ARGUMENT CHARLES ALLEN before the COMMITTEE ON CLAIMS, in behalf of ME8SKS. W. & F. STIANLY, March 25, 1875. P \ tISC// boston: WRIGHT & POTTER, STATE PRINTERS, 79 Milk Street (corner of Federal). 1 8 75. ARGUMENT of CHAELES ALLEN before the » COMMITTEE OK CLAIMS, in behalf of MESSRS. W. & F. SHAKLY, MARCH 25, 1875. BOSTON: WRIGHT & POTTER, STATE PRINTERS, 79 Milk Street (corner of Federal). 1 8 75. ARGUMENT. Mr. Chairman and Gentlemen of the Committee : The present petition rests upon the general ground that the petitioners, having entered into the largest contract, per¬ haps, to which the Commonwealth has been a party, and having performed the same on their part, have encountered such difficulties, and bee'n .subjected to such extraordinary expenses in the execution of their work, without fault on their part, and resulting on the whole in a heavy loss to them, that they are entitled to call upon the Commonwealth, in justice and fairness, to make up their loss. Of the propriety of this mode of proceeding there can be no doubt, and it is the only method open to them of obtain¬ ing relief. For this purpose, the legislature represents the Commonwealth, and is the Commonwealth. The attorney general urges upon you that the petitioners have no standing here ; that if they have any such claim as would be the subject of a suit at law or in equity against an individual, then they should be remitted to the courts by a special Act to be passed for that purpose, enabling them to sue the Commonwealth ; and if they have not such a claim, then they should not be listened to for a moment. The legislature will not sanction that position. Neither the Commonwealth nor just men deal in that manner with persons with whom they contract. It is the boast of many an honest man, that no one was ever compelled to sue him in order to obtain justice. Fair-minded men do not say, and the Commonwealth does not say, to those with whopa they contract, " If you have any claim against me, sue it. You'll, not get a cent unless you establish it in court, according to 2 the strictest rule of law." No fair man says that. Courts are established as a final tribunal to settle matters which par¬ ties cannot settle among themselves. These petitioners hope that there is no need of any other tribunal, to arbitrate between themselves and the Commonwealth ; but that if their petition is fair and just, it will be allowed without a lawsuit. Recent History of the Tunnel Enterprise before the Shanly Contract. After General Haupt- left the work, in 1861, Governor Andrew appointed J. W. Brooks, S. M. Felton and Alexander Holmes as a board of commissioners to investigate the whole subject of the Hoosac Tunnel enterprise, and report their conclusions. They employed Mr. Latrobe of Baltimore, an eminent engineer, afterwards in the employ of the State ; Mr. Laurie of Hartford, to make the necessary surveys, examina¬ tions and estimates of the cost ; a gentleman highly recom¬ mended by them for ability and integrity,* and deceased since these hearings begun ; and Mr. Storrow, to go to Europe and examine the European tunnels ; and in 1863 they sub¬ mitted a most elaborate report of their own, giving the results of their practical judgment, as successful, emi¬ nent and accomplished railroad men, together with the full reports of the several engineers whom they employed. TheSe reports made a volume. So far as science, skill, engineering ability and practical success in great railroad enterprises were concerned, it seemed as if the Commonwealth had enlisted in its behalf whatever was most likely to lead to a favorable result. At the outset, it appeared that every preparation had been made which matured wisdom could suggest, and the State entered upon the prosecution of the work with vigor, and lavish ex¬ penditure of money, and much hope and confidence, under the superintendence and care of the three commissioners. The work was prosecuted for a while under these commis¬ sioners, and then under their successors till December, 1868, when the Shanly contract was made. The result is known. The plans did not succeed. No satisfactory progress was made. The public money was 3 spent with no adequate return. The whole enterprise bid fair to be a wretched failure. It is painful to go over the history of those years, as exhibited in the public documents of the Commonwealth ; to read the record of disappointed hopes, of baffled exertions, of hopeless struggles for a result which could not be attained. But some illustrations must be given. In May, 1866, the minority of the finance committee, consisting of Henry L. Pierce and J. W. Candler (House Doc., 1866, No. 403, p. 9), say " The actual results are such as might have been anticipated from an organization so defective. Uncertainty in plans, ill-considered theories and lavish expenditures without adequate progress, have characterized the doings of the commissioners." In House Doc., 1867, No. 30, Mr. Latrobe, the engineer, shows that the expenditures under the commissioners on the Tunnel, including the Deerfield dam, to November 1, 1866, were $1,482,973.20. This did not include the amount expended under General Haupt. The work then done was 131 feet of Tunnel called finished, at both ends—the size then being only 14x19—and 5,823 feet of heading. The legislative committee of 1867, in their report dated in March, 1868 (Senate Doc., 1868, No. 102, p. 3), say " The Committee feel that the progress and reputation of this enterprise have suffered too much and too long from interruptions and delaj's, arising from causes that good business judgment and engineering skill should have lony since securely provided against." This report presents a pitiful account of the delays and difficulties which encompassed this work. There was no unity of plan among the commissioners themselves. Mr. Shute withdrew, and in March, 1866, wrote a paper explaining the causes of his withdrawal. This was a bitter paper, and the House refused to receive it on account of its personalities ; but it was afterwards published, and in it Mr. Shute refers among other things tp "the absence of any com¬ petent engineer directly responsible to the commissioners," 2 4 and speaks of "the present unsatisfactory and almost hope¬ less condition of affairs" (pp. 15 and 16). Before this, the House had requested Governor Bullock to furnish, for the use of the legislature, any communications received by him in relation to the Tunnel, from any of the commissioners or the consulting engineer ; but he declined,, in a special message, in which he referred plainly to the dis¬ sensions which had e;xisted in the board. (See Blue Book of 1868, p. 335). Mr. Hudson, another of the commissioners, made a report, which was returned by the governor because it reflected inju¬ riously upon the manner and methods of arrangement adopted by the superintendent of the work. But the House commit¬ tee afterwards recommended' its publication, and it was printed. (See House Docs., 1868, Nos. 353, 359). These things are referred to, for the purpose of recalling the desperate condition of the enterprise at that time. With a plenty of ability in different individuals connected with the work, there was a lack of united and harmonious action, which made everything seem hopeless. Certain persons .had for years expressed the opinion that the Tunnel never would be done, unless upon the contract system ; but it was feared that no responsible .contractor would be found with means and courage sufficient to under¬ take the whole work. At the time of making the Shanly contract, the cost of the Tunnel, without interest, as given by the commissioners, was $3,002,176.57. (Senate Doc., 1869, No. 6, p. 11.) This, in round numbers, is two-thirds of thé amount of the Shanly contract. At the east end, the total distance penetrated was only two feet over one mile, of which only 810 feet was then supposed to be flnished ; at the west end, a little over three- quarters of a mile was penetrated, the bulk of it, east of the Farren arch, by a small heading only. ' The Work and Losses under the Shanly Contract. Under these circumstances, Messrs. Shanly entered into their contract, December 24, 1868, and commenced actual work^upon'ithe headings in the spring of 1869, and thereafter prosecuted it continuously to its completion. The contract 5 price was ■arrived at by applying the detailed bids of Messrs« Shanly to Mr. Frost's estimates of quantities, and adding up the items, as shown by the schedule introduced in evidence- It was known at the outset to be a diñicult task, and one attended with many risks. Doubts had been entertained by many, whether any responsible* contractor would undertake the work, without a very large margin of profit. Mr. Bras- sey, the great English contractor (recently deceased), told Mr. Storrow that " the enterprise has all the contingencies and uncertainties of an untried project, and it would be unsafe to undertake it by contract." (See Mr. Storrow's report, p. 44.) The Brooks commission held the same opinion (p. 56). But the ' contractors, undertaking to do this work according to certain average rates, and not, as seems to have been supposed, to maintain those rates during each and every month, have pressed on, in spite of difficul¬ ties anticipated and unexpected, and have overcome them all. They have not been conquered by the stringency of the money market, through two seasons of panic, bringing wide¬ spread disaster and ruin to many other enterprises ; by nu¬ merous material obstacles developing with the progress of the work ; by greatly increased expenses of working, induced by causes beyond their control or power to antici¬ pate ; or by the rigorous exactions of the engineers, who assumed to direct and control their work in methods not deemed wise or economical by the Messrs. Shanly, with a stringency increasing with the increased difficulties, and to retain from them unjustly large amounts of their earnings,— an element of expense and annoyance which the pride and magnanimity of Mr. Shanly have prevented him from display¬ ing unnecessarily to the public view, but which nevertheless he has felt most keenly himself. In spite of all these, the end crowns the work. At our very doors, the fine figure of Eobert Colly er be¬ comes an accomplished fact :— " ' We want a railroad into Italy ' cries the world, ' and can go no farther for this mountain ; what shall we do to find a way ? ' ' There is no way,' heaven answers, ' except to your own persisting ; but if you seek, you shall find ; if 5'ou knock, it shall be opened unto you.' The knocking is with hard steel at the hard rock, and it is only a 6 question of persistence and of endurance ; then at last it has come to pass that even' the heart of the unwilling mountain is won, and its midnight sleep driven away ; and where for countless ages there has been only an utter and unutterable silence, there is now the mighty response of an answered prayer in the thunder of the loco¬ motive." This has been accomplished through the persistence and endurance of Walter Shanlj. If in respect to one portion of the work there have been différences of opinion between himself and the engineers, it is unfortunately nothing new in the history of this great work ; nor have they been greater than the differences which have existed, and still exist, between the engineers themselves. If he has not always followed in detail the course which they deemed wise, he can at least point to a tunnelled moun¬ tain as the result of his own methods. In the prosecution of this great work, the Messrs. IShanly have lost a large sum of money. They have expended much more than they have received. So far as they are concerned, the Commonwealth has got its Tunnel for less than its actual cost. Their hopes of reasonable profit under their contract long since disappeared, and for the last three or four years it has been simply a question, with how small a loss they could com¬ plete the work. They have completed it ; they have summed up the figures ; and, after allowing for machinery and tools on hand, find a net loss of $226,495, made up to January 1, 1875. No question is raised as to the accuracy of their book¬ keeping ; their system was apparently a perfect one. Mr. Frost found all the items right which he examined. They have exhibited a chart showing their expenses in detail. Assuming that, on the whole, they have done the work with reasonable economy, this shows the amount below actual cost value at which the State receives the product of their labor, skill, anxiety and risk, for nearly six years of contin¬ uous service. Of course no contractor would enter upon such a piece of work if he thought there was any chance of such a result. And now, looking back, what price would a contractor ask, with the knowledge now obtained, for under¬ taking what the Messrs. Shanly have performed ? What price would an engineer call a fair contract price ? 