step ^-is placed on the outer rail of a curve and the rail raised until the bubble of the spirit level rests in the middle of the tube, the outer rail has an elevation of 1 inch. Similarly, the step e, when brought to a level, would indicate a track elevation of 2 inches, etc. Having determined the amount of elevation required for the curve, the outer rail is raised with the track jack and the ballast thoroughly tamped under the ties. The elevation 1100 TRACK WORK. should be about ^ inch in excess of that required, in order that provision may be made for settlement. In dressing the track after the elevation has been made, make the crown of the ballast at not more than one-third of the width of the gauge from the outer rail, in order to secure drainage. The raising of the outer rail reduces the outer slope and increases the inner slope of the ballast. If the curve is sharp, the ballast on the outer half of the track is practically level and holds water, instead of shedding it. By crowning the ballast as directed, thorough drainage is in- sured. 1674. The Effects of Curved Track upon Loco- motive and Car Wheels. — The effect of all curved track, however easy the curve, is to wear the flanges and treads of car wheels. This effect is due to the centrifugal force which forces the flanges of the wheels against the head of the out- side rail of the curve. The elevation of the outer rail, the widening of the gauge, and the coning of the car wheels, all combine to reduce this friction and consequent wear. Where the elevation is insufficient, the friction increases, and if the gauge is the same as on straight track, there is great danger of the wheels mounting the rails, especially if the flanges are badly worn. The conclusion from many years of experiment and close observation is that the wear of rails on curved track is largely due to the driving wheels of the engine. When the tires become worn, the wear of the rails rapidly increases, and hence the importance of careful and repeated inspection of the driving wheels. As soon as they show considerable wear, the tires should be turned off to true lines. Besides preventing unnecessary wear of rails, this greatly increases the tractive power of the engine. When the treads of car wheels become badly worn, especially at the flanges, there is bound to be more or less slipping of the wheels. For the outer rail, being the circumference of a greater circle, should require a wheel of greater diameter than the inner wheel, if both are to make TRACK WORK. 1101 the same number of revolutions. This increased diameter is given by the coning of the wheels, shown in Fig. 521, in which the rail a is on the outside of the curve. An inspec- tion of the figure will show that the cone-shaped tread of the wheel b gives a greater diameter to the wheel at c d than at e f. In passing around the curve, the flange of the wheel b is forced against the rail a, while the flange of the wheel Ji recedes from the rail g. This increases the diameter of the wheel b, while decreasing that of the wheel //, and so the ex- Fig. 521. cess in length of the outer rail of the curve is at least par- tially covered. Careful experiment proves that under the most favoring conditions some slipping of the wheels is bound to occur. The friction between wheels and rails rapidly increases as the rails become worn, and, as soon as the head of the outer rail of a curve becomes badly worn, the outer rail should be taken up and placed on the inside of the curve, and the inner rail put in its place. This furnishes almost new wear- ing surfaces to the wheel, and the life of the rails is greatly prolonged. 1675. Care of Curved Track. — As curved track offers greater resistance and greater danger to passing trains than straight track, special eff"ort and pains should be taken to maintain it in perfect order. All trackmen know that a low spot on a curve will cause every car in a train to 1102 TRACK WORK. lurch heavily towards the low side. By careful watching, and by prompt and thorough repairs, curved track may be kept in perfect or- der. It is highly important that the ele- vation of the outer rail be kept uniform, and no foreman, however experienced, should place dependence upon his eye in estimating curve elevation. Both the civil engineer and the track forepian will do well to cultivate each other, the engineer imparting theoretical knowledge in exchange for practical knowledge. The result will certainly pro- mote mutual respect and enhance the efficiency of both. FROGS AND SWITCHES. FROGS. 1676. Turnouts. — A turnout is a device for enabling an engine and train to pass from one track to another. It con- sists of two lines of rails a b and c d (see Fig. 522), so laid as to form a reversed curve uniting the two tracks A B and C D. The several parts of a turnout are as follows: The switch rails r / and gh^ the frogX', and the two guard-rails / m and n o. The stationary ends c and g of the switch rails are called the heels, and the movable ends / and h are called the toes. The distance / /», through which the toes /"and // move, is called the throw. The throw must equal the width of the head of the rail, with sufficient additional width to allow the flanges of the wheels to pass freely between the main rails r s and / ti and TRACK WORK. 1103 the turnout rails a b and c d. The throw on tracks of stand- ard gauge is 5 inches; that is, the toes /"and // are moved 5 inches from their original position in the main track in forming the turnout curve on which the train is to pass from the main track ^ ^ to the siding C D. The movement of the switch rails is effected by means of a lever. 1677. The Frog. — The frog is a device by means of which the rail at the turnout curve crosses the rail of the main track. The frog shown in Fig. 523 is made of rails having the same cross-section as those used in the track. Its parts are as follows: The wedge shaped part A is the tongue, of which the extreme end a is the point. The space b, between the ends c and ^^of the rails, is the mouth, Fig. 533. and the channel which they form at its narrowest point e is the throat. The curved ends/ and g are the wings. That part of the frog between A and A' is called the heel. The width h of the frog is called its spread. Holes are drilled in the ends of the rails c^ d, k, and / to receive the bolts used in fastening the rail splices, so that the rails of which the frog is composed form a part of the continuous track. 1678. The Frog Point.— The theoretical point of frog a' (see Fig. 523) and the actual point a are quite dis- similar. The reason for making a the point of frog is that if the theoretical and actual point of frog were the same, the point would be so small that the first blow inflicted by a passing locomotive or car would completely destroy it. The frog point is accordingly placed at rt, where its width is about \ of an inch. 1104 TRACK WORK. 1(>79. The Frog Number. — The number of a frog is the ratio of its length to its breadth, i. e., the quotient of its length divided by its breadth. Thus, in Fig. 523, if the length a' /, from point to heel of frog is 5 feet, or 60 inches, and the breadth h of the heel is 15 inches, the number of the frog is the quotient of GO -r- 15 = 4. Theoretically, the length of the frog is the distance from a to the middle point of a line drawn from k to /; practically, we take as the length the distance from a to /. As it is often difficult to determine the exact point a of the frog, a more accurate method of determining the frog num- ber is to measure the entire length d I of the frog from mouth to heel, and divide this lefigth by the sum of the mouth width b and the heel width h. The quotient will be the exact number of the frog. For example, if in Fig. 523, the total length d I oi the frog is 7 feet 4 inches, or 88 inches, and the width /; is 15 inches, and the width b of the mouth is 7 inches, then the frog number is 88 -=- (15 -f 7) = 4. Frogs are known by their numbers. That in Fig. 523 is a No. 4 frog. 1680. The Frog Angle. — The frog angle is the angle formed by the gauge lines of the rails, which form its tongue. Thus, in Fig. 523, the frog angle is the angle la' k. The amount of the angle may be found as follows: The tongue and heel of the frog form an isosceles triangle (see Fig. 524). By drawing a line from the point a of the frog to the middle point b of the heel c d, we form a right-angled triangle, right-angled at b. The perpendicular line a b. TRACK WORK. 1105 bisects the angle a, and, by rule 5, Art. 754, we have tan be ^ a =: —J. The dimensions of the frog point given in Fig. 52-4 are not the same as those given in Fig. 523, but their relative proportions are the same, viz., the length is four times the breadth. The length a ^ .— 4, and the w^idth c d = 1; hence, d c — ^. Substituting these values, we have tan ^ rtr = f = ^ = 0. 125. Whence, ^ a = 7° 7^', and a = 14° 15'; that is, the angle of a No. 4 frog is 14° 15'. Frog numbers run from 4 to 12, including half numbers, the spread of the frog increasing as the number decreases. 1 681 . Classification and Description of Frogs. — Frogs, as manufactured to-day, are of two classes, viz., sti^ frogs and sprtng-rail frogs. Each has advantages peculiar to itself, which specially adapt it to certain situations. Stiff frogs contain much less material and require less shop work than spring frogs. For a given angle a stiff frog requires less space, and hence is better adapted to yard work than spring-rail frogs. They are more simply con- structed than spring frogs, and can be made at any well- equipped machine shop. Spring-rail frogs, because of their furnishing an unbroken surface to the wheel treads, are particularly adapted to the heavy traffic of a trunk line. Pig. 625. Figs. 525 and 526 represent the best types of stiff frogs. The frog shown in Fig. 525 is called a plate frog. The rails composing the frog are fastened to a plate of wrought iron or steel a c d b by means of rivets through the rail flanges, as shown in the figure. Square holes r, f are 1106 TRACK WORK. punched in the plate to receive the railroad spikes, which are driven into the cross-ties supporting the frog, holding it firmly in place. Plate frogs are perfectly rigid, and by many railroad men are considered inferior to the keyed frog, shown in Fig. 526, which is somewhat flexible and better (fix iff r£fe\ ^ B Fig. 526. suited to yard work where the curves are sharp and the frog angles correspondingly large. In this frog, the pieces of rails a and I?, forming the point, are dovetailed together and secured by heavy rivets. To retain the full strength and durability of the steel, all the parts are fitted without being heated, excepting the wings, which are bent at a very low heat. Hence, the strength of the rails is in no respect diminished, and the method of securing the parts together has advantages over bolts or rivets passing through the webs or flanges of the rails, as there is nothing which can come in contact with the wheel flanges. From its peculiar construction, it has the same elasticity as the rails in the track, which makes it an easy riding frog, more durable than a rigid frog, and less liable to injury from uneven ballasting. It presents little obstruc- tion to tamping, and, when fastened into the track with the usual angle splices, it is firm, stable, and free from any tendency to jump or move. The parts are bound together by heavy wrought-iron clamps c and d^ shown in the cross-sections A and />, A being a cross-section through the first clamp and B one TRACK WORK. 1107 through the second clamp. These clamps are tightened by means of beveled split keys, or wedges, e and/", the ends of the clamps being bent over a form to an exact angle, at one end to fit the brace blocks k and k' on the outside of the rail, and at the other end to fit the beveled keys, which are driven into the spaces between the end of the clamp and the smaller brace blocks /, /'. The keys lie on the flange of the rail, which prevents them from dropping down in case they loosen. The flange way between the frog point and the wing rails is maintained by iron throat-pieces g, h, g\ and h\ which fit the rails perfectly, and, extending beyond the point, thoroughly brace and stay it against lateral stresses. After tlie keys are driven to the extent necessary to bind the parts solidly together, the split ends are spread to prevent the keys from working out. The throat-pieces, as well as the brace blocks, are effect- ually prevented from sliding out of their positions. The clamps are firmly secured to the flanges of the rails, and the only movable pieces in the frog are the keys which, being thicker on their lower edge (owing to being beveled un- equally), together with the angles of the clamps, prevent the keys from working upwards. Trackmen, when inspect- ing track, should always examine the frogs, and any key loosened by the wearing of the parts should be tightly driven, and the split end spread open. Unless a key is loose it should never be hammered. A standard type of a spring-rail frog of keyed pattern is shown in Fig. 527. For main line tracks, and especially for those sections where the heavy traffic moves principally in one direction, the spring-rail frog is recommended. It gives to the main line the smoothness of an unbroken track; it is simple in its construction, thoroughly substantial, and is placed in position with the least amount of labor. As shown in the figure, the fixed parts of the patent keyed spring frog 2st. bound together by two heavy clamps rt and b^ shown in the details A and B, which are sections through the clamps zX. C D and E F. The parts within the clamps are secured by split keys or wedges c and d. The frog point 1108 TRACK WORK. G is made of two pieces of steel rail fitted and dovetailed together by machin- ery, without being heated, and securely riveted together. The flange way between the point and wing rails is maintained by closely fitting iron throat-pieces e and f (shown in the detail sections A and B^, which are prevented from slipping by rivets and pins through the rails. The clamps have side notches g and g' at one end (shown in detail at Z), which engage with notches in the flange at the frog point, and prevent the clamps from slipping down, even if loose. The other end of the clamp is bent over a form to an exact angle to fit the beveled split key, which is driven into the space between the clamp and the block, which is fitted and se- cured to the side wing rail. When the key is driven, the parts of / V* "j ^ ii , Lil |ii| .\.\. i— -- /' TRACK WORK. 1109 the frog are tightly bound together, and the key resting upon the flange of the rail is prevented from working down and loosening. The outer end of the clamp is secured by clips, which are riveted to the flange of the rail. In case the parts of the frog become loosened by wear, they may be tightened by driving the wedge further in and spreading the split ends so as to hold the key firmly in place. That part of the flange of the spring rail next to the frog point is planed off, allowing the head of the spring rail to lie close to the frog point, forming almost a continuous rail and fully accommodating all classes of wheels passing the frog. Powerful springs H and K hold the spring rail firmly against the frog point, and the slide arm //, which is held in place by the clip k, attached to the slide plate (shown in the detail section M N), prevents the spring rail from rising up or moving out too far. The usual length of this spring frog for any angle is 15 feet. 1682. Crossing Frogs. — Where one railroad crosses another at grade, frogs of special design, called crossing frogs, are required. They are of various patterns, depend- ing upon the angle of the crossing and the importance of the line. In Fig. 528 a cut is given of a standard crossings which embodies the best features as determined by ex- perience. This crossing is made of the best quality steel rails, fitted with exactness. The points are mitered, dovetailed, welded, or forged out of solid rails, the angle of the crossing and the requirements of the case determining which method is the most practicable. The rails are mounted on strong wrought- iron bed-plates A, B, etc., to which they are securely riveted through the flanges of the rails. The guard-rails a, b, c, and d, inside the intersecting tracks, extend unbroken on all sides, and extend outside the frog points so as to guide the trucks, causing them to pass squarely through the crossing. At all the angles the flange way is completely filled by wrought-iron throat fillers c, /, and c, which are shaped to exactly fit the rails. 1110 TRACK WORK. All the corners are braced with heavy wrought-iron braces^, h, k^ etc., forged to shape and planed to fit solid in the fishing spaces of the rails. Strong bolts, /, m, etc., passing through the webs of the rails, the throat fillers, and corner braces, bind the parts of the crossing firmly to- gether. All the inside splice joints are provided with solid iron throat blocks «, o between the rails in addition to the usual splice bars. The splice bolts / and q pass through splice bar, throat block, and rail, binding all securely together. Care should be taken that no bolts project through the bed- plates, necessitating the cutting of pockets in the crossing timbers to receive the bolt heads, as increased decay is sure" to follow. 1683. Replacing Frogs. — A replacing frog is a device for replacing derailed cars upon the track. Such a frog must combine portability and great strength. It must be flexible and compact, and of simple construction. The replacing frog shown in Fig. 529 combines practically all of these qualities. This frog consists of a heavy steel Fig. 529. bar a slightly curved. The bar is bolted at one end to a heavy steel hook b which hooks under the head of the rail. The joint r, connecting the bar and hook, allows the frog to be placed in any desired position. The end d oi the bar is hooked and pointed. In using the frog, the hook b is first adjusted; the end d is then placed directly in front of the wheel of the derailed truck, and the point d of the bar driven into the cross-tie with a sledge. This holds the TRACK WORK. 1111 replacing frog rigidly in place. A replacing frog is placed in position on both rails, and the car pulled on to the track with a locomotive. Where the trucks are slewed crosswise to the track, the car must be jacked up and the trucks straightened before placing the frogs. SWITCHES. 1 684. Classification of Switches. — Although there have been many different kinds of switches devised, only two of them have ever been in general use; viz., stub and split, or point, switches. Stub switches are now rarely used on first-class roads, even in yards, the split or point switch hav- ing entirely supplanted them. It is estimated that 50 per cent, of the derailments on American lines have been direct- ly chargeable to the defects of the stub switch. The principal defect in the stub switch lies in the open joint at the head-block. In passing over this joint, each wheel delivers a heavy blow on the ends of the rails at the point, which not only batters the rails but also causes a heavy jolt to the car, injurious to the rolling stock and caus- ing much discomfort to passengers. Stub switches are more liable to misplacement than split switches, and there is the constantly recurring need of recutting the ends of the rails at the head-block, to provide for expansion and for the removal of battered ends. 1685. The Stub Switch.— The essential parts of a stub switch are shown at A in Fig. 530. The rails a b and c d are the switch rails placed for the turnout track. Their position when placed for the main track is indicated by dotted lines at e and/". The switch rails are commonly used in lengths of 30 feet, the standard rail length, of which only 22 feet are free to move or slide, the remaining 8 feet being spiked to the ties, as shown in the figure. The mov- ing portions of the switch rails are held in place by rods g^ h, k, and /, called s^vitch rods. These rods keep the switch rails at proper gauge, and serve the purpose of track spikes. 1112 TRACK WORK. ^fe^M 1 F ' ^ TRACK WORK. 1113 The first switch rod g is called the head rod. It extends outside the rails, and by means of the connection rod in, it is attached to the lever n of the switch stand, by means of which the switch rails are moved from their connection with the main track rails o and />, to a connection with the turnout rails ^ and r. This movement of the switch rails is termed throwing the switch. The switch stand, and connection and head rods of this switch are shown in detail at B. The switch stand Z> con- sists of a cast-iron plate s to which is cast a semicircular lug /. A hole in this lug receives a pin, which is attached to the end of the lever n. The connection rod ;// is attached to the lever by means of the pin u, and is held in place by a nut. The lever handle is slotted, and when the switch is set for either track, the slot fits over a staple v, projecting above the lever far enough to receive a padlock w which locks the switch. The switch rods clamp the switch rails firmly, as shown at X. The head chair, shown at E, is of cast iron, and con- tains sockets^, y, into which the ends of the main and turn- out rails o and q securely fit. The lateral movement of the switch rail is limited by the lugs z and z\ which are cast into the chair. The head chair is usually fastened to the head- block with track spikes. The cross-tie F, which supports the head chairs and switch stand, is called the head block. The head block and all other switch ties should be of hard wood — oak preferably. The ties under the switch rails should be of sawed timber, so as to present a smooth even surface for the sliding rails. This type of switch stand is equally well suited to split switches, and on account of its compactness is especially suited to yard work. The stub switch is cheaper than the split switch, and for tracks owned by private concerns, it serves very well ; but for railroads doing a regular freight and passenger business, it is not only out of date, but should be condemned as unsafe. 1114 TRACK WORK. .1115 1686. Split, or Point, Switches.— The split, or point, switch does away with the open joint at the head block and gives a continuous bearing to the car wheels. The two common types of split switches are shown in Figs. 531 and 532. In Fig. 531, the rails A A' and ^^' are called the stock rails. In the split switch, the heels and toes of the switch rails are exactly the reverse of those in the stub switch, i. e. , the heels in the split switch are in the places occupied by the toes in the stub switch. The stock rails are spiked throughout their entire length. The switch rails C C\ D D' are usually 15 feet in length for all turnouts excepting those in yards where limited space requires very sharp curves, and switch points 12 feet in length, or even less, are used instead. The switch rails are usually straight and planed down so as to fit closely to the stock rails for 6 or 7 feet. The points C and D are planed down to a thin edge, the web of the switch rail being grooved so as to fit under the head of the stock rail. The base of the switch rail is planed so that it fits snugly against the upper part of the base of the stock rail. The ex- treme points of the switch rails are slightly below the level of the stock rails, so that the wheel treads do not come in contact with them until their size and strength are sufficient to stand the hard pounding which all switches receive. The slide plates a, b, c^ d^ e^ and /"extend under the stock rails and points, and are spiked to the cross-ties. The switch rods g, h, k, /, and m are of wrought iron, and of such dimensions as the size and weight of the rail require. They are fastened to the switch rails in various ways. In Fig. 531, the connection is made by means of cast steel sockets which are belted to the webs of the rails. The switch rod g, con- necting directly with the switch stand, is called theliead rod, and is shown in detail at E. The cast-steel sockets // and n' are longer, and extend low enough to permit the head rod to pass under the rails, as shown in the detail. The head rod is fastened to each socket with two bolts, while the other switch rods are single bolted. 