^ o ^ t:t*' v\ if'? ,. -^^Z*!^-,/ %'^'Uo^ ^^/^^\/ "o^^^-?/ V^^ ,/ %.'^^\< '^"Ts A. « O 3 A F ^^^^^ ,v .♦^'V -v ^ '^''^^^c.*'* a»^ A^^'^^ ^ ^ 4 .9^ ^.^> "^ ..^^ .T* A V-S^ y ,^'», ^^ ^Ad^ * o.-?-' A^^..^ '• o. ^^ *'^. ..^•/ *^/^-- /■ •\'.^-/ **,-^-^\/ "^ ... C^ .* o V "^0^ .■^°^ N^"" V^ .. -^o^ S • • / ^^\'^!;'^^^ .or.,-., -^o, .^^\c_^'v. 16 Field testing 16 Mine ventilation and compressed-air analysis 16 Injector locations and installation 17 Test procedures 18 Results 19 Design and development of second-generation stench injector 25 Deficiencies in design of the improved stench injector 25 Design features of the second-generation injector 26 Remote-control system for injector actuation 27 Testing of second-generation stench system 28 Installation 28 Test procedures 28 Results 28 Summary and conclusions 30 References 33 ILLUSTRATIONS 1. Evacuation time versus maximum depth of main shaft 2 2. Size of underground workforce versus depth of mine 3 V) 3. Reactivity of ethyl mercaptan with iron oxide 5 ^ 4. Vial-breaking stench injector 10 rv^ 5. Components of vial-breaking stench injector 10 '^ 6. Pressurized-canister stench injector 11 \ 7. Components of pressurized-canister stench injector 12 V9 8. Pressurized-canister injector with metering orifice 12 9. Use of pressure-balancing line to equalize pressure across metering Vo orifice 13 10. Variable-rate injection pump 14 11. Improved stench injector design 15 12. Layout of haulage levels, boreholes, and main shaft in test mine 17 13. Sampling points and transit times for compressed-air system tracer gas analysis 18 14. Main shaft ventilation-air injector location 18 ^ XI ILLUSTRATIONS—Continued Page 15. Remote venthole injector location 18 16. Compressed-air injector location 19 17. Compressed-air injector mounted on receiver tank 20 Stench test results, improved system, first shift: 18. 1-4 level 20 19. 1-5 level 21 Stench test results, improved system, second shift: 20. 1-4 level 21 21. 1-5 level 21 Stench test results, existing system, third shift: 22. 1-4 level 22 23. 1-5 level 22 Previous stench test results, existing system, first shift: 24. 1-4 level 22 25. 1-5 level 23 Previous stench test results, existing system, second shift: 26. 1-4 level 23 27. 1-5 level 23 28. Locations of air sampling points 24 29. Stench concentration versus time for air samples collected during stench tests 25 30. Refilling improved stench injector 26 31. Second-generation stench injector design 26 32. Refilling second-generation injector 27 33. Second-generation injector for compressed air 29 34. Second-generation injector for ventilation air installed at main shaft.. 29 35. Wireless remotely controlled stench injector for ventilation air in- stalled at remote venthole 30 36. Master panel installed in hoist room 30 37. Remote-control telemetry system installed on leg of emergency-escape- hoist headf rame at remote venthole 31 Stench test results, second-generation system, first shift: 38. 1-4 level 32 39. 1-5 level 32 Stench test results, second-generation system, second shift: 40. 1-4 level 32 41. 1-5 level 33 TABLES 1. Properties of industrial gas odorants evaluated against ethyl mercaptan. 7 2. Stench fire-warning system specifications 9 3. Evaluation matrix for new injection-method design concepts 16 IMPROVED STENCH FIRE WARNING FOR UNDERGROUND MINES By William H. Pomroy and Terry L. Muldoon ABSTRACT This report describes Bureau of Mines research that led to the de- sign, prototype fabrication, and successful proof-of-concept testing of an improved stench fire-warning system for underground noncoal mines. Stench systems are the most widely used means of warning miners in underground noncoal mines of fires or other emergencies. A stench sys- tem alerts miners that an emergency condition exists by injepting an odorant into the mine air. Although stench warning systems have been used successfully for over 60 yr , present systems suffer several seri- ous shortcomings, including odorant toxicity, unreliability of warn- ings, widely varying stench concentrations, and others. In 1980, the Bureau began a research program to upgrade the stench warning system. The resultant system overcomes the deficiencies of ex- isting systems by substituting tetrahydrothiophene for the commonly used ethyl mercaptan stench odorant, and through the use of a specially designed stench injector. The improved injector reliably meters stench fluid into either ventilation-air or compressed-air streams at a pre- cisely controlled rate. Prototype hardware has been fabricated and proof-of-concept tested under both laboratory and in-mine conditions. ^Supervisory mining engineer, Twin Cities Research Center, Bureau of Mines, Minne- apolis, MN . ^Program manager, Foster-Miller Associates, Inc., Waltham, MA. INTRODUCTION Fires In underground noncoal mines are a serious hazard to life and property. From 1965 to 1979, there were 115 report- able fires (at least 30 min in duration or resulting in injury) in U.S. under- ground noncoal mines, accounting for 119 fatalities (J_).