7 They do not ask the legislature to give them the fair and honest money value of their work, reckoned by any such standard as that ; but they would show you how it happened that their reasonable expectation of profit was disappointed ; how their expenses were swelled, without any fault of their own, beyond all previous calculation ; how they have ren¬ dered beneficial service outside of the requirements of their contract, which is fairly entitled to favorable considera¬ tion ; in the hope that, without too much reference to legal or narrow questions or, considerations, it may be deemed, under all the circumstances, more consistent with the charac¬ ter, the good feeling, the sense of justice of Massachusetts, not to receive this work from the contractors at less than its actual cost to them. Their unexpected and increased expenses came from several sources. Failure of Deeefield Eiver Dam. For the purpose of furnishing power to drive the machine- drills, the Commonwealth had built a dam across the Deerfield Eiver, and incidental works, at an expense of $258,000. From seeing such a large expenditure, a contractor coming here from abroad might naturally suppose that the water- power could be relied, on as sufiicient. The Messrs. Shanly were under this impression. But it proved insufficient. It was a subject of comment in Mr. Frost's reports during the summer, and is indeed a matter of common knowledge. The Messrs. Shanly were obliged to build steam-works to supply the deficiency of water-power, at an original cost of about $18,000, and the extra expenses of driving the compressors was about $10,000 more. Great Storm of 1869. Then came the great storm of October 4, 1869, unprece¬ dented in its violence and destructive power, and still fresh in the memory of us all. Its effect upon the Tunnel has been more than once described in official reports. The east and west ends were both flooded, one man was drowned, and there was much material injury, besides loss of time. What should be done ? 8 In Helps's life of Thomas Brassey, it is said,— " In the execution of any great undertaking, Mr- Brassey's anx¬ iety was that the work should be done quickly, and be done well. The minor questions as to who should bear the expense of minor matters, unprovided for by specific contract, he left to be settled afterwards ; whereas many men, perhaps I may say most men, would have insisted beforehand upon the question being settled as to who should bear the outlay." (Page 16.) From what was done, not only in respect to the damages caused by this flood, but many other matters which have eome before you, it is apparent that this description of Mr. Bras¬ sey is strikingly applicable to Mr. Shanly also. Without a day's delay, without stopping to settle in advance, or even to raise any question who should bear the expense, he at once began the work of restoration at both ends of the Tunnel. The injury at the west end was caused in this manner : The State had diverted the water of a brook through an artificial water-course adjoining the Barren arch (which is the west end of the main Tunnel), not in any manner connected with the work of Messrs. Shanly, but wholly within the lim¬ it^ where Farren's work extended ; and had built the banks of this canal so insecurely that the water broke through, washed away a large amount of the material covering the Barren arch, down into the space between the Haupt Tunnel and the west portal of the main Tunnel, so that a dam was made which set back the water and a large quantity of material into Barren's arch, and the water flooded the Tunnel for the whole length then constructed there. This is thus described by the legislative committee of 1869 (Sen. Doc.', 1870, No. 58, pp. 9 and 10) ;— " The progress of the work at the west end was seriously inter¬ rupted by the October freshet, which caused the water in the brook, which formerly crossed the line of the Tunnel, but had been diverted by the State into a canal, to break through the artificial bank into the Tunnel, the water carrying with it great quantities of earth and stone and entirely filling it in a few minutes, drowning one man and the rest escaping with difficulty, and doing damage to the "work, as 9 is: statedv to an amount somewhat less than $ÍO,000. This caused an entire suspension of the work at the west end, so far as progress is concerned, for three weeks, and an. interruption to the usual rate of progress for a longer period." (See,, also,. Senate Doc ,, 1871, No. 55, p. 15.) • . Later in the month, the Messrs. Shanly presented a claim for reimbursement to the governor and council, and in a com¬ munication dated October 21, 1869, setting forth their views in detail, they say :— " In thus promptly striving to protect the property of the Com¬ monwealth and to restore the Tunnel to the condition it was in pre¬ vious" to the storm of the 4th of October, the contractors assumed no responsibility for the cause of the accident, or any liability for its results. They had the means for prompt and efficient action at their disposal and applied them in good faith and as good neigh¬ bors, and will continue to carry on the work of restoration till com¬ pleted, in the fullest confidence that, for the great expenses they have incurred and the losses they have sustained, the Common¬ wealth will hold them harmless." The executive officers considered that, as the breaking away of the water injured both the Commonwealth and the Messrs. Shanly, both parties should join in bearing the expense, according to certain rules laid down by themselves. To this the Messrs. Shanly replied at length, saying among other things :—" They affirm that their neighbor, the State, had no right to inflict injury on them in the first instance; and, secondly, that having so injured them, it has no right to make gain out of its own wrong-doing," as it would, by the work of the contractors in restoring the property of the State, and making the banks secure for the future. The state officers did not, however, recede from their position, and finally, on January 23, 1872 (not till then), made a payment of $3,305.19, which Messrs. Shanly received, making at the same time a written protest that they did not. waive their claim for payment in full. Their statement shows a balance of $9,812.17 due on this account, including certain work done by their sub-contractors, Hocking & Hol- brook, amounting to $4,059. The accuracy of the items is not questioned. 10 Upon this plain statement of facts, it is not apparent what valid reason there was then, or is now, for refusing to pay this amount. If the State had built its canal securely, this injury would not have happened. The loss arose wholly from the failure of the State to make its canal safe. The banks built and maintained by the State were iusufScient, and when the storm came they gave way. There is no ground of equity or of law on which the State ought to be exempted from bearing this loss. The Messrs. Shanly were not bound to take into consideration that the State might leave its canal insecure. The item for clearing out the Farren arch rests on the same grounds. This was, clearing out the rubbish which remained until 1874. It was the residue of the material brought in by that storm of 1869. At the east end, the railroad was washed away between the Tunnel and Greenfield, so that it remained unused for about nine months. This made it necessary to haul every¬ thing required for the east-end work over the mountain from North Adams ; and it cut off the contractors from the use of coal for their steam-engines, erected to supply the deficiency in water-power. The weekly reports of Mr. Frost contain constant references to the labors of the Messrs. Shanly in restoring things to their former condition ; the delays and difficulties from anchor-ice and from the lack of coal. They need not be cited from, in detail, because the fact of the loss is not questioned. They afford a vivid picture of the troubles of that autumn and winter, resulting from the great flood. The losses to the Messrs. Shanly at the east end from this cause, are estimated at' $9., 122, as shown by the statement furnished. In judging of this matter, you are not without the advan¬ tage of a precedent established by two former legislatures. The railroad between Greenfield and the Tunnel was under a lease to the Vermont- & Massachusetts and Fitchburg Kail- road companies, with covenants making it their legal duty to restore the railroad, where it had been washed away. The attorney general argues that the Commonwealth was legally bound to make such restoration. Such was not the opinion 11 entertained by his predecessor. The opinion of the attorney general of that time to the contrary, is found in House Doc. of 1870, No. 323, pp. 6, 7, and after insisting that no legal duty rested upon the Commonwealth, contains in conclusion the following :— At the same time, this construction, which I think is required by the application of the rules of law, seems to'me in this instance, as in others where it has sometimes been applied by courts, to be harsh and oppressive upon occupiers of property belonging to others ; and as a matter of justice I quite agree with the report of ?dr. Appleton, submitted to me, that the loss fairly traceable to the unusual and extreme violence of the storm, should be borne by the Commonwealth, it probably not having been in the minds of the parties at the time of execution of the lease." These railroad companies would do nothing towards the work of restoration, until after legislation by which the State assumed the great bulk of the expensé ; and by the statute of 1870, chap. 252, and 1871, chap. 153,' allowances were made under which they received a little over $140,000 in money, and an abatement of nine months' rent for the rail¬ road. This action was taken after written reports by the attorney general, and by one of the railroad commissioners, and after an investigation in the executive department, as well as before different legislative committees. Thus, the legislatures of two successive years have recog¬ nized the justice of relieving the Vermont & Massachusetts and Fitchburg Eailroad companies from their obligations under their contract with the State, and have made good to them the whole damages traceable to the unusual and extreme violence of this storm, upon the line of the Troy & Greenfield Eailroad. Is their position in relation to this enterprise so much more meritorious than Mr. Shanly's, that the Common¬ wealth, in the face of the world, can be willing to say :—" To our own railroad companies, with whom we have contracted, we will make good their loss, to the amount of $140,000 in cash, and abatement of nine months' rent. To these contract¬ ors, who have come here from another country, trusting to the honor and good faith of Massachusetts, and who have rescued this enterprise from the almost hopeless discredit t 12 into which it had fallen, and made it respectable, we will not make good their loss of $18,000." Water Difficulties in Central .Section. The great and overshadowing element of increased expense is found in the unexpected influx of water in the central shaft workings, and the action of the state authorities in requiring the Messrs. Shanly to undertake to cope with it, contrary to their own judgment. This influx of water was unexpected. The opinion was generally entertained that no serious trouble in tunnelling the mountain would be met with from this source. President Hitchcock, in 1854, gave an extended description of the geological characteristics of the mountain, summing it up by declaring that he thought the Tunnel would be found dry, after penetrating a considerable distance from the surface, and gave his reasons for k. This opinion was generally followed. The commissioners appointed by Gov. Andrew, say :— " Our estimate [of cost] will be based upon Pres. Hitchcock's opinion, the highest attainable authority, that the quantity of water to be met with, except in the secondary formation at the west end, will not be so large as to be seriously troublesome." (Page 54.) Mr. Latrobe likewise founded his estimate of the cost of the Tunnel upon the same assumption. Without pausing to dwell upon other opinions which might be cited, the deliberate judgment of the official representatives of the legislature, at the time when this contract was entered into, is found