1116 . TRACK WORK. The stock rails are spiked only on the outsides of the rails, and to prevent the rails from getting out of line, the slide plates are bent upwards at the outside of the rail, forming the lip o (see detail at 7^), which holds the rail brace p solidly against the stock rail. The connection rod q is fastened at one end to the head rod and at the other end to the crank r of the switch stand, shown in detail at G. The switch stand rests upon two cross-ties s and s\ being securely fastened to them either with bolts or track spikes. The switch stand consists of the column-shaped support /, the lever «, used in throwing the switch, the target ?', and the crank-shaft r. The target v consists of two rectangular pieces of sheet iron fastened to the target rod at right angles to each other. One-half of the target is usually painted white, indicating safety, and the other half red, indicating danger. They are so adjusted that an open switch always indicates danger. The lever u carries a. cam or eccentric-shaped disk u> which, when in the position u, fits between lugs x\ the lugs are bolted to the pedestal t, and form a part of the rigid stand. When the lever is in the position //, the switch may be locked, holding the switch firmly in place. To throw the switch, raise the lever to the position u'. This releases the cam w from the lug x, and the lever being clamped to the target rod or shaft J, any movement of the lever u is communi- cated to the crank r, which, by means of the connection rod g, acts directly upon the switch rails. The throw of the switch is from 4^ to 5 inches. The rail braces / are usually of forged steel, though some are still made of cast iron. 1687. Safety Switches. — When a train passes from the main track to the side track, it necessarily passes the points of the switch first. Such a switch is called a facing switcti. When, on the other hand, a train passes from the side track to the main track, it passes the frog first. Such a switch is called a trailing switch. TRACK WORK. 1117 1118 TRACK WORK. William Lorenz, chief engineer of the Philadelphia and Reading Railroad, has the credit of designing a self-acting switch, which is provided with a powerful spring that holds the switch points firmly against the stock rail, thus keeping the main track constantly unbroken. With the switch points in this position, a train can make a trailing switch, the wheel flanges forcing the switch open as they pass from the side to the main track. As the spring is constantly act- ing, each wheel throws the switch, which instantly resumes its position for the main track. Such a switch is called a Lorenz, or safety switch, and is shown in Fig. 532. With the exception of the spiral spring'^, which is attached to the head rod and holds the switch point a against the stock rail b, this switch is similar to that shown in Fig. 531. The switch rods c, d, and e, instead of being single rods "W^ith arms at their ends for attaching them to the switch rails, as in Fig. 531, have a trussed center piece, shown in detail at B, composed of two bars/" and g, riveted together and leaving between them just space enough to allow the ends of the arms // and k to move as the switch is thrown from one side of the track to the other, the arms pivoting on the rivets / and in at the end of the center piece. This form of switch rod combines flexibility with great strength, insuring easy movement to the switch and great resistance to the severe stresses which are continually brought to bear against it. The switch rods are bent downwards near the arms, bring- ing them nearly on a level with the top of the tie, where they are less exposed to injury from derailed cars or from broken parts of the cars, such as brake rods or beams, which dragging on the ties frequently catch in switch rods, doing much harm. The safety switch, shown in Fig. 532, is of a pattern com- monly used in yards and terminals. The switch points vary in length from 7^ feet to 12 feet, the former fitting all frog numbers as high as 7, and the latter serving for frogs of all numbers. TRACK WORK. 1119 The advantages of this switch are its compactness, requi- ring little more than half the space of an ordinary switch; lightness, which insures easy handling, and its adaptation to sharp curves which abound in yards and terminals. The short points permit of trailing switches equally as well as facing switches, as the planed portion of the points is short, and, consequently, carries a much shorter proportion of the wheel base of an engine or car than the switch of the standard length. The short points also require lighter springs than the standard lengths, and are much easier cleared of snow. The details of the switch are practically the same as those of the switch shown in Fig. 531, which were fully described. A common yard stand suitable for this switch is shown in both plan and elevation at C. The target is about 4 feet above the ground, and is provided with an attachment for signal lamp. The lever is hinge-jointed, and in throwing the switch, the lever is brought into a horizontal position, resting on the semicircular iron latch plate E. In the edge of this plate are two slots n and o^ into which the lever hinges after the switch is thrown. Lugs/ and q at the sides of the slots, limit the lateral movement of the lever. The switch stand is secured to the head-block by either bolts or track spikes, usually the latter. 1688. Three-Throw Switches. — A cut of a three- throw, or double-throw, switch is given in Fig. 533. The type is that of the ordinary stub switch, except that the mov- ing or switch rails serve two turnout tracks instead of but one. The head chair A is usually of cast iron and contains sockets rt, ^, and c (see detail B) for the fixed rails d^ e, and/". The switch rails ^ and h have a total lateral movement at the head chairs of from 10 to 12 inches, depending upon the dimensions of the rails. Their lateral movement is fixed by the lugs^, k on the head chairs. The switch stand is shown in elevation at C, and in plan at D. The three positions of the switch are fixed by the slots /, w, and o in the latch plate into which the switch lever hinges. 1120 TRACK WORK. A more comprehensive idea of a double-throw switch may be obtained from the detail given at E, which shows to a re- FIG. KM. duced scale the switch and both turnout curves with main rail frogs/ and v, and the crotcli frog r, by means of which TRACK WORK. 1121 the outer rails of the turnout curves cross each other. The turnout curves of a double-throw switch are usually of the same degree, which brings the crotch frog in the middle of the main track. The defects of the stub switch already described should prevent its use.in the main track at yards, and at terminals where trains move slowly, as well as at intermediate points where trains run at top speed. A double-throw split switch has been invented and used in a limited way, and though a perfect switch so far as mech- anism is concerned, it is much more expensive and complicated than a double-throw stub switch, and is not enduring. The object of the double-throw switch, viz., economy of space, is practically attained by substituting two single split Fig. 534. switches, placed as close together as is consistent with their safe operation. Such an arrangement is shown in Fig. 534, in which a a' and b b' are the rails of the main track. A 7° 30' turnout curve c e \^ laid out to the right of the main track. This calls for a head block at c and a No. 9 frog at/". A 17° turnout curve g in is next laid out to the left of the main track, with its P. C. located so as to bring the head block ^ of the second switch far enough from the heel d of the first switch to afford suflEicient room for operating the second switch. This calls for a No. 6 frog at k and a No. 5^ crotch frog at /. 1689. Derailing Switches.— A derailing switch is a device for derailing cars, and so preventing them from accidentally running out of the siding on the main track. 1122 TRACK WORK. c fc._nr} c -&Q- n *i^r^ c ^ ' "- 1 ^L ^^ ^ _i ^L.J_J L -J c: =1 C "^l"^ 8i=^ G 1 1 1 •®^ r "fin 1 — w Hm _i "1 c HH ■ :i c: / \ \ 1 / \ 1 ^~ f I I -| \ 1 r "j f 11 11 ■ 1 ^r 11 ir □ \l ' \\ 1 r^i \Vn \\ Cj if 'n \i 1 JL llilil \\ Cjt \vA \\ -| // iV'i li / f \\m \\ 1 r-//- \l\vl \l at Wm \\ ■ 1 ;r \|\'l \\ // "1 ,— //- iim W r1/^ i"« >> 1 . / nn — ^r *>// "1 . I ■ \M W 1 It 11^ \i "1 // \m n / Mil— ^ 1 // ^ ' ;/ I* \\ 1 7 ^Pl ri 1 // \m W 1 tj ir-' i ' Cil 1 \\ Cil 1 qfc qt q q q q car: -1 -1 -1 -i II "1 Z) -i II I) II -1 11 — 1 1 "1 ^- — _1 1 ^ -1 5- j j 1 ^ i ^e» Lusaj "^1 _) ^«^-^ _) TRACK WORK. 1123 They are, of course, needed only for sidings built with grades descending towards the switch. An effective type of a derailing switch is shown at A in Fig. 535. It consists of a single switch rail a, which is hinged at the rail joint d. The switch point c is beveled, as shown in the detail at C. When the switch is closed, this beveled switch point rests against the outside rail of the siding, which is bent at an angle corresponding to the bevel of the switch point and shown at d, forming a lap switch. When the switch is open, the switch point rests against the guard rail e, the end of which is beveled to form a seat for the switch point. The beveled ends of both track and guard rail rest upon a wrought-iron head chair /, shown in detail at C, upon which the switch point slides. This switch is connected with and operated by the move- ment of the main line switch B. The figure shows the switch set for the main line, and the derailing switch set to throw from the track a car moving out of the siding. The derailing switch is operated as follows: A bell-crank g is pivoted to a cross-tie, with one end of the crank at- tached to the head rod of the switch B. To the other end of the crank is attached a strong steel wire which extends to a sheave //, directly opposite the derailing switch A, and thence to an eye k, as shown in detail at C and D, in the end of the head rod. This wire is kept taut, so that any movement of the switch B is communicated directly to the switch rail a. The connection rod / is attached to the short arm in of the switch lever; and when the switch is set for the main line E E, as shown in the figure, the resulting stress in the wire is transmitted to the short arm m of the derailing switch lever; the long arm of the lever which carries the weight o is then brought into the position n, and the switch rail or point takes the position a (see detail C), leaving the derailing switch open and protecting the main track from runaway cars. When, on the other hand, the switch is placed for the siding E F, the tension on the wire is relaxed and the long arm n of the derailing switch lever, being acted upon by the 1124 TRACK WORK. weight ays remain out with the signals until all danger is passed. As soon as the track is safe for the passage of trains, flags, torpedoes, or other signals should be removed at once. Foremen should always carry flags and torpedoes on their hand cars, and fully instruct their men in the use of them. They should be fully posted on the time of all 1152 TRACK WORK. regular trains, and should be on the watch for signals carried by regular trains. 1713. Signals. — In setting a signal requiring a train to run slowly, called a slow flag, place the flag on the engineer's side of the tracks the right hand side, slightly leaning, so that most of it can be seen, and just far enough from the rail to clear the engine and cars. A slow signal is set out one-half mile, about 17 telegraph poles, distant. A red flag or light, which is a stop signal, should be placed in the center of the track. Two torpedoes should be placed on the same rail, about 60 feet apart, between the stop signal and the approaching train. 1714. Location of Whistling Posts and Signs. — Station whistling posts should be placed one-half mile out- side the switch, not the depot, and on the engineer's side (the right side) of the track to one approaching the station. Station mile boards should be placed one mile outside the switches. If the post were placed but one mile from the station, it would, in large yards, often fall inside the switches. The object of these signs is to warn trainmen of the near approach of a station in order that they may have the train under control before reaching the station. Whistling posts for highways should be placed one-quarter of a mile from the crossing, and on the engineer's side of the track. Whistling posts or other signs should never be placed in a cut where they will not be readily seen. If on a descending grade, place the sign- outside the cut, increas- ing the distance; if on an ascending grade, decrease the distance. This rule also applies to sharp curves. All signs carrying a cross-board should have the board placed at right angles to the track. Highway crossing signs should be placed parallel to the rails, so that they may be distinctly read by persons approaching the track. All posts carrying signs should be vertical, and securely set in the ground, and so placed as not to come in contact with either trains or vehicles. TRACK WORK. 1153 1715. Obstructing the Track. — The track should never be so used as to obstruct a regular train, nor should any work be undertaken which can not be finished, and the track made safe, fully 15 minutes before the train is due. In case of a delayed passenger train, the track must be kept constantly safe and clear, and if repairs must be made, a responsible man, preferably the foreman himself, should remain out with signals until the track is safe and clear. Some foremen have a habit of leaving the hand or push car on the track while repairs are being made. This is a dangerous practice, and contrary to the rules of any well- managed railroad. The hand car should not only be kept clear of the track when not in use, but should not be left in the way of road or farm crossings. 1716. Hand-Car and Tool Houses. — Hand car and tool houses should be placed outside the switches at yards and stations, so that trains standing on the side track will not deter section men with their hand car from going to work. Tool houses must be far enough from the track to prevent obstructing the view of passing trains. 1717. Throwing Sivitches. — Foremen should not throw switches for trivial reasons. An empty hand car or push car should always be carried from one track to another, and, if carrying a light load, it can be handled without throwing a switch. Most foremen carry a switch key, but it should be used with proper discretion and never -in the absence of the foreman. The person tending to the switch should always retnain by it until it is set for the main track and locked. Any foreman who makes a practice of throw- ing switches where it is unnecessary should be discharged at once. 1718. Care of Tools. — The section foreman is re- sponsible to the railway company for all tools and other supplies issued to him. The systematic use and care of tools will greatly increase their efficiency and prolong their 1154 TRACK WORK. service, and it is evident that the foreman can not better serve his company than by instructing his men in the proper handling and care of tools. Hand cars and push cars should be oiled regularly, the axle and other boxes kept tight, and the cars kept always ready for service. Hand cars should not be used to carry steel except in emergencies, and then only a light load should be taken, the rails being placed on both sides of the car so as to balance. Both rails and ties should be trans- ported on the push car. Shovels figure largely in the tool account chargeable to track repairs. On most sections this account is unneces- sarily large, owing to the many improper uses to which the shovel is put. A shovel should never be used to hold up the end of a tie for spiking, -nor driven into a tie in place of a pick to pull the tie into its trench in the track. As soon as the edge begins to turn, it should be straightened, and, if necessary, trimmed with a cold chisel. Proper care will often double the life of a shovel. Claw bars should never be used to pry up the track, and, above all, in frosty weather, as the claws are then easily broken, and are always difficult to repair. 1719. Care of Material. — A sure test of a good fore- man is his care for all material placed in his charge. When- ever track repairs of any kind are made, all loose material of every kind should be collected, and, with the exception of rails, should be carried to the section house, where it may be sorted. Much old material, such as splice bolts and spikes, rtiay, with a little straightening, be made to serve a second time and be as serviceable as new mate- rial. All old iron should be piled in places convenient to the track, whence it may be shipped at the direction of the roadmaster. 1720. Care of Station Grounds. — It is particularly to the section foreman's interest to keep the station grounds in perfect order. By a little thought and planning, he can find time to grade the approaches to the station, plant a few TRACK WORK. 1155 shade trees, and do some sodding where it will tell. This work must not be done at the expense of regular track work, but a spare hour is often available, and the results, if the time has been wisely expended, amply pay for the outlay. Neat station grounds encourage travel, and are sure to win the approbation of superior officers. 1721. Work-Train Service. — The foreman in charge of a work train should make it his business to keep his men at work whenever the train is delayed. There is always plenty of work to do along the track at any point, and by proper forethought and planning, these unavoidable delays may be turned to full account. Every work train should be in charge of a thorough track- man, who should, in addition, be thoroughly competent to run a train. Work-train conductors and foremen in pharge of gravel pits or of steam-shovel outfits should receive their orders from and be responsible to the roadmaster of the division upon which they are working. They should send in a daily report to the roadmaster, and every evening after quitting send in to the dispatcher a lay-tip report, stating where they will work the following day. Work trains should always lay up at a telegraph station. Conductors in charge of work trains should see that all axle boxes are properly packed and oiled, and any accidents to cars or any part of the outfit should be promptly reported to the roadmaster. 1722. T.rack Inspection. — There shou4d be a well- organized system of track inspection on every railroad. The amount of inspection should be in proportion to the excel- lence of the track and the amount of traffic. Whatever the amount of traffic, the entire section should be inspected each day. In ordinary weather this work may be entrusted to a careful section hand, but in stormy weather the sect ion fore- man should give his entire section a careful inspection. It is best that the track inspection, especially at the more dan- gerous points, should be made before the passage of express 1166 TRACK WORK. trains. On double-track roads where the traffic is heavy, track inspection is performed by regular track walkers. They should always carry a track wrench, to tighten loose bolts, and a flag and torpedoes for signals. During the winter months, when the ground is frozen solid, the frost, which hinders many kinds of general track work, is constantly heaving the track out of line and surface, and greatly in- creasing the danger of accident. A rule requiring the sec- tion foreman to see his entire section daily should be strictly enforced. During extremely cold weather the track requires constant watching. ' During heavy storms, it is a good plan to go by train against the storm, to the end of the section, and inspect the track while returning on foot. Two or three inspections in a day are none too many for severe, stormy weather. 1 723. Methods of Work. — Every foreman should be on the alert to learn new and approved methods of work. By careful thought he may devise time and labor-saving methods himself. Work slowly done is not necessarily well done. In fact, expedition is an adjunct to excellence, as no man can do work rapidly without giving it his full attention, and any work, however simple, that has heart put into it, will show it by superior excellence. 1724. Discipline. — A foreman to succeed must be superior to his men both in knowledge and in force of will. Abusive and profane language will soon demoralize men, robbing them of all respect for their foreman and for them- selves. Patience in teaching men their duties. and habitual fair treatment will make an enviable reputation for any fore- man. He will always receive prompt and efficient service from his men, can always count on a full gang, and can readily increase his force for an emergency. Railroad com- panies always prefer to fill their important offices with men who have been tried and promoted in their own service. The young foreman may be sure that competence and faithful- ness will not go unrecognized or unrewarded. He should take advantage of every opportunity to increase his know- TRACK WORK. 1157 ledge of his craft, and do all in his power to make it rank as a profession. 1725. Section Records. — Every section foreman should keep a record of everything connected with the track under his charge. This record should be neatly and clearly arranged, and should contain all information which may be used as a basis for estimates, for the location of structures, or for the distribution of material. The following will suggest suitable forms for such a record : SECTION NO. 8- Length of section 6 miles 1,500 feet Length of east side track 1,200 feet Length of station side track 1,600 feet Length of west side track 1,400 feet. Bridge Number. Number of Bents. Length of Span. Distance from Station. 60 61 62 4 7 Iron 48 feet 84 feet 90 feet 3 miles 3f miles 4^ miles Culvert Number. Box Culvert. Iron Pipe. Distance from Station. 176 177 1 1 1\ miles 2 miles 178 1 54- miles Cuts, Length in feet. Height above Rail. Material. Distance from Station. One, 425 One, 650 One, 500 6 feet 4 feet 8 feet Clay Gravel Rock 2^ miles 3|- miles 5 miles Steel Rails, Amount. When Laid. Brand. Extends from Station. 3 mi. 1,000 ft. 3 mi. 500 ft. 1884 1889 E. Thompson L. L & S. Co. North To end of Sec. 1158 TRACK WORK. 1726. Average Day's W^ork for One Man. — The following is a list of the various kind of labor connected with track work, and gives the amount of each which a good man can perform in one day. This will serve to show the relation existing between the labor of one man and a gang of men at any of the different kinds of work specified: One man can Place on a grade one-eighth of a mile of ties. Spike one-tenth of a mile of track laid on soft ties. Spike one-fourteenth of a mile of track laid on hard ties. Splice and bolt one-sixth of a mile of track. Clean with a shovel one-eighth of a mile of average weeds. Unload 10 cars of gravel. Unload 8 cars of dirt. Load upon cars, 18 to 24 cubic yards of gravel. Load upon cars, 20 to 25 cubic yards of dirt. Load coal into buckets for engines, 15 to 20 tons. Unload coal into sheds, 25 to 30 tons. Put into dirt ballast track, 20 new ties. Put into gravel ballast track, 15 new ties. Put into stone ballast track, 8 to 10 new ties. Do labor equal to ballasting 60 feet of gravel ballasted track. Do labor equal to ballasting 35 feet of stone ballasted track. Chop 2 cords of 4 ft. wood. Make 15 to 25 hard wood ties. Make 35 to 40 soft wood ties. Sixty men can lay one mile of track in a day. 1 727. Tables of Material Required for One Mile of Track : TRACK WORK. 1159 TABLE 36. TONS OF RAILS REQUIRED PER MILE OF TRACK. Weight Tons (2,240 Lb.) Weight Tons (2 ,240 Lb.) per Yard. per Mile. per Yard. per Mile. Pounds. Tons. Pounds. Pounds. Tons. Pounds. 8 12 1,280 56 88 .... 12 18 1,920 57 89 1,280 16 25 320 60 94 640 25 39 640 62 97 960 28 44 64 100 1,280 30 47 320 65 102 320 35 55 68 106 1,920 40 62 1,920 70 110 .... 45 70 1,600 72 113 320 48 75 960 76 119 960 50 78 1,280 80 125 1,600 52 81 1,600 To find the number of gross one mile of track: Rule. — Divide the weight per quotient by 11. Example.— For 70 lb. rail. 70 h- 7 = 10; 10 x 11 = 110 tons. tons of rails required for yard by 7 and multiply the TABLE 37. NUMBER OF CROSS-TIES PER MILE. Distance, Center to Center. Number of Ties. \\ feet 3,520 If feet 3,017 2 feet 2,640 2i feet ' 2,348 2^ feet 2,113 2| feet 1,921 3 feet 1.761 1160 TRACK WORK. TABLE 38. NUMBER OP RAILS, SPLICBS, AND BOLTS PER MILE OP TRACK. Length of Rail. No. of Rails per Mile. No. of Splices. No. of Bolts, 4 to Each Joint. No. of Bolts, 6 to Each Joint. 18 feet 584 1,168 2,336 3,504 20 feet 528 1,056 2,112 3,168 21 feet 503 1,006 2,012 3,018 22 feet 480 960 1,920 2,880 24 feet 440 880 1,760 2,640 25 feet . 422 844 1,688 2,532 26 feet 406 812 1,624 2,436 27 feet 391 782 1,564 2,346 28 feet 377 754 1,508 2,262 30 feet 352 704 1,408 2,112 TABLE 39. RAILROAD SPIKES PER MILE OP TRACK. Size Measured Under Head. Average Num- ber per Keg of 200 lb. Ties 2 Ft. Between Centers, 4 Spikes to a Tie. Rails Used, Pounds per Yard. Pounds. Kegs. H X tV 375 5,870 2H 45 to 70 5 Xt\ 400 5,170 26 40 to 56 5 X i 450 4,660 23i 35 to 40 4iX i 530 3,960 20 28 to 35 4 X i 600 3,520 17f 24 to 35 Hx^ 4 XtV 680 720 3,110 2,910 15^ 141 i 20 to 30 Hx^ 4 X f 900 1,000 2,350 2,090 11 10^ [ 16 to 25 Hx 1 3 X 1 1,190 1,240 1,780 1,710 9 8i [• 16 to 20 nx i 1,342 1,575 n 12 to 16 TRACK WORK. IIGI TABLE 40. NUMBER OF TRACK BOLTS IN A KEG OF 200 LB- Rails Used. Bolts. Size Nuts. Bolts in Keg. Kegs per Mile. 40 to 70 |X4i Usq. 195 7.3 40 to 70 f X 4 Hsq. 200 7.1 40 to 70 |X3| lisq. 208 7.0 40 to 70 f X3i Hsq. 216 (}.6 25 to 40 f X4 Usq. 305 4.7 25 to 40 f X3i lisq. 329 4.3 25 to 40 iXU 1 sq. . 