-^ Countless millions of dollars were spent on rescue and recovery efforts, equipment repair and replace- ment, and mine rehabilitation. In addi- tion, mines shut down by fires were forced to forego hundreds of millions of tons of mineral production. ^Underlined numbers in parentheses re- fer to items in the list of references at the end of this report. The primary safety hazard in an under- ground fire is contaminated air. Since the mine's limited fresh-air supply can be rapidly consumed and replaced by smoke and toxic gas, the mine must be evacuated as quickly as possible in the event of fire. However, mine evacuation is often a very time-consuming process. In a recent survey of 50 underground noncoal mines, emergency evacuation times ranged from 5 to 85 min, with a strong correlation between the time required for evacuation and the maximum depth of the main shaft (fig. 1) (2^). Compounding the problem of longer evacuation times for deeper mines is the fact that work forces in deeper mines are usually larger than to O < X z < IJ. o Q. Ul O 20 70 30 40 50 60 EVACUATION TIME, min FIGURE 1. - Evacuation time versus maximum depth of main shaft. work forces in shallower mines (fig. 2). The average work force in mines between 3,600 and 7,700 ft deep is 195 miners per shift, whereas the average work force for mines less than 1,800 ft deep is only 84 miners per shift. As mines become deeper with the depletion of shallower ore bodies , these problems of long evacu- ation times and more miner exposure to fire hazards will tend to get worse. Mine fire evacuation must begin as soon as possible after a fire has been detected. The miners must be warned, and they must then follow an emergency escape preplan. Since time is of the essence, detection, warning, and escape must all be accomplished as reliably and quickly as possible. However, fire-warning tech- nology, the essential link between detec- tion and evacuation, has not kept pace with advances in detection and evacuation planning. In a typical stench system, ethyl mer- captan, a highly odoriferous organic com- pound, is released from the surface into the compressed-air and/or ventilation- air streams of the mine. The liquid is quickly vaporized, and the stench is car- ried in the airstreams to the working areas underground. Miners, upon smelling the stench, evacuate the mine according to the emergency preplan. Although the stench system has been used successfully for over 60 yr, it suf- fers several serious shortcomings owing to certain chemical properties of ethyl mercaptan and certain performance char- acteristics and limitations of present injection systems. These shortcomings include (1) toxicity of the odorant which can lead to debility in miners; (2) re- activity of the odorant with iron ox- ide, which can result in unreliable warn- ings because the odor may fade when transported long distances in steel pipe; (3) lack of control over the rate of agent release into the airstream, with the result that some work areas may re- ceive unbearably high stench concen- trations while other areas are missed 200 r- 50 X cr LU Q. 0} QC UJ I 100 u. O oc UJ m i 50 1,800 3,600 MINE SHAFT DEPTH, ft FIGURE 2. - Size of underground workforce versus depth of mine. 7,200 altogether; (4) lack of visual indica- tions of system status, valve positions, and proper system operation; and (5) ex- cessively long stench transit times. In 1980, the Bureau of Mines embarked on a research program to upgrade the stench warning system. The objectives of this program were to improve the safety. reliability, and effectiveness of stench systems. The work done under this pro- gram was accomplished through a research and development contract with Foster- Miller Associates, Inc., Waltham, MA O- 4^) , and is described in detail in this report. ALTERNATIVES TO STENCH WARNING Although the primary thrust of the re- search program was to upgrade the stench system, the following sections are in- cluded to acquaint the reader with avail- able and near state-of-the-art mine warn- ing system options. Subsequent analyses of existing stench warning technology and the improved stench warning system devel- oped by the Bureau are more meaningful when considered in the context of mine warning systems in general. Two alternatives to stench systems are now used on a limited basis: electrical and messenger systems. Radio systems, although not in current use, are often mentioned as a possible successor to the stench system. ELECTRICAL SYSTEMS Electrical warning systems are used where compressed-air equipment is not used extensively and where ventilation velocities are low. Bells, flashing lights, gongs, and horns have been tried and have achieved limited success. How- ever, these systems are not effective when miners are working outside the vis- ible or audible range of the alarm or when mine power fails. Where electrical equipment is used extensively in the min- ing operation, interruption of the power supply has sometimes been used to signal an emergency. However, this system is also unreliable because power interrup- tions are common in many mines, and elec- trical equipment may not be in use when an emergency occurs. MESSENGER SYSTEMS A messenger system depends on the miners to physically communicate the emergency warning from person to person. Some mines use a messenger system as the primary warning system, but more commonly a messenger system is used as a backup to the primary system. Messenger systems are particularly common in small mines where personnel are not spread out over a large area and/or where telephone systems are both reliable and extensive. The chief disadvantage of the messenger sys- tem is the time required for the signal to be passed to each worker. RADIO SYSTEMS Prototypes of high frequency (HF) , very high frequency (VHF) , and ultrahigh frequency (UHF) leaky-feeder wireless radio-transmission communication systems have been constructed and tested in sev- eral noncoal underground mines. Although originally designed for the geometry of coal mines, it was hoped these systems would find application in noncoal mines as well. However, test results showed signal ranges were limited to 30 to 50 ft from the transmission cable (5) . An alternative to the leaky-feeder ap- proach is provided by medium frequency (MF) transmission. MF has the unique capability to couple into, and reradiate from, continuous conductors in the mine (rails, trolley lines, water pipes, air lines, phone lines, etc.) in such a way that these conductors become not only the transmission lines, but also the antenna system for the signals (6^). Although this parasitic coupling ef- fect provides greater