recorded in the report of the joint committee of 1868, on the Hoosac Tunnel (Sen. Doc., 1869, No. 61, pp. 12, 13), in these words :— " Beyond the [west] shaft, all the roch is self-sustaining, and will be found so throughout the mountain. As Prof. Hitchcock has said in another connection, ' it would be a thing unheard of in geology, were it otherwise.' The chance of a great influx of water during further progress of the Tunnel, is very remote and improbable, and however great it may be, it will discharge itself at either end by natural flow. . . . The proofs derived by. actual inspection at the east end, central shaft and west end are morally irresistible 13 in forcing the conclusion that progress at all points is to depend hereafter solely on the greater or less hardness of the material, and the greater or less efficiency of the means that may he devised for break¬ ing it up." This they emphasized by italics, as if to show that no doubt Was to be entertained. Messrs. Shanly shared in this opinion, and the character of the rock throughout the whole 445 feet sunk by them, and for a short distance of tunnelling to the westward from the shaft, was a clear confirmation of it. Everything had been made ready, in expectation of rapid and continuous progress. The sides of the central shaft had been trimmed,.the machinery put in perfect • order, excavations by hand-work had been made sufiicient for the use of the large carriages for machine- drills, and these had been lowered and put in place for the westward work. All this having been done, iu March, 1871, the water was struck. At this date, they had already made up for the loss of time consumed at the outset in the work of preparation in the east and west-end workings, so that both were a little further advanced than the contract required ; and they were now proceeding at the rate of ten per cent, in excess of the con¬ tract rates. Mr. Philbrick himself testifies to this. Their pneumatic drills, already ordered, and to be applied as soon as the requisite room should be obtained, were soon to give a material increase to this excess. Coming east from the cen¬ tral shaft, there was no reason to doubt that the same advanced rate might be maintained. This was the situation when the water was first struck. Mr. Shanly's description of the subsequent difficulties from water has been laid before you by himself, in the following * written document. [Mr. Shanly's statement, printed on page 19 of the testi¬ mony, was here read.] Mr. Frost's description of the same, for 1871, may be found in the Sen. Doc.,' 1872, No. 250, p. 10. The .difficulty from the great influx of water was of the gi-avest description that can be imagined. In November, 1871, Messrs. Shanly had provided pumping power for 14 raising 200 gallons of water per minute through the eentral shaft. They represented to the governor and council the danger that would be incurred in seeking to force the heading westward. Mr. Crowell, who is described by Mr. Philhrick as the active member of the council committee at the time, is called by the attorney general, and testified to you in these words :— " I think we concluded that it was not perhaps wise for us to insist upon his pushing the work west from the central shaft. . . . My impression is now that Mr. Philhrick said something to me to the effect that with more pumps there the water might be removed, and they could proceed with the work ; but it was questionable, I think, with the council at that time whether he would not find more water, and more than he would he able to remove with another set of pumps, even." It seems, however, that Mr. Philbrick's view finally pre¬ vailed ; and the order was given (contrary, as it would seem, to the judgment of the council, and reversing the conclusion that they had originally arrived at) that the work must be resumed'at all hazards. There was no alternative for the Messrs. Shanly; so they recommenced, and had made about 127 feet of progress, when the increase of water was so great that they stopped again. It was now obvious that the water was likely soon to over¬ power the pumps. The flow was already at the rate of about 140 gallons per minute. To Mr. Shanly's mind, it was a plain proposition, that to press on in the face of this was attended with extreme danger. It seemed to him that no competent engineer could come to a different conclusion. But on the 2d of March, 1872, Mr. Frost sent to them a letter containing the following imperative order :— " I have to notify you of the conclusion of the executive council, that you must be required to resume at once the progress at the head¬ ing westward from the central shaft." It has been made known, in the present hearings, that Mr. Frost's order was written in consequence of a letter from Mr. Philhrick, saying that the governor and council were "unanimous in the opinion that the contractors should be 15 required to resume work on the western heading at once, and prosecute that point, as well as the enlargements both ways, as required by the contract." Mr. Frost testifies to you frankly that, at the time of giving this order, he thought the wise way of proceeding would be, not to undertake to make progress westward until more pumps had been provided. He was questioned closely upon this subject by a member of the Committee (Mr. Lovering), and was as little equivocal in this opinion as in any that he gave to the Committee. In this, as in some other matters, it is probable that the opinion and advice of the consulting engi¬ neer were followed, instead of his own. The written order, however, was distinct and imperative, to resume work on the heading at once, without waiting for pumps, or anything else. Mr. Shanly appealed to the governor and council for a reversal of this order, and he has laid before you, and fur¬ nished to the attorney general, his memorandum, made at the time of the hearing on that occasiqn. It is as follows :— " March 14, 1872. Central Shaft — West Heading Question.— Hearing before governor and council to-day. Mr. Allen, as counsel with me, the hearing being to discuss the question of driving west heading as ordered by Frost's letter of 2d inst. Mr. Philbrick insisted that a second large pump should be put in, and I showed the utter impossibilitj' of getting such a pump at work in time be of any service in advancing the completion of Tunnel, and that the putting of it in must inevitably retard the work eastward, on the progress of which the due and timely completion of the Tunnel really hinged. I also tried to convince the council that the forcing of the west heading, in the face of such threatening of more water, was to run the risk of being wholly driven out of the shaft, which, ' if once filled with water, would probably ndver again be pumped out. The driving of the heading, at all hazards, was, however, insisted on, water or no water ; but the new pump question yielded. I also said, that, in order to drivé the heading at all, it was absolutely necessary that it be dropped from top to bottom level, and driven on an upward slope from the starting-point below. That to accomplish this change would take till about 1st May. Agreed to. " (Signed) W. S." 16 The heading was accordingly dropped from the top to the bottom level, and in May, in an advance of only 17 feet, there was an increased flow of about 60 gallons per minute (not 100, as Mr. Philbrick said), which was more than suffi¬ cient for the capacity of the pumps. The mining was of course stopped, the hoisting of rock discontinued, the hoist¬ ing cages equipped with baling tanks ; which, in the words of Mr. Frost, given in his report of May 24, 1872, was "the only present action consistent with reasonable security " ; the regular flow being then, as stated in the same report, a little more than 205 gallons a minute. Preparations were also made for putting in new pumps of 7^ inches in diameter. In this condition of things, an order in council was passed, June 14, 1873, as follows :— " Whereas, upon a special report of Edward S. Philbrick, engineer on the Hoosac Tunnel, made upon the return for the month of May, 1872, that the Messrs. W. & F. Shanly, contractors, have not per¬ formed their contract in the progress of the work, the certificate. No. 19, which would otherwise be due, be withheld until further ordered." This was sent to the Messrs. Shanly, with a letter saying that Mr. Philbrick had reported that the progress of the work west of the central shaft was not satisfactory ; but oflering to him an opportunity to be heard, if he desired it. Upon this, Mr. Shanly made all his arrangements for abandoning the work, if, upon a hearing before the governor and council, the order should be insisted upon. He came to Boston, and his memoranda of the hearings, made at the time, have been laid before you, and furnished to the attorney general, and are as follows " June 20,1872. Council Meeting, Boston. Central Shaft.—Went before the governor and council, by request, to explain reasons for having discontinued working west from central shaft. Stated that the increase of water was so great as to require our whole, power of engines and pumps to keep it down ; that it would require at least four months to erect new power; and that during that time but little work could be done eastward, as the hoisting machinery would be mostl}^ engaged in assisting in getting in the new pumps ; and also, if we continued to work east, as at present, we might reasonably expect to have the headings meet in six months, when no further 17 pumping would be necessary. Mr. Philbricb, who was present, admitted that it was now too late to think of new pumping machinery, and that it would be better for us to abandon west workings, keeping all the force east, so as to let the water off as soon as possible. He gave it as his opinion, however, that we could not finish the work within the time. " The council will meet again on Fridaj'^, 28th inst., to hear our statement as to what we were doing and of the progress we think can be made, showing the very earliest time the work can be com¬ pleted. » (Signed) F. S." " June 28,1872. Hearing before Council. Central Shaft Question. —Had interview with governor and council on subject of central shaft and suspension of west heading work. Fhilbrick present. Had previously had a private interview with the governor, and ex¬ plained to him the great risk of filling the shaft with water if the driving of west heading be persisted in ; also stating that the filling of the shaft means the indefinite postponement of the com¬ pletion of the Tunnel. " Repeated same statement before council, and in answer to ques¬ tion from governor as to what progress we can make without driv¬ ing westwards from shaft, I stated that the most'we can promise from three headings would be what the contract requires from the four headings,—385 feet per month,—and that our progress hence¬ forward till end of year would be from 370 to 385 feet per month ; that we fully expect to- be cut through between east end and central shaft by 31st December, and that be3'ond that time we hope to make from 250 to 280 feet per month on the two headings west of shaft. Stated the whole distance now to penetrate at about 5,300 feet, of which 1,400 was east and 3,900 west of centre. Also showed that to attempt to put in more pumping machinerj' would simplj' be to delay the eastward work, and that even then it would not be possible to get another pump into working order in time to be of anj- service. " Mr. Fhilbrick ceased to urge the pump matter, and turned his arguments to show that, with the progress promised, the Tunnel could not be finished by 1st March, 1874. In figuring up the period for joining the easterly workings, he fixed the 15th January, instead of 3l8t December, as calculated by me, and said he considered that eight months after joining of headings would be required for com¬ pletion of work east and west. " After a full hearing of the matter, council decided to adopt my views, and allow us to proceed on the three headings, and without putting in other pumping machinery. " (Signed) W. S." ' 18 Mr. Philbrick's report of June 13, 1872, has also been laid before you, and no one can read it without the feeling that he hardly thought it an even chance that the work could go on, even with a third pwnp, as large as the largest of those already in. Mr. Frost, also, in his report of June 10, 1872, said that " no advance westward can reasonably be undertaken unless further means for removal of the water shall first be pro¬ vided." These matters have thus been detailed, in order that it may be seen how the prospect appeared at that time. And