576 2.6 18 to 20 i X 2i 1 sq. 654 3.3 40 to 70 1 X 3^ If hex. 170 8.3 40 to 70 |X 3f If hex. 237 6.0 40 to 70 f X3i 1^ hex. 228 6.3 40 to 70 f X 4 If hex. 220 6.5 25 to 40 tx3^ 1 hex. 415 3.4 RAILROAD STRUCTURES. WOODEN TRESTLES. 1 728. Extent of Trestling. — The amount of wooden trestling in use on American roads is very large, and covers a wide range in both material and design. As the period of construction is always a severe test of the financial strength of a railroad com'pany, it has been the almost universal policy in this country to use temporary structures of moder- ate cost, wherever possible, and to defer the erection of permanent structures until traffic is on a paying basis and finances are easy. Hence it follows that of the 2,500 miles of trestle now in use on American roads, fully one-quarter will be replaced by embankment. Of the remaining 1,900 miles, at least 800 miles will be maintained in wood. It is, there- fore, a matter of great importance that these structures, whether temporary or permanent, should be well planned and constructed in order that they may best meet the requirements of safety and economy. 1729. Average Life of a Wooden Trestle. — The average life of a wooden trestle is taken at 8 years, and the question of renewal will depend upon the compara- tive cost of an embankment with the requisite amount of masonry for watercourses, or for the rebuilding of the wooden structure at intervals of 8 years. Trestles which are to be replaced by embankments may properly differ consider- ably in design from those which are to be periodically re- newed. Temporary trestles should possess the qualities of simplicity and strength alone, while those which are to be 1164 RAILROAD STRUCTURES. St s ^ © 30 ^ GC T— 1 o CO o O CO e-i T-H r-l c^ o CO 1—1 ^ o i< CO >o ?o t- o^ I— I ^^ o o u5 ^ ^ J-^ ^—^ ^-4 1— r ^ s _« m 4) * U )C o o 1—1 r-l 00 i> -+ CO -f ir> rt ^ CO ^ ^ CO ■r? .—1 CO CO o •o CO ^ >o o C5 o_ 50 CO^ T^ 1) V 1—1 I— ( 1-^ r-^ a. "c" V. o Uh o n CO to "* 1— 1 CO CO ■x CO c> u cc 00 o '^ C5 i> »o CO o •~^ fN CO 't* «o £- 00 o 1-1 CO «©^ ^ r-T 1—1 1—1 g-o h « cJ S> ^ © C5 o iO o 00 C5 1-H *1 • 13 ll l-H 1-H o ••^ "E, u ^2 rt W) ir- CO -^ CO CO so UO CO • W 1^ n o «> <* 1—1 o f^ CO CO • 1 a> ^ -* o CO 00 00 o I-H 6 V ^ c «fr 4& 0) c 0) ""^ 1-H H ^" © o 1—1 00 CO 00 CO o t- • 4, V Vh J> ^ o «> -* ^H C5 «o • -5 O. 4; CO ^ »o »o i> X C5 o • S «©^ ^ i-T '. T-i 00 »o t- 00 o CO i> CO Oi o N 30 »c '^ 1-H »o "* C5 rH X ■ft N «> 1—1 "* t- o_ Tt< X ■^ C5 1— ( 1— t r-T co" co" c « 5 o. ^ o o o 1—1 «o «<* »c GO »o CO J> © CO ■«* o >o JO 1— ( CO a> 1-H N «& 1— 1 ^ CO a CO r^ T-H t- ankm Yard wide T— I 1— t co" c^r c " « o« t- CO i> C5 o CO "* CO 00 «> (N CO 00 »o 00 iO t- Tf< H 4» T-( CO >o 00 1—1 »o Ci -^ 1—1 1—1 1-h" Co" V S a^ -<* CO iO 1—1 '^ C5 o ■<* ■* CO so rH 5^ (N CO ^ X «o t- tN «» 1—1 CO »o J> o CO t- 1-H d ■" 1— 1 r-t CO 6 ^ £ ° -? -S ^3 H taj >i3 « c rt rt u *j ii 3 " u »o o o o >o o >o o »o ^ I— 1 1—1 (N s^ CO CO Tf -^ i. •« s RAILROAD STRUCTURES. 1165 maintained in wood should be so designed that they may be renewed without any interruption of traffic. In either case, the use of any other than the best available material is to be condemned as poor economy. The cost of the construction of a trestle is a considerable percentage of its total cost, and is but slightly affected by the character of the materials com- posing it, and, hence, the small saving effected by the use of cheaper materials is neutralized by the shortened life of the structure and its general lack of excellence A good wooden structure is preferable to a cheap iron one, though the impression commonly prevails that an iron structure must necessarily be strong and efficient. Many new lines traverse sections where timber is abundant and cheap, bringing the cost of wooden structures within safe reach of the railroad company, whereas costly structures of iron or heavy fills might have wrecked the company and the enterprise. 1 730. Comparative Cost of Trestles and Em- bankments. — The height at which it becomes more eco- nomical to substitute trestling for embankment varies widely, depending upon the locality, the cost of timber, labor, and the character of material available for making the fill. There are, of course, many situations, such as deep swamps or waterways, where an embankment is out of the question. It then becomes a choice between wooden and iron structures. The cost of an embankment increases in a vastly greater ratio than its height, as will be seen from Table 41. The cost of trestling, on the other hand, does not increase nearly as rapidly as its height, especially for heights under 50 feet. The cost of pile and framed trestles for heights from 5 to 45 feet, inclusive, is given in Table 42. 1731. Mathematical Formulas of Slight Use in Trestle Designing. — Few engineers employ mathematical formulas in designing trestles. The strength and properties of timber vary with each separate piece, and in proportioning 1166 RAILROAD STRUCTURES. the parts of a trestle it is far safer to rely upon one's own judgment, if supported by large experience, or to follow the approved examples of other men, than to rely upon any set of mathematical formulas. American railroads show a wide range in trestle design, each important road having a set of standard designs which may differ more or less from those employed on other lines. The designs given in this paper are copies of some of the best standards in use on American roads, and cover a range wide enough to meet the requirements of all ordinary situations. TABLE 42. Cost of Pile and Framed Trestles, complete, including Floor Systems for Different Heights in Sections of 100 feet. Height Pile. Framed. in Feet. $30 $35 $40 $30 $35 $40 5 1546 $605 $665 $453 $528 $604 10 611 674 738 555 647 740 15 678 742 806 634 739 844 20 746 811 877 711 829 947 25 918 1,001 1,084 966 1,126 1,286 30 986 1,070 1,154 1,042 1,215 1,389 35 1,160 1,263 1,366 1,228 1,432 1,636 40 1,227 1,332 1,444 1,303 1,520 1,736 45 1,372 1,602 1 832 1 732. Classes of Trestles. — Wooden trestles are divided into two general classes, viz., pile trestles, in which the bents consist of piles united by a cap, and framed trestles, in which the bents consist of squared timbers framed together. Pile trestles are rarely used for heights exceeding 30 feet. Framed trestles may be of almost any RAILROAD STRUCTURES. 1167 height, though special designs are required for those ex- ceeding a height of 30 feet. Fig. 548. 1733. Technical Terms and IVames. — In order that the student may understand the various parts com- posing a trestle, the following technical terms and names are V 0° °o 4 n m V *. 8^ Fig. 549. given, the number accompanying each term corresponding to the parts given in Figs. 548 and 549: 1168 RAILROAD STRUCTURES. Bent, Framed, 1. Bent, Pile, 2. Cap, 3. Cross-tie, 4. Dapping, 5. Gaining, see Dapping, 5. Guard-rail, 0. Jack-stringer, 7. Longitudinal Brace, 8. Mortise, 9. Mud-sill, 10. Notching, Gaining, Dap- ping, 5. Packing-block, 11. Packing-bolts, 12. Piles, Batter, Inclined, Brace, 13. Vertical, Plumb, Upright, 14. Posts, Vertical, Plumb, Up- right, 15. Batter, Inclined, 16. Sill, 17. Stringer, 18. Sway-brace, 19. Tenon, 20. Waling-strip, see Longi- tudinal Brace, 8. 1734. Pile Bents. — As the subject of pile driving was fully discussed in the section on Railroad Construction, no reference will be made in this section to the theory of pile driving. Where the line traverses low, marshy ground, either constantly overflowed or subject to occasional over- flow, and where the height of the rails above the surface of the ground does not exceed 30 feet, a pile bent is generally adopted. When pile bents are used for greater heights than 30 feet, only the tops of the piles penetrate the ground, and though they may reach a substantial bottom, the bent is essentially weak, owing to the small diameter of the pile and the small proportion of heart timber at the top of the tree. It is the heart timber alone which can long resist decay, and at the surface of the ground, where the timber is alternately wet and dry, decay sets in as soon as the struc- ture is erected, and in a few years, at best, the piles must be renewed, though the remainder of the trestle may be in a comparatively sound condition. Piles should be cut from live, straight, thrifty trees, free from dead or loose knots, wind shakes, and all descriptions of decay, and be stripped of bark. They should have a butt diameter of from 12 to 15 inches, and a top diameter of from 7 to 10 inches inside the bark. Squared piles are used in a RAILROAD STRUCTURES. 1169 limited way, and when so used they should measure 12 inches square at the butt, and not show more than 2 inches of sap wood on the corners. It is the custom on some lines to paint the pile for a short distance above and below the ground line with hot tar, thus tending to retard decay. Timber suitable for piles may be found in most sections of the United States. The different varieties of timber commonly used for piling are named in the following list in the order of their excellence: Red Cedar, Black Cypress, Pitch Pine, Yellow Pine (long-leaf), White Pine, Redwood, Elm, Spruce, White Oak, Post Oak, Tamarack, Hemlock. The arrangement of the piling forming the bent varies considerably with different constructors in the matter of I- 5*0 12-0 4-0 s 14-0' 33r 4-6 fh ! i i I I i Figs. 550 and 551. Figs. 552 and 553. spacing the piles, though the general arrangement is the same. For a height of bent not exceeding 5 feet, and where the 1170 RAILROAD STRUCTURES. road is to carry only a moderate traffic, a three-pile bent is generally adopted, one pile being placed directly upon the center line and the others spaced from 3 feet 6 inches to 5 feet out, the piles being driven vertically. (Fig. 550.) For trunk lines, however, whatever the height, all bents should contain four piles. For heights of from 5 to 15 feet, each bent should contain four piles driven vertically. The inner piles may be spaced from 4 to 5 feet and the outer ones about 11 feet from center to center. (Fig. 551.) Pile bents of this height will not require sway bracing, provided the penetration amounts to 6 or 8 feet in firm earth. For heights exceeding 15 feet, it is well to batter the outside piles, as shown in Fig. 552. By this means the width of the base is considerably increased, giving in appearance, as well as in fact, greater stability to the structure. Piles are battered from 2 to 4 inches to the foot, 3 inches being commonly adopted. On Western roads, vertical pile bents of heights of 20 feet and over are frequently seen, but they give the im- pression of a lack of stability, which the battered piles at once remove. Where the diameter of the pile at the cut-off point exceeds the width of the cap, the part of the pile which projects should be adzed off at an angle of 45°, (Fig. 553.) 1 735. Splicing Piles. — When the material into which the piles are driven is soft ground, extending to a great depth, it may be necessary to splice the piles in order to reach a firm foundation. In splicing, the piles are placed end to end, and united either by dowels, bands, or scarf- ings. Three different forms of splices are shown in Figs. 554, 555, and 55G. Those shown in Figs. 554 and 555 are commonly adopted. The first pile is driven until its top is within easy reach from the surface of the ground. It is then cut off and trimmed up for splicing, and the second pile placed upon and fastened to it. When the ground is in a partially fluid state, the pile already driven will have but little stiffness, so that if either of the splices shown in RAILROAD STRUCTURES. 1171 Fig. 554. Fig. 555. Fig. 556. Figs. 554 and 555 is used, the piles are liable to cant in driving and the splice to give way. In such cases it is better to strengthen the splice with scarfings, say 3 inches by 3 inches by 8 or 10 feet in length, spiked to the piles as shown in Fig. 556. This splice was used in the false work for the erection of the Poughkeepsie bridge, and proved very efficient. When the band splice (Fig. 555) is used, some de- vice must be used to keep the band in place, else, after a few blows of the hammer, it will be found wholly on one pile or the other. Rail- road spikes driven above and below the band, as shown in Fig. 555, will prevent this movement. 1736. Determining the Length of Piles Required. — If the bridge is to be a long one, requiring a large number of piles, it 'is important that the approximate lengths of the piles required and the number of each should be known before ordering the material. The fol- lowing method, adopted by the Northern Pacific Railroad Company for their bridge over the St. Louis river, at Duluth, proved very satisfactory. Test piles were driven every 300 feet along the center line, and where any considerable variation in penetration was noticed, an intermediate pile was driven. The piles were driven from a scow, the space between the piles being regulated by a rope attached to the last pile driven. After the piles were all driven, their exact location was de- termined by triangulation. A careful record was kept of the driving of each test pile, the notes being kept in the following form; 1172 RAILROAD STRUCTURES. in & o 5 > '■>-> 3 O c o u c W u o c _o '^ rt ii *j a c 0) o S 1 o 1 ^ 1 *4 2 »« 1— t o o 7-1 o T-l o 00 I— 1 e e CO I— 1 o § • •qi 'J3UI -UIBHJOIM •J3UIU1BJJ JO IIBJ o •SAVOia JO OM o T-t juioj Agia 00 CO •3l!d JO doj, -ASia CO 00 •UaAUQ 3DUB:iSlQ CO cs CO •aa^BAV JO ^%d^a C5 •jma JO 1-H •dox JO jaiauiBiQ 00 •qjSuaq to •3Ud JO O^ l—{ 5 § + o 00 CO ^ Q < O a < < a C o « 2 6 » Q B SB Penetration for Given Number of Blows. 00 Oi o ■>* o 00 1-H ■-♦< «5 O rH O rH CO o o rH CO • o o o • • O •SMOia JO -oj^ 00 o Il^d 00 1-i •U3AIJQ 9DUB1SIQ . °0 o CO •and JO ;uiod JO Aaia fe CD CO 00 rH •punojf) JO UOl^BA3l3 00 JO q;Su9q « CO f^od o CO ■JJO-inO Aioi -ag qjSuaq ■* ^j;^ O CO CO JO J913U1BIQ £^ CO 1—h ■«na JO J3}3U1BIQ i^ 1— 1 ■and JO q^Suaq *; o •jaquijx JO PU}>{ c a; c •and JO OM r-( CO •juag JO o^ CO Date and Station. -?» CO Jan. lOl 112+G5J RAILROAD STRUCTURES. 1173 age of gper Foot. CD QC Tl^ CO »o 0: CO h -t;! c .— CO (N C o > s C <; '^ -c c d d c d P J «& Vi 2 "1^ '=<> i> 1-1 ^ >o CD i5 -r tH CO '^ CO §^Q i> r-( ■i-> (U ineal Fe of Piles Driven Daily. CD 10 QO 0^ '^ GC CO 1— 1 1—1 T-T 1 '-' mber Piles -iven aily. < -^ ■ CO »o c- «« c? 0* ■M . »o 0^ i> 4) v^ I- £ Q >o" ^'' "cT ■*'" »? Oi J I- ;n . aj CO CD t- £- 3 M- >? ^ Q tH CO CO 11 ^ ^ en C rt «Hi — ^ ccH* • 1^ «o -* CO -^ Q i-H 12; i-H -* CO 1—1 _ be -^ ^ C ^ T-l 1—1 . ■p qB . CO o T-H CS ^ ■»-> f: o o CO r-i ci ^ ^ «& c ■i-i .2 '5 o o c 00 I— 1 5^ >C CO o T-* 50 1-1 4© <§& o o o .2 C5 CO CO 'c 00 0& ^ 'So u <£ o o > 00 00 CO CO t/i 00 (J o o X 9g *o -rt« CO 00 CO 0» « -o . 'O : c • *i TJ 3 tj OJ * o -6 * Ui (U 2- ^ TJ 73 a; C ii ■f-> TJ ^ . r ""^ 4) - ai ii • ^ o Si 'a O c o OJ o - - r S J3 S 4-> —^ "" 4-1 c V O fc- O V - S ^^ r^ rt aj ™ '^ t, O ^ •" .£ 3 V ■i-i C c O- TD •2 C •-; -J^ 4^ i rt Ui t/i ^ P ^ ,, «- — t/} > ^ g *^ .S 15 .= 4> rt 4-> • o CO J5 (N «o 1-1 i> '"^ £- be -*i I— 1 t^ o »o o >o CO (N 00 o t- c CO ^ 5^ iC CO CS 1—1 CO i>- T-H e> (N CO X CO r-l X ;o C5 o CO t- »« CsJ ^^ CO (7< »o CO o o Oi -+< CO '^ CO CO tc CO 1— 1 CO 00 5^ ~co^ t^ CO i> T— I »o o <-H »0 00 «5 »0 (N o ■^ o^ CO CO 1—1 O CO ,^ <35 c^ -Jn (?« « U5 ^, CO go ^ "^ I— t 9 -+• o oJ «o cc ^ 1— t t- t C^i Ci O »o Ti o CO o " 00 >* J5 »^ n C5 ^ O W5 O "O n rH 00 i-i CO C5 i> o^ ^ - o rH . I— < , V— ,-i^ >- z^ - J3 <« en V o H^ < -t H S c RAILROAD STRUCTURES. 1201 Table 48 gives the weight of drift-bolts of the sizes commonly used: TABLE 48. IJVEIGHTS OF DRIFT-BOLTS. Length in Inches. Square Section. Round Section. f in. sq. 1 in. sq. f in. diam. 1 in. diam. 18 20 22 24 26 Lb. 2.9 3.2 3.5 3.8 4.1 Lb. 5.1 5.7 6.2 6.8 7.3 Lb. 2.3 2.5 2.8 3.0 3.3 Lb. 4.0 4.4 4.9 5.3 5.8 1770. The main value of drift-bolts lies in their hold- ing power. A long series of experiments by the United States Engineer Corps, made while building the St. Mary's Canal locks, developed the following results: The mean of from 150 to 200 experiments with round and square bolts, both smooth and ragged, in different-sized holes, shows that the resistance after having been driven seven months is 10 per cent, greater than the resistance immediately after driving, the different sizes and forms being strictly uniform. The mean of 150 experiments under various conditions shows that the resistance to being drawn in the direction in which the bolts were driven is only 60 per cent, of their resistance to being drawn in the opposite direction; that is to say, the resistance to being drawn through is only 60 per cent, of the resistance to being drawn back. The mean of 50 experiments shows that smooth rods have a greater resistance than ragged bolts, both to being drawn through and also to being drawn back; that a moderate ragging reduces the holding power a little more than 25 per cent., and an excessive ragging reduces the holding power more than 50 per cent. 1202 RAILROAD STRUCTURES. The best relation between the diameter of the bolt and that of the hole, as determined by one series of 60 experi- ments, shows that the holding power of a 1-inch-round bolt in a l^-inchhole is greater than in a ff-inch or a ||-inch hole, the resistance in a |^|-inch hole being 98 per cent, and that in a f|-inch hole being 90 per cent, of that in a [^-inch hole. Another series of 35 experiments makes the holding power of a 1-inch round bolt in a ||-inch hole greater than in a |f or a ||-inch hole, the first two being practically the same, and the last being only 85 per cent, of the first. For a f-inch round bolt four experiments with each size prove that the holding power of the bolt in a |f-inch hole is about one quarter greater than in a y^-inch or a ^-inch hole. For a 1-inch square bolt, the holding power in a ||^-inch hole is only a. trifle greater than in a [f-inch hole, and about 20 per cent, greater than in a [f-inch hole, as deduced from 20 to 40 experiments for each size of hole. The holding power of a 1-inch square bolt in a f|-inch hole was practically the same as for a 1-inch round rod in a l^-inch hole. There is 25 per cent, more metal in the square drift-bolt and more labor is required in boring a ||- inch hole than in boring a f^-inch hole; hence, the round drift-bolt is 25 per cent, more efficient than the square one. In the matter of pointing the bolts, experiment goes to prove that drift-bolts with a long, slender point have about 10 per cent, greater resistance than those with short, blunt points, the conclusion being that the blunt points tear the fiber of the wood, while the slender points crowd it aside, filling up the cavities of the hole, thereby increasing the friction of the bolt. 1771. no-wels. — In place of drift-bolts, short iron rods, either square or round, called do>vels, are frequently used. They have neither point nor head, but are sheared from rods, care only being taken to make them straight. They are frequently used to fasten caps to posts, posts to sills, and ties to stringers. A common size of dowel for fastening caps to posts and posts to sills is f-inch round or square by 8 inches in length, weighing about 1 pound each. RAILROAD STRUCTURES. 1203 Dowels of f-inch round iron, 5 inches in length, are well suited for fastening ties to stringers. The following list gives the weight of 1-inch lengths of the various sizes of iron bars or rods commonly employed in this kind of work: 1 in. square 0.2806 lb. |in. diam. round 0.1240 lb. I in. diam. round 0.2204 1b. fin. square 0. 1096 lb. Jin. square 0.2149 lb. fin. diam. round 0.0860 lb. |in. diam. round 0.1687 lb. i in. square 0.0701 lb. f in. square 0.1579 lb. i in. diam. round 0.0551 lb. 1772. Bolts. — Bolts for holding the stringer pieces together, fastening the braces, guard-rails, etc., are com- monly of f-inch round iron, their lengths, of course, de- pending upon the purpose for which they are to be used. The bolt heads should be well formed, and of good weight, and the threads right-handed and well cut. & Bolt heads are of three forms — button heads, flat ■ '^ countersunk heads, and the ordinary square heads Fig. 614. (Fig- 614). Square nuts with a thickness equal to the diameter of the bolt and length of side equal to twice the diameter of the bolt are the best. The outer top corners of both head and nut should be chamfered. A cast-iron washer from 3 to 3^ inches in diameter should be placed under the head and nut of all bolts. Holes of y*^ inch less diameter than the bolts are bored through the timber to receive the bolts to insure a close fit. Table 49 gives sizes and weights of bolts, and though not exact, owing to the varying weights of heads, is amply close for approximate estimates. In ordering bolts, the term grip^ as sometimes employed, signifies the total thickness of the material to be held together; in other words, the distance between the inside faces of washers. 1773. Lag-Screws. — A lag-screw is a large wood screw which serves in place of a bolt. The head is shaped 1204 RAILROAD STRUCTURES. TABLE 49. APPROXIMATE WEIGHT OF BOLTS IN POUNDS, WITH SQUARE HEADS AND NUTS, INCLUDING BOTH. Length Under Head in Inches. Diameter in Inches. i f f 1 1 6 0.59 1.01 7 0.G4 1.10 8 0.70 1.19 9 0.75 1.27 10 0.81 1.3G 2.10 3.05 4.23 11 0.8G 1.44 2.22 3.22 4.45 12 0.92 1.53 2.35 3.39 4.67 13 0.97 1.62 2.47 3.55 4.89 14 1.03 1.70 2.59 3.72 5.11 15 1.08 1.79 2.72 3.89 5.34 IG 1.87 2.84 4.06 5.56 17 1.96 2.97 4.23 5.78 18 2.05 3.09 4.40 6.00 19 3.21 4.57 6.22 20 3.34 4.74 6.44 21 3.46 4.90 6.66 22 3.59 5.07 6.88 23 3.71 5.24 7.10 24 3.83 5.41 7.32 like a bolt head, and an ordinary wrench may be used in fastening the screw in place. A hole of the full size of the shank of the screw is bored through the first timber and a much smaller one is bored for the balance of the distance through which the thread is to pass. A wrought or punched washer cut from sheet iron should be placed under the head of each lag-screw. The ordinary form of lag-screw is in Fig. 615, Fig. 615. shown RAILROAD STRUCTURES. 1205 1774. Washers. — Cast washers are largely used in trestle building. One should be placed under the head and nut of every bolt used in the structure. The more common forms of cast washers are shown in Fig. 616, and their dimensions are given in Table 50. The solid washers are placed under the head and the slotted washers, or those TABLE 50. DETAILS OF CAST-IRON WASHERS. Dimensions , in Inches. Kind, Fig. 616. Diameter Diameter Diameter Thickness. of Back. of Face. of Hole. A n If 1 i B 3 2i 1 i C 3 If 1 f D 3 2 1 1 E 3 li I I F 3 2 f i G 3i 2i 1 * H 3| 2i li\ f K 4 2 1 t L 4f 2f I 1 J, having a second hole, under the nut. The purpose of the slot, or second hole, is to provide for locking the nut. After ] 20G RAILROAD STRUCTURES. the nut is well tightened, a nail is driven in the slot or hole with the head projecting far enough above the face of the washer to permit of its being drawn with a claw hammer. This effectually locks the nut. Wrought washers may be effectually locked by nicking the thread with a center punch after the nut has been screwed home. Wrought washers, sometimes called punched, are also used to a considerable extent in this class of structures. They are circular in form, and are stamped out from sheet iron, with a hole punched through the center of them. Table 51 gives the dimensions of wrought washers, and the number of each in a keg of 150 pounds: TABLE 51. S halving the Average Number of Wrought -Iron Washers in a Keg of 150 pounds of each Standard Size, as Adopted by the Association of Bolt and Nut Manufacturers of the United States. Size of Thickness, Size of Number in Diameter. Hole. Wire Gauge. Bolt. 150 Pounds. i i No. 18 3 80,000 1 , • A No. 16 i 34,285 1 A No. 16 i 22,000 i f No. 16 5 18,500 1 7 No. 14 f 10,550 H i No. 14 1 7,500 If A No. 13 h 4,500 H t No. 12 A 3,850 If H No. 10 1 2,500 2 H No. 10 i 1,600 H il No. 9 I 1,300 H ItV No. 9 1 950 2f li No. 9 li 700 3 If No. 9 li 550 H H No. 9 If 450 RAILROAD STRUCTURES. 1207 CONNECTIOlV WITH EMBANKMENT— PROTEC- TION AGAINST ACCIDENTS. 