signal-transmission coverage, in comparison with leaky-feeder systems, MF systems have problems in reliably receiving the transmitted sig- nal. Large, protruding antennas are re- quired on vehicular transceivers, and users of personal transceivers must wear a specially designed vest containing an antenna and radio-circuit modules. In addition, total mine coverage is not as- sured due to limits on signal range and through-the-rock transmission. Miners in remote stopes and development headings that are not linked to the rest of the mine by continuous conductors are most vulnerable, yet typically they are faced with the longest evacuation times. DEFICIENCIES OF EXISTING STENCH WARNING SYSTEMS The air-carried-stench system is the most popular means of emergency warning in noncoal mines because it is the most practical, versatile, and effective means currently available. Despite several se- rious shortcomings , its use and accept- ance is widespread because the alterna- tives offer lower levels of safety and reliability. Stench system deficiencies addressed through this research include the following: 1. Ethyl mercaptan is highly reactive with iron oxide (fig. 3). There- fore, the odor tends to fade when it is transported in steel pipe. (For this reason, ethyl mercaptan is no longer used as an odorant in the natural gas industry.) 2, Ethyl mercaptan is highly toxic. The 8-h time-weighted average con- centration limit (threshold limit value, or TLV) established by the 0.5 .4 r- 0} © o a 3 CO .3 - .2 I- .1 - 80 120 Time, min FIGURE 3. - Reactivity of ethyl mercaptan with iron oxide. 200 National Institute for Occupational Safety and Health (NIOSH) and the American Conference of Governmental and Industrial Hygienists (ACGIH) is 0.5 ppm. As a comparison, the NIOSH TLV for hydrogen cyanide is also 0.5 ppm. An absolute limit of 2 ppm has been set by ACGIH for ex- posures of 15 min or less. In low concentrations, ethyl mercaptan can cause headaches and nausea. At higher levels, it can irritate the skin and eyes, affect liver func- tion, affect amino acid levels in the blood, and retard redox processes. 3. The odor intensity of ethyl mercap- tan tends to increase steadily with increasing stench concentration. When personnel are exposed to high concentrations of stench, the odor can be overwhelming. 4. Ethyl mercaptan is highly corro- sive to injection equipment and air lines. Prolonged use of ethyl mer- captan can damage injectors to the extent that proper function may be impaired. 5. The injection methods release the stench in a totally uncontrolled fashion. As a result, areas of the mine near the injection point may be overwhelmed by the stench odor, and miners in those areas are like- ly to be exposed to potential- ly toxic concentrations of ethyl mercaptan. 6. The injection methods have been un- reliable. Injection equipment is often "homemade" and "free lanced." "Designs" are often strongly influ- enced by the availability of mis- cellaneous parts at the mine site. Typical problems include operat- ing procedures that are complex and therefore improperly followed, frozen valves , mismatches in size and shape between major system components and stench-fluid refill containers, and unsatisfactory and/or incompatable materials of construction. Available injection equipment does not permit visual system status checks. An empty or nonfunctional injector is not readily apparent, and if unnoticed until needed dur- ing an actual emergency, precious time could be lost while refilling it or performing repairs. Current systems do not have visual indications of valve positions. It is difficult for personnel to know if valves are completely open or completely closed, especially when valves are frozen or sluggish. Available systems have no immediate visual indications of proper system operation. The only positive con- firmation that the odorant has been released is to contact personnel underground, and this is often a time-consuming process. 10. Current systems seldom achieve to- tal mine coverage. Remote work- places, workplaces not using air equipment , and dead-end headings are often missed. 11. Stench transport times acceptably long. can be un- In addition, certain functional defi- ciencies in the stench system are in- herent due to its reliance on moving airstreams to carry the warning signal. The heat-induced buoyancy effects of a mine fire, for example, may cause throt- tling or reversals of ventilation flows. Stench injected into intake air may be exhausted if the intake air flow is reversed. Areas with poor or slow ven- tilation and/or areas distant from compressed-air equipment may not receive the stench warning signal. It was beyond the scope of this research to treat such inherent limitations. However, as mines become deeper, as workings become more complex, and as diesel and electric equipment displace compressed-air equip- ment, the need for novel warning systems that will address these problems will grow. DEVELOPMENT OF IMPROVED STENCH SYSTEM The development of an improved stench system capable of safely, effectively and reliably warning underground personnel of an emergency was accomplished in two steps: First, a stench agent was se- lected; and second, an improved injector was developed. SELECTION OF STENCH AGENT A survey of industrial gas odorizing agents was undertaken to identify a suit- able substitute for ethyl mercaptan. Many compounds were surveyed, and five were selected for detailed evaluation: isopropyl mercaptan, amyl acetate (ba- nana oil), dimethyl sulfide, tertiary butyl mercaptan, and tetrahydrothiophene (THT). Factors considered were boiling point, freezing point, vapor pressure, flashpoint, flammability limits, reac- tivity, solubility in water, toxicity, odor threshold, availability, cost, and past industrial uses. The results of the final evaluations are summarized in table 1, THT emerged as the most desirable agent for use in the stench system. THT is widely used in Europe as a natural gas odorant and has been used successfully on a limited basis in this country for the same application. THT is not reactive with iron oxide, so it is not subject to "odor fade." The odor intensity of THT tends to stabilize at a moderate, easily recognizable level, and it is much less corrosive than ethyl mercaptan. u C c o >, ^ 5 00 1 -H c o 0) e £ *rl o ■-I a. c C B- Xi o -w 0) Tl u M • N a .. • 0) o c O. C D -< X m •rJ o « aj •- 0- H 3 m in u u X y U •H ex U-( H - * !