in this aspect it is entirely nnimportant whether it afterwards proved that there was a largely increased influx of water or not. As Mr. Philbrick said in his report, the condition of "the rock could not be ascertained before piercing it, and after piercing it it would be next to impossible to check the flow from the newly-cut seams. If new pumps should be put in, and shotild be overtaxed by new water, the mining would have to stop again. This, then, was the situation. It was impossible to ad¬ vance westward without new pumps. To provide new pumps would take several months. If provided, the chances were that they would be useless. It so happened, however, that experience afterwards proved, as a matter of fact, that the fears of Mr. Philbrick and the con¬ viction of Mr. Shanly were both well founded. The steady flow of water was greate'r than the capacity of two pumps of the largest size used or contemplated, and the occasional flow, for a day or two, was immense. Measurements were not taken regularly (so Mr. Shanly and Mr. Frost both say), but the testimony of Mr. Shanly to finding a large cavern of water on the 21st of June, 1873 (five months before joining the western headings), which yielded over 500 gallons per minute for a day or two, is explicit, he having made a memorandum of it at the time ; and Mr. Frost's testimony is substantially to the same effect. • Mr. Shanly has also given a statement based on the actual progress made afterwards, which shows what would have been the progress of the work if his plan had not been inter¬ fered with. The opening east, which Mr. Philbrick, in his 19 report of June 13, 1872, thought could not be made before February 1, was actually effected on the 12th of December, and would have been in the early part of October. Drainage being thus obtained, the westward headings would have been joined early in September, 1873, or less than three months after the time contemplated in the contract, if regular rates of progress had been made. The loss to the Messrs. Shanly in consequence of the order of November, 1871, is set forth in a detailed statement of items which has been submitted to you, and amounts to a little over $217,000. This is exclusive of the cost of putting in the large pumps, which was just under $56,000. This result, so disastrous to themselves, and so injurious also to the Commonwealth, justifies them in the opinion which they have always entertained, that the mildest criticism that can be passed on the course pursued by the engineers is, that it was a gross blunder. Fortunate is it for the reputa¬ tion of Massachusetts, as well as for its business interests, that a contractor was in charge of that work with intelligence enough to appreciate the situation, and nerve enough to withstand these engineers to their face. The Commonwealth was spared the last and crowning discredit of seeing the central shaft filled with water, from -obedience to an official order which could not be understood otherwise than as an order to continue the wéstward workings, given in the face of an official report that the work could not be done. TJneeasonable Eequieements oe Engineers. ■ In the next place, there has been a strictness of con¬ struction on the part of the engineers manifesting itself in respect to many different mattçrs of detail, some of which, in his opinion, undoubtedly furnish to the Messrs. Shanly a just legal claim for compensation for extra work, and others have at least subjected them to unnecessary annoyance and ex¬ pense without any benefit to the Commonwealth. Several illustrations may be given :— Trimming.—One subject of question that has arisen between the contractors and the engineers, has been in respect to the trimming of the Tunnel. The Tunnel was to be made of a 4 20 certain prescribed size, and it was expected that the rock wonld be self-sustaining, and that there would be no water in any troublesome amount, so that the contractor might in working approach very closely to the prescribed size, with¬ out being obliged to excavate a greatly increased amount. The language of the specifications prepared and put out by the Commonwealth, and serving as the basis upon which all the bids of contractors were made, was as follows :— " As the rocTc is sufficiently hard to prevent apprehension from falls and slides, estimates will be made only of quantities within the exterior lines prescribed for the Tunnel." (Page 3.) This is what the Commonwealth said before making this contract :— On the 25th of April, 1868, General Haupt was applied to by eighty-three members of the legislature for information as to the best manner of completing the Tunnel. His reply to this communication has, therefore, a character almost ofiicial. In giving the terms and conditions on which a contract might be made, he says :-r- " The manner of finishing the Tunnel should be accurately pre¬ scribed in the contract, so as to prevent unreasonable exactions from the contractor. An engineer could absorb any profit, however large, by requiring excessive trimming. . . . As a Tunnel through such a rock as that of the Hoosac must necessarily be rough, and cannot be made to conform exactly to any prescribed dimen¬ sions, the amount of inequality that will be admissible should be distinctlj' recognized in the contract, and great care should be observed to leave no room for misunderstanding,' for the courts afford no means of redress to the contractor if differences should arise, although they are open to the State." (Page 15.) Unfortunately for Mr. Shanly, he had not seen this caution of General Haupt before making his contract ; and if he had seen it, he would have been slow to believe that in practice engineers would put so extremely literal a construction upon the words of a contract as has been done in this case. He made the mistake of supposing that his contract to excavate a Tunnel of a prescribed height and width, and according to a prescribed section, would be satisfied if he should excavate a 21 Tunnel which on the whole, in all its parts, should be sub¬ stantially larger than the area of the section prescribed, even although a minute examination might detect occasionally points of rock projecting an inch or more in portions of the section where no injury could arise from them. This was a grand mistake. Such was not the spirit or the construction of the engineers. The contractors had undertaken to make *a Tunnel of a certain size and section. No matter how large the general excavation might be. The contract, they say, is not complied with, unless there is a literal compliance down to the minutest measurement. There has been, they say, an increase in the size of grain cars since this contract was made, and, therefore, it was perhaps considered just that the con¬ tractors must submit to a construction that otherwise would have been monstrous. That no injustice may be done to anybody, Mr. Philbrick's own words of July 13, 1872, shall be given :— "We can't, with safety, allow them [the new grain-cars] to pass through the Tunnel, unless every inch of the established form is ' excavated. Mr. Shanly says, and Mr. Frost admits, that the former has complied with all the latter's directions in regard to trimming. This seems to indicate a lack of directions ; and, in conversing with Mr. Frost, I am sorry to say, that he does not appear to appreciate, as I do, the importance of urging the contractors at once, and per¬ sistently, in this particular." To the common mind, neither the need nor the justice of so rigid a construction was perceptible ; and, accordingly, it is not strange that Mr. Frost did not appreciate the importance of it, nor is it probable that he, .alone, would have adopted it. But Mr. Philbrick's counsels prevailed, and were executed in this wise : frames, or forms, were constructed, the inner lines of which were of the exact section prescribed for the Tunnel, and placed at distances, usually of twenty-five feet apart, and observations were taken with candles, and literally every pro¬ jecting inch was marked, and was actually removed by the Messrs.. Shanly, even on the very roof of the Tunnel. For this purpose, new scaffolds had to be erected and new blasting done. The whole Tunnel was gone over in. this way, and was, in effect, sand-papered down to such a degree of smooth- 22 ness that there was no projecting inch within the lines of section prescribed in any part of the Tunnel. The contract required it, as was supposed, and a precise fulfilment was exacted, by withholding large sums of money till it was done,^—down to the last inch. In this way, an amount of detailed trimming was got out of Mr. Shanly, that subjected him to' an expense of $110,000. You thus see that these engineers were faithful and strict, ' in getting out of INIr. Shanly every particle of work that a strict construction of his contract could be made to include. Having done this, he naturally supposed that he had fulfilled his duty as to the excavation of rock. Taking down loose rock.—He was mistaken. The Tunnel must be gone through with once more. The engineers then proceeded to examine and see if there was not some more rock that ought to come down. The rock was not of that character that had been described in the specifications which had been issued to Messrs. Shanly. These specifications had declared, in effect, that as the rock would be self-sustaining, no apprehensions were felt from falls or slides, and there¬ fore no estimates would be made or állowed for any excava¬ tions outside of the exterior lines jsrescribed for the Tunnel, because the contractor would not he called on to make any such excavations. But now it was found that the rock in certain long spaces was not self-sustaining, and apprehensions were felt from falls and slides, and it was necessary to make excavations outside of the exterior lines of the Tunnel. Who should be held responsible for this changed state of things ? Nobody is here to deny that the Tunnel should be made safe. This should be done, of course, no matter how much rock is to come down. But the question is, whether this work, now found necessary, but which the Commonwealth at the outset said, in express terms, would not be necessary, and there¬ fore should not be paid for, shall be done at the cost and expense of the Messrs. Shanly. Your attention has been called to the language of the specifications irpon which the bids were made. Now, please attend to the language of the contract itself. The contract says,— 23 " The size and general description of the work," and other par¬ ticulars, " are set forth in the schedule hereunto appended, which constitutes a part of this agreement." (Page 1.) " The engineer or engineers -of the Commonwealth shall give the lines and grades of the Tunnel, and the lines of the central, shaft, and he responsible therefor." (Page 2.) The size of the Tunnel is to he as follows :— " In rock, without arch, 24 feet wide in the clear ; 20 feet high in the clear," and larger where arching is required. (Page 6.) There are repeated references to "full-size Tunnel," "full- size section of Tunnel," etc., meaning the size just mentioned. The estimated amounts are all based on a Tunnel of the size mentioned. The contract then says,— " Estimates will be made only of quantities within the exterior lines prescribed for the Tunnel." (Page 7.) "Any material detached by blasting or otherwise, outside of said lines, must be removed by the contractors without charge." (Page 8.) The contractors are only bound to remove what is de¬ tached; and detached means "severed, disjoined, separated, disengaged, .parted from." It does not mean loosened. As if to show still more precisely what was meant, the contract recurs to this subject further on, and says,— " Estimates will be based upon quantity of material which lies within the line of section prescribed bj' the engineer or engineers ; and any material falling from outside of these lines, whether de¬ tached by blasts or falls, must be removed by the contractor without charge." (Page 10.) That shows what the contractors are to remove without charge. It is such rock ' as is detached, and falls. If they are called upon and compelled to go outside of the exterior lines prescribed for the Tunnel, and take down rock which is loose, but which nevertheless stands, and to remove it from the Tunnel after they have taken it down, the question is, whether this also shall be done without charge. Is it not plain that the express mention in the contract of the duty of 24 removing without charge material which is detached and falls from outside those liues, conveys by direct implication the idea that material which is not