1 775. Connection >vitli Embankment. — There ar, two methods, in general use, of connecting a trestle with an embankment, viz., by means of a bank crib, and by means of a bank bent. In the former method the crib is usually built of 12-in. by 12-in. square timbers halved one into the other and drift-bolted at each intersection of the timbers. There are several courses of timbers depending upon the height of the embankment. The building of the crib should be deferred until the rest of the trestle is completed, so as to allow all possible time for the settlement of the embank- ment. Before commencing the crib, a space of ample size to receive it should be excavated from the end of the em- bankment and the earth well rammed for a foundation be- fore the timbers are put in place. The correct elevation for this foundation should be determined by the engineers, so that the top of the crib may have the proper elevation with- out hewing away any of the timber. The timbers compo- sing the front of the crib, i. e., the part facing the trestle, should be at least 10 feet long, and those parallel to the track of equal length. The top of the crib should be fixed exactly at grade, so that trains may pass from the embank- ment to the trestle, and vice versa, without any jolting. Timbers frequently vary ^ inch in thickness, so that the actual elevation of the top of the crib may vary 1 or 2 inches from the calculated one. This discrepancy may be readily remedied by shims, if the top of the crib is too low, and by notching down the stringer, if the top is too high. It is well to have the stringers extend back from the face of the crib several feet. The bottoms of the stringers should be kept from coming in contact with the earth of the embankment. This may be prevented by spiking planks to the crib timbers underneath the stringers. The stringers should be drift-bolted to the crib timbers. Such a connection between embankment 1208 RAILROAD STRUCTURES. and trestle as we have just described is shown in Fig. 017. Fio. 617. Connection between the embankment and the trestle may be made by means of a bank bent, either of piles or framed. This construction is more favored than the crib form previously described. It consists of a strong frame or pile bent built into the slope at the end of the embankment for the support of the stringers. If piles are used, the bent should contain four piles deeply driven into the embank- ment, so that they will not only safely carry the train load, but will sustain the pressure of the back filling, which is RAILROAD STRUCTURES. 120i> carried up to the base of the stringers. To hold this piling in place, the back of the bent is close planked with 3 -inch or 4-inch plank. When the bank bent is of considerable height, struts of 8-in. by 8-in. stuff should extend from the bank bent to the timbers of the first trestle bent, to insure its stability. When the bank bent is of framed tim- ber, special pains should be taken to insure a safe founda- FiG. 618. tion for the sill. Sub-sills of 12-in. by 12-in. timber, laid in trenches, form a good foundation. Before laying the sub-sills, the ground should be thoroughly rammed to en- sure against settlement. This construction is illustrated in Fig. 618. 1776. Refuge Bays. — On all trestles of a length of 200 feet or more, refuge bays should be built where work- men or track walkers can find safety when overtaken by a train. They consist of small projecting platforms supported by ties which are given the additional length 4if ^4-0^ /3'a '■J Space iM —4-9— lf^4' J PS necessary to include the refuge bays. A refuge bay of approved pat- tern is shown in Fig. 619. On trestles of a length exceeding fig. 6i9. 1,000 feet, every fourth refuge bay should be large enough to contain a hand car and section gang. While repairs are being made on a trestle, before work is commenced, tnj 1210 RAILROAD STRUCTURES. the hand car, together with all idle tools, should be placed in a refuge bay, and should remain there until the work is finished. 1777. Foot Walks. — On some roads it is custom- ary to place between the rails a foot walk of inch boards from 1 to 2 feet in width. This is a mistake, in that it encourages the public to use a trestle as a thorough- fare on account of the ease in crossing it; it increases the danger of fire, as the walk forms a lodgment for coals dropped from the fire-boxes of the engines, and it tends to careless inspection on account of the difficulty of reaching the parts of the structure which are covered by the walk. 1 778. Fire Protection. — Every trestle should be pro- vided with the means of protection against fire. This is sometimes effected by covering the tops of ties and string- ers with sheet iron. A simpler and more effective protec- tion is afforded by water stored in tubs at intervals of not more than 200 feet, and provided either with buckets or large dippers. The buckets should be of metal, wood pulp, or paper. Metal well painted is preferable. The track walker should examine all tubs at least once each week and report their condition to the section foreman, whose business it is to keep them full of water. Kero sene barrels sawed in two make excellent tubs — cheap and enduring. An equally important safeguard against fire is the cutting and burning of all grass and brush from the right of way adjacent to the trestle, and the removal and burning of all rubbish which could afford any lodgment for sparks. The grass and brush should be cut early in the season, when the stubble is too green to burn. It is the contractor's business to protect the trestle against fire during construction by the removal and burning of all brush and rubbish which could in any way threaten its safety. A clause to this effect should have a place in every contract. RAILROAD STRUCTURES. 1211 FIELD ENGINEERING AND ERECTING. 1779. Locating Bents. — The number of bents com- posing the trestle and the number of the station at the beginning and end of the same are determined from an in- spection of the profile. The center line of the trestle is then run in, a plug being driven on the center line locating each bent. It is customary to place these center plugs 1 foot in advance of the bent centers so that they will not be dis- turbed while placing the bents in position. The center plugs being driven, the transit is set up at each plug and stakes set at right angles to the center line, giving the direc- tion of the sill. These stakes are, like the center plug, 1 foot in advance of the required center line of the sill. In case the trestle is built on a curve, the bents should stand on radial lines. It is of the first importance that the levels be correct, and to facilitate the checking of them, a bench mark with an elevation of about the grade of the rail should be estab- lished at the end of the trestle, and another near the lowest point of the line over which the trestle passes. At each center plug a strong stake should be driven, with the top of the stake at the level of the top of the foundation for that bent. One grade stake at each bent is sufficient, as the work- men can transfer that elevation to other points, if necessary, with an ordinary carpenter's or mason's level. 1780. Erecting. — Trestle bents of moderate height are framed, lying flat on the ground, with the sills so placed that when the bent is raised it will occupy its proper posi- tion. The raising is effected by means of blocks and a fall, the power being ordinarily applied by either horses or a gang of men. The end bent is first raised and braced in position, and the tackle for raising the next bent attached to it. Stay ropes should be attached to a bent before it is raised, to steady it and to prevent it from being pulled over after it has reached an upright position. As soon as a bent is raised, it should at once be fastened in position by means of stay lath nailed to it and the bent immediately 1212 RAILROAD STRUCTURES. preceding. The sway-bracing should be fastened immedi- ately, and when no longitudinal bracing is to be added, the stringers should be put in place and fastened before raising another bent. High trestles, composed of several sections placed one above the other, and separated by purlins (see Fig. 627), are usually erected as follows: The bottom deck having been raised, the purlins are placed upon it, and a temporary floor laid on the purlins, upon which the bent forming the next section is placed and raised precisely as though it lay on the ground. Special designs require special methods, but the plan generally adopted is that given above. A tack or nail is driven in each cap on the center line for the accurate pla- cing of the stringers. After the ties and guard-rails are in place and fastened, tacks are driven in ties at intervals of about 50 feet, to guide the track layers. 1781. Preservation of Joints. — At every point where two pieces of timber come in contact, they should be painted with some preservative material. As trestle timbers are usually rough, a considerable quantity of material is necessary, if all joints are to be properly treated ; white lead, though effective, is too expensive. Hot coal tar is a cheap and effective wood antiseptic, and available everywhere. Creosote oil is also much used, and when the finances of the company admit of it, a trestle built of timber which has been thoroughly treated with creosote oil under pressure is undoubted economy. 1782. Trestle Specifications. — There is no class of structures of the importance of wooden trestles upon which there has been so gross neglect in the matter of specifica- tions. Many important contracts contain but a few lines, while others of equal importance carry specifications purely general in character, in which many points of the first im- portance are entirely neglected. The following specifica- tions are general, but are sufficiently detailed to guide the student in making an application to a particular structure: RAILROAD STRUCTURES. 1213 STANDARD SPECIFICATIONS FOR \VOODEN TRESTLES. CLEARING. Before commencing work on any structure, the ground must be entirely cleared of logs, stumps, trees, and brush of every description. All combustible material must be piled at convenient places and completely burned. Trees outside the right of way which, by falling, may endanger the tres- tle, must be felled by the contractor, it being understood that permission to fell such trees shall be obtained by the railroad company from the land owner. Such portions of the right of way as shall be deemed necessary by the engineer shall be grubbed. DRAWINGS. The drawings are to the scale indicated and marked; but in all cases the figures are to be taken, and in case of omis- sion the engineer in charge is to be referred to for dimen- sions. Under no circumstances are the drawings to be scaled either by the contractor or by any of his men. The engineer will be required to mark the dimensions upon the contractor's blue-print and to keep a record of the same in his office. DIMENSIONS. All posts, braces, clamps, stringers, packing-blocks, ties, guard-timbers, sills, and all timber generally, will be of the exact dimensions given and figured upon the plan. Varia- tions from these will be allowed only upon the written consent of the engineer in charge. TIMBER. All timber shall be of good quality and of such kinds as the engineer shall direct, and be free from wind-shakes, black, loose, or unsound knots, worm holes, and all descrip- tions of decay. It must be sawed true and out of wind, and 1214 RAILROAD STRUCTURES. full size. Under no circumstances will any timber cut from dead logs be allowed to be placed in any part of the struc- ture; it must in every case be cut from living trees. PILES. Piles shall be cut from live, thrifty timber. They will be either round or square, as may be required by the engineer. Roimd piles must be straight, be stripped of all bark, and be well trimmed. They must be at least twelve (12) inches in diameter at the cut-off, when cut to grade to receive the cap. The smaller end must be at least eight (8) inches in diameter. Square piles must be hewn (or sawed) twelve (12) inches square. They must have at least nine (9) inches of heart wood on each face from the head of the pile after being cut off to grade, to five (5) feet below the surface of the ground into which the pile is driven. All piles must be properly pointed. They shall, if re- quired, be shod with shoes of cast or wrought iron, made according to plans furnished by the engineer. In driving they shall be banded with wrought-iron rings of suitable weight to prevent splitting. The actual cost, delivered on the ground, of the necessary shoes and rings will be allowed to the contractor. Piles must be driven to hard bottom or until they do not sink more than five (5) inches under the last five (5) blows from a hammer of at least two thousand (2,000) pounds weight, falling free twenty-five (25) feet. All piles injured in driving, or driven out of place, shall be either withdrawn or cut off, as the engineer may elect, and others driven in their stead. The piles thus replaced will not be paid for. All piles under track stringers must be accurately spaced and driven vertically, and in each bent the batter piles will be driven at the angle shown. Piles shall be measured by the lineal foot after they are driven and cut off, and the price per lineal foot shall be understood to cover the cost of transportation, removing the bark, driving, cutting off, and all labor and materials required in the performance of the work, but that portion of RAILROAD STRUCTURES. 1215 each pile cut off shall be estimated and paid for by the lineal foot as "piles cut off." The contractor must give all facilities in his power to aid the pile recorder in his duties. Parts of pile heads projecting beyond the cap must be adzed off at an angle of 45°. FRAMING. All framing must be done to a close fit and in a thorough and workmanlike manner. No blocking or shimming of any kind will be allowed in making joints, nor will open joints be accepted. All joints, ends of posts, piles, etc., and all surfaces of wood on wood shall be thoroughly painted with *hot creosote oil and covered with a coat of thick asphaltum; hot asphaltum; hot common tar; a good, thick coat of white lead ground and mixed with pure linseed oil. All bolt and other holes bored in any part of the work must be thoroughly saturated with *hot creosote oil; hot asphaltum; hot tar; coal tar; white lead mixed with pure linseed oil; linseed oil. And all bolts and drift bolts before being put in place must be ♦warmed and coated with hot creosote oil; warmed and coated with hot asphaltum ; warmed and coated with hot tar; warmed and coated with hot coal tar ; coated with coal tar; coa'ted with white lead and linseed oil. Optional methods of treatment. 121G RAILROAD STRUCTURES. All bolt holes for bolts three-quarters (|) of an inch in diameter or over must be bored with an auger one-eighth (^) of an inch smaller in diameter than the holt, in order to secure a perfectly tight fit of the bolt in the hole. For bolts five-eighths (|) of an inch in diameter, or smaller, the auger must be one-sixteenth {j\) of an inch smaller, for the same reason. TRESTLES ON CURVES. Trestles built on curves will have the outer rail elevated according to plans furnished from the Chief Engineer's office, a copy of which will be delivered to the contractor. CREOSOTED TRESTLES. All piles used in creosoted trestles must be completely stripped of bark, and be pointed before treatment. None of the sap wood may be hewn from the piles. No notching or cutting of the piles will be allowed after treatment, ex- cept the sawing off of the head of the pile to the proper level for the reception of the cap, and the beveling of such part of the head as shall project from under the cap. The heads of all creosoted piles, after the necessary cut- ting and trimming has been done for the reception of the cap, must be saturated with hot creosote oil, and then cov- ered with hot asphaltum before putting the cap in place. Timber for creosoted trestles must be cut and framed to the proper dimensions before treatment. No cutting or trimming of any kind will be allowed after treatment, except the boring of the necessary bolt holes. Hot creosote oil must be poured into the bolt holes before the insertion of the bolts, in such a manner that the entire surface of the holes shall receive a coating of creosote oil. TREATMENT OF CREOSOTED PILES AND TIMBER. All creosoted timber and piles shall be. prepared in accordance with the following process: The timber and piles, after having been cut and trimmed to the proper RAILROAD STRUCTURES. 1217 length, size, and shape, shall be submitted to a contact steaming inside the injection cylinders, which shall last from two to three hours, according to the size of the tim- ber; then, to a heat not to exceed 230° F., in a vacuum of twenty-four (24) inches of mercury, for a period long enough to thoroughly dry the wood. The creosote oil, heated to a temperature of about 175°, shall then be let into the injec- tion cylinder and forced into the wood under a pressure of 150 pounds per square inch, until not less than 15 pounds of oil to the cubic foot has been absorbed. The oil must con- tain at least 10 per cent, of carbolic and cresylic acids, and have at least 12 per cent, of naphthalene. IRON. Wrought Iron. — All wrought iron must be of the best quality of American refined iron, tough, ductile, uniform in quality, and must have an elastic limit of not less than twenty-six thousand (26,000) pounds per square inch. All bolts must be perfect in every respect, and have nuts and thread of the full standard size due their diameters. The thickness of the nut shall not be less than the diameter of the bolt, and the side of its square not less than twice the diameter of the bolt. The heads of all bolts shall be square ; round button ; countersunk; When square the thickness shall not be less than the diam- eter of the bolt, and the side of its square not less than twice the diameter of the bolt ; When round button the thickness at center shall not be less than three-quarters of the diameter of the bolt, and the extreme diameter not less than two and one-half times the diameter of the bolt; When countersunk the extreme diameter of head shall not be less than twice the diameter of the bolt, and countersunk on the under side so as to fit into a cup washer. Cast Iron. — All castings must be of good, tough metal, of a quality capable of bearing a weight of five hundred and 1218 RAILROAD STRUCTURES. fifty (550) pounds, suspended at the center of a bar one (1) inch square, and four and one-half (4^) feet between sup- ports. They must be smooth, well shaped, free from air holes, cracks, cinders, and other imperfections. All iron before leaving the shop must be thoroughly soaked in boiled linseed oil. INSPECTION AND ACCEPTANCE. All materials will be subject to the inspection and accept- ance of the engineer before being used. The contractor must give all proper facilities for making such inspection thorough. Any omission by the engineer to disapprove the work at the time of a monthly or any other estimate being made, shall not be construed as an acceptance of any defective work. PROTECTION AGAINST FIRE. The contractor must, each evening, before quitting work, remove all shavings, borings, and scraps of wood from the deck of the trestle and from proximity to the bents, and upon the completion of the work must take down and re- move to a safe distance all staging used in the erection of the work, and remove and burn all fragments of timber, shavings, etc. ROADS AND HIGHWAYS. Commodious passing places for all public and private roads shall be maintained in good condition by the con- tractor, and he shall open and maintain thereafter a good and safe road for passage on horseback along the whole length of his work. RUNNING OP TRAINS. The contractor shall so conduct all his operations as not to impede the running of trains or the operation of the road. He will be responsible to the railroad company for RAILROAD STRUCTURES. 1219 all injuries to rolling stock or damages from wrecks caused by his negligence. The cost of such damage will be re- tained from his monthly and final estimates. RISKS. The contractor shall assume all risks from floods, storms, and casualties of every description, except those caused by the railroad company, until the final estimate of the work. LABOR AND MATERIAL. The contractor must furnish all labor and material inci- dental to or in any way connected with the manufacture, transportation, erection, and maintenance of the structure until its final acceptance. Disorderly, quarrelsome, or incompetent men in the employ of the contractor, or those who persist in doing bad work in disregard of these specifications, must be discharged by the contractor when requested to do so by the engineer. Whenever the chief engineer may deem it advisable, he may name the rates and prices to be paid by the contractors, for such time as he may designate, to the several classes of laborers and mechanics in their employ, and for the hire of horses, mules, teams, etc., and these shall not be exceeded; and having given due notice to the contractors of his action in regard to these matters, they shall be boirwfl to "obey his orders in relation thereto. The chief engineer shall not, however, name a rate or price for any class of labor, etc., higher than the maximum rates being paid by the contractor paying the highest for that class. INTOXICATING LIQUORS. Contractors will not themselves, nor by their agents, give or sell any intoxicating liquors to their workmen or to any persons at or near the line of the railway, nor allow any to be brought on the works by the laborers or any other person, and will do all in their power to prevent their use in the vicinity of the work by persons in their employ. A 1220 RAILROAD STRUCTURES. continued disregard for this clause will, if deemed necessary by the engineer, be considered as a good and sufficient reason for declaring the contract forfeited. DAMAGES AND TRESPASS. Contractors shall be liable for all damages to landholders, arising from loss of or injury to crops or cattle, sustained by any cause or thing connected with the works or through any of their agents or workmen. They will not allow any person in their employ to trespass upon the premises of per- sons in the vicinity of the works, and will forthwith, at the request of the engineer, discharge from their employ any person that may be guilty of committing damage in this respect. They will also maintain any fences that may be necessary for the proper protection of any property or crops. REMOVAL OF DEFECTIVE ^VORK. The contractor will remove at his own expense any ma- terial disapproved by the engineer, and will remove and rebuild, without extra charge, and within such time as may be fixed by the engineer, any work appearing to the engin- eer, during the progress of the work or after the comple- tion, to be unsound, or improperly executed, notwithstand- ing that any certificate may have been issued as due for the execution of the same. The engineer shall, however, give notice of defective work to the contractor as soon as he shall have become cognizant of the same. On default of the contractor to replace the work as directed by the engin- eer, such work may be done by the railroad company at the contractor's expense. DELAYS. No charge shall be made by the contractor for hin- drances and delay, from any cause, in the progress of the work; but it may entitle him to an extension of the time allowed for completing the work, sufficient to compensate RAILROAD STRUCTURES. 1221 for the detention, to be determined by the engineer, pro- vided he shall give the engineer in charge immediate notice, in writing, of the detention. EXTRA WORK. No claim shall be allowed for extra work, unless done in pursuance of a written order from the engineer, and unless the claim is made at the first estimate after the work is ex- ecuted. The chief engineer may, at his discretion, allow any claim, or such part of it as he may deem just and equitable. Unless a price is specified in the contract for the class of work performed, extra work will be paid for at the actual cost of the material remaining in the structure after its completion and the cost of the labor for executing the work plus fifteen (15) per cent, of the total cost. This fifteen (15) per cent, will be understood to include the use and cost of all tools and temporary structures, staging, etc., and the contractor's profit, and no extra allowance over and above this will be made. INFORMATIOIV AND FORCE ACCOUNTS. The contractor will aid the engineer in every way possible in obtaining information, and freely furnish any which he may possess, by access to his books and accounts, in regard to the cost of work, labor, time, material, force account, and such other items as the engineer may require for the proper execution of his work, and shall make such reports to him from time to time as he may deem necessary and expedient. PROSECUTION OF THE WORK. The contractor shall commence his work at such points as the engineer may direct, and shall conform to his directions as to the order of time in which the different parts of the work shall be done, as well as the force required to complete the work at the time specified in the contract. In case the contractor shall refuse or neglect to obey the orders of the engineer in the above respects, then the engineer shall have 1222 RAILROAD STRUCTURES. the power to either declare the contract null and void and relet the work, or to hire such force and buy such tools at the contractor's expense as may be necessary for the proper conduct of the work, as may, in his judgment be for the best interests of the railroad company. CHANGES. At any time during the execution or before the commence- ment of the work, the engineer shall be at liberty to make such changes as he may deem necessary, whether the quan- tities are increased or diminished by such changes, and the contractor shall not be entitled to any claim on account of such changes beyond the actual amount of work done ac- cording to these specifications at the prices stipulated in the contract, unless such work is made more expensive to him, when such rates as may be deemed just and equitable by the chief engineer will be allowed him ; if, on the other hand, the work is made less expensive, a corresponding deduction may be made. QUANTITIES. It is distinctly understood that the quantities of work es- timated are approximate, and the railroad company reserves the right of having built only such kinds and quantities, and according to such plans, as the nature or economy of the work may, in the. opinion of the engineer, require. ENGINEER. The term engineer will be understood to mean the chief engineer, or any of his authorized assistants or inspectors, and all directions given by them, under his authority, shall be fully and implicitly followed, carried out, and obeyed by the contractor and his agents and employes. PRICE ANI> PAYMENT. The prices bid will include the furnishing of materials, tools, scaffolding, watching, and all other items of expense in any way connected with the execution and maintenance RAILROAD STRUCTURES. 