>^ c fl i_) U) a) X O £ *• , — 1 a 01 • c u ij bo O rt •H • ■n o o T^ ^ f-t f) 3 f-< < •H z o. 3 e £ Z z 3 >nO c Cl-^ a o c. u a a. w o c 09 1 ^ T3 O X (1) (U u u X S - H 0- O < <£ O Q- z z z s; r-i o en 3 en ^ C iJ 01 T3 u O O eg u ^ T3 01 u u a SJ o. C i — 0) tn aj n) a; 3 o T3 c O tfl O i-H o x: £ tn rt tn 3 3 < T3 x: • a) o J-) m ^j c c r^ •H aj 01 • F! 4J bl CJ CO (0 J o. o o. o t/J o z e M u • • ID < < ^ z z u. I— ( z O -O • O 3 Z >-. T3 tt) 1-1 iH O 0) tn o j«; JJ nj t3 O 01 — 14-1 aj o N aj 0) ^ e — X i-i tn o tn tn c ty tn C — ■£ i oc • .J ~i u y: — — (NJ — < UJ T3 to c to m ^ •H tn •o 3 C C c a c r-H bO 01 o •H 0) •H ^-^ -o u J-) • a- ^ . O aj Ifl -o CI o >^ a) -H b^ O •H fe Z VI 3 c y a; tn « x ■ » 3 tn aj U-t « e o X X ^ x; .— ( U-1 IT) H Ou - >^ o j-i o w o .. -o ^ CM c c u c tn «> • -no 01 0> 01 u t/l o Q. aj sC o < T3 • ■o i-) bn a) z o o. X C3 a. o — ' •^ tn Ifl a o c Z :^ - 3 V >. > :: U 4J -^ -^ ^ u > >> »J ^ 9j a ij a c -< Q. fc. -< 4) -< o o «c a e o 3 ur c -- • a C O 5) > 3tJOC> — '"^li C ^ >-. 'y, > a: u. >. ox (/> X a. 4-1 AJ ^ U O 3 •.-'1-1 ij -■ -- -I -< o >> C — ' -J ^ '4-1 U 4-> a. u. o X u u tn > Q. -s a) 1/ tn ^ -J w-o xe3nLt««4-> 4J o ^^ tfl D. — 'J '-» o o -.< (0 s u v a: £, u — ' O X in X tn to c 4-t X t-* 4-( 1 » u o u Oi ITV o X o lA-i 4J J o U Q, o a T3 3 O t« 0" tn O. 4J c a; a; o tfl •ii (fl i-< 4-J 13 fH o O « r t^ 3 c tn c c • •H « aj 0) d a. f— 1 c 4J X o tn to •-^ rt 4J .— ( 4J ttl •H to 3 3 > 1-1 M c « o tt! e 14-1 T3 0) ts c: o &- 1— 1 •H S o -o IJ t; c o X o tn 0) O tn tfl to 3 - o cs o X O C .H o in O M •H o u •El •o 3 3 e 4-1 tfl to n • z Q) en 4J BC 01 tfl u O 4-t 01 tn O 0) 1-1 >> z o to tn to tn tn f— 1 4-) 3 • >> c o tn 6 to iH D. O tfl a) nH p o -o nJ 3 X a) u 4J tu 4-1 iJ to tn c z - •H .s aj ^ o X T-* z tfl iH O (fl ^^ u C '-I •H 3 M •H ■o •a ifl 4-) a> a; c t; o w: i-< o T-( z 10 to •H F! u 4J aj 01 tn •H X < > 4J tn o z Ifl c (0 o T> •o 1-1 e C a) o o (fl • 4-) •o y r-* aJ X o 4) X tn ftf "0 ^ o ••-4 T3 •n aj a) tn 3 4J 3 .H 1 tn O T3 (8 01 •H TJ c: X fl ^ 1.1 (fl 4J •H Ifl X in .2 H ^ ^ N (0 a: < o <: 3 H In addition, available data suggest that THT may be far less toxic than ethyl mercaptan. Although ACGIH and NIOSH have not established a TLV for THT, the lethal concentration (LC50) for inhaled vapors of THT is 44,200 ppm (for rats), compared with an LC50 of 4,420 ppm for ethyl mer- captan. Based on this finding, and a NIOSH search of its TOXLINE computer- ized data bank of toxic substances, the Mine Safety and Health Administration (MSHA) has approved the use of THT in mine stench systems, provided the injec- tion equipment maintains agent concen- trations at nontoxic levels, (The sub- stitution of THT for ethyl mercaptan in existing stench systems thus does not satisfy the conditions established by MSHA for the use of THT in mine stench fire-war ling systems), Othe"^ pertinent chemical and physical properties made THT a favorable choice for use in the stench system. However, like ethyl mercaptan, THT is flammable (flashpoint 55° F) and needs to be mixed with an inerting agent to avoid possible explosion hazards. This potential hazard is greatest if stench is injected into compressed air. Numerous incidences of compressor fires and explosions have been recorded. Most were caused by ignition sources, such as glowing carbon deposits, igniting combustible lubricating oils in- side the compressor, lines, or receiver. The introduction of a flammable liquid (such as a flammable stench odorant) into the compressed air system would only com- pound the hazard. Laboratory flammability tests were con- ducted, and it was determined that a mix of 10 parts Freon 113'^ refrigerant and 1 part THT is totally noncombustible. Ac- cordingly, the stench fluid selected and used throughout the program was a 10:1 mix of Freon 113 and THT. STENCH INJECTOR DEVELOPMENT Prior to hardware development, numer- ous mining companies and mine safety specialists were contacted to help set performance specifications for the improved stench warning system. Both performance-range and general design specifications were thus developed. The specifications are summarized in table 2, The development program began with a com- prehensive analysis of existing stench- injection systems. Existing Stench-Injection Methods Two methods of stench injection are now in common use: the vial-breaking method and the pressurized-canister method. The vial-breaking method employs a glass vial that contains the stench fluid. The vial is placed inside an airtight steel cylin- der (fig. 4), which is connected in par- allel to 'the compressed-air line by two hoses fitted with globe valves. The sys- tem is activated as follows: First, the globe valves are opened to allow air to pass over the vial; then, a steel plunger is screwed into the cylinder to break the vial (fig. 5). The broken vial re- leases the stench fluid into the air- stream. The practices of throwing a bot- tle of stench fluid down the ventilation shaft or "puddling" the fluid at the col- lar of the downcast shaft are simply mod- ified forms of the vial-breaking method. Where the pressurized-canister method is used, the stench fluid is contained in a canister pressurized to 400 psi with a fluorinated hydrocarbon propellant (fig. 6). The