detached, and does not fall, hut has to be taken down by blasting or otherwise, and then removed, will form a proper subject of charge as for extra work,—work not contemplated in the contract? Can any argument make it plainer ? It rests on the same ground that was last year recognized hy the legislature in respect to the duty of laying a hrick arch. The contract provides that the contractors should lay bricks to an amount not exceeding 4,500,000. The argument against the con¬ tractors was, that they must lay all the arch that might be found necessary, even if it were the whole length of the Tun¬ nel, and the cost were to be reckoned by millions ; and they were accordingly called upon to lay a long distance, after the 4,500,000 brick had been used. They resisted this call, and came to thé legislature, and the legislature did not insist upon that construction of the contract. Now, what was the ground taken by the engineers ? They said, the contractors were bound to do everything that was required to be done, in order to leave the Tunnel ready for use, be the same more or less ; no matter what may be found necessary, the con¬ tractors must do it, and the attorney general declares before you that he relies on the same ground now. But the contract, in its true construction, requires nothing of the sort. Mr. Bartlett gave a legal opinion to this etfect last winter, which was published. The contractors undertake " to do and per¬ form all the work necessary to complete the Hoosac Tunnel, in accordance with the schedule hereunto appended." (Page 1.) And the clause at the conclusion of the schedule holds them to "the full and complete performance of the entire work of the completion of the Hoosac Tunnel to he per¬ formed under this contract." Take those two general provisions, with which the contract opens and closes, and examine them in connection with the other parts of the contract, and you will see that these con¬ tractors, upon a just and fair construction of the language used, do not bind themselves so far, that, being allowed to estimate only for laying 4,500,000 of brick, they must go on and arch the Tunnel from one end to the other if safety shall 25 be found to require that to be done, and at a cost of $2,000,000 to $2,500,000, as the attorney general contends; nor so far that, being allowed to estimate only for excavating rock within a certain area, and for removing what shall, be de¬ tached and falls, they must go on and take down and remove a large amount outside of that area, if safety shall be found to require this to be done. Such a contract would be a one¬ sided one. The advantage would all be on the part of the Commonwealth. The legislature of last year, without going nicely into the legal question, did not insist upon such a con¬ struction. They gave it up, and assumed the extra arching themselves. The same principle is applicable now. It may well be contended that it is plain, as a matter oí law, that the Commonwealth has no right to insist upon such a construction, and one might appeal with great confidence to the legislature on this ground alone. But it is also sub¬ mitted to the practical judgment of every intelligent man, that even if the strict rule of law were otherwise, these con¬ tractors might fairly consider that this work was outside of their duty ; that business men generally would so consider it ; and that if the matter be merely questionable, the legis¬ lature would not wish to force contractors, in a doubtful matter, to submit to an adverse decision, with no right of appeal. ■ The correspondence shows that the requirement of the engineers was that the contractors should remove from the roof and sides the slightly loosened slabs or masses, which, not threatening any danger in the present use of the Tunnel, would evidently impair the measure of probable security which belongs to entire completion ; and this duty, so re¬ quired, involved the necessity of further blasting. These are the words of Mr. Frost, in a letter which was referred to. The correspondence is long, and shows cleaidy the explicit orders for the work, the remonstrances and protests from the contractors, their final performance of the work under pro¬ test, and the subsequent recognition of it as extra work to the extent of $5,000, which wás paid. The amount unpaid is about $22,000, and Mr. Frost, who has examined the items, candidly admits that this fairly represents the cost of the work, and there is no question as to the amount. 26 Indeed, it would be doing injustiee to Mr. Frost not to say, that in respect to the details of all of these items, after full and critical examination, he declaves, without evasion or criticism, his approval of them all. Enlarging Tunnel 810 feet from East Portal.—The contract says, in referring to the east section, "a portion of which has been enlarged to the full height of 20 feet and the width of 24 feet, as proposed." It thus appears, by the eon- tract itself, that the Tunnel had been made of full size for some distance. How much? The distance is fixed by official documents beyond dispute. The Commissioners' report. House Doc., 1869, No. 192, p. 28, in the paragraph which was omitted or suppressed in reprinting "that report last year, says: "At the east end the distance excavated is 5,282 feet, and the Tunnel is of full size from its portal to a point 810 feet west." Mr. Frost's report, appended to that of the Commissioners, says : " The Tunnel has been opened out to full size during the past year for a distance of 810 feet from east portal." (Page 58. ) And again, on page 67, he says ; " Of the first half mile of this distance [at the east end] a length of 810 feet is entirely completed." This work was done under Mr. Frost's own superintendence, and at the commencement of the Messrs. Shanly's work, as he admits himself ; and while these matters were fresh in mind, he furnished them with a set of diagrams showing'what work they were to do, and these diagrams began at a point 800 or 810 feet west from the east portal, and Mr. Shanly says he gave oral assurances to the same eifect. Under tliis state of things, the Messrs. Shanly might reasonably suppose that they had no work of excavation to do for the first 810 feet. But they were again mistaken. Notwithstanding the express language of the contract that a a portion had been made of full height and width ; notwith¬ standing Mr. Frost's official statements that the Tunnel had been entirely completed for this 810 feet ; notwithstanding the approval of the Commissioners of that part of the work as a sul)stantial completion within the just meaning of the con¬ tract ; notwithstanding the diagrams ; the engineers, finding upon applying their careful scrutiny that there were a few 27 points of projecting rock in that'portion of the Tunnel also, sought to strain the contract so as to get the work of removing those, points done for nothing. . Now, this was a most disreputable piece of business, such as no man in his private transactions could do, hoping to maintain his credit as a just man. But what was, in fact, done? March 22, 1871, Mr. Frost ordered the Messrs. Shanly to commence the work of Tunnel enlargement from the jportal. May 6, he repeats this order with a threat of with¬ drawing sums from the estimates. May 8, the Messrs. Shanly reply, saying :— * " East, end, from the portal for 800 feet, we bold that we have no work to do till we come to lay the track, that part of the Tunnel having been handed over to us as finished work." Mr. Frost's reply. May 17, peremptorily ordered him to proceed with the work " in the east end of the Tunnel, com¬ mencing ivith the portal," and saying a set of frames would be furnished for his use. As Mr. Shanly still did not recognize his duty to do this work, Mr. Frost, on the 5th of August, 1871, writes to him as follows :— " In your letter of 8th Ma}', you set forward the claim that, from portal at east end for 800 feet in, you have no work to do, 'that part of the Tunnel having been handed over to us as finished work.' I have not any such understanding, and the record and memoranda in my office would seem to show very clearly that your work com¬ mences at the east portal of the Tunnel. The contract mentions about 860 feet at the west end of the Tunnel as already completed by B. N. Farren, forming part of the 931 feet which was reserved only your contract as to excavation and brick-work.- It is very desirable to have the fullest understanding as to such points. I will suggest the possibility of your having had in mind, at moment of writing, the sentence above quoted, without distinctly recalling its context." The Messrs. Shanly replied, August 7, reiterating their views, consented to do the work, but saying, " we must hold that in equity we are entitled to be paid for it extra to the contract." The cost of the work was $3,582. Now, when it is remembered that Mr. Frost was speaking of work done under his own superintendence, and pronounced 28 entirely completed by himself in an official report, the imagi¬ nation runs wild in endeavoring to understand what he was thinking of in writing that letter. Would any one of you, without the evidence before you of documents made at the time, suppose \ij)ossihle for an engineer of the Commonwealth, intrusted with the superintendence of a great work, to put himself into so ridiculous a situation as that? But that is not the worst of it. The governor and council, who in the hurry of their concluding days of official service could not have time to examine these matters minutely, and who, very likely, on referring to the reprint of the Commissioners' report, were misled by the suppression of that important paragraph (which suppression is not yet explained), have been allowed to take a position which it woiild seem that they coidd not have taken if aware of the actual facts. Mr. Frost thinks he informed them fully. But it is not to be supposed that they would have rejected this item, if they had understood the matter as you do now. Nor will the legislature readily adopt the view urged by the attorney general that no matter if the State did represent, in the schedule appended to the contract, that a part of the Tunnel was already done, yet they are not bound by it, and the contractors must, nevertheless, be held to do the work without compensation. No one of you would take such ground as that in a private transaction. Grading Embankments at East End.—The contract says : " The material removed from the Tunnel, at both ends thereof, will be deposited wherever the Commonwealth, by its officers in charge of the work, shall direct, . . . and the contractors shall not be required to haul the same more than 3,000 feet from either end of the Tunnel." The contractors were to haul and deposit this material. But the Commonwealth wished to build a railroad track, and also a county road, within 3,000 feet from the east end of the Tunnel, and so the engineers thought they could compel the contractors, not only to haul and deposit the material, but also to grade the embankments. Mr. Frost was asked the direct question what his directions to Mr. Shanly were, and he testifies explicitly that his direc- 29 tious were " to build the railroad bank," and " to build the highway " ; and that the charge was for handling the rock after it was deposited. What is reasonably implied, as the duty of the contractors, from the obligation to haul and deposit this material? You are to remember this is a work that was going on day and night ; there was no cessation in the motion of these cars, except when stopped by flood or other disaster. The question is, whether the contractors were bound to handle over the rock after dumping it; to leave it at an accurate grade ; or whether their duty was discharged by hauling out the rock and depositing it where it would be available for use by the Commonwealth, for the purposes required. The work which the Messrs. Shanly undertook to do was the construction of the. Iloosac Tunnel. The hauling and depositing of rock required by them was simply incidental to their work-fra the Tunnel. They did not undertake, in whole or in part, to build a railroad or a county road, outside of the Tunnel. No contractor upon reading the contract of the Messrs. Shanly could fairly be held to understand that he could be called upon to deposit this rock material at so accu¬ rate a grade, according to stakes set, as to serve, without further handling, as an embankment for a road. The correspondence shows that this work was done under a prptest from the Messrs. Shanly, that it was outside of their contract, and ymuld be regarded by them as extra work. [See letters from the