1223 of the work until it is finally accepted and received as com- pleted. The contractor will be paid only for the piles, tim- ber, and iron left in the structure after completion. No wastage in any kind of material will be paid for except in the case of piles, when the " piles cut off," which can not be used on any other part of the contractor's work, will be paid for at the rate agreed upon. After the material cut off is paid for, it is to be considered the property of the railroad company, and is to be neither removed nor used by the con- tractor without the consent of the engineer, and then only upon the repayment of the price which has been paid for it. The piles and "piles cut oft" will be paid for by the lineal foot, the former driven in place. The timber and lumber remaining in and necessary to the completed structure will be paid for by the thousand feet, board measure. The iron will be paid for by the pound, and only that remaining in the structure after its completion. The masonry for foundations will be paid for by the cubic yard. The excavations for foundations will be paid for by the cubic yard. The retained percentage will not be paid on the cost of any single structure until the final estimate is due on the entire work embraced in the contract. When the trestling and grading are let under one con- tract, or when a general contract, as by the miU\ includes a considerable portion or all of a line, many of the preceding clauses will be omitted in the section of the con- tract pertaining to trestles, as they are general require- ments applicable to all classes of work embraced by the contract. Special conditions obtaining in a particular section of the country may also require modifications of some of the given clauses. The specifications given are general and are intended to meet all certain requirements and secure justice to both the contractor and the railroad company. 1224 RAILROAD STRUCTURES. BILLS OF MATERIAL, RECORDS, AND MAINTENANCE. 1783. Proper Forms. — Proper forms of bills of ma- terial are of great importance to both contractor and en- gineer: to the former in ordering and placing material, and to the latter in checking, estimating, and keeping records of the same. Few young engineers have any knowledge of such forms, and many engineers of experience have been con- tent with slovenly cut-and-try methods. The following is a proper form of bill of material: TRESTLE NO. 2. DIVISION NO. 4. RESIDENCY NO. 3. BILL OF IRON. No. of Pieces. Name. Use. Size. Weight. WROUGHT IRON. 24 Drift-bolts Stringers to bank sills i" sq. X 24' 26 Drift-bolts Stringers to caps. . . . f ' sq. X 24' 6 Drift-bolts Sills to mud-sills. . . . r sq. X 20' 102 Boat spikes Ties to stringers .... Yxir 150 Boat spikes Guard-rails to ties. . . VxW 26 Bolts Guard-rails to jack- stringers rx31i' 12 Bolts Caps to posts rx22' 16 Bolts Sway-bracing |'X20' 32 Bolts To Packing for stringers tal f'x22' CAST IRON. 172 Washers. . . Under heads and nuts Separators of bolts rx3' 2''X3' 32 Between stringers. . . To tal All bills of material should be copied in a letter book. In making out bills of material, the contractor should be al- lowed the full length of each stick, including the tenon, RAILROAD STRUCTURES. 1225 pa fa o .J S3 ^ a> -<*< O 00 T-< <£> «0 00 0» eS "3 33 OS (N o^ «o 00 ♦^ T-T r-T t-' 0* H s ad x-yjcoxo x)0050ocoo ooowcjoo *?t- -«*< qo © :OSJ^- 1> ^**J* «>» &. bboTttb bbc^c>ibb bb^xbb bbbbb ^xios«»*i ^©»K)^!0©» ^bsoo?^^ WL-roiWo i-H i-( i-It-Ht-I»-Ii-1 t-I ,— 1,-lT-l y-l ■?» « *> Ci OJ « O OJ Ci -?> « « O Ci « » « 00 OO xxxxx xxxxxx xxxxxx xxxxx eoffjwoio* bc»wo*ice« boJOi©jec« ojoooobco u . a CQ 1 en cfl cn^ -Q 6 S 2 r" ? 12 * ''^ '? 'tp '55 ^ ""* a ffi « *: *J «J V V 0) V tn . 4) « « sL «4-i *«-4 *4-i rr> "rt £ -^ - «^ ^ CO A 00 S-* J-l Tl U -M .O» V S z ^i E,S rH eo 00 S50 122G RAILROAD STRUCTURES. and where the tenon is cut on a skew, as in batter posts, etc., the full size for the extreme length of stick should be reckoned. 1 784. The number of feet B. M. (board measure) in a stick of timber or in lumber 1 inch or over in thickness is found by the following rule: Mtiltiply together the breadth and thickness in inehes and the length of the stick in feet, and divide the product by 12. The quotient will be the number of feet required. If we denote the breadth by b, the thickness by /, and the length by Z, we may put the question in algebraic form as f°"°*^ ■■ Feet B. M. = *-H^. ( 1 26.) When lumber is less than 1 inch in thickness, it is always reckoned as though it were a full inch thick. A table like the following, containing the number of feet B. M. in each piece entering into the standard trestle will greatly facilitate the making out of bills of material: General. — Each trestle will require: 8 Bank sills, 12' X 12' X 12' 0' 1,152 ft., B. M. 4 Dump boards, 4' X 8' X 11' 4' 121 ft., B. M. Stringer pieces, 8' X 16' X 25' 0' contain each 267 ft., B. M. Ties, 6' X 8' X 12' 0' contain each 48 ft. , B. M. Guard-rails, 6' X 8' X 20' 0' contain each 80 ft., B. M. 1785. Inspection. — After the road is completed and turned over to the operating and maintenance depart- ments, the trestles, as well as all other structures forming a part of the roadway, should be regularly and thoroughly in- spected. At least once every year, at a favorable season, the work of inspection should be performed by the en- gineer in charge of the maintenance-of-way department. The inspection should be thorough in every detail, and where the traffic is heavy, this inspection should be made twice a year. Once each month all structures should receive a careful examination by a competent inspector. Not only the deck timbers, but all timbers entering into the structure, should be examined, and every necessary help should be afforded RAILROAD STRUCTURES. 1227 the inspector to facilitate his work. He should make out a complete report on proper blanks of the condition of each structure, forwarding them to either the division engineer or division superintendent, who, having examined and ap- proved the reports, forwards them to the engineer of main- tenance of way. A further inspection should be made by the track walker^ and that as often as he crosses the bridge or trestle, though it be several times a day. Of course, the inspection of the latter will consist only of a general oversight, but sufficient to detect at once any exterior defect or lack. The track walker will be provided with blanks for making out reports. The following form is suitable for his report: BLACK RIVER VALLEY RAILROAD. TRACK l^VALKEH'S DAILY REPORT 0!V THE CONDITION OF BRIDGES AND TRESTLES. Number of Time. Condition. Bridge. A. M. P. M. A. M. p. M. M. P. 123 A 7:45 5:45 X X M. P. 123 B 8:10- 5:20 X X M. P. 124 A 8:30 4:50 X X M. P. 124 B 9:00 4:20 X X M. P. 124 C 9:50 3:50 X X M. P. 125 A 10:30 3:30 X X M. P. 125 B 10:50 3:00 X X M. P. 126 A 11:20 2:30 X X M. P. 126 B 11:45 1:40 X X M. P. 126 C 12:00 1:10 X X Track Walker. .189. These blanks are bound in pads of fifty sheets and carry a pasteboard cover for protection. When filled out the re- port is folded and endorsed on the back : 1228 RAILROAD STRUCTURES. BLACK RIVRR VALLEY RAILROAD. Track Walker s Daily Report. Bridges and Trestles from *M. P. 123 A to M. P. 126 C. In the report, X in the column headed Condition, means "all right;" O means " injured or unsafe," by fire, washout, or from other cause. In case of danger, the fact must be reported by telegraph from the nearest station to the in- spector of bridges, the division engineer, and the division superintendent. 1 786. Inspector's Tools and Their Use. — An ax or hatchet and small auger are the essential part of an inspector's outfit. Decay generally commences at the sur- face of timber, and is at once manifest. On the other hand, dry rot, or powder post, as it is vulgarly termed, com- mences beneath the surface, and it frequently happens that a piece of timber, which from the surface appears perfectly sound, is totally decayed inside, leaving only a shell of sound timber. Where this form of decay is in an advanced stage, it may be detected by striking a few blows upon the surface of the timber, which will give a hollow sound ; but where the shell is thick, the defect may be revealed by boring a small hole into the timber, the degree of ease with which the hole is bored determining the degree of -soundness of the timber. The simplest, and an excellent way as well, of testing tim- ber is by driving a slim wire nail or spike into the wood; the soundness of the timber in this case, as in boring, will be revealed by the ease or difficulty in driving the nail. Whenever a hole is bored, it should be plugged as soon as it has served its purpose, and but few holes should be bored in the same stick. Piles in trestles need not be examined for decay until they have been several years in the ground ; but whenever there is any suspicion of decay, an examination should be made at once. Decay first attacks the piles at or near the surface of the ground, and, in order to examine them, the earth must be removed to the depth of 1 foot, or more if necessary. A short, sharp-pointed steel bar is a good tool for testing the * Mile post. RAILROAD STRUCTURES. 1229 soundness of piles. After a pile has been examined, the cavity made for the examination should be refilled and the earth well tamped. In every case where a serious defect is discovered, which in any way threatens the safety of the structure, the inspector should at once notify, by telegraph from the nearest station, the division engineer and division superintendent of the fact, stating as briefly and clearly as possible the nature and extent of the defect or damage, 1 787. Bridge Numbers. — On most roads the bridges and trestles are numbered consecutively, beginning at the terminus of the road. A much better way, now being introduced, is to number the bridges alphabetically, com- mencing at each mile post (M. P.). Thus, bridge No. 96 A means the first bridge after passing mile post 96, and at once conveys to the mind a definite idea of location. On the other hand, bridge No. 125, unless some other explana- tory reference is given, is of small aid in locating a bridge. Bridge numbers are usually painted in black figures three inches in height on a white ground. A l|-inch pine board of suitable width is given four or five coats of white lead, and the numbers painted upon it in heavy distinct lines. The boards should -6^ J On GMurd'y rail H ^^ wv/A Fig. 630. Fig. 621. be of uniform height, and uniformly placed. The first right- hand cap of a trestle and the first right-hand tie of an open culvert on passageway are suitable locations for bridge numbers. Suitable forms of bridge numbers are shown in Figs. 620 and 621. 1230 RAILROAD STRUCTURES. STANDARD TRESTLE PLANS. 1788. In this section, the purpose is to illustrate by complete plans the various types of trestles in general use, whose efficiency has been proved by long service. STANDARD SIIVGLE-TR ACK PILE TRESTLE. 1789. In Fig. 622 is given apian of a pile trestle suit- able for heights of from 6 to 20 feet. On roads with only a moderate traffic, bents of three piles each may be safely used for heights of from to 10 feet, but for all through lines no trestle bent should contain less than four piles, having at the cut-off point a diameter of not less than 12 inches, inside of bark measurement. It is customary to notch down the caps 1 inch on the pile heads. The main object for this notching is to hold the piles in place while they are being drift-bolted, in case they have been sprung in driving. The caps are drift-bolted to the piles with f in. diam. X 24 in. drift-bolts, and the stringers to the caps with drift-bolts of the same dimensions. The ties are not fastened to the stringers, but notched down RAILROAD STRUCTURES. 1231 1 inch over the stringers, which prevents any lateral move- ment. The guard-rails are so close to the rails that in case of derailment the weight of the derailed engine or car will bear almost directly upon the strrnger. This form of trestle is simple and thoroughly efficient. DIMENSIONS OF TIMBERS. Floor System : Guard-rails, 7 in. x 7 in. x 20 ft., notched 1 in. over ties. Ties, 7 in. X 8 in. X 9 ft., notched 1 in. over stringers. Stringers, 8 in. X 16 in. X 24 ft., sized over caps to 15 in. Packing-blocks, 2 in. X 16 in. X -t ft., notched 3 in. over caps. Bents: Caps, 12 in. X 12 in. X 14 ft., notched 1 in. over pile heads. Piles, at least 12 in. in diameter at cut-off. DIMENSIONS OF IRON DETAILS. Bolts: -^ in. X 15^ in., guard-rails to ties. f in. X 20^ in., through stringers at packing- blocks. Drift-bolts, f in. diam. X 24 in., stringers to caps and caps to piles. STANDARD FRAMED TRESTLE, PENNSYLVANIA RAILROAD. 1 790. The standard single-track framed trestle, as employed by the Pennsylvania Railroad, is shown in Fig. 623. Like all standard structures in use on this important line, this trestle is a model structure, combining great strength and simplicity of design. Its characteristic fea- tures are in the arrangement of the posts, by which the weight of the load is about equally divided between the vertical and the batter posts, and in the longitudinal bra- cing, shown in detail at A. It will be observed that only in trestles exceeding a height of 20 feet are the posts given dimensions so large as 12 in. X 12 in. in cross-section, and then only in the vertical posts. On the other hand, the stringer dimensions which are commonly adopted on other lines are considerably exceeded in this trestle. For spans 1232 RAILROAD STRUCTURES. of 14 feet, two stringer pieces are required, each 10 in. x IT r^r^ — qv — ^^^^ — c=l— r^l Fig. 623. in., and for spans of 16 feet three pieces, each 8 in. x 17 in. This places the excess of timber, if any, where it is most RAILROAD STRUCTURES. 1233 likely to be needed. Many trestles are weak in the stringers, especially those designed for light traffic. On account of traffic interchange, these trestles are continually required to carry loads for which they were not designed, and often far beyond the point of safety. Numerous accidents have occurred directly attributable to this cause. In designing a trestle, due regard must be paid to this point. A little extra timber in the stringers will not add greatly to the cost of the structure, and will vastly increase its efficiency and the reputation of the road. Special attention is called to the ties, which are much above the average in size of cross-section, though propor- tionately below the average in length. The same is true in the length of caps, which in trestles below 20 feet in height are only 10 feet in length, and in those of greater height only 12 feet in length, whereas 14 feet is the length generally adopted. This is unquestionably saving timber to good purpose. It is a mistake to space the guard-rail more than 15 inches from the track rail, and 12 inches is amply sufficient. The purpose of the guard-rail is to keep the derailed engine or car upon the trestle, and the less the space between the rail and the guard-timber, the less will be the danger of the ties being broken off by sudden shock and weight brought upon them. Where a wide space is left between the rail and the guard timber, a jack-stringer is indispensable, but it would seem a better policy to put the extra timber forming the jack-stringers into the track stringers, and with the extra length of tie make a shorter tie with larger cross-section. Batter posts have a batter of 3 inches to the foot. Mortises and tenons for the smaller posts are 3 in. x 5 in. X 7 in., and for the larger posts 3 in. X 5 in. X 8 in. DIMENSIONS OF TIMBERS. Floor System : Guard-rails, 5 in. X 8 in., notched 1 in. over ties. Ties, 7 in. X 10 in. X 9 ft., notched ^ in. to receive guard- rails, and ^ in. over stringers. 1234 RAILROAD STRUCTURES. Stringers : Clear Span. Number of Pieces Under Each Rail. Width of Each Piece. Depth of Stringers. 10 2 8 in. 15 in. 12 2 8 in. 16 in. 14 2 10 in. 17 in. 16 3 8 in. 17 in. Packing-blocks, 2 in. x 18 in. x ft. Bents under 20 ft. : Cap, 10 in. X 12 in. X 10 ft. Plumb posts, 10 in. X 12 in. Batter posts, 10 in. x 10 in. ; batter 3 in. to 1 ft. Sill, 10 in. X 12 in. Bents 20 ft. and over : Cap, 12 in. x 14 in. X 12 ft. Plumb posts, 12 in. x 12 in. Batter posts, 10 in. x 12 in. ; batter 3 in. to 1 ft. Sill, 12 in. X 12 in. Sway-bracing, 3 in. x 10 in. Bracing : Longitudinal, 8 in. X 8 in. Treenails : Locust, 1 in. in diameter. DIMENSIONS OF IRON DETAILS. Bolts: f in. X ; guard-rails to ties. f in. X ; guard-rail joints. f in. X ; stringer joints; packing-blocks. f in. X ; sway-bracing to caps and sills; 3 in. wrought-iron washers used. Drift-bolts (ragged): 1 in. X 24 in. ; stringers to caps. Spikes : Boat, f in. x 9 in. ; guard-rails to ties. ^ in. X 8 in. Cut, X Wrought-iron washers : ; sway-braces to posts. longitudinal braces to caps and sills. 2^ in. square for J-in. bolt. 3 in. round for f-in. bolt. RAILROAD STRUCTURES. 1235 STANDARD FRAMED TRESTLE, CLEVELAND AND CANTON RAILROAD. 1791. A style of trestle which is aptly called a com- pound timber trestle, and growing much in favor, is illustrated in Fig. 624. The character- istic feature of this type is that the main members, such as stringers, caps, posts, sills, etc., are com- posed of two or more pieces bolted to- gether. The princi- pal ■ advantages of this style of construc- tion are in the re- duction of the cost of timber and in the facility and safety with which repairs can be made. As the parts are bolted together, a defective piece may be 1236 RAILROAD STRUCTURES. readily replaced, and that without endangering or delaying traffic. In general, a better quality of timber may be had in small dimensions than in large ones, and at much less cost. As the pieces forming each member are separated from each other, there is a complete circulation of air through- out the structure, which seasons and preserves the timber. The amount of iron in the structure is necessarily large, but if it is well dipped in tar or asphaltum before being placed in the structure, the iron should outlast two or three wooden structures. This form of trestle is no more expen- sive to build than a framed structure, and its popularity is ample evidence of its general excellence. DIMENSIONS OF TIMBERS. Floor System : Guard-rails, 8 in. x 8 in., notched 1 in. over ties. Ties, 7 in. X 9 in. x 8 ft. 4 in. , notched 1 in. over stringers. Stringers, 7 in. x 14 in. x 30 ft., notched 1 in. over capa in. X 15 in. x 20 in. i3ii 'M 3 ii Brace blocks, , _ . _ . ^ . . ' ( 3 m. x 15 m. X 34 m. Bents : Caps, 6 in. x 12 in. X 12 ft. All posts, 6 in. X 12 in. Sills, 6 in. x 12 in. Sway-braces, 3 in. x 10 in. Tenon blocks, 3 in. X 12 in. X 3 ft. Longitudinal Braces : Girts, 4 in. X 10 in. X 17 ft. T.. , ( 6 in. X 8 in. Diagonals, ] 3 ._^^ g ._^ DIMENSIONS OP^ IRON DETAILS. Bolts : f in. X 14 in. ; guard-rails to ties. I in. X 26 in. ; stringer joints; packing-bolts. I in. X 21 in. ; sway-braces to posts and at inter- section of diagonal longitudinal braces. I in. X 23 in. ; longitudinal girts to plumb posts. I in. X 19 in. ; Iqngitudinal girts to batter posts. I in. X 18 in. ; packing-bolts for posts. f in. X 26 in. ; interior diagonal braces to posts. RAILROAD STRUCTURES. 1237 „j . j f in. X 3 in. ( 1 in. X S^ in. Separators : 2 in. X 3| in. STANDARD FRAMED TRESTLE, OHIO COXNECTING RAILWAY. 1792. In Fig. G25 we have the standard framed trestle adopted by the Ohio Connecting Railway. For heights under 30 feet, the bent consists of one deck, but for heights Fig. 625. above 30 feet two decks are employed, as shown in the figure. As the middle posts are directly under the rails, they carry a large share of the load, and to distribute this load the counter posts a b and c d are employed. The inner posts are given a batter of ^ inch to the foot, which helps to distribute the load. The sub-sills are inexpensive, fairly enduring, and easily renewed. The foundations should be of masonry if the trestle is to be permanent, and if the- situation does not admit of masonry, piles should be used. 1238 RAILROAD STRUCTURES. DIMENSIONS OF TIMBERS. Floor System : Guard-rails, 8 in. x 8 in. x20 ft., notched 1 in. over ties Ties, 7 in. X 8 in. X 10 ft., notched 1 in. over stringers. Stringers, 9 in. x 10 in. x 28 ft., notched 1 in. over caps. Bents: Caps, -12 in. X 12 in. X 14 ft. Posts, 12 in. X 12 in. Counter posts, 10 in. x 12 in. Sills, 12 in. X 12 in. Sway-braces, 3 in. X 10 in. Longitudinal Braces : Girts, 8 in. X 12 in. DIMENSIONS OF IRON DETAILS. Bolts : f in. X IG^ in. ; guard-rails to ties. - . ' ,-,;.'[■ sway-braces to caps and sills, f in. X 17^ in. ) -^ ^ f in. X 22:J- in. ; purlins to posts. f in. X 23 in. ; stringers to caps. "Washers : f in. X 3 in. STANDARD DOUBLE-TRACK PILE TRESTLE, BOSTON AND ALBANY RAILROAD. 1793. A double-traclc trestle is nothing rnor* than two single-track trestles so combined as to form one struc- ture. In Fig. G2(!, we have the standard double-track pile trestle as adopted by the Boston and Albany Railroad. The two special features of this trestle to which the atten- tion of the student is called are the use of split caps, shown in detail at A, and the lateral bracing more distinctly shown in the plan. The split caps, being but half the size of ordi- nary caps, may be had in better timber at less cost, and may be renewed without in any way interfering with traffic. The smaller-sized timbers, on account of their thorough and rapid seasoning, are less liable to suffer from dry rot, and being of comparatively small weight, they are easily and cheaply handled. It is a common practice, where split caps are used, to make the tenons at the end of the pile G inches in thickness. So great a thickness is unnecessary, and where RAILROAD STRUCTURES. 1239 the piles are under 14 inches in thickness the shoulder left for the cap to rest upon is entirely too small. A tenon 3 inches in thickness is ample and insures a shoulder of ample width. The stringer joint is shown in detail at B, The stringers are not notched over the caps, but are sized with 1240 RAILROAD STRUCTURES. an adz to a uniform thickness. Large timbers are certain to vary from ^ inch to \ inch in thickness; hence, the neces- sity of sizing. The notching of the stringers would prevent the removal of a cap unless the stringer was raised for the purpose. DIMENSIONS OF TIMBERS. Floor System : Guard-rails, 8 in. x 8 in., notched 1 in. over ties. Ties, 7 in. X 8 in., notched 1 in. over stringers. Stringers, 8 in. x 10 in. x 24 ft. Bents: Caps, 6 in. X 12 in. X 24 ft. Sway-braces, 3 in. X 10 in. Piles, 12 in. in diameter. Lateral Braces : 6 in. x 6 in. DIMENSIONS OF IRON DETAILS. Bolts: -^ in. X 10 in. ; splicing guard-rails. f in. X 32 in. ; guard-rails to ties and stringers. f in. X 20 in. ; through stringers at separators. f in. X 18 in. ; caps to piles. ^ in. X 14 in. ; at intersections of lateral braces. Drift-bolts : f in. X 24 in. ; stringers to caps. STANDARD FRAME TRESTLE, OREGON AND IVASHINGTON RAILROAD. 1794. High trestles furnish opportunity for construct- ive skill and judgment of a high order. Methods of con- structing trestles of this class, as of others, have changed much in recent years. More iron is introduced and less framing. Posts and sills are fastened together with dowels instead of with mortise and tenon; braces are fastened with bolts, and, wherever possible, the cutting of timber incident to framing is avoided. The braces are increased in size and reduced in number. Instead of short braces framed into the posts at each angle, long braces, reaching from one-half to the total width of the bent, are bolted to the main tmibers. By this means, the strains due either to the wind pressure or the train load are distributed throughout the structure. RAILROAD STRUCTURES. 