canister is connected to the compressed-air line or emptied into the ventilation airstream through a short length of tubing (feed line in figure 7). Both, systems use an ethyl mercaptan-Freon mix as the stench agent. Functional analysis and actual experi- ence indicated that neither the vial- breaking method nor the pressurized- canister method was satisfactory because they were fundamentally unable to meet the established performance-range or gen- eral design specifications. Alternative design concepts were therefore developed. Design Concepts '^Reference to specific products does not imply endorsement by the Bureau of Mines. Three design concepts were developed and evaluated relative to the performance specifications: pressurized canister TABLE 2. - Stench fire-warning system specifications Performance-range specifications Airflow, ft^: Ventilation air 50,000-2,000,000 Compressed air 2,000-20,000 Compressed-air pressure psig. . 80-150 Stench gas concentration, ppm: In compressed-air line '0.5-2.0 In ventilation air '0.1-2.0 Minimum duration of stench injection, min: Into compressed air 30 Into ventilation air 10 Air temperature, °F: Ventilation -30-125 Compressed -30-200 Equipment operating specifications: Temperature °F. . -30-125 Humidity pet. . 20-100 Vibration (applied) ' None Environmental corrosion pH. . 4.0-9.0 General design specification Reliability Extremely high. (Sys- stem should be simple with a minimum number of moving parts.) Life expectancy Indefinite with per- iodic maintenance. Ease of operation Simple — requiring minimal training. System status indication Visual , including "Ready to operate," "Operating correct- ly," and "Needs to be refilled." Injector costs, maximum: Hardware ^$h , 900 Installation worker-h. . 8 Maintenance worker-h/month. . 0. 5 'As an added safequard, the maximum design concentration of THT is the same as that of ethyl mercaptan, even though available data suggest that THT is far less toxic. ^Median from field survey; however, a much lower figure is probably more realistic. This figure does not include telemetry for remote injector activation, although tele- metry may represent the single largest expense for remotely operated systems. 10 FIGURE 4. - Vial-breaking stench injector. Flexible hose Valve Stench fluid Vial-breaking plunger Screen FIGURE 5. - Components of vial-breaking stench injector. 11 FIGURE 6. - Pressurized-canister stench injector. with metering orifice, pressure balanced with metering orifice, and variable-rate injection pump. Each of these concepts is described below. Pressurized Canister With Metering Orifice This concept, which provides for meter- ing of the stench flow, is a logical extension of the pressurized-canister in- jection method already in use. The me- tering capability could be added simply by installing a metering orifice in the stench-delivery tube of a pressurized- canister injector (fig. 8). Although the design is simple and in theory could satisfy the system perform- ance specifications, injector reliability would be low. Low reliability would re- sult because an extremely small orifice would be required to meter the contents of the pressurized canister (at 400 psi) into the airstream over the desired time period (10 min for ventilation air; 30 min for compressed air) . Internal canis- ter pressurization to at least 400 psi is necessary to assure complete discharge of the canister contents. Orifices sized O.OOI to 0.013 in would be required to achieve the desired stench flow rates. Particles as small as 25 vim could plug an orifice of this size, and the probability of encountering particles 25 yra in diam- eter or larger is very high, even in a clean environment. Since nothing ap- proaching clean-room conditions exists at a typical mine, the chances of a plugged 12 Stench canister Valve Feed line Bali valve Compressed-air line FIGURE 7. - Components of pressurized- canister stench injector. Manual valve Pressurized canister Pressure indicator Filter Solenoid valve Metering orifice FIGURE 8. • Pressurized-canister injector v/ith metering orifice. orifice (and, therefore, an interrupted stench discharge) are also very high. In addition, a wide variation in stench flow rate would result owing to canister pro- pellant pressure decay. The flow rate could be expected to vary by as much as 50 pet over the period of the discharge. Pressure Balanced With Metering Orifice The pressure-balanced concept was de- veloped to take advantage of the positive features of the previous concept while eliminating its undesirable features. Orifices much larger than those mentioned above can be used if the high pressure differentials across the orifice are eliminated. This can be accomplished by introducing line pressure on both sides of the orifice via a pressure-balancing line. The concept is illustrated in figure 10. The pressure difference be- tween point 1 in figure 9 (just below the orifice at the entry to the pressure- balancing line) and point 2 (at the bottom of the standpipe) is negligibly small. During steady-state flow, the fluid pressure at point 2 is also roughly equal to the air pressure at point 1 because the fluid pressure and air pressure at point 2 are in equilibrium. Since the fluid pressure at point 2 is roughly equal to the air pressure at point 1 , the driving head exerted at the orifice is equal only to the weight of the column of fluid between point 2 and the orifice. This driving head remains constant for nearly the entire discharge, meaning the flow through the orifice (the stench- injection rate) is also constant during nearly the entire discharge. During startup, before the standpipe is emptied of stench mixture, the flow rate is greater than the steady-state flow value. This does not last very long and is easily minimized by making the stand- pipe cross-sectional area as small as possible. When