Messrs. Shanly of June 27 and August 8, 1873, to Mr. Frost; and Mr. Frost's letters of August 7, September 12, 18 and 26, 1873.] Mr. F'rost, in his testimony, goes on to say that $600 was allowed to the hiessrs. Shanly for work in grading which was done before he had charge of that part of the work, and that no allowance was made for any work done "under his super¬ intendence. The memorandum of the decision of the governor and-council shows the same fact. Now, here is found another illustration of the whimsicalities of this eccentric engineer. From the fact that this matter was presented to the governor and council, and disallowed, in terms implying that no extra work was done except during the time of his predecessor, you would naturally infer that it was not recognized that any. 30 such extra work was done. But, ou the contrary, Mr. Frost's letter of August 7, 1873, Mr. Shanly's reply of August 8, and Mr. Frost's second letter of September 12, expressly recognize and stipulate that a portion of this work is outside of the contract, and to be. paid for extra ; and in the last letter Mr. Frost says,— " As to the additional work which I recognize to be outside of your contract, I shall propose to compensate you in the same man¬ ner with other claimants for current account, hy a special voucher for the amount, to he paid as soon as the work is completed." And the amount per cubic yard is fixed. Now, this was in 1873, and the very last of this work was finished in April, 1874 ; and yet the Messrs. Shanly wait for their pay till this hour. Their claim is rejected by the governor and council, with the declaration that the engineers have ad¬ vised them that nothing was due ; and they are here informed by this agent of the Commonwealth, that if they will withdraw this item from their petition to the legislature, and apply to him at North Adams, he will be ready, in the course of a week, to furnish a voucher or payment for so much as he recognizes to be work outside of their contract ! This is a very good illustration of the methods of doing business, and which the Messrs. Shanly have been subjected for over five years. The cost of this work was $3,511 ; a part incurred by injury to their rolling-stock in being forced to go down too steep a grade, in the work upon the highway. This element of injury is recognized by the engineers. Central Drain.—When the Shanly contract was executed, 5,017 feet of central drain from the east portal were supposed to be finished. The contract shows that the eastern division was 10,617 feet in length, and 5,600 feet of central drain were specified as to be made, leaving 5,017 feet supposed to be already finished. Mr. Frost admits this ; according to his own report, 2,256 feet were excavated in 1868. (House Doc., 1869, No. 192, p. 65.) He admits that this was done under his own superintendence, as engineer ; and covered up with timber, as completed, and the loose rock and debris allowed 31 to accumulate, so that no one eould examine it, even if so dis¬ posed. The final covering of this with stone, would be one of the last pieces of work to be done in the Tunnel. In point of fact, it turned out that of this 5,017 feet of cen¬ tral drain supposed to be finished, 4,816 feet' had not been brought down to grade, and 201 feet had not been touched. ■ This happened, as Mr. Frost testifies, through the eareless- ness of his subordinates, and it was not detected by himself, and the imperfection was first brought to light by the letter of Messrs. Shanly of August 7, 1874, to Mr. Frost, as follows : " As far as we have yet uncovered the central drain east of 4,800 eastern section, we find it all too high in the bottom ; so much.too high as to require a great deal of labor to bring it to the proper grade, and it will .take all the force we now have at east end to complete it ready for the drain-pipe, by latter part of this month,— that is, provided it all proves to be as much above ' grade ' as what we have already uncovered. This work, being outside of our con¬ tract, we shall charge as ' extra ' to the State." Mr. Frost's reply of August 13, says,— " I recognize that your understanding, and my belief also, at time of making your contract, regarded this length of trench as having been excavated to the proper grade. I am not, however, authorized to entertain and decide equitable considerations." And he suggests that the Messrs. Shanly should transmit to him a statement of the cost each month. Thus it appears that the agent of the Commonwealth, before the Shanly contract was made, did this work, in part imperfectly, and in part not at all,—concealed the imperfection in part dy covering it with timber, and in part by allowing loose roch and debris to accumulate upon it, so that it was not open to examination; and then represented the worh as com¬ plete,—so that the Messrs. Shanly entered into this contract upon the strength of those representations. Discovering the imperfection five and a half years afterward, they have done the work themselves, giving notice that it was outside of their contract. The engineer assented ; but to this day no allowance has been made for the $8,700 which they expended in doing it. 32 Now it is argued here by the attorney general that, never-, theless, the Messrs. Shanly, though thus ruisled, .took their own risk of the dri\in's having been completed. This argu¬ ment scarcely differs from an argument that the State might take advantage of its own fraud. So far as the Messrs. Shanly are concerned, the transaction, in its effect, was the same as a direct fraud. ]\Ir. Frost concealed the imperfection in the work done under his own superintendence, and then represented to them that the work was complete, and they were misled and deceived thereby. If he knew of the imper¬ fection, this was a gross fraud. If he did riot know of it, it was gross negligence. It is not intended, of course, to charge upon Mr. Frost that he was guilty of an intentional frand ; but he only escapes from the imputation of a gross fraud, by asserting his own gross negligence, and the effect on the Shanlys is the same. And yet it is argued here that this was a fair risk assumed by them. The Commonwealth of Massachusetts cannot afford to take that position. This is a sample of the kind of construction of their con¬ tract to which they have been obliged to submit for years, and is a good illustration of the wonderful and mysterious engineering that has characterized the superintendence of the whole work. These various matters serve to show the kind of require¬ ments that have been made by the engineers upon the Messrs. Shanly, and the spirit in which they have been met. There has never been an instance when the Commonwealth has had Avork necessary to be done, but outside of the contract, where the Messrs. Shanly have refused or hesitated or haggled for sharp terms. Suppose they had taken the example of the engineers for a guide, and said, "There is onr contract; we will do that, and we vñll do nothing else." Such was not their course. They have shown the most entire good faith to the State, under all emergencies and oppressions and embarrassments, financial and otherwise ; repairing storm damages in advance even of any request to do it ; willing to undertake extra work, with no provision made in advance for payment ; but relying with a confidence, that even the conduct of these engineers has not wholly removed, in the ultimate good faith and justice of the Commonwealth. They appeal 33 from the agents of the State to the State itself, and expect from you that justice which they have not hitherto received. Mistake in OraoiNAL Measurement. Again, it is now a conceded fact that there was an error in the computation of the amount of solid rock excavation per running foot of Tunnel, by which Mr. Shanly was misled at the time of making his contract. This computation had been made by an assistant of Mr. Frost's, who thought that the amount to be excavated, for an area of the size prescribed for the Tunnel, would be of a cubic yard less than it really was, for each running foot. Mr. Frost frankly concedes this error, and admits that the cost of this additional excavation would amount in all to $22,000, at contract rates. Mr. Shanly entered into this contract relying implicitly on Mr. Frost's figures. Every¬ body agrees that he accepted them as accurate.* This is a matter of absolute injury to the Messrs. Shanly. They were misled and deceived, though not intentionally. By this blunder, the price they got for the Tunnel is $22,000 less than it otherwise ivould have been. The contract price was arrived at by adding up Mr. Frost's various items ; $22,000 more would have been included but for this blunder in a matter- of pure mathematics. Mr. Shanly has lost this amount out¬ right. If the truth had been told to him, he would have had it. The contract price would have been just so much more. Without disputing this,—for it is indisputable,—it is said that in the western section, where arching was expected to be done, a smaller number of cubic yards was in fact exca¬ vated than Mr. Frost estimated at the outset, and this, it is supposed, in some way furnishes a reason why Mr. Shanly has now no ground of complaint. But the argument is an unjust one. In the first place, the fact is not satisfactorily established ; it was not brought up before the governor and council ; it was never intimated till near the conclusion of the hearings ; no details were given making verification possible, and it was, as it were, sprung upon us, after Mr. Frost had written Mr. Shanly a letter, dated March 8, 1875, telling him his item oí $22,000 needed no change. 34 In the second place, there is no question that excavation ■was made suiBcient to receive 4,500,000 brick laid in arch. How much excavation would be required for this was known to be a matter of estimate, not of exact computation. The amount would depend upon the thickness of the arch required, and this could not be known beforehand. If, therefore, the actual excavation required should prove more than the esti¬ mate, Messrs. Shanly must nevertheless take out the rock ; , if less, they were entitled to the advantage._ The contract price was not to be varied by the result of a conjectural esti¬ mate ; but if the contractors are to suffer from the effect of an erroneous computation in pure mathematics, in a matter wherein they were confessedly forced to rely implicitly on the statement of the engineer of the Commonwealth, it has all the effect of a positive fraud. In the third place, Mr. Frost tells you that in fact, according to the best judgment he can form upon a detailed exami¬ nation of the rock, the Messrs. Shanly have actually exca¬ vated 22,638 cubic yards of rock outside of the prescribed section of the Tunnel, in those 8,573 running feet which three of the experts, employed by the corporators, have agreed upon as likely to require arching; and that if this space should be arched, according to the recommendation of the three concurring experts, the value of this extra excavation to the State, at contract rates, will be $250,000. It is not, there¬ fore, for the State to say that the Messrs. Shanly have done less work than was estimated at the outset, when in only 8,573 running feet they have made an excavation, necessary for the State now, of 22,638 cubic yards outside of the pre¬ scribed lilies ; showing that in the whole Tunnel they have probably exceeded the assumed quantities, in their actual excavation, by as much as 50,000 cubic yards ! Shall the State avail itself of this $250,000 worth of ■ necessary work, outside of the contract, without paying for it, and send the Shanly s home with a loss of $225,000 9 The Destruction of the Haupt Tunnel Caused loss by increasing the working expenses $2,700, and by delaying the completion of the Tunnel. The necessity ■ of the Haupt Tunnel to give an exit west. 35 was recognized in the contract, and an allowance of |8,500 made for clearing out and timbering it. To understand this clearly requires some acquaintance with the situation of . the ground at the west portal of the Hoosac Tunnel. Just to the west of that portal there is a hill, through which the Haupt Tunnel was built. An open cut for the railroad has now been made through that hill, but, at the time when the Shanly contract was entered into, there was no way of deliv¬ ering the material from the west end of the Hoosac Tunnel except through the Haupt Tunnel. It was not only the duty of the Messrs. Shanly to keep the Haupt Tunnel open, but it' was their plain right to have free egress through it from the west end of the Hoosac Tunnel, until the completion