1241 The trestle shown in Fig. G27 is a copy of one built on the line of the Oregon and Washington Railroad. Its height from ground to rail is about 100 feet, and for simplicity and Fig. 627. strength of design it has no superior. By battering the inside posts, the load is well distributed over the base, which has sufficient breadth to insure stability. The system of 1242 RAILROAD STRUCTURES. sway-bracing is exceptionally good. The horizontal wales a, b, and c, which are bolted to the posts, practically double the number of decks and reduce the post lengths to one-half their actual length. They also form seats for the purlins d, /, and h. Each bent consists of three sections of equal height, separated by eight 12 in. X 12 in. purlins, r, g. These pur- lins extend longitudinally the length of two bents, breaking joints like stringers, and form decks upon which the succes- sive sections rest. The purlins are notched down 1 inch on the caps, and are also notched 1 inch to receive the sills of the bent resting upon them. The caps and sills of succeed- ing sections are bolted together. The purlins constitute the entire longitudinal bracing, excepting in the upper section, where diagonal braces k, I are employed. It would add considerably to the stability of the structure if similar braces were placed in every panet from the ground upwards. The plan shows but one dowel at each connection of post with sill. Two would be a better number, especially in the case of the outside batter posts and the counter posts 7«, «, <7, and/. DIMENSIONS OF TIMBERS. Floor System : Guard-rails, 10 in. x 12 in. and 5 in. x 8 in., notched 1 in. over ties. Ties, G in. x 8 in. x 16 ft., notched 1 in. over stringers. Track stringers, 9 in. x IG in. x 32 ft., notched 1 in. over caps. Jack-stringers, 7 in. x IG in. X 32 ft. Spreaders, 3 in. X 12 in. Bents: Caps, 12 in. X 14 in. x 16 ft. Plumb posts, 12 in. x 12 in. Batter posts, 12 in. X 12 in. Intermediate caps and sills, 12 in. x 14 in. S^ray-Bracing : Horizontal, 6 in. X 10 in. Diagonal, 6 in. x 10 in. Main sill, 12 in. x 14 in. RAILROAD STRUCTURES. 1243 Longitudinal Bracing: Horizontal, in. X 10 in. Diagonal, C in. X 10 in. Purlins, 12 in. X 12 in. X 18 ft. DIMENSIONS OF IRON DETAILS. Bolts : f in. X 49 in. ; floor system to caps. f in. X 41 in. ; sills to caps of different decks. f in. X 37 in. ; outside guard-rails to jack-stringers f in. X 27 in. i . -^ a- ^ u : . ^,„ . I longitudinal bracing. f in. X 24| in. f ^ ^ f in. X 23 in. ; sway-brace splice, sill splice, hori- zontal sway-bracing to posts. f in. X 22 in. ; stringer joints, packing bolts. f in. X 19 in. ; sway-braces to posts. f in. X 11 in. ; inside guard-rails to ties. Drift-bolts : f in. X 24 in. ; sills to piles and stringers to \ caps. Do-wels : 1 in. X 6 in. ; posts to caps and sills. Spikes I Cut 60-penny ; spreaders and brace blocks to caps. Boat, ^ in. X 9 in. ; sway .-braces to posts. Cast Washers : Under head and nut of each bolt. 1795. Practical Suggestions. — In practically all trestles on American roads, designs have, either intentionally or otherwise, placed the stringers directly over the posts and the rails directly over the stringers, so that the shock of the passing train is communicated directly to the post through the tie and stringer, and through the post to the hard, un- yielding foundation. The effect of this can not be other than to place unnecessary stress upon particular timbers, and to subject both rolling stock and foundation to unneces- sary shock. In most trestles, whether pile or framed, the stringers are placed directly above the inside posts or piles, which are usually vertical, and, consequently, must take practically all the load until from some cause or other these inside posts or piles settle, and then, and not until then, is a part of the load transferred through the cap to the outside posts or 1244 RAILROAD STRUCTURES. piles. It is evident that if the stringers were placed mid- way between the posts or piles, the load would be practically divided between them; and, as there would then be a short distance from the stringer to each post, some of the shock, at least, would be taken up by the cap. If, now, instead of placing the stringer with its center directly under the rail, it were moved say 6, 9, or 12 inches outwards from the rail, the ties would act partly as beams, and a part of the shock would be taken up by them. By arranging the posts or piles as before suggested, a further portion of the shock would be taken up by the cap. leaving a much smaller pro- portion of- it to be transferred by the posts to the founda- tion, and, through recoil, to the passing train. Now, if Jlfbtch 1 "^'^ k^ ijfotch tie. 628. under the present system the great share of the load is carried (and, apparently, with safety) by the vertical posts, would not an equal load be carried with equal safety by RAILROAD STRUCTURES. 1245 smaller timbers so arranged that each shall perform its full proportion of work ? In iron bridges the floor system is so arranged that the ties shall act as beams, and there is no reason why the floor system of a trestle bridge should not be arranged in the same way. The only objection to moving the stringers from under the rail is that in case of derailment the weight of the derailed engine or car would, through the wheels, be concentrated upon only a few ties. To obviate this danger, or, at least, greatly reduce it, the ties should be placed near together, with not more than G inches of clear space be- tween them. This would practically form a solid floor, upon which, the wheels would run without danger of biincJi- ing the ties. The guard-rail should be not more than 12 inches from the rail, and should be not less than 7 in. x 8 in. in cross-section, notched 1 inch over the ties, and bolted to at least every fourth tie. With such an arrangement of parts, posts, caps, and sills 10 in. X 10 in. in cross-section would meet every requirement. 1 796. A trestle plan embodying these ideas is given in Fig. 628, and recommended to the student for practical study and work. From the plan it will be seen that in case of derailment, so long as the guard timbers hold, the out- side wheels of the derailed trucks will bear directly upon the stringer, which absolutely insures the ties against breaking. The ties, being strongly supported at both ends, can not be broken by the inside wheels of the derailed trucks, unless they are weakened by decay. To prevent bunching, the ties must, as stated above, be placed so close together that derailed wheels will roll over them. The caps, posts, and sills are considerably smaller than those used on most rail- roads, special exception being made in the case of the Penn- sylvania Railroad, already noted. The stringers, on the other hand, are increased in section from 8 in. x 10 in., a size widely adopted, to 9 in. X 16 in., and are amply strong for spans of 14 feet. The guard-rails are also increased in size above that generally employed. The caps and sills 124r, RAILROAD STRUCTURES. extend in length but 7 inches beyond the batter posts ; where- as, many standards call for an extension of from 12 to 18 inches. Mortises and tenons are ;} in. X 5 in. X 7 in., with treenails of either white oak or locust. In pile trestling, the piles will be spaced precisely as the posts in the framed structure. FRAMED TRESTLE. DIMENSIONS OF TIMBERS. Floor System : Guard-rails, 8 in. x 8 in. X 20 ft., notched 1 in. over ties. Ties, 7 in. X 8 in. x 10 ft., notched 1 in. over stringers. Stringers, 9 in. x 10 in. X 28 ft., notched 1 in. over caps. Bents: Caps, 10 in. X 10 in. x 13 ft. .Plumb posts, 10 in. X 10 in. Batter posts, 10 in. x 10 in. Sway-braces, 3 in. x 10 in. Sill, 10 in. X 10 in. DIMENSIONS OF IRON DETAILS. Bolts: f in. X 15^ in. ; guard-rails to ties, a bolt in every fourth tie. f in. X 21^ in. ; through stringers at separators. J in. X 15^ in. ; sway-braces to cap and sill. Drift-bolts : J in. diam. X 23-in. stringers to caps. Treenails : 1 in. X 10 in. SIMPLE WOODEN TRUSS BRIDGES. 1797. The period of construction is a trying one to even the strongest companies, and any expenditure which can either be avoided or put off until this trying period is past should not be incurred. This will explain why so many wooden structures are erected on newly constructed lines, instead of those composed of iron and steel. Three forms of trusses will be considered in this chapter, though only the last is employed for bridges for standard gauge railroads. The first and second forms are suited to bridges for narrow-gauge railroads, street-car lines, and highways. ./ RAILROAD vSTRUCTURES. 1247 jr The parts will be proportioned for the maximum loads to ' which they will be subjected; and, instead of the concen- trated wheel loads, the equivalent live and dead loads per lineal foot of span will be used. Before commencing the subject of trusses, a limited space will be given to the subject of the materials entering into these structures, their comparative strength and the meth- ods by which the stresses upon the various parts are deter- mined, and the parts proportioned to resist these stresses. 1798. Bridge Timber. — The principal varieties of timiber used in bridge building are: White Pine. Spruce. Long-Leaf Yellow Pine. Short-Leaf Yellow Pine. White Oak. Of these, long-leaf yellow pine, on account of its great strength and the fact that it may be had in any desired length, is more used in bridge building than the other four varieties combined. On the Pacific Slope, Washington fir is first in demand, and by most engineers it is considered superior to- the long-leaf pine. 1799. Forces Operating in Bridges. — The forces to which the timber in a bridge is subjected manifest them- selves in shearing, crushing, bending, and breaking. These forces the student has already become familiar with in his study of the subject of Strength of Materials. 1800. Transverse Strength of Materials. — The transverse strength of a material is that by which it resists breaking. Now, it has been determined by actual experi- ment that in beams of the same material and exactly alike except in breadth, their strengths vary in the same propor- tion as those breadths, i. e., if one is two, three, or ten times broader than the other, its strength will be two, three, or ten times as great. If they are alike except in their 1248 RAILROAD STRUCTURES. lengths^ their strength will vary inversely as their lengths, i. e., if one is two, three, or ten times as long as another, it will be only one-half, one-third, or one-tenth as strong. If they are alike except in point of depth, their strengths will vary as the square of those depths, i. e., if one has a depth two, three, or ten times that of another, it will be four, nine or one hundred times as strong. From this it follows that the strength of any beam, of any size, of any material, is in proportion to its breadth in inches X square of its depth in inches its length in feet ' and if we find by actual trial what center load will break a beam of known size, and then find the ratio between its breadth in inches x square of its depth in inches its length in feet and its breaking load, this ratio will be that which any similar beam of the same material has to its breaking load. For example, if we take a piece of sound, straight-grained spruce, 4 inches broad and 8 inches deep, and place it hori- zontally upon two supports 8 feet apart, we shall find by gradually loading the beam at its center that the breaking load, including half the weight of the beam itself, is 14,400 lb. Substituting these given dimensions in the fraction the breadth in inches X square of the depth in inches length in feet ' 4 X 64 we have — = 32, and the ratio between 14,400 and o 14 400 32 = — '— — = 450. This ratio is called the constant for the center breaking load for beams of spruce, and to find the center breaking load for any beam of the same material we take its dimensions and substitute them in the following formula : breadth in sjuarc of depth , , . , , inches tn inches „ center oreaking load — 7— — —. 7-- X C. length tn feet (127.) RAILROAD STRUCTURES. 1249 In this formula, 6^ is a constant depending on the kind of timber, and its value for four of the most commonly used varieties is given in Table 52. Example. — A spruce beam is 8 in. broad, 12 in. deep, and 20 ft. long; what is its center breaking load ? Solution. — Substituting the given dimensions in the above for- mula, we have, using the value for C given in Table 52 for spruce, 8 X 144 center breaking load = — ^ — x 450 = 25,920 lb. Ans. One-half the weight in pounds of the beam itself must be deducted from this result to obtain the neat center load. 1801. Factor of Safety. — In order that a structure may endure, no part of its framework should be strained to the limit of its strength. The ratio between the ultimate or breaking load of a beam and the working load, which is the actual load placed upon it, is called the factor of safety. This factor of safety will vary, according to the character of the structure and the nature of the strains to which it will be subjected. Roof trusses which, except in cases of violent storms, support a quiescent load consisting of the roof cover- ing, snow, ice, etc., together with their own weight, may have a factor of safety as low as 3. But for bridges, espe- cially those carrying locomotives and heavy trains, where the strains are sudden and violent, a factor of safety of at least 6 should be used; and for those on important lines, a factor of 8 is none too great. Hence, in the preceding ex- ample, the beam whose ultimate center load is 25,920 lb., if used in a railroad bridge, should not be subjected to a 25 920 greater center load than — ^ — = 4,320 lb. 1802. Table of Constants. — By actual experiment, not only with small specimens of timber (usually 1 inch square and 12 inches between supports), but with full-sized beams, the center breaking loads for many varieties of tim- ber and their constants have been determined. The varieties of timber most used in bridge building, together with their 1250 RAILROAD STRUCTURES. constants for center breaking loads, are given in the follow- ing table. For highway bridges, use a factor of safety of 5; for street car bridges, a factor of 6, and for railroad bridges, a factor of 7 or 8 : TABLE 52. CONSTANTS FOR CROSS HRBAKING CENTER LOADS. Material. Pounds. Hemlock 400 White Pine and Spruce 450 Southern Long-Leaf Yellow Pine 550 White Oak 600 1803. Inclined Beams. — When the beam, instead of being horizontal, is inclined, the horizontal distance between the points of support must be taken as the span. 1804. To find tlie side of a square horizontal beam of given span, supported at both ends and required to break under a given quiescent center load : YlviW. — Multiply the clear span in feet by the given break- ing load in pounds. Divide the product by the corresponding constant^ Art. 1802. Take the cube root of the quotient. This cube root ivill be the required breadth or depth of the beam, approximately, in inches. When the size of the beam is so great that its weight must be taken into consideration, provide for this addi- tional weight by increasing the size of the beam as follows: Calculate the weight of the beam already obtained Then say, as the center load is to half this weight, so is the breadth found to a neiu breadth to be added to it. It will still be RAILROAD STRUCTURES. 1251 somewhat too small, owing to the weight of the breadth last added. This additional weight may be easily found and provided for by adding to the breadth. Example. — What is the side of a square horizontal white pine beam, 12 ft. long between supports, which will break under a quiescent center load of 50,000 lb. ? Solution.— 50,000 X 13 = 600,000; 600,000 -r- 450, the constant for white pine, = 1,333. The cube root of 1,333 is 11, almost exactly ; hence, a horizontal beam 11 inches square and 12 feet between supports will break under a quiescent center load of 50,000 lb. Ans. In this case, no account is taken of the weight of the beam, which is so small in comparison to its center breaking load that it may be ignored. 1805. To find the side of a square horizontal beam which will safely bear a given center load : Rule. — Multiply the given load by the number of times it is exceeded by the breaking load. Then find by Art. 1804 the side of a square beam to break under this increased load. The beam thus found will be, approximately.^ the safe one for the actual load, exclusive of the weight of the beam itself. If this weight must be included, provide for it by increasing the breadth, as directed in A rt. 1804. Example. — What should be the side of a square beam of white pine placed horizontally with 10 feet between supports to safely bear a center load of 12,000 lb., with a factor of safety of 6 ? Solution.— 12,000 lb. X 6 = 72,000 lb., the center breaking load for the beam. 72,000x10 = 720,000. 720,000^-450, the constant for center breaking loads for white pine, = 1,600. The cube root of 1,600 = 11.7. Hence, the side of the square is 11.7 in. Ans. By increasing the side of the square to 12 inches, we make ample allow- ance for the additional weight of the beam. 1806. To find the breadth of a horizontal rect- angular beam, supported at both ends, to break under a given quiescent center load, the span and depth of beam being given : Rule. — Multiply the center load in pounds by the span in feet. Multiply the square of the depth in inches by the 1252 RAILROAD STRUCTURES. constant^ Art. 1802. Divide the first product by the last. The quotient will be, approximately., the breadth. If the weight of the beam is so great that it need be taken into consideration, provide for this increased weight by increasing the size of the beam, as directed in Art. 1804. Example. — A horizontal beam of yellow pine is 18 ft. between sup- ports; the depth of the beam is 12 in. ; what should be the breadth of the beam to break under a quiescent center load of 50,000 lb. ? Solution.— 50,000 x 18 = 900.000 lb. The constant for the breaking center load of yellow pine is 550 (Art 1802). The depth, 12, squared = 144;'144 x 550 = 79,200; 900,000 -^ 79,300 = 11.36, the breadth of the required beam. Ans. By increasing the breadth to 12 inches, the increased center load due to the weight of the beam itself is more than provided for. 1807. To find the depth of a horizontal rect- angular beam, supported at both ends, which shall break under a given quiescent center load, the breadth of the beam and length of span being given : Rule. — Multiply the load in pounds by the span in feet. Multiply the breadth in inches by the consta?it given in Art. 1802. Divide the first product by the last ; take the square root of the quotient for an approximate depth. Calculate the iveight of a beam having the depth already found ; add half its weight to the given center load, and ivith the new load repeat the calculation ; the result will be close enough for practical purposes, though not exact, ozving to the neg- lect of the iveight of the depth last added. Example. — A rectangular horizontal beam of yellow pine is 9 in. broad and 16 ft. between supports; what should be the depth of the beam to break under a quiescent center load of 24,000 lb. ? Solution.— 24,000 x 16 = 384,000 lb. The constant for yellow pine (Art. 1 802) is 550. 550 x 9 ^ 4,950. 384,000 -h 4.950 = 77.57. ^^77:57 = 8.8 in. A beam of these dimensions, viz.. 9 in. X 8 8 in. X 16 ft., will contain 15,206 cu. in = 8.8 cu. ft. Yellow pine weighs on an average 45 lb per cu. ft. Hence, the beam weighs 45 X 8.8 = 396 lb. 396 -h 2 ^ 198 lb., which, added to 24.000 lb., the given center load, gives 24,198, RAILROAD STRUCTURES. 1253 the total center load of the beam. 24,198x16 = 387,168. 387,168^ 4,950 = 78.22, the square root of which is 8.84, the required depth of the beam in inches. Ans. From this result the student will see that in providing for the weight of the beam the depth of the beam is increased only .0-i inch, an amount so small that it may be ignored. In actual practice this depth would be increased to 9 inches. 1 808. Strength of IVooden Pillars. — The strength of wooden pillars, like that of wooden beams, depends much upon their degree of seasoning. Thoroughly seasoned sticks will often support twice as great a load as green ones. This fact should be borne in mind when erecting structures of imperfectly seasoned timber. For permanent structures, timber should not be subjected to more than from ^ to 1^ of its crushing load. The following formula by Charles Shaler Smith is for the breaking loads of square or rectangular pillars or posts of moderately seasoned white or yellow pine, with flat ends, firmly fixed and equally loaded: Calling either side of the square or the least side of the rectangle the breadth, we have Breaking load in pounds per square inch of area of pillar of white or yellow pine = 5,000 ^ / square of the length in inches ^ V /j 28.) \ square of breadth in inches ) ' in which 5,000 equals the breaking load in pounds per square inch for short blocks. Example. — A pillar of white pine is 10 inches square and 8 feet long; what is its safe load with a factor of safety of 6 ? Solution.— The length equals 8 f t. = 96 in. 96-^ = 9,216. The square of the breadth = 10'^ = 100. Applying the given formula, we have Breaking load in pounds per square inch of area = 5,000 5,000 9,216 ^.\ ~ 1.37 ..C^^x.-x.) = 3,650 lb. 1254 RAILROAD STRUCTURES. As this is the breaking load, and a factor of 6 is required, the safe load per square inch will be 3,650^6 = 608 lb., nearly, and for 100 square inches, the area of the pillar, the safe load will be 608 X 100 = 60,800 lb. Ans. Example. — A rectangular pillar is 8 in. x 10 in. x 12 ft. ; what is its safe load with a factor of safety of 4 ? Solution. — Applying the above formula, we have Breaking load in pounds per square inch of area = 5,000 5,000 1 /144' --, ~ 2.3 = 2,174 lb., the breaking load per square inch. With a factor of safety of 4, we find the safe load to be 2,174 -h 4 = 543 lb. per sq. in. The area of the pillar is 8 X 10 = 80 sq. in. , and 543 X 80 = 43,440 lb. Ans. In applying this formula to composite columns, made up of several sticks bolted together at intervals, give to each stick its proportionate share of the total load to be carried by that member, and then assume that it stands alone and unsupported. This is the only safe rule. Even though the sticks are firmly bolted together with packing-blocks notched into the sides, they should never be assumed to act as one solid stick, as the packing-blocks and washers are sure to grow loose in time. 1809. Shearing and Crushing. — For shearing and crushing it is generally safe to use a factor of safety of 2 or 3. Use for working values of the shearing stress along the grain ^ for White pine and spruce 200 lb. per sq. in. Long-leaf yellow pine 400 lb. per sq. in. Short-leaf yellow pine. 300 lb. per sq. in. White oak 600 lb. per sq. in. For crushing across the grain, take for working values of seasoned timber, for White pine and spruce 300 lb. per sq. in. Long-leaf yellow pine 500 lb. per sq. in. Short-leaf yellow pine 450 lb. per sq. in. White oak 1,000 lb. per sq. in. RAILROAD STRUCTURES. 1255 For crushing endivisc (short blocks), take for working values for White pine 2,500 lb. per sq. in. Long-leaf yellow pine 3,000 lb. per sq. in. Short-leaf yellow pine 2,800 lb. per sq. in. White oak 2,750 lb. per sq. in. 1810. Tension. — Wood fiber is much stronger in ten- sion than in any other way, and, as a result, it may be said that wood seldom or never breaks in pure tension in actual service. In long sticks in tension, the grain runs more or less across the line of the stick, and a liberal allowance must be made for the reduction of the stick by framing it. In actual work, it is not well to rely upon a working stress in tension of more than 2,000 or 3,000 pounds per square inch for ordinary bridge timber. EXAMPLES FOR PRACTICE. 1. A stick of white pine is subjected to a shearing stress along the grain of 40,000 lb. ; how many square inches of surface are necessary to sustain this stress with a factor of safety of 3 ? Solution. — From Art. 1809, we find the safe working value for shearing stress per square inch along the grain for pine is 200 lb., and to sustain a stress of 40,000 lb., it will require as many square inches of surface as 200 is contained in 40,000, which is 200 sq. in. Ans. 2. An oak tie-beam is subjected to a shearing stress across the grain of 62,000 lb.; how many square inches of surface are necessary to sustain this stress? Ans. 103.3 sq. in. 1811. To find tlie safe dimensions for a rectan- gular horizontal beam of jriven span, supported at both ends, and which is at the same time subjected both to a transverse strain and to a longitudinal tensile or pulling one, or to a longitudinal com- pressive one : Rule. — When the longitudinal strain is tensile, ^nd sepa- rately the safe dimensions as if for a beam alone, and as if for a tie alone, and add the ttvo resulting areas together. When the lo?igitudinal strain is eompressive, find separately 1250 RAILROAD STRUCTURES. »= Plunk. TJs: h 3x8 3x8 Separaton. k J 5* UI ill! r' 1: B ^m-k Fig. 629. RAILROAD STRUCTURES. 