the stench-mixture sur- face drops below the tip of the standpipe near the end of the run, the flow rate begins to decrease, since effective head decreases. Eventually, both the flow rate and effective head drop to zero. 13 Canister body Standpipe Mixture surface Pressure- balancing loop Airflow (very slow) Orifice Stench mixture stream (enters either compressed- air line or ventilation system) FIGURE 9. - Use of pressure-balancing line to equalize pressure across metering orifice. This effect can be lessened by minimizing the internal area of the canister below the tip of the standpipe. The important features of this concept are as follows: 1. The pressure below the orifice is balanced by an equal pressure above the orifice so that the pressure of the airstream into which the stench is injected has no affect on injec- tor operation. The driving head across the orifice is very low, so the size of the orifice can be relatively large (0.015 to 0.070 in) and still achieve the desired stench flow rates. The driving head is independent of the amount of stench fluid in the injector canister. Therefore, the injection rate does not decay as the fluid level in the canister drops. 14 Variable-Rate Injection Pump Concept Evaluation The variable-rate injection pump con- cept is the most precise method for stench injection. A precision diaphragm metering pump placed between the stench canister and the airstream can effective- ly control stench-fluid flow rates to ex- tremely close tolerances (fig. 10). The primary disadvantages of this system are its complexity and its reliance on elec- tric power. These factors could lead to very low system reliability. In addi- tion, the cost of such a system would be quite high compared to that of the other two concepts. The three design concepts were sub- jected to a systematic evaluation to weigh their respective advantages and disadvantages. The concept-evaluation matrix showing the parameters evaluated and the resultant ratings is shown in ta- ble 3. Based on this evaluation, the pressure-balanced with metering orifice concept was selected for further develop- ment. Detailed design and prototype fab- rication followed. A drawing of the re- sulting injector is shown in figure 11, and operating data are shown in table 3. Pressurized canister Solenoid valve Volume-metering pump Electric motor Back-pressure valve Pressure indicator Filter Metering nozzle Manual valve FIGURE 10. - Variable-rate injection pump. 15 Standpipe Stench fluid Driving head Ball valve Pressure-balance line To compressed air or ventilation air FIGURE 11. - Improved stench injector design. 16 TABLE 3. - Evaluation matrix for new injection-method design concepts Parameter Pressurized canister with Pressure balance with Variable-rate injection pump metering orifice metering orifice Rating Value ' Rating Value' Rating Value' Stench concentration range. Complexity Filtration level required Number of injector sizes required. Status indication Ease of manual operation. Initial cost, estimated.. Operating cost, estimated Number of significant leak points. Electric power required.. Remote-operation capability. Temperature sensitivity.. Reliability Maintainability Training requirements.... Life expectancy Safety Acceptable Low Very high. 5 Fair Good $800 $100 15 (2) Yes High Very low.. High Low High Medium. . . . NAp 3 3 1 2 3 3 2 1 3 3 1 3 3 3 2 Acceptable Low Medium. . . . 3 Fair Good $1,800.... $50 1 3 3 2 2 2 3 2 3 3 3 3 3 3 3 2 3 3 Acceptable Medium. . . . High 2 3 2 1 3 Poor Good $3,000.... $100 15 Yes Yes Medium. . . . Low Low High Low Low NAp 1 3 1 2 1 (2) Yes Low High High Medium. . . . High High NAp 1 3 2 1 1 1 1 1 Total 36 46 28 NAp Not applicable. 'Maximum total = 51. ^For remote-operation capability only, TESTING THE IMPROVED STENCH SYSTEM A prototype of the entire improved stench system was fabricated and proof- of-concept tested in the laboratory and at an operating underground mine to val- idate its performance and highlight any design deficiencies. LABORATORY TESTING FIELD TESTING The improved stench system was field tested at Kerr-McGee Corp.'s Church Rock No. 1 uranium mine near Gallup, NM. Mine Ventilation and Compr e ssed-Air Analysi s The system was thoroughly tested fol- lowing fabrication. Tests involved discharges of nonodorized liquids as well as the THT-Freon 113 mixture se- lected for stench warning use. Tests in both ventilation-air and compressed-air streams were performed. Parameters mea- sured included fluid flow rates, dis- charge times, and stench concentrations in the airstreams. All tests indicated conformance with the system performance specifications (table 2). The improved stench system releases odorant into both the ventilation-air and compressed-air streams, relying on these airstreams to transport the waraing sig- nal to the various workplaces. There- fore, a thorough knowledge of these sys- tems and their interactions was essential in order to plan and lay out an effective stench warning system. The test mine has two main levels, des- ignated 1-4 and 1-5, the 1-5 level being about 300 ft below the 1-4. Raises are 17 driven from these levels to the ore, which is 50 to 100 ft above the level in each case. Figure 12 presents the layout of the haulage levels, along with the lo- cations and flow rates of the ventilation shaft and boreholes. The ventilation scheme has intake air downcasting through the main shaft and borehole 6 to the haulage levels. The air travels along the haulage drifts, up the raises, through the stopes, and fi- nally through a network, of exhaust drifts in the ore horizon and out the exhaust boreholes. Exhausting fans are located on the surface at the exhaust boreholes. For both ventilation purposes and ad- ministrative reasons, the 1-4 level of the test mine is divided into two seg- ments. The area to the east of the two air doors (fig. 12) has its own hoist- ing plant, compressed-air supply, and ventilation system. The two doors form an airlock, and are normally closed; how- ever, there is a minor leakage flow from the east side to the west. The two compressed-air systems are connected, and there is normally a small net flow, again from east to west. Thus, the stench Venthole 2 95,000 ftVmin upcast Main shoft ^ 22!,00Gft7min^ total downcast 1-4 level tests were conducted in the west side of the mine without disturbing the east side. A tracer gas technique was used to determine the effectiveness of the compressed-air system in transporting the warning signal. The tracer gas was re- leased at the point where the new stench injector was to be installed, at 9:55 a.m. , a time when compressed-air usage is usually at a maximum. Starting at 10:00 a.m., air samples were taken at 3-min intervals for 30 rain, at four loca- tions underground and on the surface at venthole 1. Tracer gas was detected at all sampling points. The locations of the sampling points as well as the transit time of the tracer gas to each point are indicated in figure 13. The rapid appearance of the tracer gas in the exhaust borehole (after 8 min) in- dicated that leakage from the compressed- air line into the ventilation air was originating not very far downstream from the injection point and that the stench first reached most areas of the mine through the ventilation air rather than in the compressed air. It is also proba- ble that a large percentage of the stench injected into the compressed-air line was exhausted through venthole 1 after having passed through only a small part of the total workings. However, some stench was retained in the compressed air, indicat- ing that this mode of stench transport can effectively supplement ventilation- air transport. Injector Locations and Installation Venthole I 35,000 ftVmin upcast Main shaft 75,000 ftVmin upcast 'Venthole 3 85,000 ftVm in upcast 1-5 level Venthole 6 45,000 ftVmin downcost FIGURE 12. - Layout of haulage levels, boreholes, ond main shaft in test mine. Ventilation-air injectors were in- stalled at each of the two intake-air shafts. One injector was installed in a crawl space located just below ground level near the top of the main shaft (fig. 14). Because there was a high rate of activity near the employee and sup- ply hoist, the crawl space location was chosen to minimize the possibility of ac- cidental system activation. Approximate- ly 10 ft of copper tubing was suspended from the injector down into the shaft to carry the stench agent. 18 rrr LEGEND Main shaft Exhaust borehole Sampling pointin stope Sampling point on haulage level Transit time, minutes 1-5 level FIGURE 13. - Sampling points and transit times for compressed-air system tracer gas analysis. Shaft collar Wire mesh Copper tube Intake air Shaft lining FIGURE 14. - Main shaft ventilation-air injector location. The other ventilation-air injector was installed on a leg of an emergency- escape-hoist headframe positioned over venthole 6 about 1 mi from the main shaft (fig. 15). This injector was mounted approximately 7 ft above ground level to discourage tampering. Injector Ventilation shiaft intake FIGURE 15. - Remote venthole injector location. The compressed-air injector was mounted on the main receiver for the compressed- air system (figs. 16-17). A piece of copper tubing approximately 2 ft long joined the injector to the main com^ pressed-air line through a shutoff valve. Test Procedures The in-mine test consisted of using the improved stench system to issue the warn- ing signal during two regularly scheduled fire drills. The mine's routine practice was to conduct drills during all three 19 From air compressor Injector Pressure-balancing line Compresses-air line to mine FIGURE 16. - Compressed-air injector location. shifts over the course of 1 week. The improved system was used for the drill during the first shift (day shift) and for the second-shift (afternoon) drill. For comparison, the mine's existing vial- breaking system was used for the third- shift drill. This arrangement afforded the opportunity to evaluate and compare the performance of the two systems under constant mine conditions. The emergency plan at the mine is dif- ferent from that of most mines in that it does not call for immediate evacuation. Standard procedures require miners to proceed to a dead-end drift or stope with an air line and build a barricade. The standard procedure for fire drills (of which the miners are always informed beforehand) requires miners to note the time they smell stench and proceed to a dead-end drift or stope with an air line and barricade materials. (Barricades are not actually built.) Environmental samplers visit each work area and fill out a form showing the location of each worker, the time he or she smelled stench, the strength of the stench, the action taken by the miner, and the miner's comments. This procedure was followed during all tests. Results The main criteria for evaluating the performance of the improved stench system were (1) degree of coverage, (2) elapsed time between actuation of the injectors and the detection of odor at various lo- cations, and (3) stench concentrations measured at various locations. To give an overall view of the perform- ance of both the improved system and the existing system, stench transit times to various areas of the mine were plotted on maps of the haulage levels. These tran- sit times were based on the stench arriv- al times recorded by the mine's environ- mental samplers during the drills. Figures 18-21 show the results of the tests of the improved system (during the first- and second-shift drills and on both haulage levels.) Figures 22 and 23 show the results of the test of the existing system during the same week. Since this test was run on the third shift, there were