of the work under their contract. The railroad from the west portal of the Tunnel was to be built by other contractors,—Messrs. McClallan, Son & Walker,—whose work in August, 1873, began to interfere with the maintenance of the Haupt Tunnel by the Messrs. Shanly. On the 28th of August, 1873, the Messrs. Shanly sent to Mr. Frost the following letter, a copy of which was sent to the governor :— lioKTH Adams, 28th August, 1873. Dear Sir:—"We have to notify you that unless the work now doing under the state contract with Messrs. McClallan, Son & Walker, in the deep cutting approaching the western portal, be sus¬ pended at once, we will not hold ourselves responsible for the maintenance of the Haupt Tunnel. As the case now stands, it may be said that while we, under our contract, are bound to keep up the old Tunnel, a contract has been made with other parties to batter it down. The action of Mr. Dwyer's steam-excavator, which has stripped the outer covering from off the south side of the Tunnel for about half its length, causes the supporting timbers inside to shake and vibrate to such an extent that they must inevitably, and before long, give way, and so cause the Tunnel to close in, while his blasting operations will certainly complete the ruin. A single blast outside yesterday, brought down several carloads of rock inside, obstruct¬ ing the passage through. The Haupt Tunnel has by us been maintained in perfectly safe condition for all purposes contemplated by or required under our contract, but we cannot undertake to protect it against the batter- 6 36 ing-rams and artillery now assailing it from without. The stripping of one side, while the other is left fully loaded, would, be sufficient to overbalance the very best constructed arch. We warn you that the destruction of the Haupt Tunnel, now imminent, will cause us great damage, and seriously impede the progress of the main Tunnel. This is a matter of so great moment that we deem it advisable to send a copy of this communication to His Excellency the governor. Yours truly, (Signed) F. SHANLY & CO. Benj. D. Feost, Esq., Engineer, etc. On the 30th of August, Frost sends a reply containing the following :— " The incident which you mention occurred from the jar of an unusually heavy blast, but it showed the limits of safe proximity to have been reached. I therefore directed J. W. Dwj'er, who is making the approach cut for McClallan & Co., to withdraw his steam-shovel tb the point 700 feet distant, at which he will com¬ mence to bring up the lower (grade) breast of the cut." The matter then rested for a time, till on February 4, 1874, the Messrs. Shanly addressed Frost as follows :—, " We must again draw your attention to the condition of the Haupt Tunnel, which has never been safe, and not for two consecu¬ tive da3's even passable, since the heavy fall of rock which took place on the 4th of January. We have been entirely cut off from access to our excavation from façade and put to much loss both of time and money, and must again record our. sense of the injustice and injury done us in not being allowed to complete the façade and arch last summer." ' . Frost's reply, February 11, was very long. Among many other things, it contains the following :— " Unavoidably, your excavation has been much hindered by the successive interruptions of route of haulage of materials." . . . "A week later [i. e., after Jan. 13], ñnding the prevalent mild weather was occasioning falls from slopes, and other incidents of unavoidable danger, I became convinced that new arrangements 37 must be made in order to secure tbe concurrent progress of the rail¬ road and façade excavation." . . . " At the immediate present, it is not reasonably possible to main¬ tain safe passage through the whole length of the Haupt Tunnel. I have already made provision for the important matter of drainage through it, and must, of course, deem the State henceforward respon¬ sible^ for the maintenance of its construction. . . . When¬ ever you shall conclude to resume the excavation with your own force, or whenever you shall desire to transport any other material through the Haupt Tunnel, it seems to me that you should present to me, as the agent for the State, the option of re-opening the Haupt Tunnel for your transportation, or of allowance to you for the in¬ creased cost of moving your excavation or other materials by other route." On February 16, the Messrs. Shanly reply to him, thus :— " Referring to your letter of 11th inst. about the Haupt Tunnel, we, of course, have no further responsibility for it, but still must hold the Commonwealth responsible to us for the damage and incon¬ venience we have been, and still may be, put to, by being deprived of access through it to our works. Our sub-contractors, too, may look to us to make good any loss or inconvenience they maj' be put to through the same cause." March 6, 1874, the Messrs. Shanly again write as fol¬ lows :— ..." As we hold, that the passage through the Tunnel is no longer safe, and that large masses of the roof may come down at any moment, to the endangering of human life, if we continue to run our excavation out through the Tunnel, we have decided to erect derricks and other appliances for hoisting the material to sur¬ face-level." And asking him to indicate where the material may be dis¬ posed of. Mr. Frost replied, March 7, saying,— " Recognizing that the continuous maintenance of the Haupt Tunnel, so as to allow you transportation through it for removal of material excavated, must, before long, become a matter of consider¬ able difiSculty and expense, and also appreciating the consideration of greater safety in the alterations now proposed, I am glad to learn 38 your present conclusion to resort to hoisting direct to the surface- level by steam." After this correspondence, in which Mr. Frost recognized the responsibility of the State for the^ interference with the Messrs. Shanly's work, and the annoyance and expense to them, time passed on until August, and no means of exit at the west end were furnished,—the Haupt Tunnel was de¬ stroyed,—the material had to be hoisted up through the west shaft ; and, so long as the shaft was used for hoisting, the large amount of rock still to be excavated near the bottom of that shaft, must remain untouched. That work could not be done till egress was furnished at the west end, for blasting and hoisting could not go on together. Accordingly, August 26, 1874, the Messrs. Shanly wrote to Mr. Frost, as fol¬ lows :— " When may we count on having a track laid to the west portal, that we may run our cars out to the dumping-ground, and so enable us to complete the arch within the Tunnel ? The want of our track through the Haupt Tunnel has caused us great delay, and is now adding largely to our expenses, and the time has arrived when we must have corresponding ingress and egress provided for us." September 4, Mr. Frost replies, recognizing the increased expense to Shanly by reason of the closing of the Haupt Tunnel, in these words :— " It is expected that the ballasting of the northern side of the west approach cutting will be finished by Wednesday next, and you can then proceed to extend, with suitable curves, from end of one of your present tracks,—say 100 feet west of the west portal," etc. " So soon as you shall have laid your short, necessary lengths of track and third rail, you will please furnish me a statement of the cost. It is evidently one which you could have avoided., if continuous use of the Haupt Tunnel had been left to you." September 16, 1874, the Messrs. Shanly again write to Mr. Frost, as follows :— " We are greatly delayed in completing the excavation around west shaft, and all other finishing in west-end section in fact, by want of free access from west portal, immediately outside of which 39 Mr. Dwyer (sub-contractor for McClallan & Co.) still occupies the ground and blocks the track so as to render our sending out our cars with any degree of regularity not practicable. We wish to learn when we can be accommodated with free access to the dump¬ ing-ground, in order to allow of our arranging for closing the shaft." Mr. Frost, in his testimony, concedes that the use of the Haupt Tunnel was necessary for them to finish their work in the west end of the main Tunnel ; that the work must all he done up the west shaft till exit was possible through the west portal ; that the work remaining to be done near the west shaft could not be done until that shaft was closed and exit obtained through the portal ; that the State were forced to cut off that exit till September, 1874 ; and that Mr. Shanly was delayed in his work in consequence. It was a ■ plain invasion of the Messrs. Shanly's rights, subjecting them, not only to the extra working expenses, but also, and more important by far, to the damage resulting from delay. Upon Mr. Frost's own statement—upon facts not here in any con¬ troversy at all—this loss is manifest. It is now argued, that although it is just to allow to the Messrs. Shanly the damages sustained by them to March 1, 1874, yet nothing should be allowed for the damages during the time for which the contract was extended. . This argu¬ ment is, in substance, that the Commonwealth, while extend¬ ing the time for good reasons, might, nevertheless, prevent the contractors from doing the work within that time. The attorney general fails to appreciate the ground on which this matter rests. It is this : the Commonwealth for a long time prevented the contractors from using an exit through the west end of the Tunnel. So long as the contractors were so prevented, they could not finish the Tunnel, and the delay was the fault of the Commonwealth. Losses of Interest. Mr. Shanly has shown that, but for the delay thus imposed upon him, the use of the west shaft would have been aban¬ doned in April, 1874 ; his whole work would have been finished by September 1, 1874, and he would have been entitled to a settlement on that day. Had a settlement been then made, and they been paid the amount in full which they had then áO earned, they would have received in money $548,164. The interest on this sum from September 1 till December 22 (which was the day of the actual settlement), making proper allowances for sums actually paid between those dates, would amount to $10,603. By the Eesolve of 1873, chap. 48, it was provided that $350,000 should be reserved and retained in the treasury until the completion of the contract, and, subject to said' reservation, " the full amounts already earned or hereafter to be earned by the Messrs. Shanly shall be paid over to them." This Eesolve has not been fairly carried out according to its true spirit, as appears from the fact that when the final settle¬ ment was made with them, $456,000 which had been kept back till then, was paid, instead of $350,000 ; and the sum of $60,000 in excess of their earnings for the month had been paid to them in a recent estimate. The Messrs. Shanly put these losses of interest at $19,850, according to a detailed statement which has been laid before you. The Messrs. Shanly have also lost interest on the amounts of all those items for which payment should have been made to them heretofore ; for example, the sum due for the work on the first 810 feet, at the east portal ; for the grading of the embankments ; for the central " drain ; for the storm damages at the west end; and for taking down the loose rock. Moneys Weongfully Withheld feom Conteactoes. There is another kindred source of injury to the Messrs. Shanly, founded in a manifest and very oppressive injustice. Their performance of the contract was secured by $500,000 of money earned by them, which was retained by the Com¬ monwealth. Till their earnings reached this sum they re¬ ceived nothing. And after their earnings reached this sum, there was never a time when the State had not at least $500,000 of their earnings in its treasury, until after the passage of the Eesolve of 1873, directing that thereafter only $350,000 should be retained, and even this was to a consid¬ erable extent nidlified by the construction of the engineers, as has been shown. This retention of money was the security provided in the 41 contract itself, and it was the sufficient and only security which the contractors were bound to furnish, or the State was at liberty to exact. It was withheld as security ; and it was the security agreed upon as sufficient and satisfactory. If the contractors failed to observe the provisions of the contract, the remedy was, for the State, if it saw fit, to give them three months' notice, and put an end to the contract. But if this was not done, the, contractors were