1257 the safe dimensions as if for a beam alone, and as if for a pillar alone, and add the two resulting areas together. Example. — A rectangular horizontal beam of yellow pine of 14 feet span is to sustain a uniformly distributed transverse load of 40,000 lb., and a pulling stress of 30,000 lb. , with a factor of 6 ; what should, be the dimensions of the beam ? Solution. — A uniformly distributed load of 40,000 lb. is equivalent to a center load of 20,000 lb. A safe center load of 20,000 lb. with a factor of 6 is equivalent to a center breaking load of 120,000 lb. Apply- ing the rule given in Art. 1804, we have 120,000x14 = 1,680,000. The constant for center breaking loads for yellow pine (Art. 1802) is 550. 1,680,000-^550 = 3,054, the cube root of which is 14. 5. This gives in inches the side of a square beam which will safely carry the given load. From Art. 1810 we conclude the safe working stress in tension per square inch for yellow pine to be, say 3,000 lb. per square inch. The given tensile stress is 30,000 lb., to resist which it will require as many square inches as 3,000 is contained in 30,000, which is 10. We, there- fore, add 10 sq. in. to area of the given beam by increasing either the breadth or depth -^^ of an inch. Ans. 1812. Bridge Loads. — The trusses will be propor- tioned for the following loads, viz : Highway bridges, combined live and dead load equivalent to 1,500 pounds per lineal foot. Street car bridges, combined live and dead load equivalent to 4,000 pounds per lineal foot. Railroad bridges, combined live and dead load equivalent to 6,000 pounds per lineal foot. The foregoing are the maximum loads to which they will be subjected. The forms of trusses given will not be used for spans ex- ceeding 30 feet for railroads, or 40 feet for highways. Where larger spans occur, other and more complicated forms of trusses will be employed, the designing of which properly belongs to the bridge department. 1813. King-Rod Truss. — The simplest form of a bridge truss is shown in Fig. 029. This is called a king-rod truss, from the rod a b, which extends from the head a of the ratters to the base /) of the needle-beam c. Heavy cast 1258 RAILROAD STRUCTURES. washers are placed under both head and nut of the king-rod, and when the nut is tightened, ail parts of the truss are put under strain. Let or a q, running lengthwise through the rafter from head to foot, the rafter must be regarded as a pillar^ and the safe area required to resist this stress we find by applying formula 128, given in Art. 1808, viz.: Breaking load in pounds per square inch of area of yellow pine — 5,000 ^ , / square of length in inches ^^A 1 + (— ^ ;, \i,i ■ ■ 1 X .004) \ square of breadth m inches J The length of rafter as measured along its center line from joint to joint is 11 ft. 6 in. = 138 in. Assuming a breadth of 6 in. for the rafters, we have Breaking load in pounds per square inch of area = 5,000 i-,(f!x.oo.; = 1,604 lb., which, with a factor of safety of 8, gives a safe load of 1,604 _-_ „ -!— — = 200 lb. per sq. m. The stress a' p measured by the given scale equals 9,000 lb. ; hence, the area required to resist this stress will be ' = 45 sq. in. The breadth of the rafter has been 45 assumed as 6 inches; hence, the depth must be -v^ = 1\ inches. Since the usual market sizes of timber run only in even inches, we will make the depth of the rafter 8 inches. In this bridge the plank flooring does not rest directly upon the tie-beams, but upon the floor-beams g and «, which are spiked to the tie-beams. The tie-beams are gained 2 in. to form footings for the rafters, and the tie-rods pass through them, reducing their actual span to 10 ft., one- half the total span of the bridge. If the tie-beams were given smaller dimensions than the rafters, they would appear weak, and, though unnecessarily large, we give them the same dimensions, viz., 6 in. X 8 in. 1260 RAILROAD STRUCTURES. We determine the dimensions of the needle-beam c by first finding the load which it must sustain. The king-rods support the needle-beam, which in turn supports the tie- beams, floor-beams, and floor, and, hence, both sustain prac- tically the same load. The total uniform load we have already determined to be 17,000 lb., which is equivalent to a center load of 8,500 lb. This gives, with a factor of safety of G, a center breaking load of 8,500 X 6 = 51,000 lb. The span from center to center of king-rods is 16.5 ft. Assuming for the needle-beam a depth of 12 in., we have, from Art. 1 806, . ,, ,. 51,000X16.5 ,.^. required breadth = , -— — = 10.6 m. 1/i X 5oO As it is safe to say that the bridge will never be loaded to these limits, owing to the difficulty of loaded teams passing on the bridge, we make the breadth of the needle-beam an even 10 in. The floor-beams have a clear span of 9 ft. 7 in., or 9.58 ft. The distance from center to center of floor-beams is 2 ft. 8 in., or 2.66 ft. Hence, the total distributed load on each beam, at 100 lb. per sq. ft., is 2.66 X 9.58 X 100 = 2,548 lb., 2 54S equal to a center load of ' ' = 1,274 lb. Allowing a Xi factor of safety of 8, we have a center breaking load of 1,274 X 8 = 10,192 lb. Assuming for floor-beams a depth of 8 in., we find from Art. 1806, ... ,^, 10,192x9.58 _ ^^ . required breadth = — -—^ — — — = 2.77 in. ^ 8' X 550 This breadth we increase to 3 in., the standard dimension nearest to the one required, making the cross-section dimen- sion of the floor-beams 3 in. X 8 in. Their length should be equal to the total length of the bridge, or 23 ft. The floor- beams and stringers do not come in direct contact with the stone abutments, but rest upon timbers j, s, called wall plates, by means of which the weight of the bridge is dis- tributed over the entire bridge seat. The wall plates are of RAILROAD STRUCTURES. 1201 oak timber, 4 in. by G in., and extend the full length of the abutments. The dimensions of the king-rod may be found in Table 53. TABLE 53. WEIGHTS AND STRENGTHS OF IRON BOLTS. Ends Enlarged or Upset. Ends Enlarged or Upset. Diam- eter of Weight per Breaking Diam- eter of Weight per Breaking Shank. Foot Run. Stress. Shank. Foot Run. Stress. Inches. Pounds. Pounds. Inches. Pounds. Pounds. i .661 8,803 If 8.10 102,368 tV .837 11,133 ; Iff 8.69 109,760 f 1.03 13,754 U 9.30 117,600 u 1.25 16,621 m 9.93 125,440 f 1.49 19,779 2 10.6 133,728 1 3 1.75 23,296 H 12.0 142,912 i 2.03 26,880 H 13.4 160,384 H 2.33 30,912 H 14.9 178,528 1 2.65 35,168 n 16.5 198,016 ItV 2.99 37,632 H 18.2 218,176 H 3.35 42,336 2| 20.0 239,456 lA 3.73 47,264 H 21.9 261,632 H 4.13 52,192 3 23.8 284,928 lA 4.56 57,568 H 27.9 315,840 If 5.00 63,168 H 32.4 366,464 ItV 5.47 68,992 3f 37.2 420,448 H 5.95 75,264 4 42.3 478,464 ItV 6.46 81,536 H 47.8 508,480 ll 6.99 88,256 H 53.6 570,080 iH 7.53 95,200 4| 59.7 635,040 The load which each king-rod sustains we found to be 8,500 lb. A rod which would safely sustain this load 1262 RAILROAD STRUCTURES. with a factor of safety of would break under a load of 8,500 X G = 51,000 lb. Referring to the table, we find in the column headed Breaking Stress, the number most nearly corresponding to 51,000, which is 52,192 lb. This stress calls for a rod 1 RAILROAD STRUCTURES. 1263" 1:^ in. in diameter, which is the diameter we specify for king-rods. The stress in the rafters produces a shearing stress along the grain of the tie-beam at the footing of the rafter. This stress is equal to r /, or 7,800 lb. We find in Art. 1809 that the working stress for shearing along the grain in yellow pine is 400 lb. per sq. in., and to resist a shearing 7 800 stress of 7,800 lb. it will require ' ^ = 19.5 sq. in. There 400 must accordingly be sufficient space between the foot of the rafter and the end of the stringer to give a superficial area of at least 19.5 in. As we have made this distance 12 in., giving a superficial area of 6x12 = 72 in., there is no question of the security of this joint. The bolts /, / passing through the tie-beam at the foot of the rafter serve only to keep the rafter in place. The needle-beam projects 4 ft. 3 in. outside the truss, as shown in detail 2X A. A brace u runs from this projecting needle-beam to the head of the rafters. It is fastened with spikes, and serves to stiffen the truss and prevent lateral vibration. The joint of the rafters at their head, together with king- rod and washers, is shown in detail at B. In Fig. 630 is illustrated another form of the king-rod truss, in which the stiffeners a b, c d are introduced, their object being to stiffen the rafters and prevent their bending under the longitudinal stress transmitted to them by the king-rod. The stiffeners extend from the middle of the rafters to the base of the king-rod, where they abut against a cast-iron angle block. A cast-iron socket is let into the rafter at the head of each stiffener, and holds it securely in place. The angle block at the foot of the king-rod has two ribs which project 1 in. below the base of the block. Grooves are cut in the tie-beam to receive these ribs, which hold the angle block firmly in place. A hole is cast in the angle block through which the king-rod passes. The stiffeners practically reduce the length of the rafters to one-half their actual length, so far as their sustaining power as pillars is concerned. 1264 RAILROAD STRUCTURES. The bridge shown in the figure is to accommodate the traffic of both street cars and highway. The parts are pro- portioned for an equivalent live and dead load of 4,000 lb. per lineal foot of bridge. The material is long-leaf yellow pine. The stresses are calculated as were those for the bridge shown in Fig. G29. The clear span of the bridge is 28 ft. , and the breadth from outside to outside of truss is 19 ft. 4 in., and the height of truss above the tie-beams is 9 ft. The two king-rods ^'/support that portion of the bridge and its load between the points j, y, or together, one- half the total load. At 4,000 lb. per lineal foot, the load between j, _>/ is 4,000 X 14= 56,000 lb., one-half of which, or 28,000 lb., is carried by each king-rod. Accordingly, we lay out the out- lines of the rafters, and though we do not yet know their depth, we can draw their upper edges, which will not alter their position, and form two sides of our parallelogram of forces. We next draw the line e f^ which will be the center line of the king-rod. Upon this lay off from g, to a scale of 20,000 lb. to the inch, the distance ^//^ 28,000 lb. Com- plete the parallelogram g I h k. Then the equal sides g I and g k will represent by the same scale the longitudinal stress in the rafters. These stresses, which we find to be 27,300 lb., pass down the rafters and are taken up by the abutments. To resist these stresses, the rafters act as pillars. As before stated, the stiffeners a b and c d virtually reduce the length of these pillars, i. e., the rafters, to one- half their total length. Now, assuming that a rafter with a breadth of 8 in. will meet the requirements, we must find the requisite area of the rafter by the method given in Art. 1 808. . The total length of the rafter measured along its cen- ter line is 16 ft. 6 in. ; hence, the length of one pillar is one- half of the total length of the rafter, or 8 ft. 3 in. , equal to 99 in. Applying formula 128, given in Art. 1808, we have Breaking load per square inch of area of pillar = 5,000 5,000 .. .^. ,. 1 + (^ X .OOl) RAILROAD STRUCTURES. 12G5 With a factor of safety of 8, this rafter will bear per square inch of area, -^— — = 388 lb. 8 The stress g I upon this rafter is 27,300 lb., and to safely resist the stress it will require a rafter whose cross-sectional area is J — = 70 sq. in. As we have assumed a breadth o88 70 of 8 in., the depth will be — = 8.75 in. 8 The rafter must be notched on the under side to receive the cast-iron socket for the stiffener ; consequently, it will be best to make the depth 10 inches, a size that is readily obtained in the market. In the parallelogram g I h k, the diagonal k I represents the pull along the tie beam. Half of this stress ;// / is in one direction from the foot of the king-rod, and half in k in the other direction, making a uniform stress of in I = 23,500 lb. throughout the tie-beam. The effect of this pull is to shear off the end of the tie-beam against which the rafter abuts. By reference to Art. 1 809, we find the safe shearing stress along the grain for yellow pine is 400 lb. per sq. in., and to resist a stress of 23,500 lb. it will require .23 500 ' * ^ = 59 sq. in., nearly. The distance from the foot of 400 the rafter to the end of the tie-beam is 12 in. Assuming a breadth of 8 in. for the stringer, we will have to oppose the given stress of 23,500 lb., an area of 12 X 8 = 90 in., or nearly double the required area. The stiffeners a b and c customary, however, to make both rafter and straining beam of one size, as they form a better joint at the queen- rods and give an impression of greater strength. The 1272 RAILROAD STRUCTURES. needle-beams' in and » serve only as ties to hold the trusses in position. The cross-ties are laid directly upon the tie- beams, 16 in. from center to center. At 0,000 lb. per lineai foot, the uniformly distributed load upon each cross-tie is G,000 X 1.333 = 7,998, say 8,000 lb., which is equivalent to a center load of 4,000 lb. With a factor of safety of G, the center breaking load will be 4,000 X 6 = 24,000 lb. The distance between tie-beams is 12 ft. 10 in., say 13 ft. Assuming a breadth of 8 in. for the cross-ties, and denoting the required depth by -r, we find the depth by applying the rule given in Art. 1807, as follows: 24,000 = ^^5^ X 550, Jo whence, ;r'' = 70.90, and .r = 8.4 in. As we notch down the ties 1 in. on the tie-beams, we increase this depth to 9 in. The queen-rods virtually divide the bridge span into three short spans of 12 feet each. We accordingly find the dimensions of the tie-beams for spans of that length. The load upon each tie-beam we assume at 3,000 pounds per lineal foot. The total uniformly distributed load on the tie- beam is, therefore, 3,000 X 12= 36,000 lb., which is equiva- or* AAA lent to a center load of — '- — = 18,000 lb. With a factor of z safety of 6, we have a breaking center load of 18,000 X 6 = 108,000 lb. Assuming a breadth of 12 inches for the tie-beam, we find the depth by the rule given in Art. 1 807. Denoting the required depth in inches by ,r, we have 108,000 =:^^^^^^ — X 550; 550-r' = 108,000, whence, ;f' = 196.36 and X = 14 in., the required depth of the tie-beam. Besides the transverse stress upon the tie-beam, there is a RAILROAD STRUCTURES. 1273 longitudinal pull / q^ which amounts to 42,800 pounds. Allowing a working stress in tension of 3,000 pounds per square inch, it will require ' = 14.2G square inches of 3,000 area to resist this pull. We add this area to that already obtained for the tie-beam, being careful to make the increase in one dimension only, viz., the breadth. This gives us for the final dimensions of the tie-beam a breadth of say 13 inches and a depth of 14 inches. The longitudinal stress in the rafter c d develops a shear- ing stress along the grain at the foot of the rafter equal to the pull in the tie-beam, or 42,800 pounds. Allowing a working stress for shear along the grain of 42 800 400 lb. per sq. in., it will require— j—— ■= 107 sq. in. to resist this stress. The distance from the foot of the rafter to the end of the tie-beam is 12 in. ; hence, the superficial area opposed to this shearing stress is 13 X 12=156 sq. in., which insures ample safety. The feet of the rafters are bolted to the tie-beams, thus preventing any lateral move- ment. The needle-beams /;/ and n serve two purposes, viz., as ties to hold the tie-beams in position, and as supports for the braces j, s which maintain the trusses in an upright position. These braces are fastened in place with boat spikes. The trusses are further braced by three sets of X braces /, ^, as shown in the cross-section B. Each set has a length equal to one-third of the span. The ends of the braces are spiked to the tie-beams and bolted together at the point where they cross each other. On the inside of each tie-beam, directly over the bridge seat, a groove is cut 1 in. in depth and 4 in. in breadth, to receive the spreader «, as shown in the detail. These spreaders are 4 in. x 12 in., and are held in place by the tie bolts v, v, which are 1 in. in diameter and fitted with cast washers. The effect of the rails is to distribute the loads concentrated upon the driving wheels of the locomotive over the entire wheel base, so that cross-ties which individually could not sustain these 1274 RAILROAD STRUCTURES. concentrated loads are yet amply strong enough for their share of the distributed load. The trusses do not rest directly upon the bridge seats, but upon two G in. X 9 in. oak timbers iv, w, which extend the full length of the bridge seat and distribute the weight of the bridge over the entire foundation. The cast-iron shoulder block at head of rafters is shown in detail at D. The bridge seats are 2 ft. in breadth, and the abutments 3 ft. in thickness at the bridge seat. The faces of the abutments are vertical, while their backs have a batter of 1^ inches to the foot. WATER STATIONS. 1815. Water stations are points along a railroad where the engines stop to take in water. Their distance apart will depend mainly upon the amount of the traffic, but somewhat upon the grades. On roads with a light traffic, water stations at intervals of 15 miles will meet every requirement, while roads with a heavy traffic and frequent trains may require them at every 5 or 6 miles. They usually consist of large wooden tubs placed upon a strong framework, supported by heavy pillars which rest upon a foundation of masonry. The tubs are generally circular in form, the bottom diameter being a few inches larger than that of the top diameter, in order that the iron hoops may drive tight. White pine, cedar, and redwood are the varieties of timber principally used in the manufac- ture of tanks. The staves are planed by machinery speci- ally designed to give them the proper bevel, so that when set up the joints are close and water-tight. The staves are fastened together at the top with a single dowel between each two, merely to hold them in place while being set up. The pieces forming the bottom of the tank are doweled together and fit into a groove about 1 inch in depth, which is cut into the staves to receive them. The hoops are fastened together with lugs which grip the two ends of the hoop. The two lugs are united by a bolt threaded at RAILROAD STRUCTURES. 1276 both ends and fitted with nuts. By screwing up these nuts, a strain is put upon the hoop. The hoops are first nearly driven to place; the lugs are then tightened with a wrench, after which the driving is finished. Railroad water tanks hold from 20,000 to 40,000 gallons. A common size is 16 ft. in diameter and IG ft. in height, holding about 21,000 gallons. All tanks holding above 200 barrels are made from 3-in. stuff. This thickness is some- what reduced by planing. The bottom of the tank should be from 10 to 12 ft. above the tops of the rails. It is a com- mon practice to enclose the tank in a framed structure, the foundation and post supports forming the first story, and the tank, together with its covering, the second story. Where the supply of water is pumped, the first story is often used as a pump house, and a fire is usually maintained in winter to prevent the freezing of the water. At division or terminal points, where many engines are to be supplied, the tank is made proportionately larger, and often two are placed together. It is desirable to combine a coaling with a water station, in order that an engine may take both fuel and water at the same time. Such an arrangement is usually made at divi- sion points and terminals, though it is not always practi- cable to place a water tank and coaling station side by side. A tender of coal will serve for several tankfuls of water, so that coaling stations situated at division points, at inter- vals of say 100 miles, will serve every requirement. When the railroad has a double track, it is customary to place a water tank on each side of the roadway, so that engines may take water from either track. The tank house should stand near the track, leaving only from 2 to 4 feet clearance for cars. 1816. Source of Water Supply. — The least expen- sive and most satisfactory water supply is that obtained from either springs or brooks which have sufficient elevation to deliver water into the tank by gravity and so avoid the expense of pumping. Clear, pure water, as free as possible 137r) RAILROAD STRUCTURES. from mineral matter in solution, is greatly to be desired. If the stream from which the supply is obtained is liable to be- come muddy from freshets, a reservoir of suitable size should be constructed and kept constantly full of clear water, so that, in case of a freshet, the flow of the water into the reservoir may be stopped until the stream runs clear. Where spring water is used, and the supply in times of drouth is liable to run short, a reservoir of ample capacity should be constructed, and the surplus water stored for future use. When the source of supply is too low to be delivered by force of gravity, resort is had to pumping. Formerly, horse- power was used to a considerable extent for pumping, but of late years steam and wind power have been exclusively em- ployed. Pumping by wind mills is the least expensive, and, but for occasional calms, the most satisfactory. The only way to provide against a short supply due to calms is to make the capacity of the water tanks adequate for a number of days' supply. The tank has three pipes : an inlet pipe by which the water enters the tank, a waste pipe for prevent- ing overflow, and a discharge, or feed-pipe, 7 or 8 inches in diameter, in or near the bottom, through which the water flows to the tender tank. The discharge pipe is from 8 to 10 feet long, and jointed at the end which joins the tank, so that when the tender tank is filled, the discharge pipe, acted upon by a counterweight, swings either sideways or verti- cally on its hinge joint, out of reach of the cars. The dis- charge pipe at its connection with the tank is provided with a valve which has a lifting gate. Movement is communica- ted to this gate by means of a lever, the short arm of which is attached to the valve rod. The long arm of the lever has a rope attached, which hangs within reach of the engineman. When taking water, the discharge pipe is lowered and swung over the water hole in the tender tank. The engine- man then pulls down on the lever. This action raises the valve stem and allows the water to flow from the water tank into the tender tank. Tender tanks hold from 2,500 to 3,500 gallons. RAILROAD STRUCTURES. 1277 1278 RAILROAD STRUCTURES. 1817. Standard Water Titnks. — A general plan of a standard water tank is given in Fig. ('/.VZ. The foundation is shown in plan at A; a plan of the arrangement of timbers composing the tank seat or deck is shown at /j, and a com- plete elevation of the tank at C. The foundations should be of the most substantial character, of well-dressed stone laid in cement mortar. The foundation consists of either continuous walls laid at right angles, upon which the sills are placed and the posts mortised into them, or a pediment of pyramidal form is built for each post, as shown in the figure. Each ppst is secured to its pediment by a dowel 1 in. in diameter by 6 in. in length. The stone pediment forms a very substantial foundation. It is effective in appearance and does away with the sills, which are apt to decay from alternate wetting and drying. The posts are connected together by girts a, d, c, which are tenoned into the posts and fastened with treenails. This connection is further strengthened by | in. tie-rods d, e,/, which pass through each row of posts, a cast washer being placed under the head and nut of each tie-rod. Between each two rows of girts a series of X braces ^, //, k is placed and securely spiked to the posts and girts. The caps /, w, n, o, upon which the beams which compose the deck rest, are 12 in. X 12 in., and fastened to the posts by mortise and tenon. The deck is composed of two sets of timbers laid at right angles to each other. The first set, laid directly upon the posts, are 3 in. X 12 in., and uniformly spaced. They are held together and strengthened by bridging (see detail /?) besides being spiked to the caps. The second set of deck timbers are 4 in. X 6 in., and laid at right angles to the floor- beams. They are spaced 19 in. center to center, and ex- tend to within 3 in. of th6 tank staves. They are in direct contact with the bottom of the tank, and receive the entire weight of the water contained in the tank without allowing any of its weight to rest upon the staves. The deck is usually made octagonal in form, and where the tank is not covered by a house, the deck is made to project far enough from the tank (as shown at .