fewer active workplaces for which arrival times could be re- corded. Therefore, the results of two earlier tests of the existing system were reconstructed from mine records to provide a better comparison of the old 20 FIGURE 17. - Compressed-air injector mounted on receiver tank. and new systems. The earlier tests of the mine's existing system are illus- trated in figures 24-27. During the first-shift test of the im- proved system, air samples were taken at several locations in the mine while the stench was noticeable at those locations. These samples were then analyzed to ob- tain their quantitative stench concentra- tions (expressed as parts per million of THT in air). The locations of the sam- pling points are shown in figure 28. Stench concentration versus time is plotted in figure 29. Figure 29 also shows the upper and lower system design limits for stench concentration (from table 2). Only 2 of the 10 samples col- lected exceeded the 2.0-ppm upper design limit, and no samples fell below the 0.1- ppm lower design limit. Of 23 miners who were interviewed dur- ing the second-shift test of the improved system, only 2 rated the stench as reach- ing an annoying level , and none rated it as reaching a sickening level, indicating that odorant levels were probably very near the 2.0-ppm design goal. One envi- ronmental sampler commented that the miners thought the new stench (THT) was not as sickening as the old (ethyl mercaptan) . Mine management was pleased with the improved system not only because of im- provement in warning times , but also be- cause of the ease and simplicity of oper- ation of the new injectors. The valve 4 10 LEGEND Main shaft Sampling pointin stope Sampling pointon haulage level Transit time, minutes FIGURE 18. - Stench test results, improved system, first shift, 1-4 level. 21 LEGEND Main shaft 1^ Sampling pointinstope 4 Sampling point on haulage level 10 Transittime, minutes FIGURE 19. - Stench test results, improved system, first shift, 1-5 level. ^ i 14 taNo smel LEGEND Main shaft ^ Sampling point in stope 4 Sampling pointon haulage level 1 Transit time, minutes FIGURE 20. - Stench test results, improved system, second shift, 1-4 level. LEGEND LEGEND Main shaft i( Sampling point in stope 4 Sampling point on haulage level 10 Transit time, minutes FIGURE 40. - Stench test results, second-generation system, second shift, 1-4 level. ^ 33 5 Ve nthole 1 \ LEGEND Main shaft Sampling point in stope Transit time, minutes Venthole6 FIGURE 41. - Stench test results, second-generation system, second shift, 1-5 level. stench fluid into either compressed or ventilation air. The system is simple, easy to use, requires little maintenance, is easy to recharge, and is designed for high reliability. It can be remotely op- erated by either wireless ' or hard-wired means. The system is commercially avail- able for about $1,300 per injector. REFERENCES 1. Baker, R. M. , J. Nagy, L. B. McDon- ald, and J. Wishmyer. An Annotated Bi- bliography of Metal and Nonmetal Mine Fire Reports. Final report (contract J0295035, Allen Corp. of America). Vol- ume 1: BuMines OFR 68(1)-81, 1980, 64 pp., PB 81-223729; Volume 2: BuMines OFR 68(2)-81, 1980, 284 pp., PB 81-223737; Appendix: BuMines OFR 63(3)-81, 1980, 390 pp. , PB 81-223745. 2. FMC Corp. Mine Shaft Fire and Smoke Protection System. (Final report). Volume I. — Design and Demonstration (con- tract H0242016). BuMines OFR 24-77, 1975, 407 pp.; NTIS PB 263 577. 3. Muldoon, T. L. , T. Lewtas, and T. E. Gore. Upgrade Stench Fire Warning System — System Development and Prototype Tests (contract H02292002, Foster-Miller Associates, Inc.). BuMines OFR 136-81, 1981, 142 pp.; NTIS PB 82-122128. 4. Muldoon, T. L. , and K. Heller. Up- grade Stench Fire Warning System, Volume 2 — Second Generation System Development and Prototype Test. Final report on Bu- Mines contract H0292002 with Foster- Miller Associates, Inc., 1983, 96 pp.; available upon request from William H. Pomroy, BuMines, Minneapolis, MN. 5. Bergeron, A. A., R. L. Collins, and J. L. Michels. A Communication and Moni- toring System for an Underground Coal Mine, Iron Ore Mine, and Deep Underground Silver Mine (contracts S0133035 and J037 707 6, Rockwell Int.). BuMines OFR 156-82, 1981, 293 pp.; NTIS PB 83-115865. 6. Dobroski, H. , and L. G. Stolarszyk. A Whole-Mine Medium Frequency Radio Com- munications System. Paper in Proceedings of the 52nd Annual Technical Session (Mines Accident Prevention Association of Ontario, Toronto, Canada, May 25-27, 1983). MAPAO, North Bay, Ont . , Canada, 1983, pp. 3-15. «U.S. CPO: 1963-505-019/20^30 INT.-BU.OF MINES, PGH., PA. 27941 XgO TX^rSTBTTSTT? ■M» I'^j^n D DD n o > -l-» 3 a ;^ Q_ O Q o Q n 3 3 o -♦■ c o Q in o c Q_ ^ U) n I/) 3- =? T) 3- (n 1 u n -ti <> J (t o 3 (O — O -^ Q- n m 2 00 33 ? o 33gcD Doc li So X > JU m > 3S 1? ^1 -, m O -n oo "n w 5« m z < > r- < S T> c m < m z m S2 w >zm I" w zcw 703 o H m 3J U O 33 m O c > I— o ■0 -a O u H C Z H -< m T3 r- O •< m c CO s (^ - m"i 2 Z > I* -• 2 i o o o> Ti -n H m I fi m to ^R m O X O -smramfrm v*--\# '^0 V .<.^^ "^^. ^-^ > 0- ^^-^^^ % co^*!^^^ °- /•^;r% > /.^^.> /.-^X cO^^^.> y..^-^ •• /...;^X '>0^ '^(S .^^ A <^. TTSH* wy %./•> i'^^,- . <■ •*-. -- ^'^°'*' '.'^i^>' ^^-^^^ -life'/ .^""-^ ^f3m'^ ^-^^ - »V-.^V\/ -o,/^^\o^ V^\.^' ^o,/^\o^ " ' -^o. p »i:^'* '^ " o ., '^ O *-^.^* -'Mm-- \/ .-^l^'. ^.^* .-^^v \,^ :} .*'\ • o • '^bv^ :^^^'- ''^'^o^' f^^^': '*h\y ::SM^^\ ^^u.c^ oV-^^^sPi'- ^^-^.-J^' -^M!//^.- '^ ^^•n^. 1 •^0^ • «."?- -...-*'/ V'^^'V^^ V*^*^**/ X''^^'V V"*"^^"^%°' "-^^ ^»-' \v ^:- C- .^.5^'. -o ^-^^ ,C:^% \ .v^^^ V ■ «^^>c. '.wsm: ^v^^^ ".ww^: «,<^'"^^ -.■ei»/ .v^-^. ^.wm^: .. .^^ ^v^o'^ '"-.. 'bV ^^0^ -» o ^°'n*. ,^^''' "V'^V V'^^'V'" "V^'^'^^"' '^v*"^''*^' .!-*■ V .. ■bV .*^ 'f: 1-- %/ Or • Jii^Saff <7C' ' "^ O *° ^'^ % "^9- iV^ *bV^ o , . • .0 ;; (7> .0^ s' .vV-% LIBRARY OF CONGRESS 002 955 97