entitled to be paid for their work, subject to the retention of the amount agreed upon for security. But the engineers enforced against the Messrs. Shanly another and additional security, not provided for in the contract, and wholly unjustifiable and illegal. They withheld in their estimates, at various times, large sums of money, which had been earned, as a sentence or punishment on the Messrs. Shanly for failure to observe direc¬ tions or requests of the engineers as to methods and times oí doing certain details of the work. For instance, Mr. Frost tells you that thousands and thousands of dollars were with¬ held on account of an omission to do certain matters of trim¬ ming, at the times when the engineers wished. They would not allow the Messrs. Shanly to select their own times for doing this work. Simply for a failure to do it at the par¬ ticular times required by the engineers, this deduction was made. The strictness of construction of the engineers seemed to increase with the difficulties of the contractors. In that dark season of 1872, in July, when work was necessarily "sus¬ pended west from the central shaft, and was prosecuted to the east under the difficulties that have been described, the order came to trim ofi" every inch of projecting rock without delay. At one time $27,000 was withheld from Mr. Shanly on account of trimming. The $500,000 security was designed to cover all such matters as this. Other reservations of money were also made. It was oppressive and harsh and illegal. ■ ® . Interest Paid by Contractors. All reservations of money, as well as all increased ex¬ penses of working, had also the direct efi"ect to swell the 42 amount of interest paid by tbe Messrs. Shanly, so that in the aggregate it reached an amount quite beyond the original expectation. Including the $500,000 retained by the State, the capital required for the prosecution of the work would not fall far short of $700,000, the interest on which, at seven per cent., would be about $50,000 a year. Following close upon the water difficulties of 1872, came the financial panic of that year, culminating in its çiemorable Black Friday, and forcing strongest houses to the payment of unusual rates of interest. The following year another season of financial embar¬ rassment succeeded, which tested in the severest manner the strength of all who were carrying on enterprises which in¬ volved the necessity of large capital. In addition to the work required by the contract, the State, from time to time, were calling upon the Messrs. Shanly for extra work, which they undertook and performed, the payment for which was long de¬ layed, and some of it has not even yet been received. These advances of money, when already overburdened with a losing contract, in two seasons of wide-spread financial distress, have contributed to swell their interest account to an amount so great that it has been thought fit to make it a subject of special comment by the attorney general. But in view of the circumstances, there is occasion rather to be surprised that the amount of interest paid was as small as it appears. It is to their credit, and shows their financial strength, that this account is no larger. Indeed, looking back upon the history of their work under the contract,—considering the capital invested, the security required by the State, the two seasons of financial distress and panic which convulsed the country, the great physical difficulties to be overcome, the strict constructions of the engineers, the withholding of money earned and due, the calls for extra work, the numerous unexpected difficulties which beset the Messrs. Shanly, physical and moral,—the wonder is rather that they ever got through with the work at all. Looking back upon it now, it is simply a marvel that perseverance and pluck endured so long. 43 Official Commendations of the Messrs. Shanly. The joint standing conimittees of the legislature have not failed, from year to year, to recognize the energy, ability and fidelity displayed by them throughout their work. The committee for 1869 say,— " We feel called upon to say, generally, that every portion of this stupendous work showed a capacity, thoroughness and energy in its prosecution which speak well for the contractors, and give the best assurance that the work will be completed by them, and within the time prescribed b}' the contract." (Senate Doc., 1870, No. 58, p. 3.) The committee for 1870 say,— " The committee have made a close examination into every part of the Tunnel work, and have also made themselves perfectly famil¬ iar with all the discouraging difBculties which have from time to time been encountered in the progress of the work in the past, and have carefully compared them with all contingencies that may rea¬ sonably be anticipated in the future, and they are settled in the opinion that the contractors will be able to finish the Tunnel within the time specified in the contract." (Senate Doc., 1871, No. 55, pp. 16, 17.) The committee for 1871 say,— " Since the last session, we have visited and' examined the work¬ ings of the contractors of the Hoosac Tunnel, and find much reason for satisfaction in the apparent energy and ability displa3'ed in push¬ ing forward the work. The rate of progress then prevailing at the east end of the Tunnel, as ascertained from the state engineer, was more than twenty-five per cent, in excess of contract rate, and the report of the whole j-ear's advance at this point shows an aggregate excess of about sixteen per cent." " The progress attained during the past year in the headings, both at the east and west ends of the Tunnel, has considerablj' ex¬ ceeded that of the preceding j'ear, and is now m each of these instances in advance of the point required by the stipulation of the contract." (Senate Doc., 1872, No. 250, pp. 4, 5, 14.) The committee for 1872 say,— " The progress of this work during the past 3'ear seems to evince very commendable diligence and faithfulness on the part of Messrs. 7 44 Walter and Francis Shanly, contractors. The advance of heading westward from the central shaft was suspended during more than ten months of the year by reason of enforced delays arising out of the large volume of water encountered, and the apprehension of de¬ veloping a further increase of quantity which should exceed the resources of the pumping machineiy provided for its removal. Not¬ withstanding the suspension of progress at this single point of ad¬ vance during the greater part of the year, the great exertions made at the other points of penetration, seconded by very remarkable immunity from any considerable delay, have given an aggregate quantity of work in lineal feet of heading opened during the year which considerably exceeds the hmount of advance for that time that would have been reasonably anticipated if the difficulties and dangers of interruption which were to be met with had been fully apprehended." (Senate Doc., 1873, No. 201, pp. 5, 6.) The committee for 1873 say,— " The contractors, Messrs. Walter and Francis Shanly, seem to have continued to maintain a high standard of diligence and energy in the prosecution of their work. . . . /i has been a matter of advantage to the enterprise that the contract for its execution should have fallen into the hands of men alike energetic and competent, who have contended successfully with its many difficulties." (Senate Doc., 1874, No. 201, pp. 6, 7.) Mr. Frost, also, in his report for the year 1872, which included the dark and difficult season of this contract, says ; " The operations during the year by Messrs. Walter and Francis Shanly, contractors, upon their contract for the completion of this work, were prosecuted with most excellent resource and energ}-. . . . They have attained results of progress eminently satisfac¬ tory, in view alike of the sources of delay which were apprehended, and of the actual difficulties met and surmounted. " With the single exception of progress westward from the cen¬ tral shafti which was suspended in February, the advance of the last year in the work of driving the headings may be said to have- been substantially without peculiar hindrances, and the results obtained have satisfied the most sanguine anticipations. In the head¬ ing from the west end, up to January I, 1872, the whole length obtained was but 32 feet in excess of the contract requirement. For the year following, the contract would require a progress of 1,200 feet. The actual length penetrated was 1,61G feet, an excess 45 of more than 33 per cent. This very favorable result iß paralleled as to ratio between required and actual rates, by the ver^' creditable, as well as very fortunate progress which has been accomplished tlirotigh extraordinary efforts in the heading eastward from the central shaft. In this the contract rates would require, for the eleven and a half months' work which preceded the junction made with the east- end section, December 12, a length of 920 feet ; and the actual amount accomplished was 1,226 feet, an excess of very nearly 33 per cent. " It should, however, he remembered that the extraordinary progress is due largely to the extraordinary exertions made." Their Character as Contractors. These are the comments which have been made from time to time, as the work has proceeded. They are quoted here, because they show the concurring testimony of every legis¬ lative committee, year after year, whose official duty it was to examine and report upon their work. They do not leave it in any doubt that the Messrs. Shanly have displayed the highest qualities in the prosecution of this enterprise. To their uprightness and truthfulness. Governor Talbot has borne a willing confirmation. But it needs no witnesses to satisfy you upon this point. Such absolute fidelity to truth as has been shown here by Mr. Walter Shanly, you are not likely to find surpassed. He seems to have taken for his motto the Saxon oath,— " By Woden, God of Saxons, ^ Truth is a thing that I will ever keep, ' Until that day in which I creep Into my sepulchre." Intellectually, he is a man for great tasks and responsibil¬ ities, and not for holiday duties ; of clear perceptions ; of strong convictions ; of self-reliance almost unwavering. Such a man is not swayed much either by the doubts or the overconfidence of others. In a matter of high moment, he must needs act upon his own judgment alone. For carrying through an engineering work of supreme difficulty to-day, where is the man you would select in preference to Walter Shanly ? Whose judgment would you hold superior to his? Looking back upon the history of this great enterprise 46 \ from the beginning, who, of all those at any time engaged in its prosecution, comes out with the highest and best repu¬ tation? It is Walter Shanly. Who else has succeeded but the Shanlys? If any other reputations have suffered, no stain has come upon that of these contractors. Their chief commendation is this : that when natural and physical obstacles alone were almost enough to appall the stoutest heart, they have not been broken down by the addi¬ tion of needless annoyances, of exactions in matters of detail, —many, perhaps, comparatively petty in themselves, though serious in the aggregate,—of unwise direction and control, and all the ceaseless, nameless vexations springing from a super¬ intendence that was a constant hindrance rather than a help ; and that they persevered, even though, in the gravest exi¬ gency that has arisen in the progress of the work, the Com¬ monwealth, acting under the advice of its engineers, assumed the responsibility of imperatively controlling their course, holding them responsible for results, while forbidding them to exercise their own judgment as to the best means of accom¬ plishing those results, and forcing them to act in a manner which they at the time proclaimed to be foolish, reckless, ruinous. Their losses have come upon them through no fault of their own. The history of their connection with the work is now before you ; and they are unwilling to believe that the legis¬ lature or people of Massachusetts, on reviewing the whole matter, will wish to see them dismissed from the successful execution of this great public work, not only with these heavy outlays to bear, but also with the smarting sense of injustice which springs from the conviction, that, even in spite of the unexpected natural difficulties which they have encountered and overcome, they would have escaped without pei^uuiary loss but for the unreasonable exactions and requirements to which they have had to submit. For these reasons, they respectfully ask for an ajjpropria- tion which shall make good to them their loss. 1 n