£^) to protect the foundation and timber RAILROAD STRUCTURES. 1279 supports from the weather. The sides of the tank flare or batter outwards at the rate of ^ in. to the foot, so that the hoops will drive tight. The discharge pipe/, when not in use, takes the position shown in the figure, being held in that position by the weighted ball ^, which is attached to the chain r, running through the sheave s, and thence to its connection with the discharge pipe. A cross-section of the track is shown at G, the top of the rail being 12 ft. below the outlet of the discharge pipe. The valve connection of the discharge pipe with the tank is shown in Fig. 633. The connection may be made either Fig. 6.3.3. through the side or bottom of the tank. The bottom valve connection is shown in the figure. The valve rod a is attached to the short arm of the lever d. The weight f , attached to the end of the short arm of the lever, holds the valve firmly in place. A rope is attached to the end d of the long arm of the lever and hangs within reach of the engine- man. By pulling down on this rope, the valve is raised, and the water flows through the discharge pipe e to the tender tank. The vacuum pipe / admits air to the discharge 1280 RAILROAD STRUCTURES. pipe after the valve comes to its seat, so that the discharge pipe is quickly voided. 1818. Water Columns. — Where space is limited and the head of water is sufficient, a water column (see Fig. 034) is used in place of / W==^^'**ni a tank. One advantage of a water column is in its economy of space, as will be at once ap- parent. It can safely be placed between the parallel tracks of a double-track road, and serve engines on both tracks equally well. This water column consists of a globe valve a, connecting with the main water pipe b^ and enclosed in acham- FiG. 634. ber of brick masonry. This chamber is covered with a substantial floor of timber, and forms the foundation for the pedestal c, which supports the crane-shaped water column d. This column is jointed at its connection with the pedestal, so that the discharge pipe may be readily swung over the ten- der when taking water. The cast- iron globe f (Fig. 035) is connected with the valve disk Fig. ess. by means of the valve rod g^ and by its weight keeps the RAILROAD STRUCTURES. 1281 valve closed. When taking water, the lever h is de- pressed. This causes the short arm k of the lever to rise, and lifts the globe/". The weight being thus removed from the valve, the disk is lifted by the pressure of the water which flows through the discharge pipe to the tender tank. COALING STATIONS. 1819. Coaling stations are points along a railroad where fuel is kept in stock for supplying locomotives. They are placed at all division points, large yards, and sometimes at the summits of long grades where pushers are employed. Formerly, many roads used wood as fuel, but coal, which is far more lasting and more economical of space, is now almost universally used. The coaling stations of thirty years ago were very primitive in design. The fuel was loaded by hand, the coal being loaded into small carts and dumped from a platform into the tender. A very decided advance in design was made when the coal pockets shown in Fig. 636 were introduced. The pockets are supported on bents of trestlework, each pocket comprising the space between two bents. The figure shows the cross-section at A, and the side elevation at B. Each bent is supported by four posts, a, b, c, and d. All are vertical except the last, d^ which has a batter of 3 in. to the foot. Timbers e f, 6 in. x 12 in., are bolted to both sides of the posts and supported by batter posts ^, h, also 6 in. x 12 in., which are bolted to both post and sill. These combined form the support to the pocket floor system, which consists of 6 in. x 10 in. floor-beams >^, /, etc., laid 2 ft. center to center, as shown in the figure, and drift-bolted to the supports. Upon these floor-beams is laid a flooring of 3-in. oak planks, which are covered with plates of sheet iron from ^ to y\ in. in thickness to protect them from the wear of the coal. The bents are spaced 12 feet, center to center, and planked on both sides above the floor with 3-in. planks, forming a series of pockets. This provides for storing coal 1282 RAILROAD STRUCTURES. RAILROAD STRUCTURES. 1283 of different sizes, so as to meet the requirements of the dif- ferent types of engines. The partition walls are also pro- tected with sheet iron. The track stringers are placed directly over the middle posts. They consist of two pieces 8 in. X 16 in., and extend over two bents, as in ordinary trestle building. The ties are 7 in. X 8 in. X 10 ft., and notched down 1 in. on the stringers. They carry an 8-in. X 8-in. guard-rail, which is also notched 1 in. on the ties. Stringers are fastened to cap with drift-bolts, | in. x 24 in , round iron. Stringers are spaced 3 in., and held in place by separators of cast iron. Stringer bolts are fin. X 22 in. The bents are further tied together by the timbers ;//, w, 12 in. X 12 in., which are fastened to the caps with |-in. X 20-in. drift-bolts, and by the timbers «, n. Gin. x 12 in., which partly support the plank walks o. These walks are protected by a railing / /, which is supported by posts spiked to the timbers ///, ;//. The coal is conducted from the pocket to tender by means of the spout or chute r, composed of planks and sheet iron. This chute, when in position for coaling a tender, is repre- sented by r, and when not in use, by r' . It is fitted with counterweights s, somewhat heavier than itself, which en- able the engineman to handle it with ease. The mouth of the pocket is closed by a sliding door /, of cast iron, which works in guides, and is operated by means of a lever ti. This lever is attached to a grooved wheel, in which works a chain which is attached to the door /. The lever attach- ment is shown in detail at C. The chain is fastened to the groove of the wheel with a staple v. Power is applied to the lever by means of the rope w. The wheel is supported by two 4-in. X 12-in. oak timbers .r, x, which are bolted to the plate y and the timber in. These are so fastened at the top as to project forward, as shown at x in the elevation. This throws the wheel axis forward, so that the lifting chain will clear the woodwork. To take coal, the engineman first lowers the spout r\ he then pulls down the lever u by means of the rope u\ which raises the door / and allows the coal to run from the pocket 1284 RAILROAD STRUCTURES. into the tender. The pocket floor at z should not be less than 11 ft. above the top of the rail. The loaded cars of coal are dumped directly from the track above into the pockets. The supply track is usually an incline plane, with a grade as sharp as is consistent with safe operation. Sometimes, where space is very limited, the loaded cars of coal are hauled to the top of the pockets by cable over a steep incline. 1 820. A Modern Coaling Station. — A modern coal- ing station is shown in Fig. 037, in which the coal is han- dled by machinery. The figure includes a general plan of the station, the elevation being shown at A and the cross- section at B. The power to drive the machinery is fur- nished by the engine c. The machinery consists of an ele- vator d dzxiA a. conveyor e e, composed of link belts carrying projecting pieces of board, which, as they slide through troughs lined with sheet iron, form elevating or conveying buckets, first elevating the coal from the pocket beneath the track where it is dumped from the car, to the head of the incline, and then conveying it to the different pockets, where it is stored ready for the use of locomotives. The link belts are driven by sprocket wheels 7^ and ^. The power is trans- mitted from the engine to the machinery by means of a wire rope belt. The main sheaves /i and k are 6 feet in diameter. They are attached to shafts carrying pinions which drive the gears /and ;//, and with them the sprocket wheels y and g: The coal to be elevated to the coal pockets is first dumped from the car ;/ into a chamber beneath the track. The coal runs by gravity from this chamber through the opening into the elevating chute /, which is lined with sheet iron, and as the projecting boards carried by the link belt pass under the sprocket wheel g, they push the coal before them, forming a series of buckets, which carry the coal to the point r, where an opening in the chute allows the coal to fall into the conveying chute s. Here a similar series of buckets, passing around the sprocket wheel /, collects the coal as it falls from the elevator chute and carries it to the storage '/ /// / . ',/l/l,l/' '-////////////////////// *55m^^;mm#.^M;^^^i^Ml:^^^^^f^^, RAILROAD STRUCTURES. 1285 pockets of the station. In the bottom of the conveying chute, and directly above each pocket, is an opening of suit- able dimensions. These openings are fitted with sliding covers, which are close fitting, and all of them are closed excepting the one connecting with the pocket to be filled. The sheave ii is fitted with a sliding journal which provides for taking up any slack in the wire rope drive due to stretch- ing. The link belt of the elevator on its return is supported by the sheaves v and w, and the conveyor belt by the sheave X. These sheaves are supported by brackets bolted to the floor timbers of the chutes. The pockets are enclosed with planks and covered by a slate roof, an open space 2 feet in width being left under the eaves for the free circulation of air. The general form of the coal pockets is the same as those shown in Fig. 636. The coaling spouts j, y are made of cast iron, instead of plank lined with sheet iron. The spouts are raised and lowered by means of counterweights^ as shown both in elevation and cross-section. The pockets are lined with sheet iron or steel. The gauge line of the track is commonly placed 5 ft. from the face of the coal pockets, and the bottom of the pockets at their connection with the spouts 12 ft. above the rail. TURNTABLES. 1821. A turntable, as shown in Fig, 638, is a platform usually from 50 to 70 feet long, and from 8 to 10 feet wide, upon which a locomotive and tender may be run and then turned horizontally through any portion of a circle, and thus be transferred from one track to another forming any angle with it. The table is supported by a pivot under its cen- ter, and by wheels or rollers under its ends. Beneath the platform is excavated a circular pit 4 or 5 feet deep, having its circumference lined with brick or stone masonry 2 feet in depth, and capped with either cut stone or wood. The diameter of the pit in the clear is about 2 inches greater than the length of the turntable. The masonry lining is usually built with a step (see elevation B), which supports 1286 RAILROAD STRUCTURES. i2/. RAILROAD STRUCTURES. 1287 the rail upon which the end rollers travel. At the cen- ter of the pit is a substantial foundation of masonry, upon which the pivot rests. This foundation should be 4 or 5 feet in depth and composed of large, regularly shaped stones laid in cement mortar and well bonded to- gether. This foundation is capped by a single stone 6 ft. square and 12 in. in thickness. The pivot, shown in de- tail at C, is fastened to the foundation by heavy anchor bolts reaching the full depth of the masonry. Sometimes the pit is floored over with plank, but this so greatly in- creases the weight of the table, besides involving the ex- pense of renewal, that it should be dispensed with unless circumstances make a floor necessary. Usually, only a walk of planks, supported by the projecting ties, is al- lowed. The turntable should be somewhat longer than the total lengch of both locomotive and tender, so as to permit the engineman to move his engine a few feet in either direction from the pivot in order to secure an equilibrium. With a little practice, such an equilibrium is easily obtained. By this means the friction while turning is confined chiefly to the center of motion. Probably the best turntables in use in America are manu- factured by Wm. Sellers & Co., of Philadelphia, Pa. The turntable shown in Fig. 638 is a copy of their recent standard. They are expensive in first cost, but most economical both in operation and in the matter of repairs. Being composed chiefly of metal they are very enduring, and as the parts are readily duplicated, repairs are simple and expeditious. One man can readily turn one of these tables, loaded, without the assistance of machinery. They consist of two heavy cast-iron girders, perforated by circu- lar holes to reduce weight and cost. Each girder consists of two parts, a and b, fastened to a heavy central boxing, shown in cross-section at C. The girders are fastened to it by means of heavy iron bars c, d, 3J in. square, of rolled iron, fitted into sunk recesses on top of the boxing, and tightened in place by 1288 RAILROAD STRUCTURES. means of wedges, and also by means of two 2:J:-in. key bolts at the base of the girders, passing through the holes r, /, and confined by the keys^, ^. The central portion of the boxing is a hollow cone ^, open at top and bottom, and sur- rounding the hollow conical pivot post I'. The pivot shell is about If in. thick. On top of the post rests a heavy, loose, cast-iron cap /, which permits of a slight rocking motion of the entire platform as the engine enters and leaves the turntable. This cap supports the steel box (see detail D) containing the friction rollers w. There are fifteen of them, each about 2f in., both in length and greatest diameter. They have no axles, but lie loosely in the lower part of the box, filling its circumference, save a half-inch of space left for the free movement of the rollers. In the direction of their axis they have but ^ in. play in the box. The lid « of the box rests directly upon the rollers them- selves, and does not come down to the lower part o of the box by ^ inch. Both the rollers and the box enclosing them are finished with mathematical accuracy, so as to ensure a perfect bearing between them. The rollers are kept con- stantly oiled, as ease in turning depends entirely upon their being well lubricated. On top of the rollers is the cap/, which is secured by heavy bolts. This cap does not rest directly upon the boxing, but is separated from it by wooden wedges g, q, by means of which the table may be raised or lowered and its height exactly adjusted to the connecting track. When the engine is properly balanced, the cap bolts sus- tain all the load placed upon the turntable, excepting the small amount carried by the tracks at the end of the platform. When properly balanced on a Sellers' turntable, the end wheels should only just touch the rails. The diameter of the roller box being 15 in., it is not difficult to balance the locomotive and tender. All turntables should be pro- vided with the means of being raised -or lowered, and so adjusted as to give the proper bearing upon the circular track. 0-2^^-2 -nopuijf $c-fn»tjtis ptia 1290 RAILROAD STRUCTURES. SECTION BUILDINGS. 1822. Tool Houses. — At the headquarters of each section a tool house is erected for the storage of hand and push cars, track tools, and all track materials which may be damaged by exposure to the weather, or, on account of their portability, likely to be stolen. Among the latter class are track bolts and track spikes, nails and cut spikes, shim and pin timber, etc. The tool house should not con- nect directly with the main track, but with a siding, so that a train standing on the main track will not interfere with a crew starting for work with either hand or push car. The tool house should be placed convenient to that occupied by the section foreman, so that all tools and material may be near his hand either for repair or inspection, or for use in case of an emergency. All tools and material contained in the house should be kept in perfect order and repair. A building fully meeting the requirements of a tool house is shown in Fig. 639. It should rest upon a substantial found- ation of masonry, and stand fully 12 inches above the sur- face of the ground, so as to allow ample circulation of air among the floor timbers. At one end of the house is a work bench fitted with a vise, together with wrenches, ham- mers, hand saws, punches, and any other tools necessary in making repairs of tools or track. The hand and push cars rest upon a permanent track, shown at a. They are admitted through a sliding door shown in detail at A. A device for transferring the hand car to the tool house track is shown at C. It consists of two oak pieces b and c which serve as rails. They are held at gauge by the cross- piece d and the bolster e, which are bolted to the strips. A pin passes through the bolster ^ into a socket in the cast-iron portable pedestal /"on which the frame revolves. In using, the pedestal is placed upon a tie with the pieces r, d lying di- rectly upon the rails. The hand car is then run upon the frame, which is revolved so as to connect with the tool house track. The tool house should be well provided with racks, upon which the various tools of the section may be safely and J— m f - 7-2'— A II >1 11 '-ll\l9-0 • \*3-o' 1 n -11x19- / r« 19-4 1 * n 1~ 1 1 c ^ N L |:r -19-4'^ — , — H 11 160x11-9 7^J 7-11X9-10 7-U X9-10 U — 8-S 18-4" ;? ii FlO 640 1292 RAILROAD STRUCTURES. economically stored. Hooks of iron or of wood nailed to the sides of the house are especially handy for hanging up shovels. A locker built under the work bench is useful for storing lanterns and oil cans. The plan shown is in detail, so that it may be used as a guide for any who wish to build a safe and economical tool house. A section through the door is shown in detail at B. The roof covering is of corrugated iron, which also serves as a protection against fire. 1823* Section Dwelling Houses. — Dwelling houses for section men should be substantial, neat, and of moderate size and cost. A house meeting these requirements is shown in Figs. G40 and 641. It has a balloon frame, is strong, and may be undertaken and built by any carpenter of aver- age intelligence. It provides ample accommodation for a family of eight persons, and will contain twelve with but little crowding. The outer walls and partitions consist of two courses of inch boards nailed vertically to the frame. They should be surfaced on one side, ship lapped, and well seasoned before being put in place. This gives a smooth surface on both sides of the walls, and takes paint well. Door and window casings should be of pine. The ground floor is of material similar to the walls, excepting that the floor boards should be tongued and grooved. Complete framing plans are shown, and will serve as a guide to those undertaking similar work. The cross-section A B shows the arrangement of the stairs and spacing of floors. A framing plan of the second floor is shown at E^ and of the first or ground floor at G. A detail of the roof frame of the main body of the house is shown at F^ and of the roof of the addition at H. A detail of the sill and floor joist is shown at A', and of a door casing at L. The roof covering, like that of the tool house, should be of corrugated iron. 1824. "Watchman's Shanty. — A watchman's shanty should be large enough to comfortably accommodate one man, no more. This will include space for a stove for warming Section through AB. Section through CD. Fig. Ml. 1294 RAILROAD STRUCTURES. the building in winter. A general plan for a watchman's h' r i'xo' 1 > s'xr V 1 1 2x4' - < r sxe' 1 U 1 8'xs: frtndow Ugh U 8x10 1 rlx«" fi 1 - '^ 1 ^«xa^ B * M 1 ■ 3x« ■ 1 .L I ,^ ir«wering of tunnels . . 955 Toe of switch iioa Tongue of frog 1103 XVI INDEX. PAGE Tool house i2<)o Tools, Care of 1153 " Trestle inspector's . . 1228 Topographer's notes, Form of . 678 Topographical drawing by level contours . 777, 779 '* drawing by lines of greatest slope 777, 786 " drawing by shades from vertical light 777. 788 " drawi ng, Conven- tional signs used in 789 " drawing . . . 776 " '* Systems of 777 " survey . . 673, 824 " " of town sites 735 673 Topography Colored Conventional signs used in . . . Platting, in the field Township " divisions . " lines, how run . " posts, how placed and marked . Town sites and subdivisions . Track, Ballasting of . bolts. Loose . " Removal of . " Straining of Bridge approaches of . Care and maintenance of centers . Curved . Drainage of . gauge inspection jack joints laying " machines " outfit . level Lining of Old, work on Raising of Repairs to Shimming of Surfacing ties Tunnel . Tracks, Side " Y . . Track work, Fall 1050, 1060, 1073. 1063, 1075 806 789 677 <593 694 696 705 733 1069 1062 1062 J061 1062 1058 1032 1087 1052 1047 "55 1049 X036 1029 1032 1033 1099 1150 io63 1070 1079 1080 1048, 1073 1063 955 1057 1126 1073 Track work, General instructions for ... . " in tunnels " Spring .... " Summer " Winter .... Transit, Adjustments of . " Care of .... " Directions for using . " Engineer's .... " notes. Form of . " points. Referencing . Transverse strength of materials . Trautwine's Pocket Book Traverse tables .... Trestle, Connection of, with em- bankment " Foot walks for " foundations of crib work . *' " " grillage " " " loose rock . masonry solid rock 1148 965 1058 1063 1079 626 629 629 621 654 844 1247 858 718 1207 1210 1 180 1179 1181 1 178 1181 1 192 guard rails . loads ..... 1007 Protection of, against fire 1210, t2t8 Refuge bays for . . . 1209 Single track pile . . 1230 Plan of 1230 specifications , . . 1213 Standard double track pile, Boston & Albany R.R. . 1238 Standard frame, Oregon & Washington R.R. . . 1240 Standard framed, Cleve- land & Canton R.R. . 1235 Standard framed, Ohio Con- necting R.R. . . . 1237 Standard framed, Penn- sylvania R.R. . stringers Sway-bracing of ties, Arrangement of Trestles Cost of . Average life of . Bracing of . Classes of . . . Compound timber Creosoted Erection of . Floor system of . Framed " Dimensions of Inspection of • >33ta . 1187 . 1195 . 1 191 . 1 163 1164, 1166 . 1163 • "95 . 1166 • "35 . 1216 . 1211 . 1 186 . 1166 . 1246 i2i8, 1226 INDEX. XVU PAGE Trestles, Iron details of . . . 1 198 " on curves .... 1197 " Pile 1166 " Technical names of parts of 1167 Triangles, Equal .... 601 " Similar .... 603 Triangulation 634 " Span of bridges meas- ured by . . . 979 True meridian 611 Truss, King rod .... 1257 " Queen rod .... 1269 Tunnel, Alinement and levels for . 960 " Bench of . . . 946, 948 " Centers of . . . . 959 " Drainage of ... 950 " driving . . . .945 " " Methods of . . 946 " " Plant required for 945 " " Progress in . . 965 " Excavated material of, how- removed .... 952 " Excavation .... 863 " " Cost of . . 964 " " Measurement of . . . 961 " Explosives used in driving 948 " Grade of ... . 955 " Heading of . . .. 946, 948 " heading, drilling, and blasting .... " Laying out surface line of " Lighting of . " lines, Curved " masonry " Measuring line of " Portals of . . . " sections " shafts .... '• " Plumbing of " Stationing of " Timbering of " tracks. Care of . " Ventilation of Tunnels Turning points .... Turnouts " Automatic Turntables .... U. PAGE United States system of surveying public lands 693 946 935 965 941 863 938 959 944 950 962 941 955 955 963 935 66s 1127 1124 1285 Valley lines PAGE • 777 " Advantages of, for rail- roads .... 820 Variation, Magnetic . . . 612, 711 Ventilation of tunnels . . . 963 Verniers 625 Vertical angles 638 " curves 850 Voussoirs of arches .... 886 W. PAGE Wales of cofferdam .... 984 Wall, Retaining 899 •' Rubble 898 " Wing .... 880, 89s Washers 1205 Washouts 1059 Watchman's shanty .... 1292 Water checks 667 " columns 1280 " frontage 703 " jet. Use of in sinking piles . 1003 " supply, Source of . . . 1275 " stations 1274 " tanks 1278 Weeds, Cutting and mowing . . 1067 " Destroyed by gravel . . 1072 Wheelbarrow work. Cost of . . 914 Wheeled scraper. Use of in excava- tion 919 Whistling posts. Location of . . 115a Wing walls of culvert . . 880, 895 Wings of frog J103 Witness trees for land corners . 713 Wood, Strength of ... . 1254 Wooden pillars. Strength of . . 1253 Work, Average daily, of a man . 1158 Work train service .... 1155 Y. PAGE Y level, Adjustments of . . .658 " Sensibility of . . .661 " Use and care of . . . 661 Y tracks 1126 Yard work 1072 Yards 1145 >»> 5>>3v5S^3'5> •^.:>^^ 5 > ' o ^ O J>^ >i)X> 3^ >> i) JD3J ^:x:ft!>'*^^' ^^^^^2^.^?^ <* 5 ^ ' ^.> .:>^^'a> ) ^ > > J :> ;> J )■) ) ) ) > ) > ' ■ > C dCCCC cCCC( rccc ccccco O-'C^^^S ccocc ''■■■■■'v.- 5';'-'/;r' v^'>/\\;^';;,v::■■■:U^''^'■ VJ M'-r